Sidewalk Task Force. Presented By: Date: Don Dey, Transportation Engineer. January 26, 2007

Similar documents
ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements

12/4/2016 VIA . RE: Grocery Outlet Del Paso (DR16-328)

Citywide Sidewalk and Crosswalk Programs

IMPLEMENTATION STRATEGIES

4/14/2017 VIA . Miriam Lim, Junior Planner City of Sacramento Community Development Department 300 Richards, 3 rd Floor Sacramento, CA 95811

TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY

9/21/2016 VIA . RE: The Knot (DR16-270)

AMERICANS WITH DISABILITIES ACT TRANSITION PLAN LEON COUNTY FOR CURB RAMPS AND SIDEWALKS DEPARTMENT OF PUBLIC WORKS. 1 P age

This page intentionally left blank.

HYATTSVILLE TRANSPORTATION PLAN. City Council Update March 19, 2018

TRAFFIC CALMING POLICY & PROCEDURES

7/23/2017 VIA . Michael Hanebutt City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811

11/28/2016 VIA

S.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project

ADA TRANSITION PLAN. For

RE: Park Plaza Walgreens (P12-016)

ADA TRANSITION PLAN 2013

What Is a Complete Street?

8/31/2016 VIA . RE: Freeport Arco Fuel Station (P16-039)

City of Ann Arbor Pedestrian Safety & Access Task Force

Pavement Management Report. City Council Meeting of May 21, 2013

CITY MANUALS AND STANDARDS REVIEW

PEDESTRIAN ACTION PLAN

Draft. Lecompton. Table of Contents. Background

2015 Florida Main Street Annual Conference. Complete Streets Equal Stronger Main Streets

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

Town of Wakarusa. Americans with Disabilities Act Transition Plan: Pedestrian Facilities in the Public Right-of-Way

Tonight is for you. Learn everything you can. Share all your ideas.

Ballston Station Multimodal Study WMATA and Arlington County. Meeting Minutes

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

DOWNTOWN MIAMI PEDESTRIAN PRIORITY ZONE

Governance and Priorities Committee Report For the July 2, 2015 Meeting

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

Memphis Walkability Toolkit

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS

Final Sidewalk Feasibility Study

City Sidewalk Repair and Replacement Program

6/22/2018 VIA . Darcy Goulart, Planning Manager City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670

City of Birmingham Draft Multi-modal Transportation Plan

Closing Plenary Session

Traffic Calming Policy

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

STATUS OF 2009 PEDESTRIAN MASTER PLAN (AS OF DECEMBER 2013)

DRAFT. Lecompton. Table of Contents. Background

Sidewalk Cafe City of St. Petersburg City Code Chapter 16, Land Development Regulations

General Design Factors

Town of Roseland. Americans with Disabilities Act Transition Plan: Pedestrian Facilities in the Public Right-of-Way

City of Los Angeles. Presentation on Sidewalk Vending

3/20/2015 VIA . Teresa Haenggi, Associate Planner Community Development Department 300 Richards Blvd. Sacramento, CA 95811

CITY OF SAINT JOHN TRAFFIC CALMING POLICY

5/7/2013 VIA . RE: University Village Safeway Expansion (P13-019)

DPW Order No:

Memo. Introduction. Memphis STP Pedestrian Sidewalk Project

Village of Lyons. Americans with Disabilities Act Transition Plan: Pedestrian Facilities in the Public Right-of-Way.

Town of Bourbon. Americans with Disabilities Act Transition Plan: Pedestrian Facilities in the Public Right-of-Way

MEMORANDUM TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR SUBJECT: CONSIDERATION OF RESTRICTING PARKING ADJACENT TO 170 AND 171 BRISCO ROAD

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

ACTIVE TRANSPORTATION

Corporate. Report COUNCIL DATE: May 25, 1998 NO: R1500 REGULAR COUNCIL. TO: Mayor & Council DATE: April 27, 1998

Roosevelt Estates Neighborhood Improvements


Chapter 5. Complete Streets and Walkable Communities.

Uptown West Neighbourhood Transportation Study

Bicycle and Pedestrian Plans and Improvements

WELCOME. Thank you for joining us at the Second Public Workshop for the Carlsbad Pedestrian Master Plan. We look forward to receiving your feedback.

10/30/2012 VIA

Scenarios. The following slides will show existing pictures that deny access, followed by a retrofitted picture that provides access.

Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013

6/14/2013 VIA . Evan Compton, Associate Planner Community Development Department City of Sacramento 300 Richards Blvd Sacramento, CA 95814

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION

11/3/2014 VIA . WALKSacramento has reviewed the Stockton and T Mixed-Use project at 3675 T Street in the

complete streets design and construction standards public primer City of Edmonton

Draft North Industrial Area-Wide Traffic Plan

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007

Pedestrian, Bicycle and Traffic Calming Strategic Implementation Plan. January 18, 2011

Pedestrian Project List and Prioritization

David Hung, Associate Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA

PRESS RELEASE San Joaquin Council of Governments

POLICY: TRAFFIC CALMING

CITY OF ELKO BICYCLE AND PATHWAY PLAN

CITY OF PAPILLION, NEBRASKA

C/CAG. Sunnybrae Elementary School Walking and Bicycling Audit. San Mateo-Foster City School District JUNE 2013

Land Use Bicycle Spaces Required Type Residential

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS

INDEPENDENCE TRAFFIC SAFETY COMMISSION REGULAR MEETING. Wednesday, June 21, 2017

10/8/2014 VIA . RE: CVS Pharmacy (P13-002) Revised August 2014

CLOSED. The draft concept design has been broken down into 5 categories for the purpose of this survey:

TRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO

July 5, Arthur R. Ware, Jr. Elementary School 2017 Safe Routes to School Walkabout Report

Chapter 5: Crossing the Street

TRAFFIC CALMING TOOLBOX. For the residents of the City of Decatur, Georgia

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD

San Jose Transportation Policy

Complete Streets Design Considerations. Second Street Corridor Complete Streets Workshop and Assessment Manchester, NH April 26, 2013

5/31/2016 VIA . Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811

TRANSPORTATION BENEFIT DISTRICT NO. 1 MINUTES OF THE BOARD OF DIRECTORS MEETING

Bicycle-Pedestrian Master Plan: Chapters 3 and 4 Distribution

PEDESTRIAN CROSSING TREATMENTS

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION

Transcription:

Sidewalk Task Force Presented By: Don Dey, Transportation Engineer Date: January 26, 2007

Introduction Task Force members Meeting Schedule Special Guests Sidewalks Causes & Priorities Sidewalk Maintenance Program Public Outreach Funding Legal / Liability ADA Sidewalk Enhancement Program Legal issues Funding Other ADA Recommendations Sidewalk Gap Closure Enhancement Program Issues Funding Questions

Sidewalk Task Force Members Technical Representatives Armenia Jensen - Engineer Brad Bannister - Real Estate Rick Brandini - Arborist Tim Day - Planning Commission Al Signorotti - 50/50 sidewalk program Don Dey - Transportation Manager Local Citizens Bob Dillon Vicki Laze Marilyn Mitri Walter Schinke Mary Yates

Meeting Schedule/Guests Meetings held once a month from March to October, 2006 Special Guests included: March 20 th - Mayor Al Pinheiro Task Force Welcome and Council Direction April 17th - Marcus Beverly (ABAG) Sidewalk Liability June 19 th Dr. Larry Costello (U of C Extension) Arborist

Meeting Schedule/Guests (cont.) Special Guests included: July 17 th Jay Baksa (City Administrator) Financial Budget August 21 st Jeff Holm & Karen Bobo (FHWA) ADA requirements September 18 th Jolie Houston (City Attorney) Legal

Causes Causes & Priorities The main cause of sidewalk damage is tree roots. Improper street trees placed in inadequate parkway space. Root Damage Eighth Street Church Street south of Tenth Street Ninth Street

Causes (cont.) Causes & Priorities

Priorities Causes & Priorities Recommendations are for a first come first serve basis Could give priority to the primary streets corridors first (expressways, arterials, collectors) Could give priority to the streets in the immediate vicinity of a school (up to ½ mile) first

Priorities (cont.) Causes & Priorities Root Pruning Pop Outs Root Pruning Pop Outs

Sidewalk Maintenance Program Sidewalk Maintenance Program - $4.6 million Items to Address Public Outreach Funding Legal/Liability

Sidewalk Maintenance Program Public Outreach Recommend a public outreach program that makes property owners aware of their responsibility to maintain sidewalks Recommend that Community Service Operations implement an aggressive program with root pruning for those properties where tree roots may become a problem Recommend that Community Service Operations prepare a brochure and widely advertize the tree root pruning service. The brochure should be enhanced with diagrams / pictures that illustrate root pruning g and root barrier systems Recommend that Community Services Operations continue to work with property owners to identify the most appropriate trees for the parkway space available Suggest Engineering hire a summer intern to inspect all City sidewalks each year and report the repair needs to the property owner.

Sidewalk Maintenance Program Funding Continue the 50/50 sidewalk maintenance program funding level at no less than $250,000 per year. Recommend that this program be open to all property owners (residential and commercial) and that the program funding should only include sidewalk repair and associated tree removal/ replacement. Recommend that City seek other Federal, state, Regional funding sources to pay for repair of damaged sidewalks or missing sidewalk sections. Recommend that property owners be required to repair sidewalks to t current City standards when a property is sold or transferred. This T program would not have a maintenance cost cap. Recommend that the property owner could NOT seek financial assistance from the 50/50 sidewalk program less than 90 days prior to the sale of the property. This means that the property owner must get their name on the 50/50 list at least 90 days prior to the sale of the property. Property betterments such as sidewalk gap closures or curb ramps are not part of the sidewalk maintenance requirement.

Sidewalk Maintenance Program Legal/Liability Approve a City ordinance that limits City liability for failure to maintain sidewalks. This places greater responsibility for maintaining aining the sidewalk on the property owner. ABAG has identified that the City can NOT completely transfer liability if City requires the installation of street trees. Initiate a City practice of notifying a property owner of substandard sidewalk maintenance and request that the property owner repair the damaged sidewalk. If the property owner does NOT repair the sidewalk (the issue is older residents on fixed income or very low l income families), the City has the option to either repair the sidewalk s and lien the property or record a notice against the property to be activated at the time of sale. City may also give further cost consideration for citizens over 62 years old. A process for consistency needs to be established for consistency when this City practice get initiated.

ADA Sidewalk Enhancement ADA Sidewalk Enhancement Program - $3.3 million Items to Address Legal Issues Funding Other ADA Recommendations

ADA Sidewalk Enhancement Legal Issues Federal standards adopted in 1992 control the removal of all barriers riers on public facilities for the circulation of pedestrians with physical disabilities. Under Federal standards sidewalks in public right of way are a public facility. Federal standards require the construction n of curb ramps at intersections to remove the physical barrier caused by a street curb if a sidewalk is present. Recommend that curb ramps be constructed at all street corners (this complies with the federal mandate for ADA accessibility) It is recommended that the City place high priority on cross-town routes (arterials and collectors) to be constructed first. Local streets would be a second level priority. Recommend that all deficient curb ramps that do NOT meet ADA slope and landing standards be upgraded to meet new ADA standards. The property owner would responsible for repairing / updating the curb ramp if it is in need of maintenance repair. The City would be responsible if it was simply an upgrade to the existing design.

Funding ADA Sidewalk Enhancement Recommend that the City allocate $200,000 per year to construct new curb ramps where currently no ramp exists. This would remove the current backlog in approximately 16.5 years (in 2006 dollars).

ADA Sidewalk Enhancement Other Recommendations Recommend the removal of obstacles in the sidewalk path of travel (ADA standards require a minimum sidewalk unobstructed clearance width of four (4) feet. This width should NOT be encroached by newspaper racks, street light poles, fire hydrants, trees, traffic sign posts, public telephones, etc.). First Street was noted as particularity bad for obstacles in the sidewalk. This would be a high priority corridor. Recommend that parking restrictions (red curbs) a minimum of 15 feet be painted in advance of all marked and unmarked crosswalks (street intersections) for better pedestrian sight visibility. The specific issue noted was the difficulty of drivers and pedestrian to see each other around parked cars. Those most at risk are pedestrians s in wheel chairs, pedestrian with walkers or pedestrians pushing strollers. Priority corridors are the City s s arterial and collector streets. Recommend that the City hire an ADA expert Recommend that the City establish an ADA Review Committee

Sidewalk Gap Closure Sidewalk Gap Closure Enhancement Program - $1.1 plus million Items to Address Funding Issues

Sidewalk Gap Closure Funding Recommend that the City program at least $30,000 per year for gap closure projects

Issues Sidewalk Gap Closure Construct sidewalk where the sidewalk is discontinuous (gap in sidewalk s network), which is generally a path of pedestrian travel leading from a residential or office development to government service, commercial or medical facilities. Initiate a City practice of notifying a property owner of sidewalk gaps and requesting the property owner to install the missing sidewalk. If the property owner does NOT construct the missing sidewalk, the City has the option to either construct the missing sidewalk and lien the property or record a notice against the property Require all new development to install sidewalks along their property perty frontage to City standards. There is no City requirement to install sidewalks in an industrial area. City currently conditions the installation of sidewalks in industrial areas when discretionary approval by a property owner is requested Some notable areas include the Murray Avenue corridor and location on where medical offices move into industrial buildings Require the construction of sidewalks in industrial area where no sidewalks currently exist

Sidewalk Task Force Questions