PARDON OUR DUST Arlington Boulevard (Route 50), 10 th Street and Courthouse Road Interchange (ARRA) Project No. (FO) 0050-000-728, C501, B612, B611
WELCOME Larry Tomlinson, P.E., L.S. Area Construction Engineer & Ken Connors, P.E., C.C.M., P.M.P Project Manager 2
Tonight s Agenda: Introduc of the onstruction eam Project Update Construction Elements Sequence of Construction Detours & Lane Closures Night Work Questions 3
Project Partners Virginia Department of Transportation Arlington County Flippo Construction Co. Inc. Citizens 4
Construction Team & Contact Information Project updates will be posted on VDOT s website at: 5 http://www.virginiadot.org/projects/northernvirginia/route_50-10th_street_and_route_50- courthouse_road.asp VDOT Field Office Location: 1426 Columbia Pike, Arlington, VA 22204 VDOT Construction Management Contact Information: Shirley Reeves Project Inspector Shirley.Reeves@VDOT.Virginia.gov Jitender (Jay) Babra Construction Manager Jitender.Babra@VDOT.Virginia.gov Ken Connors, P.E.,PMP Project Manager Ken.Connors@vdot.virginia.gov Contractor: Flippo Construction Co., Inc. Contact Information Roger Shunnarah Project Manager rshunnarah@flippo.com Sean Igoe Office Engineer sigoe@flippo.con
Project Information Contract Amount: $ 21,434,864.85 New interchanges at both 10 th Street and Courthouse Road Adding C-D roads to both EB and WB Route 50 10 bike trails on both sides of Route 50 13 retaining walls (MSE and VDOT St d. RW) Art work on eight (8) retaining walls Two (2) new bridges Three (3) signalized intersections Lighting (roadway lighting and bridge LED accent lighting) Utility construction Special design SWM structures Landscaping 6
Project Location 7
Project Vicinity 8
Route 50-10 th Street and Courthouse Rd. Interchanges Overview of Completed Project with New Traffic Signals 9
Phased Construction: Stage 1- Phase IA SPRING 2011 Pavement build-up night work. Lane closures during non-rush hours. Install construction signs and erosion control measures. 10
Phased Construction: Stage 1- Phase IB SPRING 2011 Pavement build-up night work. Lane closures during non-rush hours. Install drainage structures and pipe along Rt. 50 WB. 11
Phased Construction: Stage 1 - Phase II SUMMER/FALL 2011 Construction of North Fairfax Drive and Portion of Courthouse Road Retaining Wall (temporary shoring) Temporary Pavement Pedestrian Detour A Shift Rt. 50 WB traffic to new build-up section. 12
Phased Construction: Stage 1 - Phase III WINTER 2011 13 Closure of Ramp from WB 50 to Courthouse Road Closure of Fairfax Drive Detours 1 and 2 Temporary Signal from Courthouse to Rt. 50 WB. Construct CD road, Fairfax Drive & Courthouse Rd. ramps.
Phased Construction: Stage 2 - Phase I SPRING/SUMMER 2012 Construction of New Bridges 10th Street & Courthouse Road Retaining Walls (temporary shoring) Temporary Signal & Detours 3 and 4 Fairfax, Taft & Troy to reopen 14
Phased Construction: Stage 2 - Phase II Fall 2011 Open New Bridges 10 th Street & Courthouse Road Retaining Walls (temporary shoring) Temporary Signal & Detours 3 and 4 Demolition of old Courthouse Road Bridge 15
Phased Construction: Stage 2 - Phase III WINTER 2012 16 Retaining Walls (temporary shoring) Temporary Signal & Detours 3 and 4 Construct 10 th Street Bridge ramps Rt. 50 EB open from 10 th Street & Courthouse Road Overlay Rt. 50 EB
Phased Construction: Stage 3 - Phase I SPRING/SUMMER 2013 Construction of Ramp E From Rt. 50 EB to North Rolfe Street Finalize construction of EB Route 50 EB Trail 17
Phased Construction: Stage 3 - Phase II FALL 2013 Construction of Ramp E from Rt. 50 EB to North Rolfe Street Finalize construction of EB Route 50 EB Trail 18 Finish Retaining Walls
Traffic Detours During Construction Detour 1 (Winter 2011 to Spring 2012) Westbound Rt. 50 ramp to N. Courthouse Rd. closed. Signed detour will be 15th St. N. Westbound Rt. 50 to N. Fairfax Drive closed. Signed detour will be 10th St. N. to N. Barton. Detour 2 (Winter 2011 to Spring 2012) Fairfax Drive closed between N. Troy Street and N. Scott Street Signed detour will be N. Scott St. to 13th St. N. to N. Troy Street (Scott, Taft, Troy Streets remain open, only access to Fairfax Drive is closed).
Traffic Detours During Construction 20 Detour 3 (Spring 2012 to end Winter 2012/Spring 2011 Ramp from southbound 10th St. to eastbound Rt. 50 and Fairfax Drive closed. Signed detours (two) will be Washington Blvd. to N. Pershing to Rt. 50, and N. Barton to N. Pershing to Rt. 50
Traffic Detours During Construction Detour 4 (Fall 2012 to end Winter 2012/Spring 2013) Ramp from eastbound Rt. 50 to Courthouse Rd. closed. Signed detour will be Washington Blvd. to Garfield St. to Clarendon Blvd. 21
Limitations Of Operations Route 50 EBL & WBL's Day Open all lanes to traffic no later Reduce to 2 lane of traffic no earlier than than Monday 5:00 AM 11:00 PM Tuesday 5:00 AM 11:00 PM W ednesday 5:00 AM 11:00 PM Thursday 5:00 AM 11:00 PM Friday 5:00 AM NO LANE CLOSURES Saturday NO LANE CLOSURES NO LANE CLOSURES Sunday NO LANE CLOSURES 11:00 PM Route 50 EBL & WBL's Day Open all lanes to traffic no later Reduce to 2 lane of traffic no earlier than than Monday 3:00 PM 9:00 AM Tuesday 3:00 PM 9:00 AM W ednesday 3:00 PM 9:00 AM Thursday 3:00 PM 9:00 AM Friday 3:00 PM 9:00 AM Saturday NO LANE CLOSURES NO LANE CLOSURES Sunday NO LANE CLOSURES NO LANE CLOSURES 22
Typical Section 23
Aesthetic Retaining Walls Aesthetic MSE Wall Panels Art Pattern Walls Special Provision Artist Coordination Cast-in-Place Walls Rustication Treatment (Sine Wave Pattern) Special Pedestrian Handrail 24
25
26
Accent Lighting With Decorative Steel Facia Panels Backlit Panels Color LED Accent Lighting LED Lighting Controller 27
28 Question & Answer Session