Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca

Similar documents
MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY

Ocean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science

Chapter 9: Sea operations

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

BACKGROUND TO STUDY CASE

Delivery and Deployment of the U.S. Navy s Submarine Rescue System

Location: Barkley Canyon Date: September 9, 2013 Constraints: none

LESSONS LEARNED. Marine Operations Minas Passage

Polar Research Vessel Operational Requirements and Summary of Technical Studies

Learn more at

SeaSmart. Jonathan Evans

Modelling and Assessment of Marine Renewable Energy Resources. Andrew Cornett Canadian Hydraulics Centre National Research Council Canada May 2008

Multi-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services

Sea Views SEACAMS. month s edition. In this. Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog

Ocean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors

Stevpris installation

TRIAXYS Acoustic Doppler Current Profiler Comparison Study

Appendix 5: Currents in Minas Basin. (Oceans Ltd. 2009)

RV Southern Surveyor program

Mooring Modifications for the Reduction of Losses to Vandalism

Isis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator.

RR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010)

HYDROGRAPHIC AND SITE SURVEY REPORT

US Navy Wave Energy Test Site. Kaneohe, HI

Using AUVs in Under-Ice Scientific Missions

RVSS Appendix A Overview

Ocean Observatories Initiative. Coastal & Global Scale Nodes. Hydrogen Safety. OOI Surface Mooring Hydrogen Safety Review

Appendix 11-B Anchor Handling Systems, Set Up and Handling

RISK ASSESSMENT -HEATS-

Cathodic Protection Retrofit Options Comparison of Current Distribution

This guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy.

UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016

REVISED SILT CURTAIN DEPLOYMENT PLAN

Dear Captain, Anchor lowering procedure all berths. Page 3: Mooring procedure Parker Point 2 and 4. Page 4: Mooring procedure Parker Point 3 and 5.

Saab Seaeye Cougar XT Compact

Managing Dynamic Positioning (DP) Operations

Large-scale Field Test

IMCA Competence Assessment Portfolio June 2013

Summary of Architecture Parallel Session. G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania

Fully Submersible Heavy Lift Vessel

Offshore Wind Energy Stringent quality assurance and quality control. Coastal and Freshwater Fast responding and flexible organisation

IMCA Competence Assessment Portfolio June 2013

A FINAL REPORT BY PARTRAC LIMITED: MAY 2006

11 Anchor Handling & MOU Moving 11-2

NSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader Community

The Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy

Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations

TARPON A Minimal Facilities Platform

Aasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen

R E V I S E D D A T E 0 4 /

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

ORE Open Research Exeter

NWEI. Fred.Olsen. Columbia Power

MEASUREMENT COMMUNICATION INSIGHT

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010

PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL

(a) Calculate the speed of the sphere as it passes through the lowest point of its path.

Update on Canadian Research Vessels Ship Procurement Projects

Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009)

Wave Hub Update All Energy 21/22 May Stuart Herbert Commercial Director

1 Module A (uniform topography) survey lines Module B (topographic wake) survey lines Module C (submesoscale soup) survey lines...

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX

Geo-Vibro Corer

Ketchikan Harbors Thomas Basin and Bar Point Harbor

CB-40 Data Buoy Quick Start Guide

Products and Services HR3D, AUV3D

USCG Development Proposal: Heavy Oil Tracking Tactics, Techniques and Procedures Presented to: Ms. Brenda M. Burke (RDC)

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers.

voyageplan SS Itinerary Principal Investigator(s) RV Southern Surveyor program

Focus on Operational Efficiency and Crew Safety - Introducing Advanced ROV Technology in Marine Towed Streamer Seismic

The Wave Glider: A Mobile Buoy Concept for Ocean Science. 009 Liquid Robotics Inc.

Original URI Scanfish MKII

Noise Experiment #2. Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA February 22 February 2010

Break in the Bahamas. Cutters Head to the Caribbean to Wire Saw Sunken Pier. A 25-foot by 25-foot steel pier section had sunk into the water.

Cargo and hull damage while at anchor in heavy weather

[***] = both land and marine [***] = Marine only [***] = Land only + ([***] = Shallow Water) if needed

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd

ANY OTHER BUSINESS. Guidelines for passenger ship tender operator. Submitted by Cruise Lines International Association (CLIA) SUMMARY

MSC Guidelines for the Review of Oil Spill Response Vessels (OSRV), Lightship and Stability

A Wind Profiling Platform for Offshore Wind Measurements and Assessment. Presenter: Mark Blaseckie AXYS Technologies Inc.

Welcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives

Application for Consent to Conduct Marine Scientific Research. F Internal Waves in Straits (IWISE) Institution Contact Information Director

The topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by

Tides. Tides: longest waves. or seas. or ripples

Astrolabe Reef Access Plan Stakeholder Presentation

High Frequency Acoustical Propagation and Scattering in Coastal Waters

Understanding the Dynamics of Shallow-Water Oceanographic Moorings

FINAL REPORT DERELICT FISHING GEAR IDENTIFICATION AND REMOVAL PROJECT PORT SUSAN

Application of Value Engineering The Crosstown Project

Quicker and Safer Deployment of Deepwater MODU Moorings.

TRACK RECORD SEP. 2018

SOP GEN-007X Crane and Winch Operations

Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018

DIVE PLAN Leg 1 Dive 11 Recover Wally 1

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe

UNDERWATER SERVICES COMPANY PROFILE

CONSTRUCTION OF LNG RECEIVING TERMINAL ON THE SAINT LAWRENCE TIDAL CURRENT CONDITIONS IN THE LEVIS AREA

SPHL-R. A part of the James Fisher Hyperbaric Rescue Service. (Self Propelled Hyperbaric Lifeboat Recovery) Subsea UK Expo 2016

NT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test

UNIT Coastal Navigation 1 (Intermediate 1)

Transcription:

Sensor Platform Project Marine Trials Bidders Conference Fundy Ocean Research Center for Energy fundyforce.ca 1

Project Team FORCE OceanWorks International Preliminary Design, Operational Procedures Murray Scotney, OceanMoor Technical Svcs Operational Procedures Mike Wilson, PICC Cable Engineering 2

Agenda The Project (15 min) Scope, progress, preliminary design, cable The Site (15 min) CLA, seabed topography, currents, data The Trials (15 min) RFP requirements, recovery, redeployment Q and A - (1hr) 3

Objectives: 1. To enhance confidence that we understand the site and the effects of turbines on the environment. 2. Develop Canadian expertise in tidal site characterization 3. Develop the infrastructure, equipment and techniques to reliably: A. Characterize and monitor high flow sites B. Assess the interaction of turbines on its surroundings 4

Infrastructure: A recoverable platform - A cabled node - Removable instrument bay - Serviced by moored surface vessel 2 to 3 times a year 5

Project Plan: Today Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Phase 1: Definition Phase 2: Preliminary Design and Trials Phase 3: Design/Build Marine Trials Phase 4: Integration Data Cable Install Phase 5: Install 2012 2013 2014 6

Status: Preliminary Design Phase 2 Risk Studies: Operations Assessed highest risk Stability Data Cable Float Release Mechanism 7

Next Steps: Operational Trials Marine Trials: Retire risks associated with operations to the greatest extent possible Demonstrate: Mooring Recovery ROV demonstration? 8

Next Steps: Cable Deployment Install Data Cable: also serve as deployment test cable for medium voltage cables 9

FORCE Crown Lease Area One of the most powerful in the world 7000 MW in Minas Passage 2500 MW estimated safely extractable straight flowing currents, speeds over 5 m/s pushing 14 billion tonnes of water on avg. 10

FORCE Test Area 11

12

Berth Site ADCP Data Collection 14

Site D ADCP Data September 2011 Current Direction Spring Tide Ebb Ebb Neap Tide Operations Window 15

Slack Water at FORCE Courtesy of Dr. Richard Karsten and Dr. Joel Culina Acadia Tidal Energy Institute 16

Site D ADCP Data September 2011 Current Direction Spring Neap Spring Neap 17

18

Relevant Information Environmental Assessment Report including all appendices and 2010 addendum ADCP Data Sets and Summary Reports 400kHz and 600kHz high F sampling Sonar Surveys 2m and.4m multibeam.025m side scan Meteorological Report Seabed photos and video 19

Marine Services RFP: Conduct sea trials to verify deployment concepts. Components: Part 1: Engineering Study Part 2: Sheltered Harbour Trial Part 3: Minas Passage Trial

Part 1: Engineering Study A detailed mooring plan backed up with an engineering analysis Identify deck equipment and mooring arrangement Describe the process to control the mooring lines and position the vessel ( geometry described in App 3) The engineering study will validate assumptions in anchor size Installation and recovery plan for the moorings FORCE will validate the analysis conducted via 3 rd party engineering consultant 21

Part 2: Sheltered Harbour Trials Test Float Recovery Device Refine recovery/deployment procedures Evaluate deck layout Validate positioning of the vessel on mooring Training Conduct near home port (mutually agreed location) Assets should test actual equipment to be used (mooring may be scaled back) Data cable to be simulated with 1.25 wire rope and DMA 22

Part 3: Minas Passage Trials Trial will be conducted at neap tides.for safety mooring should be able to hold through 10 knts. Recovery will be done around slack water. Assess performance of float release in high flow. Float submergence is critical factor. Validate mooring plan and test positioning control in high flow Evaluate marine asset performance Validate recovery/deployment procedures in high flow Training Data cable to be simulated with 1-1.25 wire rope and DMA 23

RFP Schedule 10 Apr: Bidders Conference 26 April: RFP submission deadline 06 May: Begin shortlisted candidates presentations 10 May: Notification of successful contractor 31 May: Contract Award Summer: Sheltered Harbour + Minas Passage Trials Contract to be awarded in phases based on performance and results on each phase. 24

Safety and Risk Management Contractors Safety System will be provided to FORCE for review 15 days after initial contract award Inspection of certifications and vessel surveys will be conducted prior to Part 2 and Part 3 FORCE will develop node recovery procedures Contractor will develop transit plan and mooring procedure Joint risk review process Part 2 and Part 3 Risk management plan developed for each phase 25

The Sensor Platform -The FORCE Science Node will be replaced by a Sea Trial Node Base for the marine trials. -The two nodes are physically the same 4.1 m Physical Specifications Summary 4.5 m x 4.1 m x 1.0 m Weight in air 10 tonnes Weight in water 8.7 tonnes 4.5 m 26 1 m

Tension Control - Recovery must be accomplished with this cable attached. - Tension force on this cable is not to exceed 4500 Kg. - For the trials a wire rope will be used to simulate the data cable. 27

Node Recovery Procedure - When ready for recovery, the Node will release a float that pulls a 60m messenger line to the surface. - The messenger line is attached to the main lift line that is attached to the main lift point of the Node. - It is left to the contractor decide how best to safely retrieve the buoy and lift line and to recover the node to the ship deck for servicing. 28

Float Release Mechanism - The lift line for the Node is contained within the Node itself in the Float Release Assembly. Main lift points 29

Float Release Mechanism - The Float Release Assembly contains the lift line, float, and release mechanisms. Acoustic Release Lift Line and drum Float Main Lift Points Solenoid Release 30

Stage 1: Initial Positioning and Lift Line Recovery - When ready for recovery, the float can be released from a shore station signal or if that fails, by an acoustic release activated from the vessel. - The Watch Area diagram is overlaid here for reference. 31

Stage 2: Recovering the Node - The vessel must be able to be repositioned in order to not exceed the maximum allowable tension force on the cable. Lift line lead angle will be key indicator. - Cable tensions max : 4500kg ideally b/t 500-1000 kgs. 32

Stage 3: Node on Deck - Once on board, proper cable tension must be maintained. Ideally redeployed in same tidal cycle. However, trials will validate ability to maintain tension over multiple tidal cycles. Tension monitor will be applied. - Node will also be secured. 33

Servicing the Sensor Platform - NOT REQUIRED FOR SEA TRIALS - The Instrument Node is replaced with abandonment pod and will require a crane in order to lift them in and out. A crane will be required to swap out the instrument pods. 34

Redeployment - The recovered lift line can be used to launch the serviced Node once it is ready and an acoustic release is attached. - Deployment requires the proper SDC tension to be maintained. - The vessel will have to be repositioned as the Node is deployed in order to maintain the proper tension. 35

Redeployment - Any deck tie downs removed prior to luffing overboard. - Vessel to reposition as node deployed to seabed - All procedures and personnel to adhere to marine and safety best practices. 36