The 2017 Panama City Beaches Beach Interim Renourishment Project. Answers to Common Questions

Similar documents
2018 Beach Preservation Project Information

Navarre Beach & Dune Restoration Project Status Report to be regularly updated June 17, 2016 Report

Long Term Success and Future Approach of the Captiva and Sanibel Islands Beach Renourishment Program

Trusted Partners Delivering Value, Today and Tomorrow BUILDING STRONG

Protecting our Beaches

Dauphin Island East End Beach and Barrier Island Restoration Project. Beau Buhring South Coast Engineers

Beach Renourishment in Jacksonville

Dare County Nourishment Project Town of Duck

Climate Change Impacts to KSC Launch Complex

Delaware Chapter Surfrider Foundation - Indian River Inlet Monitoring

FINAL ENVIRONMENTAL IMPACT STATEMENT ON BROWARD COUNTY SHORE PROTECTION PROJECT SEGMENTS II AND III BROWARD COUNTY, FLORIDA

ST. LUCIE COUNTY, FLORIDA

ST. JOSEPH PENINSULA, GULF COUNTY, FLORIDA Beach Re-Nourishment and Environmental Enhancement Project RECOMMENDATIONS

Planning Considerations for Nearshore Placement of Mixed Dredged Sediments

North Shore of Long Island, Feasibility Study

Regular Workshop October 20, 2014 Agenda Item: Dr. Albert E. Browder, PE; Olsen Associates, Inc.

SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT

US Beach Nourishment Experience:

Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update

Building Coastal Resiliency at Plymouth Long Beach

RE: Hurricane Matthew Beach Damage Assessment and Recommendations [CSE 2416]

ATLANTIC COAST OF LONG ISLAND, JONES INLET TO EAST ROCKAWAY INLET, LONG BEACH ISLAND, NY. Contract #2 Construction Scope. April 18th-19th 2018

AGENDA REQUEST AGENDA ITEM NO: IV.B.1. Consent Agenda No. 2. June 4, 2018 BY Development Services Timothy Litchet City Engineer DavisShaw SUBJECT:

County of Santa Barbara Permit Option Analysis Goleta Beach JULY 13, 2017

Town of Duck, North Carolina

CHAPTER 281 INFLUENCE OF NEARSHORE HARDBOTTOM ON REGIONAL SEDIMENT TRANSPORT

AGENDA REQUEST. July 21, 2014 Timothy Litchet

TITLE: North Carolina s Changing Shorelines. KEYWORDS: erosion - shorelines - mapping - sustainability

UPPER BEACH REPLENISHMENT PROJECT RELATED

Beach Restoration in Okaloosa and Walton Counties. FSBPA Technology Conference Clearwater, FL

New Jersey Coastal Zone Overview. The New Jersey Beach Profile Network (NJBPN) 3 Dimensional Assessments. Quantifying Shoreline Migration

AD-A II~lllII I I 7

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL

Louisiana CPRA SJB Group, Baton Rouge Coastal Engineering Consultants U.S. Army Corps of Engineers Federal and State PDT Members

2013 FEDERAL STORM RESPONSE

4/20/17. #31 - Coastal Erosion. Coastal Erosion - Overview

A REVIEW OF THE CONDITION OF THE MUNICIPAL BEACHES AS A RESULT OF HURRICANE SANDY IN THE BOROUGH OF STONE HARBOR, CAPE MAY COUNTY, NEW JERSEY

Follets Island Nearshore Beach Nourishment Project

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING

Appendix F: Public Access Plan

6/19/2006 The Reef Ball Foundation 1

Montserrat. Wise practices for coping with. i b bea n Se a

PINELLAS COUNTY COASTAL MANAGEMENT PROGRAM SUMMARY PLANNING DOCUMENT. Prepared For:

Shoalwater Bay Shorline Erosion Dredging

FINAL REPORT FOR 2013 ON THE CONDITION OF THE MUNICIPAL BEACHES IN THE TOWNSHIP OF UPPER, CAPE MAY COUNTY, NEW JERSEY

Effectiveness of Beach Nourishment in Response to Sea Level Rise

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT

Impact of Hurricane Matthew on the Atlantic Coast of Florida

Beach Nourishment Impact on Beach Safety and Surfing in the North Reach of Brevard County, Florida

Absecon Island Shore Protection The planning behind the project

Recycling of Surplus Sand to Extend the Time Between Beach Fill Episodes

FINDING OF NO SIGNIFICANT IMPACT

Figure79. Location map for the 10 NJBPN profile sites in Atlantic County, NJ 155

FINAL REPORT FOR 2013 ON THE CONDITION OF THE MUNICIPAL OCEANFRONT BEACHES THE BOROUGH OF AVALON, CAPE MAY COUNTY, NEW JERSEY

Coastal Hazards and Management in North Carolina. Braxton Davis April 14, 2015

Inlet Dredging budget also slashes federal

Table 4. Volumetric Change Rates Pre-Project and Post-Project for the Town of Duck

2013 ANNUAL REPORT - TO THE CITY OF NORTH WILDWOOD ON THE CONDITION OF THE CITY BEACHES

2014 ANNUAL REPORT - TO THE CITY OF NORTH WILDWOOD ON THE CONDITION OF THE CITY BEACHES

April 7, Prepared for: The Caribbean Disaster Emergency Response Agency Prepared by: CEAC Solutions Co. Ltd.

La Quinta Channel Extension Port of Corpus Christi Ingleside, Texas. Mark Coyle

HARBOR INFRASTRUCTURE INVENTORIES Marquette Harbor, Michigan

Nome Harbor Page 2 of 12

Cat Island Chain Restoration

SHOREHAM BEACH LOCAL NATURE RESERVE

Broad Beach Sand & Dune Habitat Restoration Project. Revetment Owners Meeting July 12, 2017

Figure 262. Location map for the 10 NJBPN profile sites in Atlantic County, NJ 279

MISSOURI-MADISON RIVER FUND RECREATION PROJECT APPLICATION FORM FY2019

Controlling Coastal erosion

BEACH NOURISHMENT BY RAINBOWING FOR THE VISAKHAPATNAM PORT TRUST BY DCI. Capt. MVR MURTHY ABSTRACT

St. Pete Beach enews. The Official Electronic Newsletter of St. Pete Beach. August 3, 2017

Assateague Island National Seashore North End Restoration Project Timeline

Inlet Management Study for Pass-A-Grille and Bunces Pass, Pinellas County, Florida

USE OF SEGMENTED OFFSHORE BREAKWATERS FOR BEACH EROSION CONTROL

Town of Duck, North Carolina

Investigations and Recommendations for Solutions to the Beach Erosion Problems in the City of Herzliya, Israel

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

2015 ANNUAL REPORT - TO THE CITY OF NORTH WILDWOOD ON THE CONDITION OF THE CITY BEACHES

Chapter 11. Beach Fill and Soft Engineering Structures

BEACH FILL CONSTRUCTION USING SEABED REHANDLING AREAS. Kevin R. Bodge, Ph.D., P.E. 1

United States Department of the Interior

BEACH NOURISHMENT PROJECTS IN CARBONATE MATERIAL BEACH

Grays Harbor Federal Project

David Revell, PhD And others. CSBPA Coastal Conditions 2018 Bodega Bay, CA

Regional Sediment Management Opportunities within Intracoastal Waterway (IWW) Dredging Program in the State of Florida

Your monthly newsletter from the Florida Shore and Beach Preservation Association. Read Full Story

PEASE DEVELOPMENT AUTHORITY DIVISION OF PORTS & HARBORS ANNUAL DREDGE REPORT

KEYNOTE PRESENTATION FSBPA olsen

Saco River Maintenance Dredge PROJECT PLAN AND TIMELINE JUNE 15, 2017

For more information: Photography: Rijkswaterstaat (Leo Linnartz, Carrie de Wilde, Jurriaan Brobbel, Joop van Houdt), Deltares

Beach Scraping at Popham Beach State Park. Phippsburg, Maine

Ennore Coal Port Project: Port Basin and Entrance Channel

EVALUATION OF BEACH EROSION UP-DRIFT OF TIDAL INLETS IN SOUTHWEST AND CENTRAL FLORIDA, USA. Mohamed A. Dabees 1 and Brett D.

Appendix C3. Cost Engineering

The Sand Beaches of New Hampshire and Maine

4/20/17. #32 - Coastal Erosion Case Histories - Lake Michigan

MOREHEAD CITY HARBOR, NC. Dredged Material Management Plan (DMMP)

Figure 38. Locations of the 28 NJBPN profile stations in Ocean County, NJ.

Mouth of the Columbia River Jetties Three-Phase Construction Plan

Transcription:

The 2017 Panama City Beaches Beach Interim Renourishment Project The fourth renourishment of the Panama City Beaches will be under construction during March and April 2017, with a planned completion by May 1 st. This is a very important project for maintaining the health of our beaches! The following questions and answers provide many of the details of the project. Q: Where is this project taking place? Answers to Common Questions The interim renourishment project is taking place along four segments of beach spanning from the west to east ends and totaling approximately 3.5 miles. The approximate half mile Pinnacle Port segment will place sand from just west of Pinnacle Port and into, but not including all of, Carillon Beach to the east. The approximate one-mile City Pier segment will place sand from and including the city pier beach west to the Palazzo condos. The approximate one-mile County Pier segment will place sand from and including the west side of the county pier west to the Casa Loma. The approximate one-mile Treasure Island segment will place sand from and including Moonspinner condos west to approximately just east of Gulf Drive/Hurt Street. Q: How much sand is being placed as part of this project? How does this compare to the 1998/1999, 2005/2006, and 2011 projects? A total of approximately 840,000 cubic yards of sand will be placed within the 4 project areas, although the contract allows for an additional 25% (within the four areas) if deemed necessary at the time of construction. The initial restoration of the Panama City Beaches in 1998-1999 placed approximately 9.8 million cubic yards of sand along the 18.5 miles of beaches. The 2005-2006 project placed approximately 3.3 million cubic yards of sand along 17.5 miles of beaches, and it was conducted in response to 2004 s Hurricane Ivan. The 2011 project placed approximately 1.3 million cubic yards of sand along a total of 7.5 miles of the beaches (east and west ends) and was referred to as a repair project as it was conducted in response to several storms following Hurricane Ivan. That project also formally incorporated and provided a project at Pinnacle Port and Carillon Beach. The current project is a little smaller than the 2011 project and is being called an interim project as it does not encompass the entire shoreline like the first two projects. However, it was deemed necessary due to the

eroded condition of the four segments and should increase the longevity of the entire 18.5 mile project area, thus delaying the need for the next full renourishment. Q: How much is this project costing? And who is paying for it? The construction cost for the repair project is approved up to $17.8 million (if all options/allowances are exercised), although the base bid is $14.1 million, and it is entirely locally-funded. The local cost-share is provided by the Third Cent Bed Tax, an additional one cent bed tax that began being collected in 1997. This beach renourishment fund has ample dollars available for this project. In addition, the Bay County TDC has applied for $4.5 million in State of Florida Beach Management Funding Assistance Program funding. If not secured this year, the Bay County TDC will have two more years to re-apply under this grant program for reimbursement of the state cost-share (approximately 30%). Q: How long will this project take to construct? The project is expected to take approximately two months, however construction may move faster or slower. There may also be circumstances that cause lengthy delays due to construction shutdown, like weather conditions or major repairs to equipment, so please keep checking the Construction Schedule. Q: What is the project schedule? The order of work will be finalized by the contractor and the Bay County TDC prior to construction. At this time, the contractor is expected to utilize more than one dredge, so construction may be occurring in more than one location at one time. Please see the Construction Schedule for further details on schedule. This construction schedule will be updated at least every seven days. Q: Who is managing this project? The Bay County TDC, on behalf of Bay County, will be managing construction of this project. CB&I, formally known as Coastal Planning and Engineering, Inc., the coastal engineering firm that Bay County/the Bay County TDC has retained for coastal engineering services since the mid-1990 s is the engineer of record for the project and will be leading the construction management in conjunction with the Bay County TDC. Q: Who is the dredging contractor?

Weeks Marine is the dredging contractor. They also constructed the 2005-2006 beach nourishment project, which was managed and partially federally-funded by the US Army Corps of Engineers. Q: Where is the sand coming from that is being placed on the beach? The sand for large-scale beach nourishment projects such as this come from our permitted, offshore borrow areas. The main borrow area is located approximately 3.5 miles offshore of the Thomas Drive area, with secondary borrow areas near the St. Andrews Bay entrance channel. Q: How does the sand get to the beach? The sand is dredged from the offshore borrow areas into a hopper dredge. The hopper dredge motors from the borrow area closer to the project site and hooks up to a submerged pipeline. The submerged pipeline runs from just off the beach up onto the beach and connects to shore pipeline, which runs laterally along the dry beach. The sand is discharged as a water/sand slurry mixture through the pipeline, and bulldozers reshape the sand to meet the designed construction template. Q: Why does the sand coming out of the pipe look darker than the sand on the beach? The sand coming out of the pipe is a water/sand mix, and it often contains darker, fine material that wash out as the sand is reshaped on the beach by the bulldozers and dries out over time. This is not contamination. There is a detailed Quality Assurance/Quality Control plan in place that will immediately address any sand quality issues that may arise Q: How fast does the project move down the beach? How long will it be in front of my property? Construction should progress at a rate of 500 feet to 1,500 feet per day. Barring any temporary work stoppages, this means the active construction area may only be in front of your property for a couple days. Please be patient. Everyone, including the contractor, engineers, and the Bay County TDC wants the project to continue moving down the beach and closer to completion. Q: How do I access the beach when construction is occurring in front of my property? How do I get over the dredge pipe? The active work/construction area is limited to an approximate 1,000-2,000-foot section of beach. Simply walk laterally along the beach until you get around the active work area, locate a sand bridge that goes over the dredge pipe, and you will be able to access the Gulf. The

contractor will build these sand bridges over the dredge pipe, which is strung laterally along the shoreline, so that pedestrians may have access to the Gulf. Q: What are the work hours for construction? Unless the work temporarily ceases for repair or weather, work will continue 24 hours a day. These are extremely expensive projects, and it is not feasible to halt work overnight or on weekends. Q: Why is this project important? The beaches of Panama City Beach that you see today are actually the result of three previous nourishment projects one completed in 1998/1999, the second in 2005/2006, and the third in 2011. Hurricane Opal (1995) caused significant erosion of the beaches and left very little dry beach along much of the Panama City Beaches. To combat this erosion, as well as erosion from storms since then, renourishment projects have been undertaken. These projects not only provide recreational beach width for the benefit of residents and visitors, but during storm events, the sand also provides critical protection for structures and infrastructure landward of the beach. Because of the 1998/1999 project, there was very little damage to upland development when Hurricane Ivan struck in 2004. In addition, a healthy beach provides nesting areas for species such as sea turtles and shorebirds. This beach nourishment management program is much like a roadway or other such infrastructure once it is built, it must be maintained. The work you see ongoing now is a small maintenance project that will help ensure continued use of a sandy beach and storm protection for the upland. Q: What about sea turtle nesting? The sea turtle nesting season begins May 1 st, when the project is expected to be complete. There are permitted procedures in place if there are construction delays that cause the project to move into May. Project Areas and Construction Schedule: We will be providing a construction schedule overlaid on aerial photography once a tentative schedule is set. We will update this map and a brief paragraph description of the construction activities at least every seven days.

This schedule is tentative, as well as weather and equipment dependent; please check back frequently for updates!