Large-scale Field Test

Similar documents
PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

STRUCTURAL STABILITY ASSESSMENT

NUMERICAL AND PHYSICAL MODELING

Plan B Dam Breach Assessment

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

Flow transients in multiphase pipelines

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

TDLP INC. The Dam & Levee Professionals. Kevin Chancey Sarah Edens. Monica Murie Jason Unruh

3D NUMERICAL MODELLING OF THE CAPACITY FOR A PARTIALLY PRESSURIZED SPILLWAY

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

CROSS-SHORE SEDIMENT PROCESSES

The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam

OECS Regional Engineering Workshop September 29 October 3, 2014

AMEC010570_0001. Via . Mt. Polley Mine Tailings Facility Optimization Potential- Follow Up from Dam Safety Review 1.

Huntington District. For More Information Contact (304)

Dams as Systems. Pat Regan Federal Energy Regulatory Commission (FERC)

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER

AIR-WATER FLOW STRUCTURES AT AN ABRUPT DROP WITH SUPERCRITICAL FLOW

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

MIKE Release General product news for Marine software products, tools & features. Nov 2018

Greenup Lock Filling and Emptying System Study

HYDRAULIC JUMP AND WEIR FLOW

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca

SeaSmart. Jonathan Evans

CLOSURE PLAN. CFR (b) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio. September, 2016

As temporary grade control facilities along waterways until final stabilization is established.

Illinois State Water Survey

Aalborg Universitet. Published in: Proceedings of Offshore Wind 2007 Conference & Exhibition. Publication date: 2007

Technical Report Culvert A Hydraulic Analysis

SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING. Kara Hurtig, Water Resources Engineer, Northwest Hydraulic Consultants, BC, Canada

Row / Distance from centerline, m. Fan side Distance behind spreader, m 0.5. Reference point. Center line

HISTORY OF CONSTRUCTION

ANALYSIS OF THE POSITIVE FORCES EXHIBITING ON THE MOORING LINE OF COMPOSITE-TYPE SEA CAGE

WAVE OVERTOPPING AND RUBBLE MOUND STABILITY UNDER COMBINED LOADING OF WAVES AND CURRENT

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection

Water Storage for Agriculture

Démocratisation des modèles hydrauliques CFD 3D : plusieurs exemples réalisés avec ANSYS CFX

Chutes Part 2: Synthetic linings

SPH applied to coastal engineering problems

Control of Nuclear Gloveboxes and Enclosures Using the No- Moving-Part Vortex Amplifier (VXA)

INTERACTION BETWEEN WIND-DRIVEN AND BUOYANCY-DRIVEN NATURAL VENTILATION Bo Wang, Foster and Partners, London, UK

Drilling Efficiency Utilizing Coriolis Flow Technology

BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY

Figure 1 - Photo of Surveyed Area. Figure 2 - Void Survey Results

High Frequency Acoustical Propagation and Scattering in Coastal Waters

A Depletion Compensated Wet Bath Simulator For Calibrating Evidential Breath Alcohol Analyzers

Compaction, Permeability, and Fluid Flow in Brent-type Reservoirs Under Depletion and Pressure Blowdown

LABORATORY EXPERIMENTS ON WAVE OVERTOPPING OVER SMOOTH AND STEPPED GENTLE SLOPE SEAWALLS

BURIAL OF INSTRUMENTED CYLINDERS IN THE SINGAPORE STRAIT

TECHNICAL MEMORANDUM 002 EMORANNO. 001

SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL

VW Liquid Settlement System VWLSS-200

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam.

Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting. August 21, 2017

Physical Model Study of the San Antonio River Lock System

Measuring Discharge in Shallower Rivers: ADCPs go from Rio to Pro

High Frequency Acoustical Propagation and Scattering in Coastal Waters

APPLICANT: Pacific Northwest National Laboratory Attention: Mr. Charles Brandt 1529 West Sequim Bay Road Sequim, Washington 98382

FROTH: Fundamentals and Reliability of Offshore Structure Hydrodynamics EPSRC

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

APPLICATION NOTE. AN-9608 July 2001 SEEPAGE MEASUREMENT IN AN OPEN CHANNEL THROUGH A WEIR

Historic dam failures and recent incidents. Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman

Northern Indiana Public Service Company Michigan City Generating Station Primary Settling Pond Number Annual RCRA CCR Unit Inspection Report

Remote sensing standards: their current status and significance for offshore projects

Stormy Phillips BASICS OF LEASE AUTOMATIC CUSTODY TRANSFER (LACT) SYSTEMS

Sontek RiverSurveyor Test Plan Prepared by David S. Mueller, OSW February 20, 2004

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

APPENDIX J HYDROLOGY AND WATER QUALITY

INTRODUCTION TO COASTAL ENGINEERING

PROPOSING A NEW PORTABLE DEVICE FOR BRIDGE SCOUR INSPECTION

Installation Operation Maintenance. Bermad Level Control Valve with Modulating Horizontal Float Pilot valve One Way Flow IOM.

Full scale VIV response measurements of a drill pipe in Gulf of Mexico loop currents (OMAE )

St. Louis County, MN Coastal Hazard Analysis Flood Risk Review Meeting. May 2, 2018

A Computational Assessment of Gas Jets in a Bubbly Co-Flow 1

Acoustic Focusing in Shallow Water and Bubble Radiation Effects

Vehicle- or rack-mounted liquefied gas meters, pump supplied

CHAPTER 5 CULVERT DESIGN

HEC 26 Aquatic Organism Passage Design Manual Evolution & Application

Annex E Bridge Pier Protection Plan

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models

Low-crested offshore breakwaters: a functional tool for beach management

Pneumatic blending in a bin or silo that is, aerating. Saving time, labor, and money with pneumatic batch blending

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 1, 2012

RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION

Structure Failure Modes

Bayfield & Ashland Counties, WI Coastal Hazard Analysis Flood Risk Review Meeting. June 05, 2018

Project to Refine a Prototype Unmanned, Tethered ADCP Platform for Measuring Streamflow

Pneumatic blending in a bin or silo that is, aerating. Saving time, labor, and money with pneumatic batch blending. Copyright CSC Publishing

Waves, Bubbles, Noise, and Underwater Communications

EXAMINATION OF AE WAVE PROPAGATION ROUTES IN A SMALL MODEL TANK

Bay County, MI Coastal Hazard Analysis Flood Risk Review Meeting. May 14, 2018

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Profile LFR-43 HELENA ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy

THE WAVE OVERTOPPING SIMULATOR IN ACTION

Transcription:

Vaskinn 1 Large-scale Field Test Kjetil Arne Vaskinn kav@trh.statkraftgroner.no Statkraft Grøner AS SUMMARY The objective the controlled failure of large-scale embankment is to monitor and record the failure process and mechanisms in detail. This will provide valuable data to assist in understanding the fundamental failure process, for developing predictive models and for assessing the validity of smaller scale laboratory testing. The tests will take place in Nordland in Norway. The paper gives a short description of the test site and the plans for the tests in 2002 and the preliminary plan for the instrumentation. 1 INTRODUCTION Breach formation is the term used to cover the factors that lead to an uncontrolled release of water from a dam structure. It is well known that the most common causes of failure of an embankment are water overtopping the crest or internal erosion (so-called piping). Although there have been tests and analysis of homogeneous structures of non-cohesive material, the failure of multi-element structures incorporating impervious cores remain poorly understood. Experimental tests will be undertaken to support the theoretical development of models of the failure modes and rates of failure. Tests will include both large-scale fieldwork (failure of 6m high embankments) and smaller laboratory modelling (0.8m high). The large-scale experimental facilities will allow studies of the factors that govern the initiation and growth of breaches under controlled conditions. Also, the issue of scaling from the laboratory to the prototype scale will also be addressed. 2 OBJECTIVES The objective of this part of IMPACT is to undertake experiments of controlled failure of large-scale embankments in order to monitor and record the failure process and mechanisms in detail. This will provide valuable data to assist in understanding the fundamental failure process, for developing predictive models and for assessing the validity of smaller scale laboratory testing. 3 DESCRIPTION OF THE TEST SITE 3.1 Location The test site is located in the middle of Norway (Nordland), downstream of the reservoir Røssvatnet and upstream of the reservoir Stormyrsmagasinet. See map (Figure 1) and picture (Figure 2). The test embankments may be constructed to a height of 6m and subsequently force to failure under controlled conditions. The picture in Figure 2 is taken during a testing period of the gates at the dam Røssvassdammen. There is normally no water flowing in this part of the river.

Vaskinn 2 Pictures in Figures 3 and 4 show the test-dam used during the 2001 field-test in the Norwegian project: Stability and Breaching of Rockfill Dams. Figure 5 gives a view of the river reach downstream from the test-site. Figure 1 Test-site in Nordland Figure 2 Arial photo of the test-site

Vaskinn 3 Figure 3 The test-dam used in the Norwegian project Stability and Breaching of Rockfill Dams (2001) Figure 4 The test-dam used in the Norwegian project Stability and Breaching of Rockfill Dams (2001)

Vaskinn 4 Figure 5 The river reach downstream of test-site 3. 2. Water-level/discharge The gates at the dam Røssvassdammen have a total capacity up to 450m3/s. The gates are new and the operation of them is easy and flexible. The high capacity through the gates gives us the opportunity to simulate breaching in large reservoirs (slow reduction in the water level in the reservoir as a function of time) and small reservoirs. The release of water from the upstream-reservoir will be done in close co-operation with the dam-owner, Statkraft SF. The site is located such that there will be minimal impacts on the environment and no impacts on local infrastructure. 4 TEST-PROGRAM 4.1 Test dams There will be 5 tests in total. 3 of the tests will be done in 2002: Test 1: Homogeneous earthfill (minimal cohesive) dam / embankment with failure by overtopping. Test 2 Homogeneous (maximum cohesive) dam / embankment with failure by overtopping. Test 3 Composite (2 layers) embankment with failure by overtopping. Moraine core, rockfill support/protection layer. In addition to tests 1-3, a test of toe stability will be made at the test-site. The proposed geometry and layout of the test-dams are shown in Figures 6 9.

Vaskinn 5 Figure 6 Test-dam no.1 Figure 7 Test-dam no. 2 There is an option of two different tests with test-dam no. 1: First run a test with a protective layer downstream, then run the same test without the protective layer. The test planned in IMPACT is without the protective layer.

Vaskinn 6 Figure 8 Test-dam no. 3 Figure 9 Test-dam 4 (for dam-toe stability)

Vaskinn 7 4.2 Field work-plan In outline, the plan for the field test is: 1. Preparing the site for the test dam 1.1 Building of transport road to the riverbed 1.2 Work at the riverbed/prepare the foundation of the test-dams. 1.3 Preparing the side-slopes 2. Selection and transport of the materials for dam building. 3. Building of test-dam #1 4. Test #1 5. Cleaning up at dam-site and preparing for test #2. Step 2-5 will be repeated for each test. A local contracting firm will undertake building of the dam. A call for tenders has already been made to select the firm to do the job. This is done to make ensure that the building/construction of the test-dam will be done according to our-plans. 5 INSTRUMENTATION FOR THE FIELD TEST 5.1 Data collection Based on discussions in the working group, the IMPACT meeting in Wallingford and during the workshop in Trondheim 17th and 18th of April 02 it is clear that the following data should be collected: 1. Breach formation geometry: 3D surface of breach at any time 2. Water levels: record level variation with time at: - Upstream reservoir 2 locations minimum - 3D surface through breach - Downstream water levels along the river 3. Gate Operation and Water level in Røssvassdammen (flow into test area) 4. Water pressure through embankment/dam 5. Flow / velocity patterns - Flow through the embankment/dam in the initial phase and at through the toe during testing of toe-stability - Flow through the embankment/dam during braking of the dam. - Flow in the river downstream of the test-dam 6. Sediment movement (materials from the test-dams) 7. Material properties: - Particle size distribution - Liquid / plastic limit - Type of clay - Compaction - Rock properties (interlocking effect) - (Clay will require further tests e.g. chemistry) - Permeability of the test-dam - Porosity of the test-dam

Vaskinn 8 5.2. Instrumentation for data collection There are a number of approaches that could be taken for collecting data. The methods that are chosen are considered to be simple, well tested and documented and cost effective. 5.2.1 3-D surface of the breach at any time A grid will be painted across whole of embankment, including crest and upstream face to aid video and photography. The following methods will be used: Video Photo Photogrammerty Sonar upstream Point measurement within the dam-body either through wires or balls. Measurement in the dam is done to provide information to calibrate and verify data from the other methods. Video will be taken from: Downstream: 3 camera stations (2001-2) Above: 1 camera Upstream: 1 camera Still camera shots can be taken from video footage as the qualities of the photos are high enough, but as a security additional camera will be used. Photogrammetry is a possible method for identifying movement of embankment material. This requires at least two cameras, firing simultaneously, at a fixed spacing. Possible camera-positions are shown in figure 10. Figure 10 Possible positions for the cameras

Vaskinn 9 Sonar offers a possible means of monitoring breach growth underwater. Sonar is however not appropriate for downstream conditions, but could be placed underwater upstream to show growth of breach through upstream face. Sonar has been used for monitoring/mapping of dams in Norway. Figure 11 show an example of a Norwegian dam. Figure 11 Sonar picture of a dam A possible solution to monitor the growth of the breach is to use movement sensors e.g. floating balls. These can be buried within the dam and are released as erosion occurs. These sensors need to be uniquely identifiable, unrestricted by cables, traceable or disposable. 5.2.2 Water levels Water level will be recorded through automatic recording (pressure sensors): 2 points upstream of the test-dam several points downstream to monitor the flood wave Automated system will be complemented with some manual readings of staff-gauges 5.2.3 Pressure sensors in the dam. There will be place at least 10 pressure sensors in the test-dam. See Figures 6-9 5.2.4 Inflow rate into the test-reservoir Discharge through the gates at Røssvassdammen is equal to the inflow to the reservoir upstream of the test-dam. The discharge will be measured through measuring the gate opening at every minute. The waterlevel in the lake Røssvassdammen will be recorded.

Vaskinn 10 5.2.5 Discharge There are two different situations in which monitoring of the discharge is necessary: During testing of the toe-stability During the breach The discharge may be monitored through readings of calibrated staff-gauges in addition to automatic sampling of water pressure/water levels. Discharge will also be recorded through an Acoustic Doppler Current Profiler (ADCP). The ADCP is either mounted on the bottom looking upward (will be used for monitor the discharges during the breach or the ADCP can be floating on the surface looking downwards. (EasyQ) 5.2.6 Sediment movements The sediment movement will be recorded by survey only. Based on the changes in bed surface elevation, calculation of sediment transport will be done. 5.2.7 Properties of the Materials Details still to be decided.