SPECIFICATION FOR THE INSTALLATION OF CURED IN PLACE RESIN SLEEVE FROM MANHOLE TO MANHOLE. (TOWN LINER)

Similar documents
SECTION ACCEPTANCE TESTING FOR SANITARY SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS

SECTION PRESSURE TESTING OF PIPING

P-04 Stainless Steel Corrugated Hoses and Metal Bellows Expansion Joints

TECHNICAL DATA. Q= Cv S

VACUUM TESTING PRECAST CONCRETE MANHOLES

TECHNICAL DATA. Q = C v P S

TECHNICAL DATA 3 MODEL G-3000 DRY VALVE RISER ASSEMBLY

pvc well casing & drop pipe

TECHNICAL DATA Q = C. v P S. 2 Model G-2000 Dry valve. Page 1 of 13

Operating Procedures for GripTight 15.5 SDR & IPS Test Plugs

Installation and Operating Instructions for Automotive Winch Synthetic Rope

CLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD. 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems.

PNEUMATIC STOPPERS OPERATING MANUAL. Type F G H - FOG

CIPP For Large-Diameter Pressure Pipes. Andrew Costa Aegion Corporation

Safety. April 2018 Supersedes all previous publications 2018 Chevron Phillips Chemical Company LP

FIBERGLASS MANHOLES SANITARY SEWER LINES

BASIC REQUIREMENTS FOR FIBER REINFORCED PLASTIC (FRP) TYPE 3FC COMPOSITE CYLINDERS

NATURAL GAS MAINTENANCE. Part 192 Subpart "M"

Bermad Pressure Reducing. Model: 42T

Spray Gun 134-A. 1 Liter High- Pressure Gel Coat. Usage Instructions & Parts List

The purpose of this task is to prevent damage from occurring to the pipe or it s coating when backfilling an exposed pipeline.

GENERAL GUIDELINES FOR PROPER RIGGING PRACTICES AND INSPECTION & REMOVAL CRITERIA FOR SLINGS PER OSHA

22. Specialty Valves.

Instruction Manual. PE-25/32/37 Tapping Machines. POLYTAPP Valves

STANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL)

Standard Pneumatic Test Procedure Requirements for Piping Systems

Appendix C Field Testing of Pipelines

CLASS DH - PNEUMATIC TESTING - GREATER THAN 1 BAR (15 PSIG)

TECHNICAL MANUAL 4'' END PORT PRESSURE VESSEL. Lenntech. Tel Fax.

Vacuum Bagging Wings Instruction Manual Purdue University

COMMON PRECAUTIONS Data Sheet - Be Sure To Read Before Handling Page 1 of 6

Liquefied gas cargo tanks and process pressure vessels

Water Hammer In Irrigation Systems 1

APPENDIX B TESTING PROTOCOLS. Method A: Straight Test Method B: Angular Deflection Test. Method C: Shear Load Test

Composite Pilings. For A Lasting Foundation

Proof load is the load applied in performance of a proof test. Proof test is a nondestructive tension test performed by the sling manufacturer or an

Casing Design. Casing Design. By Dr. Khaled El-shreef

IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC PURPOSE

EMERGENCY PIPE REPAIR

HYDROSTATIC LEAK TEST PROCEDURE

BS Series Basket Strainer

CHEMICAL. Straight cut rod is provided in the materials listed below and includes nuts / washers.

OPERATION MANUAL NTF-15

DBML-60/80 Squeeze Tool

WSC Performance Standard and Recommended Installation Procedures for Sanitary Water Well. Pitless Adapters, Pitless Units, And Well Caps

HCMTCB MATERIALS SAMPLING & TESTING PERFORMANCE CHECKLIST

3 GALLON, OILLESS PANCAKE COMPRESSOR INSTRUCTIONS. Item #31289

For use in Natural Gas & Liquefied Petroleum Gas Applications

INTRODUCTION TABLE OF CONTENTS

American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM

SECTION 25 TESTING AND DISINFECTING WATER MAINS General

Casing Spacer Technology Leaders

PRESSURE RETEST. 49 CFR, (g) Co#: Vin#: DOT Spec: MAWP:

DESIGN DATA A WET PIPE BLADDER TANK FOAM/WATER SYSTEM WITH HYDRAULICALLY ACTUATED DELUGE CONCENTRATE CONTROL VALVE

Copyright, 2005 GPM Hydraulic Consulting, Inc.

Testing Procedures of Watertight Compartments

Model 7989T Steel Pipe Squeezer Sch. 40 & Sch. 80. Operations Manual

FLAMMABLE GASES AND FLAMMABLE CRYOGENIC FLUIDS

product manual HM-4140, HM-4150, HM-4160 HM-4160A HM-4150 Humboldt FlexPanels

WAVE CYBER HANDLING &

SAFETY MANUAL FOR FLAMMABLE PRODUCT TRANSFER

Lockout / Tag out Program

Flange Bolt Torquing. for Resistoflex Plastic-Lined Piping Products. Torquing. Retorquing. Hydrotesting. Annual retorquing

General Performance Data Hose Ref Minimum Bend. Safety Pressure at 20 C (BAR) Working Pressure at. Flow Rate at 3 bar (lit/min) Working Pressure

1 Exam Prep. Tabs and Highlights

OPERATING PROCEDURES

Warning: NEVER ALTER TEST EQUIPMENT

O&M Receiving and Inspection. Storage of Water Treatment Media

TECHNICAL DATA. Q = C v P S

Allspeeds Ltd. Royal Works, Atlas St Clayton le Moors Accrington Lancashire England BB5 5LW. Tel +44 (0)

DESIGN DATA OBSOLETE. C. Inspections - It is imperative that the system be inspected and tested on a regular basis. See Inspection

Dean Pump Self-Priming Chemical Process Pumps

Date of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1

ROPV R40 E Series User Manual

Installation, Operation and Maintenance Instructions for Pacific PA Non-Storage Heat Exchanger

ob or Customer: Engineer: Contractor: Submitted by: Approved by: Order No: Specification: Installed Date: 1 1/2" 4" 1/8 Bend PVDF 1 1/2" 4" Caps PVDF

Installation, Operation & Maintenance Manual for Flo-Max Coupler Bracket Model FM150

OPERATION MANUAL NTF-60 Plus

ACCU-PULSE Installation and Operation Instructions

PASSENGER SHIPS Guidelines for preparation of Hull Structural Surveys

GETZ EQUIPMENT INNOVATORS PART No. 4G59678 CARBON DIOXIDE MINI PUMP FOR EXTINGUISHER SERVICE (Revised )

Evaluating Surge Potential in CSO Tunnels

3" UC Ultra-Chuck Durable Lightweight Air Inflated Bladder Chuck Operation/Repair Manual. (76.2 mm) DOUBLE E COMPANY, INC.

Sterile Visual Flow Indicator

RST INSTRUMENTS LTD.

User Information Sheet 024

Vessels subject to External Pressure

DVS Technical Codes an Bulletins

Inflatable Packer Single & Double. Single & Double Packer Dimension. Wireline Packer. Water Testing Packer (WTP) Packer

Inert Air (N2) Systems Manual

T e l N o : F a x N o : E m a i l : a i s h c m c - m e. c o m w w w. c m c - m e.

TECHNICAL DATA. Page 1 of 12

RE: PROPANE SYSTEM & REGULATOR TESTING/INSPECTION PROCEDURE

Auto-Rewind Hose Reels INSTRUCTION MANUAL FOR OXY-LPG MODEL

Installation Guideline for Placing Fiber Optic Cable into an Underground Duct

San Antonio Water System Standard Specifications for Construction ITEM NO. 841 HYDROSTATIC TESTING OPERATIONS

AcornVac Vacuum Plumbing Systems - Trouble Shooting Guide

Subsea Safety Systems

OCEAN DRILLING PROGRAM

Transcription:

CI Code: 2391/AB/211 SPECIFICATION FOR THE INSTALLATION OF CURED IN PLACE RESIN SLEEVE FROM MANHOLE TO MANHOLE. (TOWN LINER) Intent It is the intent of this specification to provide for installation of up to 300 feet long tubular resin impregnated sleeve, affixed to the walls in the middle of a main sewer pipe run, starting from one manhole to another manhole or to a blind outfall, upstream or downstream General The method involves the impregnation of an absorbent carrier material; the inversion of the material into the pipe, the curing of the sleeve leaving behind a hard plastic sleeve mechanically bonded to the host pipe. Reference specification Tensile strength ASTM-D638 Flexural Strength ASTM D-790 Flexural Modulus ASTM D-790 Chemical Resistance ASTM D 543 Industry Specifications ASTMF- 1216- Standard Practice for Rehabilitation of Existing Pipelines and Conduits by the Inversion and Curing of a Resin Impregnated Tube The carrier material The carrier material shall be of fibrous absorbent composition tailored to achieve the following 1. Allow the migration of resin from its internal structure by compressing to a thickness of less than 90% of its uncompressed thickness under a pressure 1psi 2. The material must consist of non degradable fiber's such as polyester or polypropelene or Corrosion resistant fiberglass. 3. The material must have an abrasion resistant, chemically resistant, fully bonded coated surface in the lateral portion to ensure that on curing a smooth surface free from blemishes, pinholes or loose non wetted fibers. 4. Where fiberglass is used a surface veil or a layer of felt must be used to act as barrier to prevent osmosis or wicking of the strands. 5. The carrier material must be resistant to the resin used and must withstand any installation forces without losing its integrity. The resin The resin must be a thermosetting resin cured by either heat or chemically via the use of accelerators, or any other safe energy source which does not involve the use of electical current within the main sewer, unless where evidence can supplied of the intrinsic safety. The resin must give give sufficient working time above ground to enable impregnation of the fabric, but must cure to sufficient hardness to carry overburden loads within a maximum of 8 hours from time of insertion inside the pipe. The resin used must have resistance to most chemicals to be found within a sewer system. As a minimum it must have resistance to the following chemicals at the following temperatures Chemical Resistance The resin must be resistant to the chemicals likely to be within the pipe and as a minimum must be resistant to the chemicals below. The test is done in accordance with ASTM D 543. Exposure should be for a minimum of one months at 73.4F. During this period the CIPP test specimen should lose no more than 20% of its initial flexural strength and flexural modulus when tested in accordance with Section 8 of this practice. Chemical Solution Tap Water (ph 6-9) 100% Nitric Acid 5% Phosphoric Acid 10% Sulfuric Acid 10% Gasoline 100% Characteristics of the Repair Sleeve Starting Point: Length in Main Pipe: Time for cure Thickness: Concentration From D/S or U/S manhole Up to 300 feet 3 hours at 110 deg F 6mm or 7.5mm 68 North Biesecker Road, Thomasville, PA 17364. Tel: 888 639 7717. Fax: 240 465 1199.Email: info@easy-liner.com

Resin Carrier Combination The resin and the carrier fabric when cured must meet the following minimum criteria Testing Method ASTM- D 790 Flexural Strength Flexural Modulus Testing Visual Inspection 4500 psi 250 000 psi On completion of the work a CCTV survey should be carried out and the repairs must be verified as per below 1. There should be no evidence of water ingress within the liner. 2. The sleeve should be watertight internally.where bends or other pipe deformities are present the maximum wrinkling allowed is 3% of the pipe diameter. Pressure Testing If required by the owners bid documents, testing may take place by placing two push rod plugs to the beginning and the end of the sleeve. Air is fed into the isolated area and pressure losses are monitored. Test criteria and acceptable losses to be determined in advance by the engineer in consultation with the contractor Design Considerations The design is based on the assumption of a partially deteriorated pipe. The CIPP is designed to support the hydraulic loads due to groundwater, since the soil and surcharge loads can be supported by the original pipe. The groundwater level should be determined by the purchaser and the thickness of the CIPP should be sufficient to withstand this hydrostatic pressure without collapsing. The following equation may be used to determine the thickness required: P= 2KE L. 1.C 1 - v 2 (SDR - 1) 3 N where: P = groundwater load, psi (MPa), K = enhancement factor of the soil and existing pipe adjacent to the new pipe (a minimum value of 7.0 is recommended where there is full support of the existing pipe), EL = long-term (time corrected) modulus of elasticity for CIPP, psi (MPa) n = Poisson s ratio (0.3 average), SDR = standard dimension ratio of CIPP, C = ovality reduction factor = [1-0.01q/ (1+ 0.01q) 2 ] 3 q = percentage ovality of original pipe = 100 x (Mean Inside diameter - Minimum Inside Diameter) Mean Inside Diameter Using this formula we derive the following tables Diameter Thickness Max Pressure Head (inches) (mm) ft 8 6 40 10 6 20 12 6 11 15 7.5 14 The table is based on K = 7, E = 125,000 psi (50 year strength figure), v = 0.3, C=0.64 (ie 5% ovality) and N=2 Hydraulic Design Considerations A CIPP liner can reduce the inside pipe diameter and may affect flow in small diameter pipes, but the reduction is usually more than offset by the improved flow characteristics. These compare favorably with an existing concrete pipe s high Manning flow coefficient of about 0.015 or corrugated pipe Manning flow coefficient of 0.024. Reduced flow is insignificant in oval sewer pipes. Area reduction is only 0.6% at 5% ovalization and 2.4% at 10% ovalization The analysis may be done using the Manning Equation 68 North Biesecker Road, Thomasville, PA 17364. Tel: 888 639 7717. Fax: 240 465 1199.Email: info@easy-liner.com

Brief description Method statement The pipe must be clean and free from debris, encrustation and standing water. Using a camera measure the length of felt tubing required. Insert the fibre liner tube into a bladder tube. Mix the resin and hardener required and pour the required amount of resin into the tube. Attach a Vacuum pump to the other end of the tubes and feed the material through the nip roller, spacers and conveyor system. Adjust the speed of impregnation to ensure thorough wet out on both top and bottom. Carefully wind the fibre liner.bladder combination into the tank ensuring tension at all times. Turn the trailing end of the bladder back on to the nose cone. Strap the tubes to the cone using a ratchet strap. Introduce regulated compressed air (Max 6psi) to the tank and allow sufficient bladder tubing to extrude out. Deflate the tubing by venting out the air. Tuck in the tubing into the pipe run. Switch on the compressor and allow the pressure to build up to 6psi by holding the winding arm. Gradually unwind the arm at a speed that maintains 6psi pressure till the bladder tubing is fully everted into the pipe and comes out at the required termination point or the downstream manhole. Connect the boiler to the shaft of the tank and introduce warm water at the prescribed temperature whilst allowing the air to escape through the relief valve. Continue introducing warm water till the water level backs up to a level just above the crown of the pipe. Leave the combination of tubes till the felt tube cures Once cured puncture the bladder tube at the upstream end next to where it is clamped on the pipe. Slowly rewind the arm of the tank to un-invert the bladder tube thus forcing water out into the manhole.

Brief description Method statement The pipe must be clean and free from debris, encrustation and standing water. Using a camera measure the length of felt tubing required. Mix the resin and hardener required and pour the required amount of resin into the tube. Attach a Vacuum pump to the other end of the tube and feed the material through the nip roller, spacers and conveyor system. Adjust the speed of impregnation to ensure thorough wet out on both top and bottom. Carefully wind the felt liner into the tank ensuring tension at all times. Turn the trailing end back on to the nose cone. Strap the tube to the cone using a ratchet strap. Introduce regulated compressed air (Max 6psi) to the tank and allow sufficient felt tubing to extrude out. Deflate the tubing by venting out the air. Tuck in the tubing into the pipe run. Switch on the compressor and allow the pressure to build up to 6psi by holding the winding arm. Gradually unwind the arm at a speed that maintains 6psi pressure till the felt tubing is fully everted into the pipe comes out at the downstream manhole. Deflate the felt tubing and disconnect it from the tank. Load the bladder gun with sufficient bladder tubing. Switch on the compressor and allow the pressure to build up to 4psi by holding the winding arm. Feed the bladder into the deflated felt tube. Gradually unwind the arm at a speed that maintains 4 psi pressure till the adequate amount of bladder tubing corresponding to the length of felt tube is everted into the pipe. Connect the boiler to the shaft of the tank and introduce warm water at the prescribed temperature whilst allowing the air to escape through the relief valve. Continue introducing warm water till the water level backs up to a level just above the crown of the pipe. Leave the combination of tubes till the felt tube cures Once cured puncture the bladder tube at the upstream end next to where it is clamped on the pipe. Slowly rewind the arm of the tank to un-invert the bladder tube thus forcing water out into the soil. Once the bladder is retrieved, trim the ends of the

Preparatory Procedures Cleaning of the Main Pipe The manhole to manhole section of main pipe must be free debris, obstructions, scale or any other material that reduces the effective bore of the pipe or loose material which may be pushed forward by the inversion process. If inverting upstream, provision needs to be made for reducing the flow to no more than 15% of the bore of the pipe Prerepair survey A videotaped survey must be done on the main run with a pan and tilt camera to confirm the proposed repair falls within the limitation parameters set by the manufacturer on the following aspects: The presence of bends, groundwater infiltration, flow rates form laterals and through the main pipe, gradient of pipe run. Repair Process On completion of the the survey, a report should be submitted to theta Engineer confirming the feasibility and the required program of works. Post Repair Survey On completion of a given run, video taped evidence must be provided by the contractor.the repair sleeve should be monitored for excessive wrinkling, exposed unwetted fibers and pinhole leaks. Testing Subject to the result of the Inspection test, the Engineer reserves the right to select approximately 10% of the repairs for further testing using a water. The test shall comprise of pushing a plug to the downstream end of the sleeve, inserting a bypass plug at the upstream end and filling the isolated section with water. Losses shall be measured and must be within levels set by the local code. If the failure rate exceeds 10% and additional retest area of an equivalent size shall be selected for further testing. Quality Assurance The workmanship of the works shall be warranted for a period of 12 month following substantial completion. The material shall be warranted as per terms and condition of the manufacturer for a similar period PROVIDED the contractor applies the product in accordance with the current guidelines (Standard Operating Procedure) set out by the manufacturer. Typical Bill Items Description Measurement Unit Rate Main Pipe Cleaning Per Run General Contractor Pre repair CCTV of Main pipe and mapping of laterals. Mobilization of Repair Equipment Set up for Installation of Liner Installation of 8 liner designed to withstand an external hydrostatic pressure of 10 feet. Post repair survey of pipe Black and White survey of main pipe. Set up of equipment for reconnecting lateral Cost of reconnecting each lateral Lump sum Each ft Each