Cambourne to Cambridge Public Transport Route. 14 November 2018

Similar documents
CAMBOURNE TO CAMBRIDGE BETTER PUBLIC TRANSPORT PROJECT PHASE 2 PUBLIC CONSULTATION MADINGLEY MULCH ROUNDABOUT TO CAMBOURNE

Technical note. 1. Introduction

CAMBOURNE TO CAMBRIDGE Better Bus Journeys: Phase One

Report to: Greater Cambridge Partnership Executive Board 4 July Transport Strategy - Future Public Transport Requirements

Members of the Local Liaison Forum: Helen Bradbury, LLF Chair, Cllr Bridget Smith LLF Vice Chair.

CAMBRIDGE SOUTH WEST PARK & RIDE

Design Workshops Summary of all Feedback January 2017

Transport Workshop Dearbhla Lawson Head of Transport & Infrastructure Policy & Funding University of the Third Age.

March Maidstone Integrated Transport Strategy Boxley Parish Council Briefing Note. Context. Author: Parish Clerk 2 March 2016

From: The following comments and proposals have been raised as a result of the public consultation:

A1307 Haverhill to Cambridge: Approval to consult on transport improvement concepts

City Deal Public Consultation Response - Cambourne to Cambridge Better Bus Journeys A428/A1303 Improvements

Map 1 shows the two roads, and how they fit into the public transport network in and around Cambridge.

The existing site constraints which may be encountered for the A428 scheme proposals are divided into sections as follows.

GETTING WHERE WE WANT TO BE

Madingley Road / A428 Corridor Study Options Appraisal Report Cambridgeshire County Council. 20 June 2014

Cambridge Past, Present & Future Wandlebury Ring, Gog Magog Hills Babraham, Cambridge CB22 3AE Phone

MILTON ROAD LLF PROJECT UPDATE

Cambridge Access and Capacity Study

CSRM Modelling Summary Report for Cambridge and South Cambridgeshire Local Plans July 2013

Update June 2018 OUR 2017 PUBLIC ENGAGEMENT

Cambourne to Cambridge Better Bus Journeys 16/03/2018 Reference number QUALITATIVE RESEARCH

Cambourne to Cambridge Better Bus Journeys Cambridge City Centre - Potential Bus Priority Greater Cambridge Partnership. July 2017

WEST AND SOUTH WEST RING ROAD DOWNSTREAM TRAFFIC IMPACTS

Bus and Transit Lane Review Update

CAMBRIDGE SOUTH EAST. Transport Study. Consultation extended to 9 April. Formerly known as A1307, Three Campuses to Cambridge.

ONE SIZE DOESN T FIT ALL RECONCILING OVERLAPPING TRANSPORT NETWORKS IN A CONSTRAINED URBAN ENVIRONMENT

Milton Road Project Update. Paul van de Bulk 30 January 2018

Greater Cambridge Partnership Cambourne to Cambridge Better Bus Journeys: Phase One Summary Report of Consultation Findings

North West Non-Technical Summary of the Transport Assessment September 2011

TRANSPORT AND MOVEMENT

ANNEX1 The investment required to achieve the Government s ambition to double cycling activity by 2025

Corporate. Report COUNCIL DATE: June 26, 2006 NO: C012 COUNCIL-IN-COMMITTEE. TO: Mayor & Council DATE: June 22, 2006

9. Parking Supporting Statement

Northern Beaches Bus Rapid Transit (BRT) Pre-Feasibility Study. Summary Report

Standing Committee on Policy and Strategic Priorities

1.2. South Cambridgeshire Local Plan Proposed Submission, July 2013

Progress update on the Sustainable Movement Corridor scheme Guildford Borough Council, June 2016

Berwick Health and Education Precinct: Casey Amendment C207 (Part 1) Submission to Planning Panels Victoria

A127/A130 Fairglen Interchange Improvement Schemes. Information Leaflet February 2017

PAEKĀKĀRIKI HILL ROAD / BEACH ROAD / SH1 INTERSECTION PROGRESS REPORT

High frequency bus services operating to Little Island; Creation of a new Park and Ride site and train station at North Esk;

Nottingham Cycle City Frequently Asked Questions

ENFIELD TOWN THE REVISED DESIGN

Appendix 11 Barton Greenway Review

LEEDS BECKETT UNIVERSITY. Transport Strategy

I write in response to the current consultation. I am copying this to Derrick Ashley and I will be posting this online.

PUBLIC INQUIRY QUESTION

HISTON ROAD Have your say on better public transport, cycling and walking journeys

University of Leeds Travel Plan

MILTON ROAD ~ MITCHAM'S CORNER PARAMICS MODEL INITIAL OPTION TESTING

Living Streets response to the Draft London Plan

A1307 HAVERHILL TO CAMBRIDGE

Western Orbital Study Options Report Cambridge City Deal Partnership. September 2015

Determining bicycle infrastructure preferences A case study of Dublin

Our journey a 20 year Transport Manifesto for the North East

London Cycle Network Annual Report 2000

MARKHOUSE ROAD IMPROVEMENTS

SCHEME DESIGN AND ENGINEERING

Wellington Public Transport Spine Study

Chelmsford City Growth Package

Initial ideas for bus and cycle links

Cycle network linking Wolverhampton city centre and Bilston town centre with employment sites and residential areas:

BELFAST RAPID TRANSIT. Ciarán de Búrca Director, Transport Projects Division Department for Regional Development

Rural Travel Hubs. Feasibility Study Report. November 2017

Speed Limit Policy Isle of Wight Council

DYNAMIC LANES FOR AUCKLAND

CUERDEN TRANSPORT PROPOSALS

CAMBRIDGE EAST SUSTAINABLE TRANSPORT STUDY

CAIRNGORMS NATIONAL PARK AUTHORITY FOR DECISION

Douglas Land Use and Transportation Strategy (DLUTS) Summary. August 2013

Greater Cambridge City Deal. Initial consultation on better bus, cycling and walking trips. Milton Road

Strategic Director for Environment. Enclosures Appendix A - Option drawings. Jamie Blake- Strategic Director for Environment

Active Travel Strategy Dumfries and Galloway

AMETI PANMURE: A SUSTAINABLE TRANSPORT SOLUTION - OR NOT? Phil Harrison, Opus International Consultants

National Transport Awards Cambridge Park & Ride

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

1 This technical note considers the issues associated with the use of tidal flow bus lanes on key public transport corridors in Cambridge.

Cambridge Cycling Campaign The Bike Depot 140 Cowley Road Cambridge CB4 0DL.

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

21.07 TRANSPORT CONNECTIVITY AND INFRASTRUCTURE

DOE Climate Change Proposals

Cork to Limerick Route Pre-Feasibility Study Update

Cycle City Ambition Grants

GD 0043/18 ACTIVE TRAVEL STRATEGY

Cambourne to Cambridge Better Bus Journeys

Cambridge Past, Present & Future Wandlebury Ring, Gog Magog Hills Babraham, Cambridge CB22 3AE Phone

Bristol City Council has produced a draft Bristol Transport Strategy document.

UK Integrated Behaviour Change Programmes

Cambridge South East Transport Study LLF 6 June 2018

4. Guided Bus Explained

Guildford Borough (Draft)

Cycle traffic and the Strategic Road Network. Sandra Brown, Team Leader, Safer Roads- Design

5 DECEMBER Cycling In London. Andrew Summers, Transport for London Strategy and Policy Manager Active Travel and Health.

IAN WHITE ASSOCIATES. Crawley Station Gateway Public Realm

Safe Speed programme ATTACHMENT 1. Randhir Karma, Group Manager Network Management and Safety

Birmingham Connected. Edmund Salt. Transportation Policy Birmingham City Council

Draft Central District Plan

Regional Bus Priority

Phone: Ref No: 06/2018/0884

Transcription:

Cambourne to Cambridge Public Transport Route 14 November 2018

Key City Deal Commitment 10-15% reduction in vehicles from 2011 figure Equivalent to a 24% reduction today Continued growth increases the challenge CPIER Recommendation #7 A package of transport and other infrastructure projects to alleviate the growing pains of Greater Cambridge should be considered the single most important infrastructure priority [ ] in the short to medium term.

Strategic Case 8,000 new homes by 2031 Generating 44,000 new jobs 1 million houses in the Oxford to Cambridge arc by 2050 Need to provide scheme to connect homes to employment and services Increasing population has led to congestion along the A428/A1303 making it unsustainable More demand for a modal shift from cars to public transport, walking and cycling

A world class public transport system for Greater Cambridge will: Offer a genuinely competitive alternative to the car Quicker, reliable and, where possible, segregated from other vehicles Integrate bus, rail, mass transit, walking and cycling both physically and through timetabling, ticketing, and information Focus on better serving employment clusters outside the city centre, with a wider journey to work geography Be feasible to deliver, and can be sustained

Cambridgeshire & Peterborough Combined Authority The Cambourne to Cambridge scheme must align with CAM proposals and be future-proofed 30 January 2018 8 February 2018 May 2018 31 October 2018 January 2019 Cambridgeshire and Peterborough Combined Authority agrees development of the Cambridgeshire Autonomous Metro (CAM). GCP formally adopts CAM Combined Authority requests halt to work and independent review Combined Authority Review evidence confirms off-road as optimal solution. CA Board agrees scheme to advance at pace. Confirms route as essential first phase of CAM Combined Authority Board will review the Strategic Outline Business Case for the CA Metro, prepared by consultants Steer

Project elements Phase1 East from Madingley Mulch roundabout to Cambridge city prioritised as a key area of congestion. 2 Phase West from Madingley Mulch roundabout, via P&R site, to Bourn Airfield and continuing to Cambourne New Park & Ride site at Waterworks or Scotland Farm

Progress Phases of Consultation Technical Assessment Route Development Phases of Project Oct/Nov 2015 Initial public consultation 6 route options and P&R site February 2016 Public consultation responses published Nov-Jan 2018 Phase 1 consultation proposed more detailed plans for three routes, onroad, tidal on-road and offroad. Two Park and Ride sites - Scotland Farm and The Waterworks. Technical Assessment Route Development Executive Board agree in principle to a segregated route given wider economic benefits and to undertake further work. May 2018 Public consultation responses published May October CA Mayor requests halt to work whilst review considers alignment with CAM. CA review concluded October/November 2018 C2C progress tabled for November/December GCP Assembly and Board

45% 40% 35% Public Consultation Results Q. Please indicate which overall route would be your preferred choice? 40% Off-Road Option This off-line route option appears to be sufficiently distanced from designated sites and therefore unlikely to have any adverse impact on these. On-Road Option Options A and B are located in close proximity to this (Madingley Wood SSSI) nationally designated site and proposals could have an adverse impact, through direct and indirect effects, on the notified features of the ancient woodland. 30% 33% Natural England Consultation Response 25% 20% 15% 18% Off-Road Option We consider that the harm associated with either of the options for Route C could be minimised or avoided subject to a robust mitigation strategy. 10% 5% 0% 6% 4% On-Road B Off-Road C On-Road A None Not Sure 2,049 complete responses 8 On-Road Option The proposal by reason of the proximity to the cemetery and loss of verge would result in irreversible, adverse impacts upon the approach, setting and layout of the cemetery site. Historic England Consultation Response

Jo Baker Mott MacDonald C2C Project Director

Strategic and Technical Assessment On road Option A o Option A and Option B were assessed against each other using Mott MacDonald s in-house Investment Sifting and Evaluation Tool (INSET) to arrive at a preferred on-road option. o The findings of the INSET assessment have concluded that the on-road option is Option A. o However, a potential optimisation of the route has been explored to reflect the aspiration in Option B for some improvements to outbound traffic, and a need to further consider the operation of Junction 13 of the M11. Option B o o Option A and Option B were assessed against each other using Mott MacDonald s in-house Investment Sifting and Evaluation Tool (INSET) to arrive at the highest scoring on-road option. Option B did not score as high as Option A. The need for gantries was a significant reason for the differences in scores. Although, this was not in the original proposal by the LLF gantries were included for safety and operational purposes.

One of the main outcomes of the consultation was the development of an Optimised on-road option. This would include both inbound and outbound public transport priority, without the need for gantry structures and within the highway boundary.

Optimised On-Road Option Optimisation Optimisation Optimisation of Madingley Mulch Roundabout Carriageway Widening for 200m of west bound bus lane added. Optimisation of M11 Junction 13 Change to M11 to allow two right turn lanes from off-slip Inbound bus lane up to M11 Public transport priority at M11 Bus gate priority at Eddington Avenue Optimisation High Cross Junction Park and Ride access relocated to Eddington Avenue, additional eastbound and westbound bus lane and bus gate at approach to junction. Bus Lane from West Cambridge Development to Storeys Way Bus lane removed Optimisation Buses share with general traffic from junction with Eddington Avenue / High Cross

Strategic and technical assessment Off-road Option C o o o Option C was split into the pink, blue and (through West Cambridge) development light green routes. These represented different alignment routes for Option C. The route was broken down into five areas and assessed using INSET to arrive at a recommended Specific Route Alignment. The recommended off-road specific route alignment is the Blue route through Madingley Mulch, and adjacent to Coton village and the light green route through West Cambridge, and the Rugby Ground connection to Grange Road.

Option Assessment Off-road and On-road options were subject to financial review including wider scheme benefits and BCR. Level 1: = Conventional Transport Benefits >>Provides BCR Level 2 = Wider Economic Benefits related to transport scheme (i.e. not land-use changes) >>Provides Adjusted BCR Level 3 = Wider Economic Benefits associated with land-use changes. Nationally significant >> Provides Local Growth Benefits 800,000,000 700,000,000 600,000,000 0.25 0.2 500,000,000 400,000,000 0.15 0.1 0.05 0 Scheme Costs 190M 80M 300,000,000 200,000,000 100,000,000 0 On-line Off-line BCR Adjusted BCR Scheme Benefits Local growth

Option Assessment results Multi-criteria assessment tool results Key findings from the assessment Off-Road Aligns better with transport policy More reliable journey Less disruption to existing roads Future proofing Aligns better with aspiration for CAM (Cambridge Autonomous Metro) Better in terms of heritage and biodiversity Key findings from the assessment On-Road Has less impact on green belt Lower cost

Specific Route Alignment Project team continues to welcome views and contributions from stakeholders throughout the continuing development of plans for Phase 1 of the route, in conjunction with Phase 2 consultation and planning, working to deliver a single route option for GCP Board decision in late 2019.

Next Steps Jan 19 Feb 19 Mar-Oct 19 Oct 19 Strategic Outline Business Case for the CAM Metro to Combined Authority Board Phase 2 public consultation - tbc pending December Board decision Ongoing technical assessment and route development Consultation results published and considered in ongoing planning. Assessment and mitigation design continues. Specific Route Alignment Decision. Present a final option in the outline business case. Expected late 2019.

Q & A

1. LLF Technical Group The LLF technical Group is very disappointed with Mott McDonald s recommendation (report dated November 2018 ) in favour of an off-road bus-road solution on this alignment. After having spent many hours with Mott MacDonald, we note that virtually none of our concerns have been addressed. This scheme still does not stand up to scrutiny: It offers poorer connectivity to, and longer onward journey times into, the City than an on-road alignment (ii) It offers poorer connectivity to the Cambridge Biomedical Campus and the Science Park than an on-road alignment (iii) It costs 154 million to construct; between 2-47* million for onroad alignment (iv) It has a Benefit Cost Ratio of 0.17-0.2 - one tenth of what is required for public sector investments Will the Transport Director please explain why a scheme with such major deficiencies is still preferred? Will he agree to work with the LLF to address our concerns, and be open to developing alternative off-road and on-road solutions?

2. Steve Jones, Convenor of the Coalition of 23 Parish Council: Why does GCP continue to push an off-road busway scheme which, at huge cost, will not deliver the people Cambourne and the proposed Bourn Airfield to where they want to go. We in the Coalition have undertaken extensive traffic surveys which tell us that only a very small proportion of people can possibly benefit. What do you propose to do for the majority of residents of Greater Cambourne who will still need to drive to work? What modal split between cars and buses have you assumed in your analysis of demand to justify the cost of this busway?

3. Philip Allen, District Councillor Comberton and Harston Ward: Given that the Mayor and the Combined Authority, as strategic transport authority, have placed the condition on the C2C that it is CAM compliant, will the GCP now work up fully a comparative CAM compliant option of a northern route including the Girton interchange?

4.1. Stephen Coates, Save West Fields It is very clear that the route from Grange Road to Drummer Street simply does not work. Given that no evidence has been provided, how can you proceed? We previously saw documents talking about a bus interchange on Queen s Green, the Backs. How can Officers seriously claim such an interchange would not be built if this plan goes ahead?

4.2. Ellen Khmelnitski, Gough way Residents Association Grange Road is not where people want to go and it is too narrow and too congested without Cambourne buses. You must know very well that Silver St is even narrower and that modest gains in journey times will be completely lost on the way to the City Centre. Why are you avoiding clarifying this crucial problem?

5. James Littlewood, Cambridge CPPF With reference to the Arup report (Appendix 2, page 10 JA papers), there is a cursory rejection of the alternative off-road proposal put forward by us, the LLF and others - that it is less attractive in terms of programme, planning and environmental constraints, as well as journey time. There is no information provided which decision makers can refer to in order come to a position, for example: Has the fact that Girton will undergo significant upgrade to become four-ways as a result of it becoming part of the Oxford-Cambridge expressway, and incorporating the CAM into this work would enable pooling of resources (eg Highways Agency), been considered in the assessment? This route would provide access to other communities (not just those from the West) who as a result would have access to the CAM and reduced journey times. Ie others would benefit. Has this been considered as part of the assessment? There may be no requirement to cross the M11 and the length is the same or shorter than the preferred option. Has this been incorporated into the assessment? What environmental assessments have been undertaken to reach the conclusion in the assessment? No information or evidence has been provided to date. Can the Assembly ask that this information is made available to both the public and the Board before they make a decision to discount this option?

6. Pauline Joslin, Hardwick Parish Council: Will the Greenways Comberton to Grange Rd route be aligned/adjacent to the express bus route?

7. Markus Gehring, Ward Councillor, Newnham: In the 2015 consultation: almost 70% of respondents preferred an onroad bus lane in bound from Madingley Mulch roundabout into the city centre In the Dec 2017-Jan 2018 consultation: 40% of respondents preferred Option B, an On-Road tidal Public Transport lane 40% of respondents preferred Option A, an On-Road tidal eastbound Public Transport lane = 80% preference for on-road In Mar 2018, the Mott MacDonald report concludes: No clear preference was shown. How can Mott MacDonald conclude this? The latest plans have been developed with no changes despite such a clear message. What is the purpose of public consultation, and what value do GCP place on it?

8. Stephen Coates, Save the West Fields Why does the preferred alignment include a hugely destructive leg from the West Cambridge Site to Grange Road, harming the West Fields, when the metro scheme would have a tunnel from the West Cambridge Site into town? Why do so much damage for something that would not be required if the metro goes ahead? Why do the documents claim that the Rifle Range leg would be temporary when officers have told Save the West Fields this week it would be permanent? If it is temporary why not run the buses down Madingley Road until the metro is built? It is clear that there is a clear legal challenge in choosing the Rifle Range leg based on harm to the purposes of the Greenbelt. Why are Assembly and Board members being asked to make a decision without proper disclosure of the legal evidence this route is workable. The claim that it increases pedestrian and cycle access does not work when you consider that the Comberton Greenways project can deliver the same benefits without a new road?

8.1. Mark Abbott, Coton Parish Council: Of all the possible routes and alignments, GCP has chosen the one that inflicts the most harm to the residential houses, school and landscape setting of Coton Village. Why have you done this?

8.2. James Littlewood, Cambridge CPPF: The Arup and officers reports refer to avoiding adverse impacts in the West Fields and coton village. However the greatest impact of significance would actually be on Madingley Hill (ie the section between Madingley Mulch and the M11). This does not seem to be reflected in the summary assessment of Route Options, which scores Route A as positive in this respect. Nor is it reflected in the proposed mitigation options for which it appears that only the section next to the village would be mitigated. Please can the Assembly ask why the length of route with potentially the greatest landscape impact, which is covenanted by the National Trust, does not appear to register in the constraints or mitigation?

8.3 Ellen Khmelnitski, Gough way Residents Association: In Table 4 you claim that the off-road option will have no negative effect on flood risk. How can you be so sure? Is it really possible to build a road 20 m wide in a flood plane and maintain that it will not increase flood risk?

8.4 Pauline Joslin, Hardwick Parish Council: Has the GCP route given due consideration to any stray bullets from Barton Rifle Range?

9 Philip Allen, District Councillor Comberton and Harston Ward: Given the time it will take for plans for the CAM to be sufficiently advanced and financing found, and the recently adopted new Local Plan for South Cambridgeshire that requires high-quality public transport from Cambourne to Cambridge, quite possibly in a shorter time frame than the CAM could bring, can the GCP put in a temporary inbound bus lane on Madingley Hill as an interim measure?

10.1 Stephen Coates, Save West Fields: Why has the GCP chosen a route through the West Fields which would assist St John s and Jesus development plans? St John s said in its Local Plan appeal: It is entirely appropriate that any proposed development at Grange Farm should exploit the opportunity [of the Cambourne to Cambridge busway] to connect into the corridor and better enhance its sustainable qualities. The plan is therefore illustrative but acknowledges that a route through the St John s College land at Grange Farm enables connectivity to new proposed residential development on the edge of the City By choosing to cross Jesus College and St John s College land this route assists their development plans. The GCP has said that it needs some developer contributions to pay for the busway - why should we not assume the GCP has decided to put a temporary route across the West Fields to make development easier in the future. We already have documents where some of the landowners have said development of the West Fields could part pay for the busway.

10.2 Ellen Khmelnitski, Gough way Residents Association: In Table 8 you claim that the developer of the scheme will contribute 38,000,000. It's a huge sum of money. Where does it come from?