SG36KTL-M Quick Installation Guide. 1 Unpacking and Inspection

Similar documents
SG33KTL-M Quick Installation Guide. 1 Unpacking and Inspection

GV Standard X-Vent. Setup, Commissioning & Installation Guide

Installation, operating and maintenance Instructions for Seemag bypass level indicator

BRILLIANT WONDERS LED BUBBLERS INSTALLATION INSTRUCTIONS CMP SERIES. Brilliant Wonders LED BUBBLERS

Medium Voltage Switchgear. Installation Manual for Pressure Relief Ducts

E Cube Lift Model: ECU Installation Instructions

Operating Instructions

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6

Differential Pressure Regulator Type Type 45-6 (0.1 to 1 bar, DN 15) Mounting and Operating Instructions EB 3226 EN

BRILLIANT WONDERS LED BUBBLERS INSTALLATION INSTRUCTIONS & PRODUCT MANUAL CMP SERIES

CONDUCTIVITY POINT/S LEVEL SWITCH JAYCEEAQUA 4000 SERIES

Operating Instructions

Operating instructions Safety Rope Emergency Stop Switches ZB0052 / ZB0053 ZB0072 / ZB0073

Sensoric 4-20 ma Transmitter Board Operation Manual

Flamco Flamco-Fill STA Flamco-Fill STM

Low Wind High Yields Series

PROPORTIONING VALVE. Model 150 INSTRUCTION MANUAL. March 2017 IMS Company Stafford Road

INSTALLATION PROCEDURE 1/4 & 1/8 MILE PERMANENT TRACK

User Manual. Quantos Automated Dosing Liquid Module

ECHO MANUAL WARNING. L B A ltim e te rs. ECHO is a trademark of LB Altimeters, Denmark

EX-RECESSED CEILING LIGHT FITTINGS

A4 Operation Manual. Fig.1-1 Controller Socket Diagram

Pressure Dump Valve Service Kit for Series 3000 Units

Further technical information is available on

MP15 Jockey Pump Controller

ATOC Meteorological Tower (6 meter-4 level) Guide

Roller AC Servo System

A4s Operation Manual

INSTALLATION AND OPERATING INSTRUCTIONS. T10219-AD Deckboat 40 with AutoDeploy and Wireless Remote Control

Transmitter CS 21 Operation Manual

Operating instruction

Pressure Dump Valve Service Kit for Series 2300 Units

AHE58/59 AC Servo System

Copyright 2004 by the Thomas G. Faria Corporation, Uncasville CT No part of this publication may by reproduced in any form, in an electronic

Model 6810A Dual Lane Scoreboard Owner s Manual Rev B

Pneumatic Target Transfer System Model PT01

INSTRUCTION MANUAL Pressure Relief Device LPT

For ELECTRIC ANCHOR WINCH Models: T Pontoon 35 T sw Salt Water Series Coastal 35

MODEL 9875 STADIUM BASEBALL SCOREBOARD. Instruction Manual

USER MANUAL. JET TST and JET TST S.

Magnetic level switch type MR783 Instruction Manual

For ANCHOR WINCH Model: T Big Water 45 T sw Salt Water Series Big Water 45

Data sheet Pressure switch type CS December 2001 DKACT.PD.P10.A B1119

ORNAMENTAL CANTILEVER GATE INSTRUCTIONS

Mounting and Operating Instructions EB 3007 EN. Self-operated Pressure Regulators. Differential Pressure Regulators (opening) Type Type 42-25

SERIES 2 RAMP OWNER S MANUAL TOOLS REQUIRED: BEFORE YOU BEGIN... Read and understand these instructions before beginning a ramp setup.

Operating Instructions. Ball valve fitting according to ZB For pressure transmitter VEGABAR 82. Document ID: 50027

Conductor Bushings Series 8174

C&G 2395 Exam Paper June Section A-All questions carry equal marks. Answer all three questions. Show all calculations.

BMW Motorrad. Installation Instructions. BMW Motorrad Communications System for Schuberth C3

KTM OM-2 SPLIT BODY FLOATING BALL VALVES INSTALLATION AND MAINTENANCE INSTRUCTIONS

OxyScan Graphic. Operating Instructions. UMS Micro-oxygen sensor 501. Microprocessor instrument

Arran LED Floodlight Luminaire

Overspeed governors (113 OG Моment 250 MR, 114 OG Moment 250 A3, 115 OG Moment 250 MRL, 119 OG Moment 250 MRL/1)

Hand lever valves VHER

e.do Gripper Safety requirements, technical features and assembly and integration instructions

COOPER POWER SERIES. Under-oil arrester disconnector installation/operation instructions. OEM Equipment MN800010EN

ServicePlus S21R & S27R Series 2 Installation Instructions

Erection, maintenance and disposal Inverted installation. Zinc oxide silicone-housed surge arresters PEXLIM R-X, Q-X and P-X

Safety. Operating instructions Solenoid valve for gas VG 6 VG 15/10 DANGER. Contents WARNING CAUTION. Changes to edition 09.14

Stand-Alone Bubble Detection System

Chapter 2 Rigging. Cutting Wire Rope. Anchoring Wire Rope to Drum. Winding Wire Rope Onto Drum

Apex Evaporator Manual

! Warning, refer to accompanying documents.

USER S MANUAL 1000W and 2000W

Version-E E100930

Transmitter CS 21 Operation Manual

Alphasense 4-20 ma transmitters offer convenience and easy maintenance for toxic sensors:

3200 WHOLE HOUSE FAN INSTALLATION & OPERATION MANUAL

CCT-7320/ROC-2313 Reverse Osmosis Controller

RAI-M series RUDDER ANGLE INDICATOR SYSTEM

User Manual V14.1 IP68 LED FLEX NEON

LIFTING MAGNETS ERIEZ MAGNETICS

Coriolis Mass Flow Meter

Cantilever Brake. Dealer's Manual. ROAD MTB Trekking. City Touring/ Comfort Bike

Installation Instructions for the Walking Beam Interlock for Eaton EHD, FDB, FD, HFD, FDC, FW, HFW, FWC, Circuit Breakers and Molded Case Switches

Metham Aviation Design Limited, Station Approach, Four Marks, Alton. Hants. GU34 5HN Tel +44 (0) Fax +44 (0)

SM6. instructions for use. connection with compartment for incoming cable from the top. MV distribution factory built assemblies at your service

PLEASE READ CAREFULLY BEFORE INSTALLING OR USING MEGA POOL SAVER MPS 1100

Agilent 1220 Infinity II LC Mobile Upgrade Kit

Spectrum AquaLight (SAL ) Color Underwater Light Owner s Manual

High-performance submersible pressure transmitter For level measurement Model LH-10

D Issue E Original. Instruction Manual. TIC Instrument Controller

I.H.S INSTALLATION INSTRUCTIONS

CCSSL35 Carry out the wiring and testing of electrical circuits and equipment

RS(H)10,15 USER MANUAL. Read the complete manual before installing and using the regulator.

36E DSI, HSI & Proven Pilot Two-Stage Combination Gas Valve INSTALLATION INSTRUCTIONS

Procedure Troubleshooting the Interconnect Cables

Version-E Manual

VACUUM REGULATORS CONTENTS

User Manual. Quantos Automated Dosing Powder Module

PLAQUE MFM0680 UNDERWATER LIGHT. Operating Instructions

LTB013EN. Operating Instruction Trimod Besta Level Switch types XA 5, XB 5 for use in potentially explosive atmospheres acc.

Inoxair. Repair Manual. Content. Edition: 12/2010. Subject to technical changes for reasons of the continous development.

Misaligned Folds Paper Feed Problems Double Feeds Won t Feed FLYER Won t Run iii

OPERATION and MAINTENANCE Guide

Infrared Linescanners

Instructions for Use

DT400/436 Tee Connector Installation Instructions

Pull-rope emergency stop switch Type HENEX and SEGEX OPERATING INSTRUCTIONS

Transcription:

SG36KTL-M Quick Installation Guide This guide provides a general instruction of the installation procedures of SG36KTL-M. In no case shall this guide substitute for the user manual or related notes on the device. Make sure to read over, fully understand and strictly follow the detailed instructions of the user manual and other related regulations before installing the equipment. Any violation could result in personal death or injury or device damage. 1 Unpacking and Inspection Step 1 Remove the backplate and fasteners from the packaging. Step 2 Inspect the inverter for visible damages and check the completeness of the delivery contents according to the inner packing list. Contact your supplier if any of the contents is missing. SG36KTL-M is unavailable if any damage is detected. 1

*Images shown here is for reference only! Actual product you receive may differ. Item Name Description A Inverter unit --- B Backplate It is used for mounting inverter onto the wall. C Documents Documents include quality certificate, packing list, product test report, and quick user manual. D Fastener set Six units. It is used for fastening backplate onto metal frame. E Fix screws 2 M4 16 screws for fix the inverter to the backplate. F DC Eight pairs. PV input cables must be equipped with the connectors connector. G MC4 cable Eight pairs. Please insert MC4 cable gland to the plug unconnected DC input terminal. 2

2 Mounting Inverter onto Metal Frame Select the installation location and regulate the clearances of multiple inverters, referring to the user manual. Move the inverter to the installation site with the help of another person or the lifting device by means of the handles. Install the inverter onto Metal Frame as following procedures. Step 1 Place the backplate onto the chosen metal frame and adjust it until it is in a horizontal position. Step 2 Mark the positions to drill holes by using the backplate as the template. Step 3 Drill 6 holes at the marks you have made. If the shape of the metal frame doesn t fit the holes on the backplate, re-drill holes on the backplate of appropriate position according to the chosen frame. In order to avoid electrical shock or other injury, inspect existing electronic or plumbing installations before drilling holes. Step 4 Fasten the backplate against the metal frame with bolts and nuts. The dimensions of fasteners used in the following diagram are recommended. The torque for fastening the nut is 35 Nm. 3

Item Description Remark A Hexagonal socket nut M10 B Spring washer - C Washer - D Hexagonal bolt M10*45 E Metallic wall - F Backplate - Step 5 Lift up the inverter above the backplate and then slide down to make sure that the recesses on the back of the inverter fit perfectly together with the backplate. Step 6 After fit the inverter to the backplate, fasten the inverter to the backplate with two M4 16 screws. 4

3 Electrical Connection Death hazards due to high voltage existing inside the inverter! Make sure that all the DC and AC cables to the inverter are not live before you start the electrical work. Do not turn on the AC side or DC side circuit breaker until all inverter electrical connections have completed. 3-1 Open the Connection Cabinet Loose the four screws on the front cover of the connection cabinet and remove the front cover to see the internal layout of the connection cabinet. 5

3-2 Cables Selection AC Cable No. Description Remark A Protective layer External diameter of the cable: 37~44 mm B Length of insulation to be stripped off 24 mm C Insulation layer - D Cross section of AC cables Range: 16-50mm 2 ; DC Cables Cross-sectional area Cable External diameter Max. withstand voltage Max. input current for each PV string 4~6mm 2 12AWG~10AWG 6~9mm 1100V 12A Second PE Cable The cross-sectional area of the second PE cable shall be exactly the same with that of the PE cable of the AC cable. RS485 communication cables Shielded twisted pair cables or Shielded twisted pair Ethernet cables. 6

3-3 AC Connection Pull the cables and connect L1/L2/L3/N/PE cables ends to the corresponding terminal blocks. Fix the AC cable to the corresponding terminals with torque of 8 12 N m. 3-4 DC Connection Step 1 Check the connection cable of PV string for the correct polarity and that the open-circuit voltage does not exceed the inverter input limit 1100V, even under the lowest operating temperature. Check the positive and negative polarity of the PV cells. After confirmation, you can insert the DC connectors into the input terminals on the bottom of the inverter. For the same MPPT, reverse connection of a single string is prohibited. A permanent failure of the system or inverter may follow if otherwise. 7

Step 2 Insert the positive and negative DC connectors into the input terminals on the bottom of the inverter until there is an audible sound. 3-5 Second Protective Earth Terminal There is a second PE terminal on one side of the inverter and it should be grounded. Fig. 3-1 Second PE terminal The ground connection of this second PE terminal cannot replace the connection of the PE terminal of the AC cables. Make sure the two PE terminals are all grounded reliably. Sungrow shall hold no liability for any possible consequences caused by ignorance of this warning. 8

Cable Connection Fig. 3-2 Second PE connection Item Name Description A Screw M6 12mm B Lock washer - C Washer - D Cable socket - E Yellow-green cable* - * Connection parts are not within the scope of delivery 3-6 Communication Connection There are two communication waterproof connection terminal on the bottom of the inverter. RS485 A/B terminals, RS485 interface and Ethernet interface (optional) are provided on the configuration circuit board of the junction box. A 120Ω terminating resistor can be connected between the A and B communication cable through the dip switch. 3-7 Completing Installation Seal the gaps between the cables and the glands inside the lower part of the cabinet by fireproofing mud. Inspect before commissioning and reassemble the front cover of the connection cabinet. 9

4 Commissioning Before starting SG36KTL-M, make sure all installation and connections are completed and verified. Step 1 Close the AC circuit breaker. Step 2 Rotate DC switch to ON position. Step 3 Suppose there are sufficient sunlight and enough DC power. PV arrays initialize and supply DC power to inverter. The LCD display is activated when DC voltage exceeds inverter startup votlage. If there is a defect on the display, contact Sungrow. Button Operation Description Press for less than 2 seconds Move upwards or downwards or scroll among set values. Hereinafter, it is referred to as Press. Press for more than two seconds Press for less than 2 seconds Press for more than two seconds Step 4 Press to choose country code. Confirm the settings by Pressing ENTER. Return to the previous menu or cancel the command. Hereinafter, it is referred to as Press ESC. Move left or right, or turn pages. Hereinafter, it is referred to as Press. Enter into the sub-menu or confirm the command. Hereinafter, it is referred to as Press ENTER. Step 5 Select the country code according to the installation country of the inverter. Each country code represents corresponding local protective parameters that have been preset before delivery. Before country setting, there is warning screen. Operate according to the warning information and press ENTER. 10

After setting the Country parameter, please proceed to set other parameters of the inverter in accordance with the specific requirements of the local grid. Before commissioning, please check thoroughly if the set parameters meet the local grid requirement. Refer to Protection Parameter Setting in User Manual for country code explanation. If the inverter is installed where the country code is not included, please choose item Other and manually set the protection parameters. Step 6 If the country code set as GR, a Grid codes page as shown in the right will appear. Press to select grid code and press ENTER to confirm. If the country code set as DE, a Grid codes page as shown in the right will appear, where LV signifying low-voltage grid; MV signifying medium-voltage grid. Press to select grid code and press ENTER to confirm. If the country code set as TK, a Grid codes page as shown in the right will appear. Press to select grid code and press ENTER to confirm. If the country code set as TH, a Grid codes page special for Thailand will appear. Press to select grid code and press ENTER to confirm. 11

If the country code set as Other, a Grid codes page as shown in the right will appear. Press to select grid code and press ENTER to confirm. If the country selected is not the abvementioned 5 countries, enter the next step directly. Step 7 After selecting the Grid Code, there will be a Pro-stage type selection screen and then corresponding sub-menu will come up. For detailed information, please refer to Protection Parameter Setting in User Manual. Step 8 Set the inverter time as per local time. Incorrect time setting will affect the data logging. Press to move the cursor and Press to set the specific time and date. Press ENTER to confirm setting. Step 9 After configuring all parameters, there will be a setting confirmation screen. Check whether all above-mentioned parameters are correct. Confirm by Pressing ENTER. Cancel by Pressing ESC and reset. Step 10Inverter will enter into startup process. Observe the status of LED indicators and the LCD main screen. If commissioning succeeds, the RUN indicator will be on and Run will be displayed on the State area. If commissioning fails, the FAULT indicator will be on and Fault will occur on the display. Press to view current fault information. Remove the existing fault and then repeat the commissioning procedures. 12