GSE CAGING AND SPINUP BUFFER LINE INSTALLATION

Similar documents
GSE CAGING BALLAST SYSTEM INSTALLATION

(PTP) PROBE PRESSURE MEASUREMENT SYSTEM INSTALLATION AND LEAK CHECK PROCEDURE

(PTP) REMOVE PROBE SPINUP GAS/VAC. LINES (HORIZ.)

PROCEDURE TO MEASURE READOUT LOOP RESISTANCE

INTERNAL LEAKAGE CHECK OF THE FLIGHT GMA

TEST OF GMA SPINUP ASSEMBLY PRESSURE SENSOR CALIBRATION

BLEED DOWN OF THE HIGH GMA PRESSURE

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

POROUS PLUG CHARACTERIZATION TEST

GMA FUNCTIONAL TEST SETTING & TESTING OF SPIN UP PARAMETERS. P0586 REV -- 20, June 2000 GPB SCIENCE MISSION PROCEDURE

CALIBRATING THE GMA PRESSURE SENSORS AND THE ECU ENGINEERING UNIT

Proton Monitor Thermal Vacuum Test Procedure GP-B P0635

Vibration/leak Test 2.5 and 6 Vatterfly Valves (3179 and 3223) spare units. GP-B Engineering Procedure P0761 Rev.-

PROBE-C CAGING VALVE INSTALLATION

CHECK READOUT LOOP CONTINUITY IN PROBE C

DESIGN VERIFICATION AND QUALIFICATION OF NEW POPPET AND BUSHING ON GMA FLIGHT SOLENOID VALVES

GMA TO SPACE VEHICLE PLUMBING HOOKUP

LOW PRESSURE VOLTAGE BREAKDOWN TEST PROCEDURE FOR GSS FSU FLIGHT SPARE HVA BOARD October 28, P0938 Rev

GDS OPERATING PROCEDURE

SCRUB LAUNCH RECOVERY PROCEDURE FOR THE GMA

GMA SLEEP PROCEDURE AT VAFB

GMA VENT EXTENSION SERVICE PROCEDURE

GUARD TANK PRESSURIZATION FOR TRANSPORT

Proto-qual Vibration Test Procedure 2.5 and 6 Vacuum Valves (3179 and 3223) Retest of Flight Spare Valves. GP-B P0735 Rev.-

CLEANLINESS TEST OF PROBE SPINUP EXHAUST LINES

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

GMA PREPARATION FOR E28 TESTING

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Burst Disk on SMD

ASSEMBLY OF GAS FLOW HARDWARE INTO SM GMA

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Prepare Payload for Mass/CG Measurements and Condition Payload During Spin Balance Test

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test.

BLEED DOWN OF THE GMA HIGH PRESSURE AT VAFB

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Relief Assembly on SMD

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Spacecraft Battery Magnetic Field Survey

PREPARE FOR CRYO OPS FOLLOWING TRANSPORT TO B1610 To be performed at Vandenberg Air Force Base building 1610

Pressurize Well to One Atmosphere with Probe Installed

Canadian Light Source Inc. Vacuum Component Leak Test Technical Procedure

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR DISCONNECT MAIN TANK VENT LINE FROM GAS MODULE MAIN TANK SUBATMOSPHERIC

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR REGULATE GUARD TANK PRESSURE

Please refer F 90 of the present manual for the identification of the valves used in the detector.

PROCEDURE FOR THERMAL CYCLING IN LIQUID NITROGEN

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR STOP PUMPING ON SMD VACUUM SHELL / DISCONNECT VACUUM MODULE

CERTIFICATION OF THE TEMPERATURE MONITOR AND ALARM

HYDROSTATIC LEAK TEST PROCEDURE

B. Assemble the Method-25 sample train with a heated probe/filter.

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

RK-IR Sample Draw Aspirator Adapter Operator s Manual

PUMP DOWN MAIN TANK TO SUBATMOSPHERIC CONDITION

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00

SINORIX Valve Reconditioning

PROPORTIONING VALVE. Model 150 INSTRUCTION MANUAL. March 2017 IMS Company Stafford Road

Paper Session II-C - Verification of International Space Station Component Leak Rates by Helium Accumulation Method

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR MAIN TANK SUBATMOSPHERIC FILL FROM NBP SUPPLY DEWAR GUARD TANK PRECOOL

Section 3- Repair and Calibration Procedures

STANDARD OPERATING PROCEDURES

Operation Manual - PN A MENSOR MODEL 73 SHOP AIR BOOSTER

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR CONNECT VACUUM MODULE / PUMP ON SMD VACUUM SHELL

CSA Sample Draw Aspirator Adapter Operator s Manual

INSTALLATION AND OPERATION INSTRUCTIONS

CTG Certification Protocol -- Version 3.0 SUMMARY

BS Series Basket Strainer

Reduce Liquid Level in Main Tank- Liquid at NBP To be performed at Vandenberg Air Force Base building 1610

Description Advanced Features Typical Applications

SUBSTATION MAINTENANCE ELECTRICAL OPERATING PROCEDURE

DRAFT. Operating Procedures for the NPDGamma Liquid Hydrogen Target in TA-53, Building MPF-35

ROTATING DISK VALVES INSTALLATION AND MAINTENANCE 1. SCOPE 3 2. INFORMATION ON USAGE 3 3. VALVE TYPES 3 4. OPERATORS 5 5. VALVE CONSTRUCTION 6

ACCREDITATION OF ON-LINE LEAK SEAL ORGANIZATIONS

LUDLUM MODEL 239-1F FLOOR MONITOR. Revised December 2010

Document Number: 302/34000/76 SV/sv Revision: (B) 2009/02/05

SEMASPEC Test Method for Determination of Cycle Life of Automatic Valves for Gas Distribution System Components

Gas Lines. Technical Manual. Sumitomo (SHI) Cryogenics of America, Inc Vultee Street Allentown, PA U.S.A.

Installing ASI Umbilical Delivery Systems

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE

G92 Series BASOTROL Automatic Pilot Gas Valve

KTM OM-2 SPLIT BODY FLOATING BALL VALVES INSTALLATION AND MAINTENANCE INSTRUCTIONS

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Configure SMD for Transport to SLC-2W To be performed at Vandenberg Air Force Base building 1610

Operators Manual. Supera Floor Stand Anesthesia Machine M1000. Models: M1000 Basic Non-rebreathing M1200 Basic M1200

Inert Air (N2) Systems Manual

INSTALLATION, OPERATION & MAINTENANCE MANUAL

KENNEDY VALVE OPERATION & MAINTENANCE MANUAL

Operation Manual. Diaphragm Sensed Gas Pressure Regulators

NB/NBR NITROGEN BOOSTER FOR AVIATION SERVICE

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR MAIN TANK SUBATMOSPHERIC FILL FROM NBP SUPPLY DEWAR GUARD TANK PRECOOL.

2 CYLINDER MOBILE CART USER S MANUAL / INSTRUCTIONS

INSTALLATION AND OPERATION INSTRUCTIONS

MB-SP Series Solvent Purification System

INSTRUCTION MANUAL. FLOW CONTROL DRAWERS MANUAL / PLC CONTROL SERIES Model Version Perma Pure LLC Tel:

Installation Instructions

ACCURACY, PERFORMANCE, AND HANDLING OF OIL-FILLED DIGIQUARTZ PRESSURE INSTRUMENTATION

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Upright SMD (Rotate from Horizontal to Vertical Orientation)

RK LEL Sample Draw Aspirator Adapter Operator s Manual

KIRBY MORGAN DEEP SEA DIVING HELMETS ALL MODELS HELMET AND EMERGENCY GAS SYSTEM DAILY SET-UP AND FUNCTIONAL CHECKLIST APPENDIX A2.

GETZ EQUIPMENT INNOVATORS RECOVERY SYSTEM CLEAN AGENT FE-36 / HALOTRON 1 PART NO. 4G59751 OPERATIONS MANUAL

BGA244 Binary Gas Analyzer

Model 10E Enviro-Line Environmental Pressurization System Installation & Operation Manual

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

Beverage Systems. Component Inspection and Service TSB-Y Date: Subject: Products Affected: Description: July Inspection of CO 2

ACRYLIC FLOW METERS 0-30, 0-70 & LPM

TECHNICAL DATA CAUTION

RADIATION PROCEDURES MANUAL Procedure Cover Sheet

Transcription:

Stanford University Program Operation Order No. GRAVITY PROBE B PROCEDURE FOR PAYLOAD VERIFICATION GSE CAGING AND SPINUP BUFFER LINE INSTALLATION Sept. 28, 2000 Prepared by: B. Muhlfelder Approvals Program Responsibility Signature Date Dorrene Ross GP-B Quality Assurance Chris Gray Vacuum Specialist Barry Muhlfelder Payload Technical Manager NOTES: Level of QA required during performance of this procedure: X Stanford QA Representative Government QA Representative All redlines must be approved by QA

Page 2 of 10 Revision Record: Rev Rev Date ECO # Summary Description Acronyms and Abbreviations: Acronym / Abbreviation Meaning GSE Ground Support Equipment SMD Science Mission Dewar QA Quality Assurance personnel HEPA High Efficiency Particulate Air filter

Page 3 of 10 Table of Contents A Scope... 4 B Requirements Verification... 4 C Configuration Requirements... 4 D Hardware Required... 4 E Software Required... 5 F Procedures Required... 5 G Equipment Pretest Requirements... 5 H Personnel Requirements... 5 I Safety Requirements... 6 J General Instructions... 6 K References and Applicable Documents... 6 L Operations... 6

Page 4 of 10 A Scope This procedure effects the installation and leak check of the GSE for the caging, P1, and spinup buffer lines. The system is mounted on the exterior of the dewar at the tophat. B Requirements Verification C B.1 Requirements Cross Reference: N/A B.2 Expected Data for verification per requirement: N/A Configuration Requirements Probe-C is integrated into the SMD per drawing 65113-1C34292 and may be oriented with the +Z axis in any orientation such that ports can be accessed during installation. D Hardware Required D.1 Flight hardware required Description 65113-1C34292 Probe-C / SMD Assy. 1 No. Req d D.2 Commercial test equipment (fill in chart ): Manufacturer Model Serial Number Calibr. Exp. Date

Page 5 of 10 D.3 Mechanical/Electrical Special test equipment: N/A D.4 GSE Hardware: Description Gamah to VCR connector with manual Nupro valve 12 No. Req d. wrenches D.5 Tools Description No. Req d D.6 Expendables Description Aluminum gaskets for 1/4 Gamah connectors Nickel Steel gaskets for 1/4 VCR connectors Felpro C-100 anti-seize compound Helium gas (filtered) Nitrogen gas (filtered) Quantity E F G Software Required: N/A Procedures Required: N/A Equipment Pretest Requirements: N/A H Personnel Requirements This test to be conducted only by certified personnel. Ken Bower, Chuck Warren, Dave Murray, Tom Welsh, Rob Brumley, Chris Gray, and Mike Taber are qualified to perform this procedure. The QA representative shall be either Russ Leese or Dorrene Ross.

Page 6 of 10 I Safety Requirements I.1 Movement of the gantry used to support the HEPA downflow booth (if required) requires two persons. I.2 Care should be taken to prevent nicking, overtorqueing, or otherwise damaging flight vacuum sealing surfaces. I.3 Care should be used when manipulating any electrical cables connected to any part of the flight hardware. This procedure does not imply any authority to disconnect any such electrical connectors. I.4 General emergency procedures can be found in FIST Emergency Procedures (P0141). J General Instructions J.1 Redlines must be approved by QA. J.2 Any nonconformance or test anomaly should be per P0108. Do not alter or break test configuration if a test failure occurs; notify quality assurance. J.3 Only the following persons have the authority to exit/terminate this operation or perform a restart: Chris Gray, Ken Bower J.4 Work done inside the HEPA downflow unit should be performed under conditions consistent with class 1000 cleanroom practices (apparel, tool cleanliness, operational restrictions, etc.). J.5 During this entire operation the spinup and P1 line valves are to remain closed. K References and Applicable Documents: N/A Op. Order No. Date Initiated Time Initiated L Operations L.1 Verify cleanliness of system. L.1.1 L.1.2 L.1.3 L.1.4 Install or verify installation of the HEPA downflow unit over the top of the SMD/probe. Measure the background particle count of the area around the tophat record in the table below. Remove bagging material from buffer line assembly. Connect a clean gas supply (Nitrogen recommended) to a buffer line. L.1.5 Lightly blow clean gas through the buffer line and measure the particulate output near each connector of the manifold and record the measurements in Table 1 below. If the resultant particle count is higher than the background count, purge

Page 7 of 10 L.1.6 L.1.7 and/or reevaluate the system. If the particle count is not above the background count, accept the system. Maintaining a light positive gas flow, remove buffer line from gas flow. Repeat steps L.1.3 through L.1.6 for each assembly. L.1.8 Cleanliness acceptable: completed by: QA approval: 1 2 3 4 5 6 7 8 9 10 11 12 Background Buffer Line Reading Table 1 L.2 Installing flight buffer line assemblies. L.2.1 L.2.2 Verify all buffer line assembly valves are open. Install one buffer line assembly (with gasket) on to each of the flight caging ports, spinup ports, and P1 port. Use a back up wrench on the port fittings to prevent torque stresses from transferring to the flight hardware. Properly tighten the nut until the gasket is fully deformed to provide a proper seal. If desired, anti-seize compound may be applied to the contact area between the nut and plain fitting of the connector saver (NO ANTI-SEIZE COMPOUNDS MAY BE APPLIED TO THE FLIGHT HARDWARE). L.3 Flight Manual Valve leak checks L.3.1 Hook up leak detector to probe vacuum.

Page 8 of 10 L.3.2 Bag each spinup line manual valve and P1 valves. Flow He gas into bag for 60 minutes. L.3.3 L.3.4 Record background leak rate. Record in Table 2 below leak rates for each valve. Remove bag. Valve Number S1 S2 S3 S4 P1A P1 Table 2 Leak Rate For caging lines attach leak detector and He supply to each buffer line. Open paired manual valves for each circuit, backfill with He gas to 1 atm, pump out He gas, and then refill with He gas to 1 atm. Close flight valve to 60 in-lbs. He background for leak detector shall be less than 1e-7. Wait 30 minutes. Record in Table 3 below leak rates for each caging valve Valve ID C1 C2 C3 C4 C5 C6 Table 3 Leak Rate After successfully completing leak test, pump out each caging line and close each manual flight caging valve with 60 in-lbs of torque.

Page 9 of 10 L.4 Leak check the buffer lines. L.4.1 L.4.2 L.4.3 L.4.4 L.4.5 Connect a certified Helium leak detector to a buffer line assembly utilizing any hardware. Perform a leak check of the entire plumbed assembly. Note: buffer lines have been previously leak checked so that most important aspect of current leak check is Gamah connector checkout. Perform repairs (and/or repeat any steps above) until no leaks are detected. Repeat steps L.4.1 through L.4.3 for each buffer line assembly. Vacuum performance acceptable: completed by: QA approval: L.5 Helium purge the buffer lines. L.5.1 L.5.2 L.5.3 L.5.4 L.5.5 L.5.6 Connect a vacuum system and clean Helium gas supply to a buffer line assembly. Evacuate the buffer line assembly. Fill the buffer line assembly with Helium gas (to two atmospheres absolute pressure). Repeat step L.5.2 and L.5.3 one additional time. Close the buffer line assembly valve with 60 in-lbs of torque. Repeat steps L.5.1 through L.5. for each buffer line assembly. L.6 Leak check the buffer line manual valves. L.6.1 L.6.2 L.6.3 L.6.4 Connect a certified Helium leak detector to a buffer line assembly utilizing any hardware. Perform a leak check of the buffer line manual valve. Perform repairs (and/or repeat any steps above) until no leaks are detected. Repeat steps L.7.1 through L.7.3 for each buffer line assembly. L.6.5 Leak detector background shall be less than 1e-7. Record valuves in Table 4 below. Record duration of each leak check of buffer line valve in Table 4 below. Valve ID He Background Leak check duration Buffer Line Leak Rate S1 S2

Page 10 of 10 S3 S4 C1 C2 C3 C4 C5 C6 P1 P1A Table 4 L.6.6 Vacuum performance acceptable: QA approval: Operation completed. completed by: Completed by: Witnessed by: Date: Time: Payload Test Director: Responsible Quality Engineer: