APPENDIX A1 - Drilling and completion work programme

Similar documents
W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS

W I L D W E L L C O N T R O L FLUIDS

Practice Exam IADC WellSharp Driller and Supervisor

PTRT 1471: Exploration and Production I. Chapter 6: Drilling and Well Completion

Industry Code: Alberta Small Employer OHS Legislated Requirements

Chapter 5 HORIZONTAL DRILLING

Casing Design. Casing Design. By Dr. Khaled El-shreef

FREQUENTLY ASKED QUESTIONS

DEPARTMENT OF ENVIRONMENTAL PROTECTION Office of Oil and Gas Management

Squeeze Cementing. Brett W. Williams Cementing Technical Advisor January 2016 Tulsa API Meeting

Texas Administrative Code

BLACK HILLS PLATEAU PRODUCTION COMPANY

Along-string pressure, temperature measurements hold revolutionary promise for downhole management

SUPPLEMENT Well Control for Drilling Operations Workover & Completion for Drillers Core Curriculum and Related Learning Objectives

Solid Expandable Tubular Technology: The Value of Planned Installation vs. Contingency

Completions & Workovers Module 1.9

Why Do Not Disturb Is a Safety Message for Well Integrity

The key to connectivity

Recommended minimum functional specifications and standards for geothermal wells in the Netherlands v.5

Offshore Managed Pressure Drilling Experiences in Asia Pacific. SPE paper

Extended leak off testing

PROPOSED NEW SUB- CODE 1 RIG UP AND TEAR. Possibly Fits into Existing Code. 7/26/2018 Review PROPOSED NEW CODE EXISTING OPERATION

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS

Best Practices - Coiled Tubing Deployed Ball Drop Type Perforating Firing Systems

NORSOK standard D-010 Rev. 3, August 2004

Chapter 4 Key Findings. 4 Key Findings

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

DEPARTMENT OF ENVIRONMENTAL PROTECTION Office of Oil and Gas Management

EXAMINER S REPORT AND RECOMMENDATION STATEMENT OF THE CASE

INTERPRETATION NOTE ISSUED UNDER THE PETROLEUM DRILLING REGULATIONS (CNR 1150/96)

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD

Innovating Gas-Lift for Life of Well Artificial Lift Solution. The Unconventional Solution!

International Well Control Forum. IWCF Drilling Well Control Syllabus Level 3 and 4 March 2017 Version 7.0

The report gives a summary of the background and motivation for the audit activity and summarizes the observations made at the meetings.

Perforation Design for Well Stimulation. R. D. Barree Barree & Associates LLC

Deepwater Horizon Incident Internal Investigation

Understanding pressure and pressure

A PROACTIVE APPROACH TO ADDRESSING ANNULAR PRESSURE ISSUES AND STRAY GAS MIGRATION IN THE UNCONVENTIONAL SHALE PLAYS

ECD Reduction Tool. R. K. Bansal, Brian Grayson, Jim Stanley Control Pressure Drilling & Testing

Inflatable Packer Single & Double. Single & Double Packer Dimension. Wireline Packer. Water Testing Packer (WTP) Packer

SUPPLEMENT Well Control for Drilling Operations Workover & Completion for Supervisors Core Curriculum and Related Learning Objectives

Perforating Options Currently Available in Horizontal Shale Oil and Gas Wells. Kerry Daly, Global BD Manager- DST TCP

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

Subsea Safety Systems

OCEAN DRILLING PROGRAM

New generation of solid expandable liners help give operators a jump on trouble zones

SPE Forum: Source Control for Wells in Shallow Water. Lars Herbst, Gulf of Mexico Regional Director

AADE 2009NTCE-04-04: PRACTICAL ASPECTS AND VALUE OF AUTOMATED MPD IN HPHT WELLS

Development of a Subsurface Mudline Packer to Reduce Risk of Flow after Cementing and Sustained Casing Pressure, While Providing a Platform for P&A.

Captains Meeting 2009 Introduction to Well Testing- Expro. Edwin Schoorl

NORSOK Standard D-010 Rev 4. August 2012

Well Control Drill Guide Example Only. Drill Guide is the list of drills, questions and attributes that are in DrillPad.

NOT TO COPY -- NO DISSEMINATE WITHOUT WRITTEN AGREEMENT. Presentation JB AG JCN JR 1

Study Guide IADC WellSharp Driller and Supervisor

Coal and Water Protection. PADEP: Well Plugging & Subsurface Activities Division Bureau of Oil and Gas Planning & Program Management

NORSOK Standard D-010 Rev 4, August 2012

Inflatable Packers for Grouting 11/10/00

Advanced Applications of Wireline Cased-Hole Formation Testers. Adriaan Gisolf, Vladislav Achourov, Mario Ardila, Schlumberger

Characterization of Completion Operational Safety for Deepwater Wells

COGCC OPERATOR GUIDANCE MECHANICAL INTEGRITY TEST GUIDANCE: PRACTICES AND PROCEDURES

International Well Control Forum. Well Intervention Pressure Control Level 2 Syllabus July 2015 Version 7.0

Casing and Cementing Requirements

North Dakota Petroleum Council Re-stimulation Initiative

WILD WELL CONTROL WARNING SIGNS OF KICKS

HPHT Annular Casing Packer. Obex Annular Casing Packer

Oil, Gas and Salt Resources of Ontario

Engineered solutions for complex pressure situations

COAL SEAM METHANE - EXPLORATION AND PRODUCTION

117 NORWEGIAN OIL AND GAS RECOMMENDED GUIDELINES FOR WELL INTEGRITY

Colorado Oil and Gas Conservation Commission

Chapter 5 Drilling and Well Testing Practices

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

Mobeetie Resource Dev LLC EXAMINER S REPORT AND RECOMMENDATION STATEMENT OF THE CASE

30 C.F.R. Subpart D Oil and Gas Drilling Operations

Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation

1. UPDATE 12/12/2014: What wells are regulated under the MIA Program? Must they be drilled, stimulated, and completed? Must they be in production?

Directive 059: Well Drilling and Completion Data Filing Requirements

Enbridge G & P (East Texas) LP EXAMINER S REPORT AND PROPOSAL FOR DECISION STATEMENT OF THE CASE

How HSE regulates onshore oil and gas

The Alberta Energy Regulator (AER) has approved this directive on January 31, Introduction Purpose of This Directive...

IWCF Equipment Sample Questions (Combination of Surface and Subsea Stack)

Oil Well Potential Test, Completion or Recompletion Report, and Log

Colorado Oil and Gas Conservation Commission (COGCC) Completed Interval Report, Form 5A Data Field Definitions

WELL SUSPENSION AND ABANDONMENT GUIDELINES AND INTERPRETATION NOTES OFFICE OF THE REGULATOR OF OIL AND GAS OPERATIONS

Step-Rate Formation Integrity Test Method for Geothermal Wells

Reclassification and Recompletion

BANDAR PANJI-1 WELL CONTROL INCIDENT REPORT

Coiled Tubing string Fatigue Management in High Pressure Milling Operation- Case Study

SPE MS Well Collision Avoidance Management and Principles

Drilling Efficiency Utilizing Coriolis Flow Technology

OIL/GAS WELL COMPLETION REPORT. Well Name and Number Surveyed elevation (feet): KB GL

CHDT Cased Hole Dynamics Tester. Pressure testing and sampling in cased wells

Case studies from classes led by Dr. Ron Fulbright, University of South Carolina Upstate. IMPROVED BLOWOUT PREVENTER

Form MMS 123A1123S Electronic Version. Application. We have incorrect pressure tests for the annulars on subject ABP The ABP shows we

Testing Services Overview

PHE KE30-A8 WORKOVER PROGRAM

Petroleum Development

A Novel Approach to Capitalize WITSML Data in Geospatial Platform for Realtime Monitoring and Risk Assessment

International Association of Drilling Contractors North Sea Chapter HPHT Guidance on MODU Safety Case Content

DIRECTIONAL DRILLING

Transcription:

APPENDIX A1 - Drilling and completion work programme Information about the well and drilling To the extent possible, the international system of units (SI) should be adhered to, and the drilling programme shall as a minimum contain information about the following: 1. the ID number of the well as given in the Danish Energy Agency numbering system 2. the name of the well. Wells not named by the operator will be named by the Danish Energy Agency 3. name of operator and information about the operator's organisation in connection with the drilling operation and the rig owner s organisation and other companies involved 4. well surface position and maximum tolerance on this position. The position shall be given in geographical and Universal Transverse Mercator (UTM) co-ordinates 5. name of the rig and rig owner/operator 6. time schedule or duration of the operation 7. water depth/ground level elevation 8. expected rotary table elevation above reference level when drilling unit /equipment is ready to start drilling. For jack-ups the elevation shall be measured from mean sea level (msl) 9. estimated total well depth, positions for targets and planned well trajectory. In case a well safety zone (anti-collision) is unintentionally crossed, an amendment along with a risk assessment shall be submitted to the DWEA for approval 10. information about directional drilling and a description of method for and maximum vertical interval between measuring the well inclination and direction 11. depth to and description of the anticipated geological horizons and eras a. stratigraphic column showing and describing anticipated lithology, pore pressure and fracture pressure gradients, planned casing points, estimated reservoir pressure and temperature. Method used for pore pressure and fracture pressure prediction should be stated b. representative interpreted seismic sections near the planned well (normally 2 intersecting lines). Location map and location map including offset wells c. depth and time structure maps showing primary and secondary prospects as well as time and possibly depth structure maps for other key horizons with a scale of not less than 1:25,000 d. the velocity functions used in the area e. a prospect description of primary and secondary objectives 12. abnormal pressures a. an evaluation of the possibilities of encountering over-pressured zones with the well in question. This shall be based on seismic data and/or experience from neighbouring wells b. a description of methods and procedures to be used for detecting any overpressure in the well

13. an evaluation of the possibilities of encountering zones with H 2 S and other poisonous gases within the well, including description of the methods for detecting and handling of same 14. an evaluation of the possibilities of encountering gas pockets in the well in question based on seismic data and experience from neighbouring wells, including the possibility of encountering shallow as well as deep gas pockets 15. a list of any other possible significant deviations from the geological/drilling prognosis which may be encountered during the drilling of the well, (e.g. salt zones, swelling clay, high pressured zones) and information on precautions planned in this connection 16. a summary sequence of all operations including an estimate of the time required for the different main operations (typical as a time versus depth curve i.e. drilling curve). The summary shall give a general description of the operations, including information on any special safety related requirements (caused by e.g. possible gas pocket or abnormal pressure) 17. tentative well schematic for plug and abandonment of the well and for re-establishing the well site. Final plug and abandonment programme must be submitted to DWEA for approval 18. information of preparedness and contingency plan for handling H 2 S and other dangerous gases 19. contingency plan related to well operations for use in the event of major accidents or emergency situations regarding health, safety and environment 20. information about planned underbalanced drilling operations and its safe performance Information about the risk assessment ALARP principle The programme shall include the risk assessment, cf. section 1. assessment of subsurface conditions and identified potential hazards shall be stated identified risks shall be recorded and stated and mitigation measures shall be specified and implemented residual risks shall be as low as reasonable practicable (ALARP). Information about casing diameter of drilled hole casing dimension grade and type planned setting depth for the casing strategy for centring of casing, including type of exterior packers and stabilisers, where applicable programme for cementing of casing, including type of cement, estimated height of cement behind the casing, and strategy for calculations of necessary volumes of cement demonstration of the sufficiency of the casing string strength with regard to burst, collapse, and tension and added safety factor including justification. Reference may be

made to company procedure for casing design calculation. In this case the parameters used in the design (pressure, cementing height, mud density etc.) must be stated procedure and minimum requirements for testing the formation strength after drilling out the individual casings, including calculations demonstrating that the required formation strength is sufficient for drilling to the next casing setting depth precautions to be taken if the required formation strength is not obtained. Information about the cement programme detailed information about cement type planned used information about the previous casing, dimensions, leak off test (LOT) or formation integrity test (FIT) and the actual casing to be installed and cemented information about hole size and drilling mud in the borehole information about estimated pressure profile identifying any possible anomalies and top overpressures planned height of good cement behind the casing, how this objective is achieved and verified (e.g. CBL, VDL or USIT). Calculations of cement volumes should also be outlined information about thickening time, main and tail slurry and pumping time, and all cement additives, and in case of hazardous additives or substances, plans for safe handling complete cement testing programme including testing time after cement job, test values, duration, acceptance criteria etc. Information about well control equipment and blow-out preventer system a list of all well control equipment available on-board the drilling unit, specifying manufacturer, size, working pressure, maximum pressure, arrangement, specific purpose, function and categorisation (primary or secondary) information regarding the control system operating the blow-out preventer stack. A list of the blow-out prevention equipment available on the drill floor ready for mounting on the drill pipe procedure for kick control, stating i.e., the data and calculations which by routine are updated to ensure the necessary background for handling emergency situations information on how blow-out preventers, measuring equipment, drilling fluid circulation and mixing equipment are expected to be used under such conditions programme for function testing of the blow-out preventer and pressure testing of blowout preventer and casing at different stages during the drilling operation. The programme shall also include test intervals, acceptance criteria, maintenance and monitoring procedures and plans for well control incidents, including the elimination, minimising, containing, controlling and preventing of a full blow-out. Reference to a well control manual would suffice. Information about drilling fluid

a detailed description of the types of drilling fluids to be used specifying density and rheological properties etc. a detailed description of the components of the drilling fluids. Reference may be made to relevant chemical data sheets a detailed description of check equipment and procedures for the drilling fluid or reference to relevant standard procedure for monitoring the drilling fluid volume a list of the quantities of safety related material (e.g. barite and cement) to be stored on the drilling platform during normal operations and an argumentation for these quantities (cf. section 6.1) information about potential borehole instability caused by drilling fluid and formation interaction, and established mitigation plans information about environmentally harmful drilling mud discharge to sea while drilling, type, content and quantity. Information about independent verification The programme shall include independent well verification, cf. section 4. Information about logging and measurements information on types of measurements and logs to be run at various intervals and zones programme for taking geological samples, including a coring programme tentative programme for planned drill stem testing or test production. Final test production programme shall when applicable be submitted and approved separately. Information about dispensations The programme shall include the dispensations from the operator s own management system/standards and justifications. If the above information requirements are for some reason not stated in the drilling programme, references shall be made to relevant documents.

Completion programme In the following, the minimum required documentation to be submitted with regard to completion operations is outlined. The completion programme shall as a minimum contain the following: The documentation to be submitted will depend on the type of the chosen lower and upper completion to be installed. The equipment information shall include type, data specifications, installation, tests and acceptance criteria. Information about scope of work The programme shall include the main objectives of the completion. Information about the well The programme shall include: well description and its current state well and reservoir data which could be a potential hazard (CO2, H2S, etc.) well schematic prior well operations well barriers schematic stating primary and secondary barriers prior well operations pore pressure and fracture gradient profile along the wellbore and its stratigraphy well geology if not provided with the above profile. Information about the well operation The programme shall include: detailed well schematic of the proposed solution(s) well barriers schematic stating primary and secondary barriers of the proposed solution(s) lessons learned from previous completion if available detailed programme of the operation including planned tests and their acceptance criteria for all safety and environmental critical elements detailed programme of the contingencies if any including planned tests and their acceptance criteria for all safety and environmental critical elements. Information about the risk assessment ALARP principle The programme shall include the risk assessment, cf. section 1. assessment of subsurface conditions and identified potential hazards shall be stated, i.e. all potential leak paths to surface or intra formations (crossflows) identified risks shall be recorded and stated and mitigation measures shall be specified and implemented residual risks shall be as low as reasonable practicable (ALARP).

Information about independent verification The programme shall include independent well verification, cf. section 4. Information about completion The programme shall include information on: completion fluids wellhead system x-mas tree design. Information about upper completion The programme shall include information on: tubing and hanger surface controlled subsurface safety valve and annular safety valve as applicable downhole pressure and temperature gauges, chemical injection valves Electrical Submersible Pump (ESP), Hydraulic Submersible Pump (HSP) or gas lift valves. Information about lower completion The programme shall include information on: liner type production packer flow control components (sliding sleeves, nipples, etc.). Information about perforation and perforation guns if applicable: type and data safety procedures covering as a minimum safe handling of all devices and equipment planned used, running in and pulling out of hole and firing description of the planned explosives, safe handling and shot density target intervals and depths. Information about stimulation, fracturing and acidizing if applicable: type and data regarding fracturing fluid, proppant and acids, including expected quantities safety procedures covering as a minimum safe handling of all equipment intended used, vessel hook-up activities and coordination, running in and pulling out of hole pressure, function or inflow tests of valves, fracturing lines and other equipment as applicable, specifying test frequency and acceptance criteria. Information about dispensations The programme shall include the dispensations from the operator s own management system/standards and justifications.

If the above information requirements are for some reason not stated in the completion programme, references shall be made to relevant documents.