CHEROKEE COUNTY ROADWAY CAPITAL PROGRAM MANAGEMENT PROJECT STATUS REPORT October 1, 2018
CONSTRUCTION STATUS MONTHLY REPORT 10/2018 Project Description Contractor East Cherokee Dr at Old Hwy 5 Notice to Proceed Estimated Completion Date Current Contract Amount Earned to Date % Complete Intersection Improvements CMES, Inc. 2/15/2017 5/15/2018 $ 2,827,747.10 $ 2,713,786.85 96% Project complete. Status East Cherokee Dr at Gaddis Rd/Chadwyck Ln Roundabout Baldwin Paving Company, Inc. 6/12/2017 12/8/2017 $ 1,525,985.38 $ 1,561,678.52 102% Project complete. Hickory Rd at Stringer Rd/ Carriage Ln Intersection Improvement and Traffic Signal Installation Glosson Enterprises 9/5/2017 9/30/2018 $ 1,228,961.00 $ 914,030.40 74% Contractor working on correction items. Countywide Traffic Signal Upgrade and Timing Project; PI 0013135 Traffic signal upgrades at 37 intersections - GDOT funded GTG Traffic Signals, Inc. 1/17/2018 7/15/2018 $ 517,877.35 $ - 0% Approximately 56% of the intersections have been upgraded with new signal heads, new traffic signal cabinets and flashing yellow leftturn arrows. Countywide Traffic Signal Signing and Striping Upgrade Project Signing and Striping upgrades at 37 intersections - County funded GTG Traffic Signals, Inc. 2/15/2018 5/15/2018 $ 239,418.00 $ - 0% 70% striping work completed. 100% concrete work completed. Signs still remaining to be installed. Work completed in conjunction with GDOT project. Bells Ferry Road at Ridge Road Intersection Improvement and Traffic Signal Installation Bartow Paving Company, Inc. 5/21/2018 11/16/2018 $ 1,037,585.36 $ 647,043.62 62% Project about 70% complete. Concrete work complete. Signal work to be completed mid October 2018. Final paving to be completed beginning November 2018. Batesville Road at Lower Birmingham Road Sixes Road at Wellstar Way (Gresham Mill Parkway) Intersection Improvement Bartow Paving Company, Inc. 7/23/2018 11/19/2018 $ 412,602.49 $ - 0% Traffic Signal Installation GTG Traffic Signals, Inc. 8/6/2018 12/3/2018 $ 154,000.00 $ 28,800.00 19% Clearing work and utility relocation have started. Storm pipe work to take place in October 2018. All signal poles have been installed. Signal to be in operation by end of October 2018. Page 2 of 7
CONSTRUCTION STATUS MONTHLY REPORT 10/2018 Project Description Contractor Notice to Proceed Estimated Completion Date Current Contract Amount Earned to Date % Complete Status John Tate Road cul-desac Reconstruct Cul-de-sac Bobby Tucker Trucking, Inc. 6/11/2018 9/8/2018 $ 144,384.37 $ 111,923.88 78% Paving completed. Contractor working on correction items. 2018 Resurfacing Project Resurfacing 17.3 miles of roadways Bartow Paving Company, Inc. 5/29/2018 11/24/2018 $ 3,535,309.87 $ 2,284,462.17 65% Contractor has paved 65% of roads. On schedule to complete project by end of November 2018. East Cherokee Dr at Tripp Road Intersection Improvement and Traffic Signal Installation Bartow Paving Company, Inc. TBD TBD $ 689,393.85 $ - 0% Awaiting contracts to be executed. Pre-Construction Meeting scheduled for November 1, 2018. CCWSA relocation work in progress. SR 140 at Lower Burris Rd/Puckett Creek Rd Intersection Improvements & Traffic Signal Installation TBD TBD TBD TBD TBD TBD Project includes installation of left-turn lanes and a traffic signal on SR 140 at Lower Burris Road and Puckett Creek Road. Bids to be received October 11, 2018. Stover Road Improve substandard County road and realign intersection with Univeter Road In-house by Roads & Bridges 100% Project complete. Brick Mill Road Reconstruction - SR 140 to Buford West Way In-house by Roads & Bridges 45% Grading and re-alignment complete. Concrete curb, gutter and driveway apons complete. Stone base 50% setup. Paving expected week of 10/1. Recreation Lane Rosewood Circle Garland Mountain Trail Pave unpaved portion of a County road Pave unpaved portion of a County road Pave unpaved portion of a County road In-house by Roads & Bridges 100% Project complete. In-house by Roads & Bridges 10% In-house by Roads & Bridges 40% All utility conflicts to be resolved by 10/5/18. Base preparation and grading complete. Paving expected week of 10/15. Page 3 of 7
PRE-CONSTRUCTION STATUS MONTHLY REPORT 10/2018 Project Description Consultant/Designer Earney Road Hames Road Roadway Reconstruction - Old Country Place to Capital City Club property Roadway Reconstruction - SR 92 to Jamerson Road; includes roundabout at S. Jett Road intersection Proposed Letting Date American Engineers, Inc. (AEI) Winter 2019 Atwell Group (LAI) TBD Design / Pre-Construction Status Updating utility plans, erosion control plans and quantities to prepare plans for bidding. Right-ofway acquisition is complete - verification of current owners still needed. Will need temporary construction easements from adjacent property owners; plans being updated with new right-of-way information. Project design is approximately 90% complete and under review. Right-of-way and construction easements still to be acquired. Designer addressing latest comments from Engineering. R/W Parcels (closed/req'd) 18/44 0/52 Comments Project includes reconstruction of Earney Road from Old Country Place to Capital City Club Project includes reconstruction of Hames Road from SR 92 to Jamerson Road, including the installation of a roundabout at the intersection of Hames Road and S. Jett Road. Curb and gutter and sidewalk will be installed along the entire length of Hames Road. East Cherokee Dr at SR 140 (PI 0013368) Intersection Improvements & Traffic Signal Modification AMEC, Inc. & Moreland-Altobelli Assoc, Inc. (MAAI) Fall 2019 Plans updated to meet current GDOT standards. GDOT approved ROW plans. Appraisal preparation and review in progress. Utility certification complete. All comments from GDOT FFPR have been addressed. Right-of-way acquisition to proceed once appraisals are approved by GDOT. Designer and appraiser still working on some cost to cure issues for appraisals. 0/22 Project includes providing right-turn lanes on all quadrants of intersection. GDOT has committed to fund $1,000,000 of construction cost dependent upon approval of environmental document. NEPA document approved 5-18-17; Utilities certified 4/2018. East Cherokee Drive at South Holly Springs Rd/Thornwood Dr. Intersection Improvements AECOM Winter 2019 Construction and right-of-way plans complete. Plans being updated to meet current GDOT and EPD ES&PC standards. Updated Traffic Signal Warrant Study completed - intersection still does not warrant a traffic signal installation. ACOE permit received on 10/16/2017. Right-of-way acquisition in progress. 0/15 Project includes providing left-turn lanes and deceleration lanes on East Cherokee Drive for both South Holly Springs Road and Thornwood Drive. SR 140 at Darnell Road Intersection Improvements BM&K Construction & Engineering, Inc. TBD Design is being reviewed by County. All utility companies have located their facilities that are in conflict. Plans submitted to GDOT for review. 0/6 Project includes adding left-turn lane from westbound SR 140 to Darnell Road. Canton Road Sidewalk Project (PI 0012601) Installation of sidewalk on west side of Canton Road from Cobb Co line to Stockwood Drive Moreland-Altobelli (MAAI) Fall 2018 Project revised to include 5 ft sidewalk vs 6 ft sidewalk to minimize utility relocations and right-ofway acquisitions. Revised concept report approved by GDOT on 12/21/2017. Parcel appraisals being updated to reflect recent plan changes. Appraisals approved by GDOT. Notice to proceed with Right-of-way acquisition issued on 5/2/18. 13/16 Project is 80% federally funded, designed per GDOT PDP. Concept report has been approved. Bells Ferry Road South of Steels Bridge Road Trickum Road at Wagon Trail/Trickum Hills Dr Intersection Improvements - Improve sight distance on NB approach to Bells Ferry Rd/Steels Bridge Atwell Group (LAI) Construction and right-of-way plans complete. Project on hold. Plans will need updating. intersection Intersection Improvements Keck & Wood, Inc. Construction and right-of-way plans complete. Project on hold. Plans will need updating. Project includes providing a center left turn lane for both side roads. Page 4 of 7
PRE-CONSTRUCTION STATUS MONTHLY REPORT 10/2018 Project Description Consultant/Designer Bells Ferry Road - Southfork Way to Victoria Road (PI 0013526) Proposed Letting Date Widening from 2 to 4 lanes VHB, Inc. 2022 Design / Pre-Construction Status GDOT restarted design phase. Survey is complete. Logical termini approved by FHWA in May 2017. Public Information Open House held in April 2018. Consultant reviewing and responding to comments received at PIOH. R/W Parcels (closed/req'd) 141 Comments GDOT design and construct. County to acquire right-of-way. Project limit revised to end at Victoria Road. GDOT is proposing to use HB 170 funds for construction. Bells Ferry Road over Little River/Lake Allatoona (PI 0013525) Bridge Replacement Project VHB, Inc. 2020 GDOT restarted design phase. Survey is complete. Updated concept report has been submitted to GDOT. Working with ACOE and marina owners regarding permitting needs and impacts to marina operations. Public Information Open House held in April 2018. Consultant reviewing and responding to comments received at PIOH. 1 GDOT design and construct. County to acquire right-of-way. GDOT working to bid with Bells Ferry Road project. County will look at possibility of advanced acquisition of restaurant parcel. Bells Ferry Road at Kellogg Creek Road and Victory Drive Towne Lake Area Multi-use Path Intersection Improvement - Design Southeastern Engineering, Inc. (SEI) 2019 Multi-use Trail - Design Moreland-Altobelli (MAAI) Fall 2018 Heard Road Extension Scoping Study VHB, Inc. Field surveys are complete. Public Information Open House held in April 2018. Plans update per new traffic count information and comments received at PIOH. Field surveys are complete. Designer working on concept layout. Designer completing Phase I - Towne Lake Hills South Dr to Towne Lake Hills East/West Dr. Consultant has completed preliminary alignment and is working on details and cost estimate. Concept with new typical section and project phasing has been submitted to the County for review. Intersection improvement(s) to improve traffic flow at the Bells Ferry Road/Kellogg Creek Road/Victory Drive intersection(s). Project also includes improving horizontal alignment on Victory Drive in vicinity of Patriots Park. Current curve does not meet standards for posted speed limit. Multi-use trail along Parkside Lane and Towne Lake Parkway, from Towne Lake Hills South Drive to Bells Ferry Road. Will be constructed in phases. Scoping study to determine project scope, schedule and budget. Determine path for potential roadway and right-of-way needs. Determine environmental permitting requirements and potential utility conflicts. Noonday Creek Trail Extension Scoping Study Heath & Lineback Engineers Cobb County has approved alignment to Noonday Park. Revised concept report submitted to GDOT on 12/15/2017. Federal funds have been awarded for design, right-of-way and construction phases. City of Woodstock to solicit RFP's for design services in Fall 2018. Scoping study to determine feasibility of extendin Noonday Creek Trail from SR 92 south to Shallowford Road/Noonday Park in Cobb County. County is the project manager - City of Woodstock is funding project. Little Road Widening and improvements - Hickory Road to Vaughn Road Moreland-Altobelli (MAAI) TBD Preliminary plan comments have been addressed. Plan revisions continue as a result of right-of-way negotiations. Right-of-way acquisition complete. Plans being revised to address right-of-way acquisitions. Completed Plans originally designed in-house. An EPD stream buffer variance and an ACOE Nationwide permit for stream impacts have both been obtained in summer 2014. Union Hill Road - Bridge over Canton Creek Bridge replacement/upgrade project Heath & Lineback Engineers 30% plans received in September 2018. Geotechnical work scheduled for October 2018. Project includes replacement of substandard bridge on Union Hill Road over Canton Creek. Union Hill Road - Bridge over Mill Creek Bridge replacement/upgrade project Heath & Lineback Engineers Field surveying in progress. Geotechnical work scheduled for October 2018. Project includes replacement of substandard bridge on Union Hill Road over Mill Creek. Lower Dowda Mill Road - Bridge over Sharp Mountain Creek Bridge replacement/upgrade project Heath & Lineback Engineers Field surveying in progress. Geotechnical work scheduled for October 2018. Project includes replacement of substandard bridge (one lane - wood deck) on Lower Dowda Mill Road over Sharp Mountain Creek Page 5 of 7
PRE-CONSTRUCTION STATUS MONTHLY REPORT 10/2018 Project Description Consultant/Designer Wrights Mill Road Hunter Trail/Hunter Road Widen, improve and resurface a substandard width roadway Widen, improve and resurface a substandard width roadway BM&K Construction & Engineering, Inc. Southeastern Engineering, Inc. (SEI) Proposed Letting Date Design / Pre-Construction Status Designer is looking at improvements at both ends of the project - up to Wrights Mill Court from south and Wright Mill Way from north. Construction plans 95% complete. Designer working on completing right-ofway plans. Designer updating the final plans with utility comments and has submitted plans to County for review. Right-of-way acquisition authorized on 10/4/2018. R/W Parcels (closed/req'd) 0/12 0/19 Comments Project includes improving vertical alignment and pavement widening of Wrights Mill Road to bring it up to current County standards. Project includes bringing Hunter Trail/Hunter Road up to current County standards. S. Cherokee Lane Improve a substandard County roadway BM&K Construction & Engineering, Inc. Construction plans have been submitted to the County for review. Project includes improving horizontal and vertical alignment on 3,000 feet of substandard roadway. Martin Lane Widen and pave a substandard width roadway In-house design In-house Right-of-way agent has visited all property owners. Approximately half support project and are willing to donate right-of-way. The other half are opposed to widening. Based upon results of right-of-way acquisitions, it is recommended that we pave this roadway as-is and achieve maximum pavement width within existing right-of-way. Kellogg Creek Road at Jacobs Road Toonigh Road Trickum Road - Sycamore Lane to Belles Lane Trickum Road - Gunnin Road to Barnes Road Univeter Road at Pinecrest Road Univeter Road at New Light Road Woodstock Road at Victory Drive Wiley Bridge Road at Cox Road Lower vertical curve at intersection with Jacobs Road Lower vertical curve at Deerfield Drive Southeastern Engineering, Inc. (SEI) In-house design In-house In-house Awaiting utility companies to locate and redesign their facilities on the latest construction plans. Rightof-way acquisition authorized on 10/1/2018. Plans are complete. Minimal right-of-way and easements required. Installation of a center left-turn lane Arcadis Project kick-off meeting scheduled for 10/24/2018. Installation of left-turn lanes Arcadis Project kick-off meeting scheduled for 10/24/2018. Intersection Improvement Intersection Improvement and Traffic Signal Installation Roundabout Roundabout MaesAwyr, LLC Southeastern Engineering, Inc. (SEI) Southeastern Engineering, Inc. (SEI) Southeastern Engineering, Inc. (SEI) Project kick-off meeting to be scheduled for end of October. Project kick-off meeting to be scheduled for end of October. Project kick-off meeting to be scheduled for end of October. Project kick-off meeting to be scheduled for end of October. 0/6 Project includes improving vertical geometry on Kellogg Creek Road to improve visibility at Jacobs Road intersection and approach to 90 degree curve. This improvement will improve sight distance at approach to Blalock Road. Roadway improvements include installation of a center left-turn lane for entire length and installation of sidewalk along the west side of the corridor. Consultant will evaluate the corridor and make a recommendation as to the best solutions and configurations for a proposed typical section - including left-turn lanes, operational improvements and sidewalk. Project includes intersection realignment and installation of a left-turn lane on Univeter Road at Pinecrest Road. Project includes intersection realignment and installation of a left-turn lane on Univeter Road at New Light Road and the installation of a traffic signal. Intersection improvements that include the installation of a roundabout. Intersection improvements that include the installation of a roundabout. Copper Creek Drive Sidewalk Installation of sidewalk on the east side of Copper Creek Drive Keck & Wood, Inc. Project kick-off meeting to be scheduled for end of October. This project includes the construction of sidewalk along the east side of Copper Creek Drive, between Sixes Road and Garnet Court. Page 6 of 7
PRE-CONSTRUCTION STATUS MONTHLY REPORT 10/2018 Project Description Consultant/Designer Proposed Letting Date Design / Pre-Construction Status R/W Parcels (closed/req'd) Comments Trickum Road at SR 92 Intersection Improvement Project TBD Federal funds have been awarded for right-of-way and construction phases. County is soliciting for engineering design services. Intersection improvements project to include dualleft-turn lanes and receiving lanes on northbound and southbound Trickum Road approaches to SR 92. Also includes reconfiguration of Trickum Road at Gunnin Road intersection. 575 at Towne Lake Parkway Interchange Operational Improvements Scoping Study TBD Federal funds have been awarded for additional scoping studies/concept report development. County is soliciting for engineering design services. Scoping study to determine project scope, schedule and budget to program possible State funds and future SPLOST funds. 575 at Ridgewalk Parkway Interchange Operational Improvements Scoping Study TBD Federal funds have been awarded for additional scoping studies/concept report development. County is soliciting for engineering design services. Scoping study to determine project scope, schedule and budget to program possible State funds and future SPLOST funds. Rhine Road Right-of-way Research In-house Engineering. In-house Complete. Roper Road Right-of-way Research In-house Engineering. In-house Complete. McCurley Road Right-of-way Research In-house Engineering. In-house Complete. Collett Drive Right-of-way Research In-house Engineering. In-house Complete. Old Jones Road Right-of-way Research In-house Engineering. In-house In-progress. Brown Road Right-of-way Research In-house Engineering. In-house In-progress. Rampley Trail Right-of-way Research In-house Engineering. In-house Complete. Gannt Road Right-of-way Research In-house Engineering. In-house In-progress. Lula Payne Trail Right-of-way Research In-house Engineering. In-house Complete. Westbrook Road Right-of-way Research In-house Engineering. In-house Complete. Page 7 of 7
HICKORY ROAD AT STRINGER ROAD INTERSECTION
BELLS FERRY ROAD AT RIDGE ROAD INTERSECTION IMPROVEMENT
JOHN TATE ROAD CUL-DE-SAC PROJECT
2018 RESURFACING PROJECT AT BALLGROUND HWY
BRICK MILL ROAD RECONSTRUCTION