Culpeper District Albemarle County Monthly Report Special Issues FY Revenue Sharing Program - If you wish to participate in the Revenue Sharing Program for the fiscal year starting July 1, 2012, applications are due November 1, 2011. Please see attached letter from Mike Estes dated August 9, 2011. Preliminary Engineering PROJECT Route 53 Safety Project Shoulder Widening 0.4 Mi E. of Monticello Loop Route 53 Safety Project Shoulder Widening 0.06 Mi E. of Monticello Loop Route 53 Safety Project Intersection Improvements at Route 20 Route 708, Dry Bridge Route 53 Safety Project Intersection Improvements at Route 729 Route 616, Black Cat Route 677, Broomley Route 637, Dick Woods Bridge Replacement over Ivy Creek Route 250, Bridge replacement over Little Ivy Creek LAST MILESTONE Design Public Hearing Project Scoping Project Scoping -- NEXT MILESTONE Right of Way September 2011 Summer 2011 Project Scoping AD DATE May October March 2014 December 2014 December 2014 Page 1 of 5
Preliminary Engineering Cont. PROJECT LAST NEXT MILESTONE MILESTONE Route 762, Rose Hill Church Lane, Unpaved Route 704, Fortune Lane, Unpaved Route 672, Blufton, Unpaved Route 608, Happy Creek, Unpaved Brocks Mill, Rural Addition -- Project Scoping Spring 2012 Route 774, Bear Creek, Unpaved 2016 Route 703, Pocket Lane, Unpaved 2016 Dates to be determined following evaluation of Scoping Team comments. AD DATE Construction Activities Georgetown (NFO) 0656-002-254, C501 Scope: 5 wide Pedestrian Facility with Crossing and Resurfacing with Refuge Islands. Next Major Milestone: SBL scheduled to reopen August 24 th to meet school opening date Contract Completion Date: September 23, 2011 Meadow Creek Parkway 0631-002-128, C502, B612, B613, B657 Scope: Grade, Drain, Asphalt, Utilities, Signals, Landscaping and Bridges. Next Major Milestone: Complete major construction items by August 25 th. Landscaping will not be completed until October. Contract Completion: October 14, 2011. I-64 Eastbound Shadwell Exit (FO) 0064-002-815, N501 Scope: Widen Ramps and Improve Signals. Next Major Milestone: Project complete Contract Completion Date: December 2, 2010 Jarmins Gap (NFO)0691-002-258, C501 Scope: Grade, Drain, Asphalt Pave, Planting and Utilities. Next Major Milestone: closed beginning August 29 th for approximately 60 days to facilitate box culvert installation. Landscape Architect and Engineers are working with HOA Committee on revisions to Old Trail/Jarmins Gap Stormwater Management Facility Contract Completion: September 21, 2012. Page 2 of 5
Construction Activities Bridge Deck Repair and Polymer Overlay (NFO) 0250-002-798, N501 Scope: Patch deck and epoxy overlay on the Route 250 Bridge over the Rivanna River. Next Major Milestone: Complete project. Contract Completion Date: July 29, 2011. Bridge Deck Repair and Polymer Overlay (NFO) 0029-002-044, N501, N502 Scope: Patch decks and epoxy overlay on the Route 29 Bypass over Route 29. Next Major Milestone: Complete project. Contract Completion Date: August 20, 2011. Slurry Seal Schedule SS7A-967-F11, P401 Scope: Slurry Seal various subdivisions in Albemarle Co. Next Major Milestone: Complete, pending possible additional work. Contract Completion Date: October 1, 2011. Bridge Repairs (NFO) BRDG-967-040, N501 Scope: Bridge Repairs - District Wide (Term 2). Next Major Milestone: Completion of Term 2 Work. Contract Completion Date: 7, 2012. Plant Mix Schedule (NFO) PM7A-967-F11, P401; PM7B-967-F11, P401 Scope: Plant Mix Southern Culpeper District. Next Major Milestone: Completion. Contract Completion Date: December 1, 2011. Plant Mix Schedule PM7K-967-F11, P401 Scope: Plant Mix (Secondary Routes in Albemarle, Greene, and Louisa Counties) Southern Culpeper District. Next Major Milestone: Completion. Contract Completion Date: December 1, 2011. Pipe Rehabilitation (NFO) BRDG-967-045, N501; BRDG-967-062, N501 Scope: Pipe Rehab in (Culpeper, Louisa, Madison, Albemarle, Fauquier, Orange, and Rappahannock Counties) Northern Culpeper District. Next Major Milestone: Executed, Begin Construction. Contract Completion Date: April 29, 2012. Guardrail Repair GR07-967-096, N501 Scope: Guardrail repairs District wide. Next Major Milestone: Preconstruction set for August 24, 2011. Contract Completion date: July 1, 2012. Page 3 of 5
Traffic Engineering Studies Completed Route 743, Hydraulic Intersection of Georgetown ; Installation of right on red arrow southbound on Hydraulic recommended and pending installation. Route 20, Scottsville At Calvary Baptist Church 7850 Scottsville ; safety study completed recommending installation of Watch for Turning Vehicles signs; No change in speed limit recommended. Sign installation pending. Route 600, Watts Passage from Route 641 to Route 20 Centerline pavement marking review completed recommending installation of centerline markings from Route 784 (Burnt Hill ) to Route 641 (Burnley Station ); Installation pending. Route 692, Plank at Route 693, Stillhouse Rd Safety review of intersection/ consideration of speed zone adjustment completed; recommendation for stop sign upgrade. Sign installation completed 4/18/2011. Route 626, Langhorn Rd/James River Rd Review of James River Heritage Trail bicycle route signage completed recommending installation of W11-1 Bicycle signs with W16-1P Share the plaques. Sign installation completed 6/26/2011. Route 743 Advance Mills area Review of tractor trailer truck advisory signs completed; no additional signage warranted. Route 810, Crozet Ave from existing 25 mph zone to north of Buck Speed study completed; no change in speed limit recommended. Route 250 from existing 45 mph zone west of Route 240 to four lane segment approaching I-64 Speed study completed; no change in speed limit recommended. Route 665, Buck Mountain from Route 601 (Free Union Rd) to Route 664 (Markwood Rd) Speed study completed; speed limit changed to 45 mph with curve warning signs; all signs installed 7/21/2011. Route 664/663, Buck Mountain from Route 665 Markwood Rd to Existing 35 mph zone - Speed study completed; no change in speed zone recommended Route 240, Crozet Ave at Route 1230 Meadows Drive Safety review of intersection completed; warning sign installation recommended pending installation. Under Review Route 706, Dudley Mtn from Route 631 (Old Lynchburg Rd) to Route 708 (Red Hill Rd) Speed study underway. Route 29 from Route 1575 (Austin Dr) to Route 763 (Dickerson Dr) Review of existing advance intersection and industrial intersection warning signs underway. Route 601 (Garth Rd) from Route 654 (Barracks Rd) to Route 601 (Free Union Rd) Review of roadway to determine potential for installation of Share the signs underway; subject of Route 614 from Route 601 (Free Union Rd) to Route 810 (Browns Gap Rd) Review of roadway to determine potential for installation of Share the signs underway; subject of Page 4 of 5
Traffic Engineering Studies cont. August, 2011 Route 676 (Owensville Rd) from Route 676 (Tilman Rd) to Route 614 (Garth Rd) Review of roadway to determine potential for installation of Share the signs underway; subject of Route 678 (Owensville Rd) from Route 250 (Ivy Rd) to Route 676 (Tilman Rd) Review of roadway to determine potential for installation of Share the signs underway; subject of Route 601 (Garth Rd) at Route 658 (Barracks Farm Rd) Intersection safety review study underway. Route 29 at Route 631 (Rio Rd) Review of EB approach stop bar for right turn lane underway; request from Delegate Bell. Route 637 (Dick Woods Rd) from I-64 interchange to Route 250 Review of roadway to determine potential for installation of centerline pavement markings underway; subject of Route 743 (Earlysville Rd) at Route 676 (Woodlands Rd) Safety review underway. Route 866 (Greenbriar Dr) at Route 1427 (Hillsdale Dr) Multi-way stop study underway. Routes 1670 (Ashwood Blvd), 1675 (Kendalwood), 1723 (Crosstimbers), 1737 (Watercrest) & 1720 (Timberwood Pkwy) Crosswalk study underway at multiple locations; subject of Routes 1765/1769, 1770/1769 & 1770/1771 Intersections in Fontana Subdivision - Multiway stop studies underway. Study also includes review of Routes 1765 (Fontana Dr) and Route 1771 (Verona Dr) for centerline and edge line pavement markings. Maintenance Activities State Force Maintenance Crews Have been working on storm cleanup. They are also mowing, cleaning Pipes and ditches, machining gravel roads, doing shoulder restoration, tree removal and applying dust control on various routes throughout the County. View memo re: FY Revenue Sharing Program Return to consent agenda Return to regular agenda Karen P. Kilby Programming/Investment Management Director Virginia Department of Transportation 1601 Orange Culpeper, VA 22701 Page 5 of 5