Please find below the Town staff s responses to NCDOT s recommended roadway stipulations listed in a letter dated May 25, 2015.

Similar documents
Walton Acres at Riverwood Athletic Club Clayton, North Carolina

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016

Traffic Impact Analysis Chatham County Grocery Chatham County, NC

#!! "$% ##! &! # '#! % $ #!

ACCESS MANAGEMENT PLAN: BLUFFTON PARKWAY BLUFFTON PARKWAY: PHASE FOUR TOWN OF BLUFFTON & BEAUFORT COUNTY, SC

CHAPTER 3 STUDY AREA OPERATIONAL OVERVIEW

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC

Purpose: Financial Implications and Impact Statement: It is estimated that the cost to implement:

Traffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County

STATEOF NORTHCAROLINA DEPARTMENTOF TRANSPORTATION

MEMORANDUM. Our project study area included the following locations:

Harrah s Station Square Casino

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Co-ordinator Transportation Committee. Director, Mobility Services and Corporate Fleet Services Environment and Transportation Department

Appendix D: Concept Screening

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY

Figure 1: Vicinity Map of the Study Area

2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE

Traffic Impact Analysis (TIA) Process and Procedures Manual. September 2017

Shockoe Bottom Preliminary Traffic and Parking Analysis

Delaware Avenue Corridor Study

MoPac South: Impact on Cesar Chavez Street and the Downtown Network

King Soopers #116 Thornton, Colorado

IH 20 RANGER HILL PUBLIC MEETING

Route 29 Corridor Assessment Update. Development of Possible Solutions

TRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT

2016 Church Street Access Study. 100 Clinton Square 126 North Salina Street, Suite 100 Syracuse, NY

Traffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017

Preliminary Transportation Analysis

1. Provide a dedicated westbound approach bus lane at the intersection;

Traffic Academy: IJS & IMS FAQ/RULES OF THUMB

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017

MASER ASSOCIATES. Engineers Planners Surveyors TRAFFIC IMPACT ANALYSIS FOR PROPOSED RESIDENTIAL MULTI-FAMILY SEA GULL VILLAGE TOWNSHIP OF COLTS NECK

BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA

Appendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM

Washington St. Corridor Study

Date: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc.

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation

Recommended Roadway Plan Section 2 - Land Development and Roadway Access

South Albion-Bolton Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives

3.0 PROJECT DESCRIPTION

Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017

Brian McHugh, Buckhead Community Improvement District. SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project

Realignment & Intersection Improvement Alternatives for the Intersection of Lorain Road & Brookpark Road

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota

Grant Avenue Streetscape

FINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...

University Avenue & Farley Avenue/University Bay Drive Area Scenario Base Conditions Multiple concerns

WASHINGTON CITY TELEGRAPH ROAD & GREEN SPRINGS DRIVE INTERSECTION STUDY

Congestion Mitigation at IH 27 and U.S. Hwy 70 in Plainview, TX

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

MEMORANDUM. David Mohlenbrok, Environmental Services Manager

Stakeholder Focus Group Meeting #3 January 9, 2013 Cattlemens, 2000 Taylor Road, Roseville

CAPE COD COMMISSION 3225 MAIN STREET P.O. BOX 226 BARNSTABLE, MA (508) Fax (508) Transportation Safety Report

US-6 Spanish Fork Fact Finding Study. December 2017

Roundabouts Near At-Grade Railroad Crossings

University Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007

SH-6 Corridor Improvement Study Policy Committee Progress Report M O N D AY, J U N E 1 0, B R A Z O S C E N T E R

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Chapter 16: Traffic and Parking A. INTRODUCTION

Richmond-Adelaide Cycle Tracks

LSC TRANSPORTATION CONSULTANTS, INC. 516 North Tejon Street Colorado Springs, CO (719) FAX (719)

Let s Make I-40 Better Action Team. Friday, March 29, 2019 Hosted by RTP Foundation

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

SECTION 7 INVENTORY OF SELECTED INTERSECTIONS AND RECOMMENDATIONS FOR FURTHER STUDY

Roundabout Feasibility Memorandum

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study

QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017

Queensgate Drive Corridor Traffic Study

TRAFFIC ASSESSMENT River Edge Colorado

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio

CIRCLE DRIVE TRAFFIC AND ACCESS MANAGEMENT POLICY GUIDE. Management Principles and Implementation Concepts

I-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)

ROUTE 22 CORRIDOR STUDY: CORRIDOR MANAGEMENT PLAN APPENDIX A A-12

Practical Application of Turn Lane Design Criteria in Developing Suburban & Urban Corridors

FY 2006 TRANSPORTATION CAPITAL PROGRAM

Chapter 2: Standards for Access, Non-Motorized, and Transit

Station Plan: Penn & 43rd Avenue

Access requests to County streets and roadways are processed through one of the following methods:

APPENDIX I TRANSIT TRAVEL TIME SAVINGS

Traffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

WEST AND SOUTH WEST RING ROAD DOWNSTREAM TRAFFIC IMPACTS

4.0 TRANSPORTATION SYSTEMS

Traffic Study North Shore School District 112

ENKA INTERMEDIATE SCHOOL

Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County.

DUNBOW ROAD FUNCTIONAL PLANNING

Transcription:

TOWN OF CHAPEL HILL Public Works Department 6850 Millhouse Road Chapel Hill, NC 27516-8173 phone (919) 969-5100 fax (919) 969-2003 www.townofchapelhill.org TO: FROM: Chuck Edwards, NCDOT Division 7 District Engineer Kumar Neppalli, Traffic Engineering Manager SUBJECT: Obey Creek Development Improvements US 15-501 DATE: June 3, 2015 Please find below the Town staff s responses to NCDOT s recommended roadway stipulations listed in a letter dated May 25, 2015. I appreciate your willingness to provide a written response by email prior to the Public Hearing on June 8, 2015. Please let me know if you need additional information. US-15-501 and Market Street/Proposed Obey Creek Access Intersection Construction of dual exclusive southbound left turn lanes, each with 300' of full storage and appropriate tapers on US 15-501. Response: Obey Creek Applicant can accommodate this roadway stipulation, and would like to revisit and analyze the necessity of the second turn lane at the time of driveway permit application. Construction of a second exclusive eastbound left turn lane with 225' of full storage and appropriate tapers on existing Market Street Response: We believe that the Obey Creek Applicant is not responsible for this roadway stipulation. Initial investigation revealed that the existing ROW is not enough to accommodate this stipulation and the Town requests that NCDOT consider removing this condition. Town will work with NCDOT to look other measures as the Park and Ride Lot development occurs. Provision of a minimum 250' protected internal stem length prohibiting parking and left turn maneuvers on existing Market Street and appropriate internal intersection configurations to avoid adverse impact to US 15-501. Response: Town will work with NCDOT to implement this measure if feasible and as Park/Ride Lot development occurs.

Closure or relocation of the proposed frontage street connection to beyond the limits of the protected internal stem length on existing Market Street. Response: Town will work with NCDOT to implement this measure if feasible and as Park/Ride Lot development expansion occurs. Construction of an exclusive northbound right turn lane with 300' of full storage and appropriate deceleration taper on US 15-501. Response: Obey Creek Applicant agreed to construct this roadway stipulation. Construction of dual ingress lanes and three egress lanes consisting of an exclusive left turn lane, an exclusive through lane, and an exclusive right turn lane, each with 300' of full storage on the Obey Creek site access. Response: Obey Creek Applicant agreed to construct this roadway stipulation with the exception of 300 of full storage on the Obey Creek site access. Obey Creek Developer and NCDOT agreed to review the internal storage requirement. Provision of a minimum 300' protected internal driveway stem length prohibiting all turning and parking maneuvers on the Obey Creek site access and appropriate internal intersection configuration to avoid adverse impact to US 15-501. Response: Obey Creek Developer and NCDOT agreed to review the internal storage requirement and protected stem design configurations. Modification of existing traffic signal to accommodate the new intersection geometry with consideration of appropriate timing plans to maximize efficiency in both peak and off peak periods with preferential signal timing and progression provided to US 15-501. US 15-501 and Sumac Road/Obey Creek Access Intersection: Construct dual exclusive southbound left turn lanes, each with 375' of full storage and appropriate tapers on US 15-501 Response: Obey Creek Applicant can accommodate this roadway stipulation, and would like to revisit and analyze the necessity of the second turn lane at the time of driveway permit application. Construct an exclusive northbound left turn lane with 400' of full storage and appropriate tapers on US 15-501. Response: Obey Creek Applicant agreed to construct this roadway stipulation. Construct and exclusive northbound right turn lane with 300' of full storage and appropriate deceleration taper on US 15-501

Response: Obey Creek Applicant agreed to construct this roadway stipulation. Provide a single ingress lane and three egress lanes consisting of an exclusive left turn lane, an exclusive through lane, and an exclusive right turn lane, each with 250' of full storage on existing Sumac Road. Response: Town agreed to consider this stipulation and discuss with NCDOT as the Park and Ride Lot development expansion occurs. Provision of a minimum 250' protected internal driveway stem length prohibiting all turning and parking maneuvers on existing Sumac Road and appropriate internal intersection configuration to avoid adverse impact to US 15-501. Response: Town and NCDOT agreed to review this stipulation as the Park and Ride Lot development expansion occurs. Closure or relocation of the proposed frontage street connection beyond the limits of the internal protected stem on existing Sumac Road. Response: Town and NCDOT agreed to review this stipulation as the Park and Ride Lot development expansion occurs. Provide dual ingress lanes and three egress lanes consisting of an exclusive left turn lane, an exclusive through lane, and an exclusive right turn lane, each with 300' of full storage on the proposed Obey Creek Access. Response: Obey Creek Applicant agreed to construct this roadway stipulation. Obey Creek Developer and NCDOT agreed to review the internal storage requirement. Provision of a minimum of 300' of protected internal driveway stem length prohibiting all turning and parking maneuvers on the proposed Obey Creek Access. Response: Obey Creek Developer and NCDOT agreed to review the internal storage requirement and protected stem design configurations. Closure or relocation of the proposed frontage road connection beyond the limits of the internal protected stem. Response: Obey Creek Applicant can accommodate this roadway stipulation, and would like to revisit and further analyze the design of the frontage road at the time of driveway permit application. Construct new traffic signal to accom1nodate the new intersection geometry with consideration of appropriate timing plans to maximize efficiency in both peak and offpeak periods with preferential signal timing and progression provided to US 15-501.

Dedication/Reservation by the Applicant: The Department's consultant, Stantec, has recently completed a corridor traffic analysis repo1i for US 15-501 from NC 54 to US 64. The purpose of the study was to evaluate the existing (2013) and future year (2040) operations in regards to the corridor's ability to acco1nmodate anticipated future growth. The study evaluated both "superstreet" and improved traditional intersections. The study identified that, in the 2040 scenario, "superstreets" provided the best operation for both the main-line as well as side streets, but also indicated that main-line operation in the subject area could be expected to operate acceptably using traditional intersections with the addition of a third through lane on US 15-501 in both directions. In order to accommodate the identified improvements directly attributable to site traffic impacts and to provide for the anticipated future improvement necessary for acceptable operation in the long range planning period, the applicant shall: Dedicate any needed right of way to accommodate required road improvements listed above and also adjust site plan to reserve sufficient right of way along the project frontages to accommodate a future third through lane on both directions of US 15-501. Response: Obey Creek Applicant agreed to reserve sufficient width along its property frontage to accommodate an additional future through lane. NCDOT has acknowledged that the requirement for dedicated right turn lanes into the Obey Creek would not be required if the additional through lanes are added in the future. The Town and/or other developer will work with NCDOT to reserve/dedicate the ROW required on west side of US 15-501 as future development occurs. Alternative Improvements NC 86 (Columbia Street)/NC 54 (Fordham Blvd.) Interchange: Upon further evaluation by the development team members, construction of the westbound loop ramp as recommended in the HNTB traffic analysis has been determined to be beyond the ability of the applicant due to identified substantial potential impacts to adjacent properties and right of way needs beyond his control. As such the loop project is best pursued through the State Transportation Improvement Program (STIP) process. Based on information provided in the HNTB traffic analysis, the development team me1nbers have identified extension of turn lane storage on the existing westbound off ramp as a feasible and reasonable alternative to address identified traffic queuing and operation issues in the short term. As a condition of the pending driveway permit, the applicant shall extend the existing dual left turn lane storage along the full extent of the existing westbound off ramp to accommodate queue lengths identified in the 2022 build scenario of the traffic study. Response: The Town will extend the existing pavement markings to extend the queue length of the left turn lanes as feasible within the existing pavement. The Town staff will coordinate this work with NCDOT and we would like to complete this work in July, 2015. The draft TIP 2016-2025 included several improvements to the westbound ramp (U-5304-D/E) and the improvements are scheduled to be constructed in 2023. The Town and NCDOT will work at the June 16 th project scoping meeting to finalize further details on this TIP project.

Previous Requirements and Conditions: All other requirements and conditions included in my previous correspondence dated September 26, 2014 and listed below for ease of reference remain unchanged and applicable. Proposed US-15-501 and Site Access #1 Intersection: NCDOT concurs with the study recommendations to eliminate this access due to proximity to the Dogwood Acres Drive signalized intersection. Proposed US-15-501 and Site Access #2 Intersection: NCDOT is agreeable to connection of the proposed restricted right-in/right-out access subject to: Construction of an exclusive northbound right turn lane with 150' of full storage and appropriate deceleration taper on US 15-501. Construction of a single ingress lane and a single right turn-only egress lane with a minimum of 100' of full storage on the site access. Provision of a minimum of 150' of protected internal driveway stem length prohibiting all turning and parking maneuvers on the site access. Response: Obey Creek Applicant can accommodate this stipulation, and would like to revisit and further analyze the design of the frontage road at the time of driveway permit application. Closure or relocation of the proposed frontage road connection beyond the limits of the internal protected stem. Response: Obey Creek Applicant can accommodate this stipulation, and would like to revisit and further analyze the design of the stem length at the time of driveway permit application. Proposed US 15-501 and Site Access #5 Intersection: NCDOT is agreeable to the proposed connection subject to: Construction of an exclusive northbound right turn lane with 150' of full storage and appropriate deceleration taper on US 15-501.

Construction of a single ingress lane and a single right turn-only egress lane with minimum of 1OO' full storage on the site access. Provision of a minimum 100' protected internal driveway stem length prohibiting all turning and parking maneuvers on the site access. Response: Obey Creek Applicant can accommodate this stipulation, and would like to revisit and further analyze the design of the stem length at the time of driveway permit application. US 15-501 and Culbreth Road/Mt. Carmel Church Road Intersection: In consideration of existing geometric and right of way constraints at this location, NCDOT concurs with the TIA recommendation to reconfigure the westbound Mount Carmel Church Road approach to provide dual exclusive right turn lanes and a combination through/left turn lane and optimize signal timing as a feasible approach to enhance existing operation and mitigate anticipated impacts of site traffic at this intersection. As a condition of the pending driveway permit, the applicant shall reconfigure the intersection geometry as recommended and modify and optimize existing signal as needed to accommodate the new configuration.