Port of Zeebrugge: Upgrading the Brittannia Dock

Similar documents
Ennore Coal Port Project: Port Basin and Entrance Channel

Port Sections Guide Section 01

Eilat 's artificial lagoons project on the Red Sea - Israel R. Raviv Ir. R. Raviv, Coastal Engineering Ltd., P.O. Box 7322, z/b 37072,

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

(Refer Slide Time: 0:25)

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

LIST OF CORRECTIONS. 14 / July /052(T) - 07/125(T) - 08/136(T) - 08/137(T) - 12/177(T) - 15/212(T) - 18/232-22/285(T)

(Refer Slide Time: 1:01)

LIST OF CORRECTIONS. 02 / January /052(T) - 07/125(T) - 08/136(T) - 08/137(T) - 12/177(T) - 15/212(T) - 18/232-22/285(T)

Risk Assessment and Mitigating Measures Regarding Pile Installation at EBS Biohub Jetty

Low-crested offshore breakwaters: a functional tool for beach management

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

THE WAVE CLIMATE IN THE BELGIAN COASTAL ZONE

Shoreline Response to an Offshore Wave Screen, Blairgowrie Safe Boat Harbour, Victoria, Australia

OECS Regional Engineering Workshop September 29 October 3, 2014

Richards Bay Coal Terminal

APPENDIX F 3. Computation Result for Salinity in the Lagoon

Dredging Stiff to Very Stiff Clay in thewielingen Using the DRACULA System on a Hopper Dredger

REBO terminal. REBO terminal Energy Port Oostende. the ideal hub for offshore wind & heavy lift activities in the North Sea

الاسكندريه مصر Tel Fax: (+2) Mob: (+2)

Light draught m

CHAPTER 132. Roundhead Stability of Berm Breakwaters

BEACH NOURISHMENT BY RAINBOWING FOR THE VISAKHAPATNAM PORT TRUST BY DCI. Capt. MVR MURTHY ABSTRACT

Large scale wave run-up tests on a rubble mound breakwater

A New Strategy for Harbor Planning and Design

DESTRUCTIVE WAVE OVERTOPPING TESTS ON FLEMISH DIKES

CORPS FACTS. Harbor Dredging U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG

Implications of proposed Whanganui Port and lower Whanganui River dredging

Ennore Breakwater Construction

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

Dredging Keeping Our Underwater Highways Open

MONITORING SEDIMENT TRANSPORT PROCESSES AT MANAVGAT RIVER MOUTH, ANTALYA TURKEY

Ketchikan Harbors Thomas Basin and Bar Point Harbor

Safety Improvements of Fijian Jetties. Authors Tim Morrison MWH Christchurch, NZ Nigel Beatson MWH Nelson, NZ Mandar Panvelkar MWH Sydney

Ninilchik Harbor Page 2 of 11

Minimal Structures for Marginal Nova Scotia Developments

methods and construction sequences for the modifications and

CHAPTER 212 THE BEACH REHABILITATION PROJECT AT OSTEND-BELGIUM. ir. R. SIMOEN* ir. H. VERSLYPE** ir. D. VANDENBOSSCHE***

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Forth Ports Limited. Ruling Depths & Under Keel Clearances

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering

Introduction of world construction methods and trends. Franz-Werner Gerressen, Head of Method Development, Tokyo,

Development of TEU Type Mega Container Carrier

MIKE Release General product news for Marine software products, tools & features. Nov 2018

A: Formalities. DELOS WP 1.1 Inventory on LCS, questionnaire, detailed description, revision D AUTH GR. Participant code and who to contact.

NUMERICAL MODELING OF WAVE PENETRATION IN OSTEND HARBOUR

Dauphin Island East End Beach and Barrier Island Restoration Project. Beau Buhring South Coast Engineers

Nome Harbor Page 2 of 12

WAVE OVERTOPPING OF RUBBLE MOUND BREAKWATERS

Concepts & Phenomena

Breakwaters and closure dams CT 5308 Exercise 2011: Pointe Noire, Congo

A methodology for evaluating the controllability of a ship navigating in a restricted channel

Cross-shore sediment transports on a cut profile for large scale land reclamations

SPEECH. by Deputy Director-General of the Danube Commission s Secretariat. Mr. Pjotr Suvorov. (Linz, April 2013)

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

Bridge Design for Marine Vessel Collision

GEOSYSTEMS GEOSYSTEMS FOR MARINE APPLICATIONS. Protective Fabrics Space Composites Aerospace Composites Advanced Armour

Controlling Coastal erosion

Construction Dewatering

NAVIGATION IN CONFINED WATERS: INFLUENCE OF BANK CHARACTERISTICS ON SHIP-BANK INTERACTION

WEEKLY NAVIGATIONAL BULLETIN NO.26 FOR THE RIVER TEES, HARTLEPOOL AND TEES BAY. Issued by the Harbour Master on 02 November

BoatWasher Swede, , MS Float

Alaska Deep-Draft Arctic Port System

Mouth of the Columbia River Jetties Three-Phase Construction Plan

CHAPTER 134 INTRODUCTION

AD-A II~lllII I I 7

APPENDIX D REAL ESTATE PLAN

Nearshore Dredged Material Placement Pilot Study at Noyo Harbor, CA

Mooring Solutions for Yachts

CHAPTER 2. Types and Functions of Coastal Structures TABLE OF CONTENTS. VI-2-1. Applications... VI-2-1

Passing Vessel Analysis in Design and Engineering. Eric D. Smith, P.E. Vice President, Moffatt & Nichol

Cordova Harbor Page 2 of 9

The development of the historical harbour of Paphos, Cyprus H.J. van Wijhe*, M. Meletiou^ Division, P.O. Box 152, 8300 AD Emmeloord, The Netherlands

Development of New Type of Breakwater Reinforced with Steel Piles against a Huge Tsunami

DONGE FLUSHING YARD. This combination of using and constructing equipment improves the quality of our products since 25 years.

Unit 18 LEAVING THE DOCK

REVITHOUSSA LNG TERMINAL JETTY AND TERMINAL INFORMATION

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY

Cook Inlet pipeline crossing is about making the best choices

Introduction Introduction

Structure Failure Modes

Welcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives

The Masterplan Coastal Safety: a wave of opportunities

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

photo: deltaport berth 2 project

Optimization of Tidal Windows for Deep-Drafted Vessels by Means of ProToel

The construction of Deepwater Navigation Channel (DNC) in the Bystry arm of the Danube Delta has started in The whole project provides the

DREDGING & MINING MEDIUM DUTY ABRASIVES HANDLING HOSE

ADANI PORTS & SEZ LTD. ++ MUNDRA PORT ++ GENERAL INFORMATION

CHAPTER 83. DESIGN OF A DETACHED BREAKWATER SYSTEM by Osarau Toyoshima Director, Sea Coast Division, River Bureau, Ministry of Construction, JAPAN

Press release LAUNCH. FlanSea WAVE PIONEER Wave energy converter

ABSTRACT INTRODUCTION

DEPARTMENT: CIVIL ENGINEERING SEMESTER: III SUBJECT CODE / Name: CE2303/ Railway, Airport and Harbors Engineering UNIT 5 2 MARK QUESTIONS AND ANSWERS

Voting should indicate preference to one option (Option 1, Option 2, or Option 3)

The Challenge of Wave Scouring Design for the Confederation Bridge

Bear Cove Coastline Reestablishment

INVESTIGATION OF WAVE AGITATION INSIDE THE NEW FISHERY PORT (CASE STUDY: NEW MRZOUKA FISHERY PORT, LIBYA)

ISLAND HARBOURS AND THEIR INFLUENCE ON ADJACENT SHORES

BALD HEAD ISLAND, NC SAND SHARING SYSTEM OVERVIEW AND ASSESSMENT. Erik J. Olsen, P.E. olsen associates, inc.

Transcription:

ABSTRACT Port of Zeebrugge: Upgrading the Brittannia Dock by L. Missinne 1 and L. Van Damme 2 The Flemish authority started with the upgrading of the Brittannia Dock in the port of Zeebrugge. The Brittannia Dock was the first dock that was constructed (the working harbour ) during the construction of the new outer harbour of Zeebrugge and as a result of this historical background, the bottom depth in the Brittannia Dock is at TAW -5, which is no longer sufficient to receive today s vessels. So the upgrading of this port area was needed. The upgrading of the Brittannia Dock consists of three phases. In the first phase, a new rubble mound breakwater is built over the full width of the dock. In the second phase the lake that exists after the construction of the new breakwater will be filled up and in the third phase a new commercial jetty will be built parallel to the breakwater at the northern side. So in the future, two vessels (type Humbermax) will be able to moor at the same time in the remaining part of the Brittannia dock. 1. INTRODUCTION: SOME HISTORICAL BACKGROUND OF THE PORT OF ZEEBRUGGE The port of Bruges had known an exceptional growth during the late Middle Ages but with the silting up of the Zwin the downfall started. It was just in the last decade of the 19 th century, under the impulse of King Leopold II, that the Belgian parliament took the decision to build a new full-fledged seaport in Bruges at sea, or Zeebrugge. Until 1960 the port stayed almost unchanged. With exception of the repair due to war damage, no big infrastructural works were carried out. In 1960, for the first time a global program was drafted to make the port of Zeebrugge accessible for ships of 50000 dwt at high tide and for ships of 35000 dwt without tidal restrictions. In 1970 another important decision was taken concerning the port of Zeebrugge. As a consequence of the report of the commission Verschave it was decided to build out the port of Zeebrugge to a polyvalent deep-sea-port. As a first phase a new sea lock was constructed for ships of 125000 dwt, the inner harbour of 1300 ha was constructed and a kind of seawarded extension of the harbour dams was carried out to improve the access to the new sea lock. In 1976 the decision was taken to build a complete outer harbour surrounded by high breakwaters. During the construction of the new outer harbour a lot of materials, as sea sand, sea gravel, stones and concrete blocks were used. To process these materials, different kind of vessels (working vessels, hoppers, jack-up platforms, ) were needed. These vessels needed a protected water area for the transfer of the different materials and as shelter during stormy weather. Within the existing port area there wasn t enough protected water area for transfer and shelter. So in a first phase a working harbour had to be constructed, with two important functions: transfer and eventually storage of materials and protection of all the vessels. This working harbour is now better known as the Brittannia Dock. 2. THE BRITTANNIA DOCK After studying different alternatives, the location and the configuration for the Brittannia Dock was chosen as shown in Figure 1 and Figure 2. Between the borders of the Brittannia Dock about 16 ha of water area and about 12 ha of terminal grounds are available. 1 Flemish Authority, Ministry of Public Works, Maritime Access Devision, Belgium, lies.missinne@mow.vlaanderen.be, 2 Flemish Authority, Ministry of Public Works, Maritime Access Devision, Belgium, luc.vandamme@mow.vlaanderen.be 1 of 13

Figure 1: The Brittannia Dock used for handling RoRo-cargo and cars Brittannia Dock Figure 2: Map of the port of Zeebrugge 2 of 13

The quay wall in the south of the Brittannia dock has a length of 530 m and is equipped with a small dock which was used for the loading of working vessels during construction of the outer harbour. The wave climate in front of the quay wall is about 25 % of the climate outside the dock. The tests to check this wave climate were carried out on the wave diffraction model at Flanders Hydraulics in Antwerp. For the construction of the dikes in the Brittannia Dock, dikes under slope were preferred above dikes constructed with caissons because the underground in Zeebrugge is very sensitive for settlements. Within the type of dikes under slope, two alternatives were investigated: rubble mound breakwaters and sand asphalt breakwaters. Finally, this last type was chosen based on the cost benefit analysis. The dikes were constructed on the original underground but under the northern dike an important ground improvement was carried out. Today the Brittannia Dock is used for handling RoRo-cargo and new cars by Cobelfret. In 2008 the following cargo was handled: RoRo-cargo (road haulage units, rhu): 464.821 rhu, 1379 vessels were handled at the terminal. Cars: 412.702 The evolution of processed tonnage is showed in Table 1. This table shows the steep increase of the tonnage during the last 4 years. Table 1: evolution of the processed tonnage in the Brittannia Dock The maximum dimensions of the vessels to be handled in the Brittania Dock are: Length: 203 m Width: 32.9 m Draught: 7.8 m The total terminal surface is 21.2 ha. The terminal efficiency for roro-cargo operations in 2008 amounts to 21.926 rhu/ha which is up to twice as high as the average in the port of Zeebrugge. This leads to the fact that the terminal currently operates over the maximum efficient capacity. Additional cargo handling will lead to congestion effects on the terminal and connecting harbor road and will make operational changes necessary, leading to higher cargo handling costs. Although the terminal has 6 quays and 4 berths, only 3 berths can be used efficiently and safely for RoRo-cargo handling. This is a consequence of the historical background of the Brittannia Dock, as the working harbour: the bottom depth in the biggest part of the dock is at Z-5 and is no longer sufficient to receive today s vessels. So a redesign or upgrade of this port area is needed. This upgrade is carried out by the Flemish authority and the Port Authority Bruges-Zeebrugge. The upgrade consists of three phases: first, a new rubble mound breakwater is constructed over the full width of the Brittannia Dock to cut of a part of the Brittannia Dock. This phase started in March 2008 and will be finished in 2010. In a second phase, the lake that exists after the construction of the breakwater will be filled up. This results in an extension of the terminal with about 10.4 ha. In the last phase a second commercial jetty will be constructed parallel to the new breakwater at the northern side. So in the future, two vessels (type Humbermax) will be able to moor at the same time in the remaining part of the Brittannia Dock. Phase 1 and 2 are paid integral by the Flemish authority. Phase 3 is paid for 80% by the Port Authority and for 20% by the Flemish Authority. The project of the redesign of the Brittannia Dock will have a positive impact on the operational efficiency of the terminal, leading to both cost savings and increasing capacity of the terminal. 3 of 13

3. CONSTRUCTION OF A WORKING AREA As during construction of the new rubble mound breakwater, the existing terminal remains in operation, a working area in the SW-corner of the dock (see Figure 3) was constructed to create some space for the storage of materials. Figure 3: Working area For the construction of this working area geocontainers were used. A geocontainer consists of a geotextile which is unrolled with care in a split barge. Then the split barge is filled with sand and the geotextile is sewed up and reinforced with rope ties. Finally the split barge is positioned and the geocontainer is dumped. By constructing the working area in that way the slope under water could be made steeper (theoretically ½ instead of 1/7 without geocontainers) so less sand was needed for construction of the working area. The making of a geocontainer is shown in Figure 4, Figure 5, Figure 6 and Figure 7. The average volume of one geocontainer is about 270 m³. In total 24 geocontainers were used. The use of geocontainers was a test case to see how easy or difficult it is to handle these geocontainers. The aim was to see if geocontainers can be used in the future in the core of new breakwaters instead of more expensive stones. In total about 47.000 m³ of sand was needed for the construction of this working area. The sand came from the Albert II-dock in the outer harbour of Zeebrugge. This sand was dumped on the new built quay walls at the Albert II-dock when the ground in front of this quay walls was dredged. It was transported over the road during the night to minimize the influence on the traffic in the port. The total surface of the working area is about 3600 m². The working area is mainly used for storage of materials. Figure 4: geocontainer is brought to the split barge Figure 5: Geocontainer is sewed up 4 of 13

Figure 6: geocontainer is reinforced with rope ties Figure 7: geocontainer ready for dumping 4. DESIGN AND CONSTRUCTION OF THE NEW BREAKWATER The new breakwater is a typical rubble mound breakwater with a core of stones 2-300 kg and a covering layer of stones 300-1000 kg. The top level is at +8 m TAW. In the first part of the breakwater (the bend in the western side) the stones in the covering layer moved during a serious storm in October 2008. As a result of this, there was decided to change the stones in the covering layer in that part into stones 1000-3000 kg. Within the breakwater two cross-sections can be distinguished. The western part and the last 80 m in the east are built according to cross-section 1. The part in the middle is built according to crosssection 2. Figure 8: cross-section 1 5 of 13

Figure 9: cross-section 2 About one month before the works should start, probings were carried out from a jack-up platform. The results indicated that under the construction level of the breakwater (which was foreseen at -8 m TAW), there was an important amount of sludge and the original bottom wasn t at -8 m TAW but at - 10.5 m TAW. This wasn t foreseen because a suction hopper dredger had cleaned up the whole construction area. So, before the construction of the breakwater could start, the sludge had to be dredged. In total 65.615 m³ sludge was dredged with a crane on a pontoon, loaded in split barges and dumped on a dumping site at sea. In cross-section 1, the sludge is dredged over about 85 m (this means under the entire width of breakwater + 10 m extra at the seaside of the breakwater) to the original bottom (about -10.5 m TAW). In cross-section 2, the sludge isn t dredged under the entire breakwater but just over a width of about 70 m. There was sought to an optimal solution with a safe design and a minimal dredging width in order to save an amount of money. To save a quantity of expensive stones, there was decided to dump sand to reach the same level as before dredging. In cross-section 1, the sand is dumped to TAW -8 to reach the same construction level as originally foreseen. Because the split barges and the tug-boats were mobilized anyway, there was sought for a solution to optimize the design and save more stones. This optimum was found in collaboration with prof. dr. ir. J. De Rouck from the university of Ghent. So, in cross-section 2, the sand is dumped to -4.5 m TAW. After the sand was dumped, some control probings were carried to check the resistance of the dumped sand. The results were insufficient as can be seen when comparing Figure 10 and Figure 11. This figures show probings which are carried out at the same location before and after dumping the sand. The red line in this figures indicates the same reference level (-10 m TAW). Above this line the influence of the dumped sand can be clearly remarked as can be seen in Figure 11. But the resistance of the sand is less than 2 MPa, so there is a risk of liquefaction of the sand under loading. To avoid this risk, there was decided to carry out a compaction on the outer slope of the dam in cross-section 1. In cross-section 2, a compaction was not necessary because there is no sand under the outer slope of the breakwater in this cross-section. 6 of 13

Figure 10: Probing before dumping the sand Figure 11: control probing after dumping the sand The compaction was carried out with a sheet pile (type AZ 48) which is reinforced with horizontal steel plates (see Figure 12). A vibrator was put on this sheet pile and at each location it vibrated for about 15 minutes to realise a compaction of the sand. Figure 12: Sheet pile used for compaction There was no possibility to do new control probings after compaction, so the efficiency of the compaction could not be tested. 5. CALCULATIONS OF THE BREAKWATER The calculation of the global stability of the breakwater is carried out with two different methods of calculation. These two methods are the Morgenstern-Price method and the finite element method. The software that was used for each method is respectively SLOPE/W (Geoslope) and Plaxis V8 (Plaxis BV). The global safety factor must be at least 1.15 for temporary situations and 1.30 for final situations. Three loading combinations were studied: 7 of 13

BC1: Temporary situation for the outer slope: This situation appears during the filling of the lake at the southern side of the breakwater. When the water level at the northern side is at -1 m TAW (extreme low water) the situation is most critical. BC 2: Final situations for the outer slope: The new created site is now taken into utilization and a loading of 6 ton/m² can be applied. When the water level in the dock is at -1 m TAW (extreme low water) the situation is most critical. BC 3: Temporary situation for the inner slope: This situation appears in the temporary situation between the completion of the breakwater and the filling of the lake. Originally a filter in sand asphalt (with a thickness of 2.5 m) was foreseen on the inner slope. The permeability of a filter in sand asphalt is very low and calculations of the water balance showed that a difference of 2 m in the water level between both sides of the breakwater could appear. Calculations with Plaxis showed that when there s a difference in the water level between both sides of 1 m, the global safety factor is about 1.15. When the difference in water level increases to two meter, the safety factor is less than 1 and the inner slope is no longer stable. To avoid this risk, the decision was taken to change the filter in sand asphalt in a filter of geotextile (see below - FILTERCONSTRUCTIONS). The results of the calculations showed that both with SLOPE/W and Plaxis a safety factor higher than 1.15 was achieved for BC1 and BC3 and a safety factor higher than 1.3 for BC2 (with exception for cross-section 2 with PLAXIS were a safety factor of 1,29 was achieved see Table 2). cross-section 1 cross-section 2 PLAXIS SLOPE/W PLAXIS SLOPE/W BC1 1,42 1,43 1,28 1,32 BC2 1,32 1,33 1,29 1,32 BC3-extreme low water BC3-extreme high water BC3-water level difference of 1 m 6. PROPELLER EROSION 1,32 1,37 1,16 1,22 1,48-1,28-1,15-1,25 - Table 2: Safety factors As can be seen in Figure 9, the construction level of the seawarded toe of the breakwater in cross section 2 is at -10.5 m TAW (original bottom). In cross section 1 the construction level of this toe is at - 8 m TAW. Calculations showed that with the same construction level as in cross section 1 (-8 m TAW) the stones in the toe in the zone of cross section 2 will not be stable under the propeller erosion of the vessels that will moor in the future at the new commercial jetty. That propeller erosion is also the reason why in cross section 1, the stones 300-1000 cover the stones 2-300 kg in the seawarded toe over the whole width. 7. SETTLEMENTS OF THE BREAKWATER The settlements of the new breakwater are measured using two fixed points. The evolution of the altitude of the two reference points in time can be seen in Figure 13. The settlements are partly due to the settlement of the underground under loading and are partly due to the internal compaction of the stones in the breakwater. As can be seen, the settlements are limited. The total settlement in a period of 5 months is less than 8 cm. It must be pointed out that the measurement of the settlements could only start when the construction level of the breakwater was above the water level. So a part of the settlements was not measured. The main reason why settlements were measured was to see the evolution of the settlements in time. Depending on this evolution, the start of the construction of the road on the breakwater was chosen. 8 of 13

Plain concrete will be used for the construction of the road. So it s important to know when the settlement of the breakwater has stopped to avoid structural cracks. Figure 13: settlements in time 8. FILTERCONSTRUCTIONS Two kinds of filter constructions are used in the construction: at the seawarded toe of the breakwater a granular filter is provided which consists of three layers (from the bottom to the top: gravel, stones 0-2 kg and stones 2-300 kg). At the land side of the breakwater, a geotextile in polyester is placed to avoid sand grains from the infilling, migrating through the dam. This geotextile is placed on a layer of stones 0-2 kg with a thickness of about 0.5 m and secured with sand which is gained in the inner harbour of Zeebrugge. There the construction of a new quay wall has finished and the surplus ground must be removed. The sand was gained with a crane on a pontoon, loaded is split barges and dumped in the Brittannia dock. The sand above 0 m TAW was transported to the Brittannia dock over the road and profiled with a crane. The calculations of the filterconstruction are based on the assumption that the filter must be stable on itself for more than one year. To realize this, an enormous amount of ballast must be used as can be seen in Figure 14. Today there must still be supplied 80.000 m³ of sand and 125.000 m³ of ground to realize this filter construction. Originally a filter in sand asphalt was foreseen. Calculations showed that in the temporary situation between the finishing of the breakwater and the filling of the dock, the inner slope of the breakwater might be unstable. The permeability of a breakwater with a filter in sand asphalt is very low, so there was a possibility that under the tidal loading, the filter would be pushed off the breakwater. To avoid this risk and because it was not known how long this temporary situation would take, there was decided to use a filter in geotextile instead of a filter in sand asphalt. 9 of 13

Figure 14: Realization of the filter 10 of 13

9. QUANTITIES OF STONES In Table 3 the quantities of the different materials used for the construction of the breakwater are indicated. Gravel Stones 0-2 kg for the granular filter Stones 2-300 kg Stones 300-1000 kg Stones 1-3 ton 100.000 ton 7.645 ton 200.000 ton 49.000 ton 5.338 ton Table 3: Quantities 10. PHASE 2: FILLING OF A PART OF THE BRITTANNIA DOCK The ground for the filling of the lake at the southern side of the breakwater comes from the inner port of Zeebrugge. The supplies of the ground will be done partly over the road and partly with split barges. 11. PHASE 3: CONSTRUCTION OF A RO-RO JETTY The study of the jetty has started in August 2009. The jetty consists of a gangway (in two parts) which runs parallel to the new breakwater. The gangway is constructed on piles. In front of the gangway but connected to it, 14 bollards will be installed each on their own pile. Eight couples of two piles are placed about 5 m in front of the gangway and are covered with a fender to allow safely mooring of the vessels. The execution of the works will start in January 2010. Figure 15: Ro-Ro jetty parallel to the new breakwater 11 of 13

Figure 16: Cross-section of the jetty The tubes of the jetty have the following characteristics: Tubes for the gangway: length 26 m, steel quality X70, diameter 1420 mm, thickness 19 mm. Tubes for the bollards: length 34.5 m, steel quality X70, diameter 2250 mm, thickness 21.8 mm, filled with concrete over 30.5 m. Tubes for the fenders: length 32.5 or 33 m, steel quality X70, diameter 2250 mm, thickness 21.8 m. 12. TOTAL COST OF THE PROJECT The estimate of the cost of phase 1 amounts to 16.885.938,65. Phase 2 and phase 3 are put out to contract for respectively 17.571.482,54 and 4.781.833,57. This means that the total cost of the projects amounts to 39.239.254,76. All prices are VAT included. 13. CONCLUSIONS The Brittannia Dock in the outer harbour of Zeebrugge was the working harbour during the construction of the new outer harbour of Zeebrugge (which started in 1976). It was the first dock that was built and it was used for transfer and storage of materials and as a protected water area for all kind of vessels used during the construction of the new outer harbour. Due to its historical background, the Brittannia Dock is today no longer optimal equipped to receive today s vessels and the Flemish authority and the port authority Bruges Zeebrugge started in March 2008 with an upgrade of this old port area. The upgrade consists of three phases: in the first phase, a new rubble mound breakwater is built over the full width of the dock. In the second phase the lake that exists after the construction of the new breakwater will be filled up and in the third phase a new commercial jetty will be built parallel to the breakwater at the northern face. So in the future, two vessels (type Humbermax) will be able to moor at the same time in the remaining part of the Brittannia dock. 12 of 13

14. ACKNOWLEDGMENTS The data of the handled cargo at the Brittannia Dock were received from the Port Authority Bruges Zeebrugge. 15. REFERENCES Scheltjens, T. (2009). CBA of roro-terminal extension on the Brittannia Dock in the port of Zeebrugge. Antwerpen, 33 p. Bituminfo 39, December 1980, p. 5-20. Van Damme, L (1992). Propeller Erosion: comparison between calculated and measured velocities at the Hermes terminal in Zeebrugge Belgium. 10 th International Harbour Congress, Antwerp. 13 of 13