Safety Monitor Requirements. September 2012

Similar documents
Safety Monitor Requirements Revised. February 2018

Safety Monitor and Firm Gas Monitor Requirements. September 2008

Safety Monitor and Firm Gas Monitor Requirements. September 2007

Gas System Operator Incentives Initial Proposals Consultation 2011/12

Indiana Electricity Projections: The 2018 Forecast Update

Gas Interruptions. customer guide

NASCO Guidelines for the Management of Salmon Fisheries

Network Transmission System Gas Supply Emergency / Gas SCR Overview

Network Transmission System Gas Supply Emergency / Gas SCR Overview. Jenny Phillips

Order No. 55/18 CENTRA GAS MANITOBA INC.: PRIMARY GAS RATE APPLICATION, EFFECTIVE MAY 1, April 26, 2018

Exercise Yield Report

System Flexibility Indicators

WORKING GROUP ON STOCK ASSESSMENTS 5 TH MEETING DOCUMENT SAR-5-08 TARGET SIZE FOR THE TUNA FLEET IN THE EASTERN PACIFIC OCEAN

Amendment to Gas Quality NTS Entry Specification at the St Fergus NSMP System Entry Point

Rebalancing Global Crude Flows

Portuguese Market Outlook up to 2040

UK Energy Futures. Richard Smith Head of Energy Strategy & Policy

M A N I T O B A ) Order No. 123/13 ) THE PUBLIC UTILITIES BOARD ACT ) October 22, 2013

Connecting Coal Bed Methane to the NTS. Transmission Workstream 1 st July 2010

IMPACT & IMPLEMENTATION REPORT SUMMARY SECTION (For AEMO to complete and administer)

Progress with the Road Investment Strategy

ANNEX1 The investment required to achieve the Government s ambition to double cycling activity by 2025

2 FUSION FITTINGS FOR USE WITH POLYETHYLENE PRESSURE PIPES DESIGN FOR DYNAMIC STRESSES

Emerging Crash Trend Analysis. Mark Logan Department of Main Roads, Queensland. Patrick McShane Queensland Transport

Manufacturers continue capacity expansion as technology orders grow

Global Containerboard Outlook

PITCH IMPROVEMENT PROGRAMME

MARKET AND CAPACITY UPDATE. Matthew Marsh September 2016

Assessing Permeation of Gas through Polyethylene Pipe

Have You Ever Heard the Phrase

17-06 BFT RECOMMENDATION BY ICCAT FOR AN INTERIM CONSERVATION AND MANAGEMENT PLAN FOR WESTERN ATLANTIC BLUEFIN TUNA

2018 Annual Economic Forecast Dragas Center for Economic Analysis and Policy

Livestock and Dairy Market Outlook

Rebalancing Global Crude Flows

Increased Onboard Bicycle Capacity Improved Caltrain s Performance in 2009

Preliminary 2012 EAI Integrated Resource Plan (IRP) Action Plan

Gas National Transmission System. April Maintenance Programme. April March Draft Version 1.0

Water & Sewer Rate Study

Environment, Climate Change and Land Reform Committee. Environmental impacts of salmon farming. Written submission from Fisheries Management Scotland

European Commission. Harmonisation of BCS: Aggregation methods (business surveys) and Quality checking (consumer survey)

Projections of UK Oil and Gas Production. Click to edit. and Expenditure. Master title style. March Click to edit Master subtitle style

Energy Security: Markets and Policy

Liquefied Natural Gas: Current Trends and Future Directions

REPORT ON RED-LIGHT MONITORING SYSTEMS

CLUB AND TOURNAMENT HANDICAPPING

TECHNICAL NOTE THROUGH KERBSIDE LANE UTILISATION AT SIGNALISED INTERSECTIONS

Sulphur Market Outlook

Best Practice RBI Technology Process by SVT-PP SIMTECH

Control of Vibration at Work

Powered Lawn Mower Market in United Kingdom to Market Size, Development, and Forecasts

I HAVE A QUERY. Putting you in touch with the RIGHT people

Ensuring Reliability in ERCOT

Response to further information request Ministry of Education Notice of Requirement (200 & 252 Park Estate Road)

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)

NY Wind Overview and 2016 Operation

Seasonal Summary. For The Great Lakes. Winter

SUMMARY REPORT Q1/2015

Steel Market Outlook. AM/NS Calvert

The primary purpose of the TFF is to help promote a healthy farm tenanted sector in Scotland. It aims to fulfil this purpose by:

2018 Long Term Forecast

ANNUAL REVIEW OF INDUSTRY EXPERIENCE - FINAL REPORT AS OF DECEMBER 31, 2016 COMMERCIAL VEHICLES ALBERTA AUTO INSURANCE RATE BOARD 29 SEPTEMBER 2017

DRAFT for a State Policy for Healthy Spaces and Places

Appendix N(b): Portishead Station Outline Travel Plan

MISO Energy and Peak Demand Forecasting for System Planning

Section Three - Certificates of Description. Part One - Identity Classification. Part Two Vehicle Categories

Congestion Reduction in Europe: Advancing Transport Efficiency. MG Tackling urban road congestion D3.4

Energy Storage Market Forecast

4 th IEA-IEF-OPEC Symposium on Energy Outlooks. Riyadh, 22 January 2014

1.0 PURPOSE 2.0 REFERENCES

2009 Forecast for the Chicago CBD

GAZIFÈRE INC. Prime Rate Forecasting Process 2015 Rate Case

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

System Performance, Availability and Reliability Trend Analysis Portfolio Review 2016

It Was Never Going To Be Easy

BBL Reverse Flow project and implications for IP Bacton. Presentation to the UNC Transmission Workgroup 7 th June 2018

Pre Feasibility Study Report Citiwater Cleveland Bay Purification Plant

Municipal waste management in Cyprus

Advice June 2012

Proposal for a COUNCIL REGULATION

I HAVE A QUERY FOR GAS TRANSMISSION QUERIES ONLY FOR DOMESTIC GAS QUERIES, PLEASE CONTACT YOUR NETWORK OPERATOR

Beef & Cattle Market Outlook. Glynn Tonsor Dept. of Agricultural Economics Kansas State University

How to forecast in a cyclical industry?

Memorandum INTRODUCTION METHODOLOGY. Smart Growth. Bruce Robinson, Transport Advisor, Infrastructure Planning

Short and Medium-Term Oil Market Outlook. 13 th Shanghai Derivatives Market Forum - 25 May 2016

Pacific Gas and Electric Company Monthly Report On Interruptible Load and Demand Response Programs for June 2012

Variability in the tropical oceans - Monitoring and prediction of El Niño and La Niña -

SR 826/PALMETTO EXPRESSWAY EXPRESS LANES PD&E STUDY From US 1/SR 5/Dixie Highway to SR 836/Dolphin Expressway FPID No.: ETDM No.

TEP-UNS Electric Load and Peak Demand Forecast Overview

BMO Capital Markets 2014 Farm to Market Conference New York, New York. May 21, 2014

July Ballast Water Management FAQ

Sustainable Fisheries for Future Generations The Fisheries White Paper

CMM Conservation and Management Measure for the Management of New and Exploratory Fisheries in the SPRFMO Convention Area.

ITEM 2.3 South of Fraser Rapid Transit Surrey-Langley technology decision. That the Mayors Council on Regional Transportation receive this report.

Analysis of 2015 Trail Usage Patterns along the Great Allegheny Passage

Integrated Regional Traffic Management. Michael Aherne Technical Director POLIS Conference 2009

SEASONAL PRICES for TENNESSEE FEEDER CATTLE and COWS

Analysis of Highland Lakes Inflows Using Process Behavior Charts Dr. William McNeese, Ph.D. Revised: Sept. 4,

Safety Assessments Revised Toy Safety Directive 2009/48/EC

18 th May Global Steel Industry Trends: Is the perception the reality?

New Zealand Fisheries Assessment Research Document 98/21. Not to be cited without permission of the authork) Malcolm Clark

Transcription:

Introduction This document sets out Safety Monitors for the 2012/13 winter, pursuant to National Grid s obligations under the Uniform Network Code (UNC), Section Q. Safety Monitors were introduced in 2004 to replace the so-called Top-up monitors, which had existed (through the Network Code) since 1996. Safety Monitors define levels of storage that must be maintained through the winter period. The focus of the Safety Monitors is public safety rather than security of supply. They provide a trigger mechanism for taking direct action to avoid a potential gas supply emergency (as defined in the Gas Safety (Management) Regulations). Removal of obligation to publish Firm Gas Monitor Modification 0411S, Removal of the Obligation to Publish Firm Gas Monitor from the UNC was accepted by the Modification Panel on 21 June 2012 and was implemented on 13 July 2012. Hence the Firm Monitor requirement is no longer published. Safety Monitor Methodology It is our responsibility to keep the monitors under review (both ahead of and throughout the winter) and to make adjustments if it is appropriate to do so on the basis of the information available to us. In doing so, we must recognise that the purpose of the Safety Monitors is to ensure an adequate pressure can be maintained in the network at all times and thereby protect public safety. It is therefore appropriate that we adopt a prudent approach to setting the Safety Monitor levels. The concept behind the Safety Monitors is to provide sufficient gas in storage to support those gas consumers whose premises cannot be physically and verifiably isolated from the gas network within a reasonable time period. To achieve this all gas consumers are categorised into one of two groups: Protected by Monitor - Gas is held in storage to facilitate continuity of supply to these consumers even in a 1 in 50 winter Protected by Isolation Network safety would be maintained if necessary by physically isolating these customers from the network The storage deliverability Safety Monitor indicates the minimum level of deliverability required to both safely isolate loads that are protected by isolation and also support loads that are protected by monitor. The deliverability Safety Monitor is therefore providing operational cover should an emergency be called on any particular day, whilst the space Safety Monitor provides sufficient gas in store to support protected by monitor loads for the remainder of the winter. The level of the Safety Monitor is dependant on the level of non storage supplies (NSS) and therefore if the level of NSS reduces, the Safety Monitor will increase. This assessment is undertaken on a regular basis by National Grid throughout the winter period. - 1 -

Operation of Safety Monitors It is a requirement of National Grid s Safety Case that we operate this monitor system and that we take action to ensure that storage stocks (space) do not fall below the defined level. The level of storage established by the Safety Monitor is that required to underpin the safe operation of the gas transportation system. Its aim is to ensure the preservation of supplies to domestic customers, other non-daily metered (NDM) customers and certain other customers who could not safely be isolated from the gas system if necessary in order to achieve a supply-demand balance and thereby maintain sufficient pressures in the network. The space Safety Monitor defines the minimum level of stored gas required in aggregate in all UK storage, on each day of the winter. We monitor the level of gas in all storage facility types throughout the winter to ensure that the actual aggregate stock level does not fall below the space Safety Monitor level. If this were to occur, there would be insufficient gas left in storage to underpin the safe operation of the system in a 1 in 50 cold winter. Under these conditions, we would therefore be obliged by our Safety Case to take action to remedy this situation. In the lead-up to such a situation, we would advise the market with the objective of encouraging mitigating action. If necessary, however, the Network Emergency Co-ordinator (NEC) may require the relevant storage operators to reduce or curtail flows of gas out of storage. In this situation, we would expect the market to rebalance in order to achieve a match between supply and demand. We would continue to provide information to the market as the situation developed. For this winter we will continue to provide through our website a five day ahead view of the supply/demand balance, historic and forward projections of storage use and how these levels relate to the Safety Monitor requirements and the setting of the Gas Balancing Alert (GBA) trigger. The combination of relevant information and clarity of the remaining storage position should assist market participants in ensuring security of supply. While National Grid would seek to minimise the extent of any intervention in the market, the balance between allowing the market to resolve the situation and taking action via the NEC will clearly depend on the severity of the situation and the associated timescales. Approach to the Safety Monitor Levels This note is published in conjunction with the Winter 2012/13 Outlook Report, which contains more detailed coverage of our preliminary view of supplies for the coming winter. For winter 2012/13 there continues to be significant levels of uncertainty with respect to NSS levels, in particular with import supplies. We will continue to review the Safety Monitor levels throughout the winter and, if necessary, we will revise them to reflect material changes to the supply-demand balance. National Grid will continue to provide winter feedback to industry regarding supply assumptions and resulting changes to Safety Monitors by means of monthly updates via Operational forums and our reporting on our website. - 2 -

Supply Assumptions Figure 1 shows a simplified representation of how supply is forecast to meet demand for winter 2012/13. The data set to create this chart is from the past 5 winters with a weighting towards the most recent winters. The supply is broken down into three discreet areas, one of non storage supply (NSS), one of storage and an area in between where storage and NSS are both expected to contribute to some extent. Figure 1 Winter 2012/13 Simplified Representation of Supply The chart shows considerable variation in NSS, this is not surprising given the different winter conditions. In winter 2010/11, the level of NSS reached record levels in excess of 400 mcm/d as the headroom of capacity was utilised to a greater extent than in previous winters. Winter 2011/12 saw much lower demands with significantly lower NSS levels. For winter 2012/13 there is considerable uncertainty regarding the level of individual supply components, most notably LNG. For the winter security assessment central view on NSS, published within the 2012/13 Winter Outlook Report, we have used an NSS assumption based on a weighted rolling average of the last five years of NSS: this is shown by the blue line on the chart above. For the Safety Monitor calculation, which has a focus on public safety by maintaining adequate pressures within the network, it is prudent to assume a level of NSS which will be available throughout the winter, notably at times of high demand: this is set at 95% of the blue line. - 3 -

Within winter monitoring of actual NSS levels will enable us to determine whether the NSS v demand relationship used within the Safety Monitor calculation methodology is fit for purpose: if it is found not to be, it can be revised based on the latest information. Table 1 shows the anticipated availability of storage in winter 2012/13. Table 1 Storage Space and Deliverability Assumptions 1 Storage type Space (GWh) Deliverability (GWh/d) Short (LNG) 300 143 Medium (MRS) 10665 558 Long (Rough) 40000 485 Total 50965 1186 Demand Assumptions The basis for the calculation of the Safety Monitor levels is our 2012 demand forecasts for 2012/13, using a severe (1 in 50 cold) load duration curve. Our base case for demands assumes relatively low power generation. These could be potentially significantly higher if there is a shift in the relative economics of gas and coal fired generation, resulting in decreased use of coal and increased use of gas for power generation. Within day profiles for isolating various loadbands, such as power stations and large industrial loads are based upon operational experience of emergency exercises undertaken by National Grid. The profiles are reviewed and updated as new information becomes available, but as stated previously the Safety Monitor calculation has a focus on public safety, hence a prudent approach is taken to revising the isolation profiles. Safety Monitor Levels Table 2 shows the initial Safety Monitor requirements for space and deliverability. Table 2 Stored Safety Gas and Storage Safety Deliverability Requirement Assumed total storage space (GWh) Space Safety Monitor (GWh) Space requirement (%) Deliverability Safety Monitor (GWh/d) 50965 2359 4.6% 672 1 This table represents our operational assumptions and is based on proven performance. Reported deliverabilities may be different from name plate capacities. Space includes 814GWh of Operating Margins and excludes Hill Top Farm, which will be added when operational. GWh to mcm conversions assumes a CV of 39.6 MJ/m 3. - 4 -

Monitor Profiles Figure 2 shows the space profile for the Safety Monitor whilst Figure 3 shows the deliverability profile for the Safety Monitor. The objective of the Safety Monitor profile is to identify at any point in time the requirement for gas in store to underpin the safe operation of the gas transportation system for what remains of the winter period. The Safety Monitor allows for the possibility of late winter cold weather patterns based on analysis of historical temperatures. However, in the event of cold weather earlier in the winter, the profiles may be reduced to reflect the occurrence of cold weather. Figure 2: Space Safety Monitor 2500 2000 Space (GWh) 1500 1000 500 0 01-Oct 01-Nov 01-Dec 01-Jan 01-Feb 01-Mar Space (GWh) - 5 -

Figure 3: Deliverability Safety Monitor profile 800 700 Deliverability (GWh/d) 600 500 400 300 200 100 0 01-Oct 01-Nov 01-Dec 01-Jan 01-Feb 01-Mar Deliverability (GWh/d) Notes on Demand Assumptions National Grid forecasts both diversified demand and undiversified demand. The diversified peak day is the peak day for the whole country, whilst the undiversified peak day is the peak day for each area of the country added together. For planning and investing in the network, National Grid uses 1 in 20 peak day undiversified demand conditions (in addition to analysing other less severe weather conditions). This allows for the fact that there is no single profile of demand across the country associated with a 1 in 20 cold peak day, and therefore ensures sufficient transportation capacity is available to meet 1 in 20 demand under a range of conditions. For security planning including Safety Monitors, National Grid uses diversified demand forecasts, which is the appropriate basis for assessing the balance between supply and demand on a national basis. - 6 -