Update from Port Metro Vancouver Deltaport Third Berth Project Community Liaison Group. Meeting Date: August 28, Construction Update

Similar documents
Corporate. Report COUNCIL DATE: June 26, 2006 NO: C012 COUNCIL-IN-COMMITTEE. TO: Mayor & Council DATE: June 22, 2006

72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME. Public Information Meeting

George Massey Tunnel Replacement Project

Pattullo Bridge Replacement Project Community Connections Phase 2 Consultation. Appendix 3: Open House Display Boards

Design Criteria. Design Criteria

McKenzie Interchange Project Spring 2016 Comment Period. Appendix 1: Display Boards and Feedback Form

Low Level Road Improvements Traffic Analysis. Report

WELCOME PTH 59N - PTH 101 INTERCHANGE FUNCTIONAL DESIGN STUDY PUBLIC INFORMATION SESSION MONDAY, JUNE 13, :00 P.M. - 8:00 P.M.

Transportation Impacts: Toronto York Spadina Subway Extension

WELCOME TO OPEN HOUSE # 1 June 14, 2017

NEW WESTMINSTER AREA STUDY

Date: February 18, 2015 Page: 1 of 9. ICBC invests $1.195 million to improve Surrey, Delta & White Rock roads

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI

City of Prince Albert Statement of POLICY and PROCEDURE. Department: Public Works Policy No. 66. Section: Transportation Issued: July 14, 2014

The Corporation of Delta COUNCIL REPORT Regular Meeting. The following report has been reviewed and endorsed by the Chief Administrative Officer.

Parks Highway: MP Lucus Road to Big Lake Road

Proposed Low Level Road Project

Welcome to the Sellwood Bridge Project Open House!

Chapter 7. Transportation. Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails

List of Display Boards

Wyldewood Estates. Pre-Application Public Engagement Summary of Issues and Responses

Annacis Island Wastewater Treatment Plant OUTFALL PROJECT

Northbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project

WEST AND SOUTH WEST RING ROAD DOWNSTREAM TRAFFIC IMPACTS

SC 41/Joe Rouse Intersection Improvements

ICBC invests $738,000 to make Surrey, White Rock and Delta roads safer

2015 Data review. Capturing Ready Lane NEXUS vehicles

Appendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

1. What is the Doran Street and Broadway/Brazil Grade Separation Project (Project)?

Current Travel Needs and Operating Conditions (See pages 4 9 of the Discussion Guide)

Sixth Line Development - Transit Facilities Plan

5 REQUEST FOR GRADE-SEPARATED PEDESTRIAN UNDERPASS CROSSINGS OF LESLIE STREET AND ST. JOHN S SIDEROAD TOWN OF AURORA

Introduction of the term Traffic Control Zone and formalization of Fraser River Traffic Control Zone procedures

Design of Stanley Park S-Curve

REPORT. Engineering and Construction Department

Johnwoods Street Closure Summary Response

Washington St. Corridor Study

FY 2006 TRANSPORTATION CAPITAL PROGRAM

Welcome! San Jose Avenue Open House August 25, 2015

Marine Environment Plans

Trans-Canada Highway 1 RW Bruhn Bridge Replacement

Lagoon Spawning Bed Rehabilitation

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

COUNTY ROAD 22 HORSESHOE VALLEY ROAD. Municipal Class Environmental Assessment. simcoe.ca

Union Pacific Railroad

North Vancouver Community Associations Network. November 15, pm to 9 pm

Iowa Highway 58 Corridor Improvement Study

Port Mann/Highway 1 Improvements

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012

Welcome. If you have any questions or comments on the project, please contact:

Welcome to the Open House

C C C

Frequently Asked Questions (FAQ)

CITY OF SASKATOON COUNCIL POLICY

PAEKĀKĀRIKI HILL ROAD / BEACH ROAD / SH1 INTERSECTION PROGRESS REPORT

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

Project Description Form 6V

Highway 1 Kamloops to Alberta Four-Laning Program

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

#!! "$% ##! &! # '#! % $ #!

Corridor Studies. LA 415 and LA 73

AIRPORT ROAD ENVIRONMENTAL ASSESSMENT

ICBC invests $1.175 million to help make Surrey, Delta and White Rock s roads safer in 2013

George Massey Tunnel Replacement Project

STATE AID FOR LOCAL TRANSPORTATION Rev. July 2010 De MINIMIS WRITE-UP FOR PM For parks, recreation areas, wildlife or waterfowl refuges Page 1 of 3

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway

SCHEME DESIGN AND ENGINEERING

8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN

4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL

North Shore Transportation Improvement Strategy

The Corporation of Delta COUNCIL REPORT Regular Meeting. BNSF Railway Company North Colebrook Siding

ECONOMY PEOPLE ENVIRONMENT

Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017

Capital Beltway HOT Lanes Project

Corporate. Report COUNCIL DATE: May 25, 1998 NO: R1500 REGULAR COUNCIL. TO: Mayor & Council DATE: April 27, 1998

SANTA MONICA BOULEVARD CORRIDOR

ITEM 2.3 South of Fraser Rapid Transit Surrey-Langley technology decision. That the Mayors Council on Regional Transportation receive this report.

REPORT CONCURRENCE. City Manager. The General Manager concurs with the recommendation of this report.

5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION

Richmond-Adelaide Cycle Tracks

2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE

A plan for improved motor vehicle access on Railroad Avenue in Provincetown

Public Involvement Outreach Requirements for Public Information Open House Meeting: C.N , HSIP-5003(12) 132 nd and West Center Road, Omaha

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.

Traffic Management Guidelines for Structure Rehabilitation Projects

Welcome to the McKenzie Interchange Project Open House!

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN

Draft North Industrial Area-Wide Traffic Plan

(This page left intentionally blank)

MOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9.

TEMPORARY TRAFFIC CONTROL GUIDELINES FOR HIGHWAY-RAIL GRADE CROSSINGS

University Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007

Portland International Airport Bicycle and Pedestrian Plan (October 2003) Staff Acknowledgements

ADA on Construction. Guidance for Section C Plan Preparers

Mission Bay Loop (MBL) Public Meeting

Accommodating Pedestrians in the Work Zone

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection

I-215 / NEWPORT ROAD INTERCHANGE PROJECT PRESS KIT

Service Business Plan

Transcription:

Update from Port Metro Vancouver Deltaport Third Berth Project Community Liaison Group Meeting Date: August 28, 2008 Construction Update General Update The Marine Works portion of the project is progressing well with regard to schedule - the contractor (DCL) is slightly ahead of the schedule it originally submitted in December, 2006. Six of the ten caissons, including four of the six re-floated caissons, have been placed in their final locations and filling of them is proceeding well. On-site repairs of the two damaged caissons (already re-floated) are progressing well. DCL is leaving the remaining two caissons on the seabed until the rock mattress in their final caisson trench locations has been fully prepared for their placement. This rock mattress preparation is in progress. Preloading of a large area in the west of the expansion footprint has been completed and preloading of the southeastern area is in progress. Seaspan has been relocated to the new tug basin. The Westshore safety boat has been relocated to a new facility at Westshore Terminals. Interim relocation of the Roberts Bank Lifeboat Society has been arranged, as has a final on-site location acceptable to Seaspan and the Port. TSI has issued its first tender call for the terminal works. Although several months behind the schedule TSI originally anticipated, TSI still hopes to complete its terminal works shortly after the completion of the Port s Marine Works. Barge Berth Discussions with DFO regarding the proposed temporary barge berth are still in progress. DFO is reviewing environmental impacts and assessing what compensation may be required. No approval has yet been given. Highway 17 The Hwy 17 northbound off ramp leading onto Hwy 99 southbound is nearly complete. The Hwy 17/Ladner Trunk Road intersection work is behind schedule due to BC Hydro and Delta Cable delays in the relocation of their services. The project is expected to be completed by mid September.

Environmental Update AMS 2007 Annual Report The first annual report for the Adaptive Management Strategy is now available. It has been posted on the DP3 Project Website (still being hosted at www.portvancouver.com for the time being). A summary information sheet is also available on the site. Habitat Compensation Sandbar Stabilization: Baseline data gathering has been completed and analysis under way. DFO wishes to review the findings before making a decision on whether we should proceed with the pilot project. Since that review cannot be completed until later in the fall, this project s physical works will not proceed until next year, dependent on DFO approval. East Causeway: There has still been no DFO decision on the temporary barge berth so this project is still on hold. The Port has been making strenuous efforts to comply with the requirements of the EAO s Table of Commitments and Assurance, by finding a way to import the necessary materials by water via the proposed barge berth, instead of trucking them through Delta (approximately 15,000 one-way truck trips would be needed for this habitat compensation project). Reefs: Some base rock has been installed work is expected to continue in the next few weeks as equipment becomes available. Salt Marsh: Tenders have been called for the last phase of the salt marsh enhancement works (culvert installation and drainage channel extension). That work is expected to be completed this fall. Caisson Refugia The caisson refugia have been cast into the caissons. Habitat becomes available as each caisson with refugia is placed. Off-site Compensation (Rose-Kirkland Island): Work on the off-site compensation is in progress. It is not expected to be complete this year. Page 2 of 6

Response to questions since June meeting Questions from DCLC regarding proposed barge berth (submitted by R. Emsley) 1. Was this in the original assessment documentation? The proposed temporary barge berth was not included in the original environmental assessment for the project. The proposal has been submitted to DFO for consideration. If the project is not approved, the Port and TSI will be have to ship material for the Habitat Compensation work and terminal construction work through Delta by truck. The Port would prefer the temporary barge berth option to moving materials through Delta. 2. Who is assessing the environmental impact of this placement? DFO is assessing the proposal for the temporary barge berth. 3. Who is the approving authority is it DFO and have they given the go ahead? DFO. They have not given approval for the temporary barge berth. 4. How much of the material required to construct the barge berth will remain once it is no longer needed. What will be done with any temporary material? The material for the temporary barge berth will be removed when it is no longer needed. All the material is temporary and will be disposed of in an environmentally acceptable manner, yet to be determined. 5. From the diagram it looks as though the northerly dredge slope protrudes into the inner causeway. Is this temporary? The dredge slopes of the tug basin will be restored to the approved design grades and locations when the temporary materials are removed. 6. When is this construction going to take place? Construction timing depends on DFO approval. If DFO approval is received, the Port and TSI would like to start the construction as soon after approval as possible. Questions from DCLC regarding Orca s sighted at Roberts Bank on August 5, 2008 (submitted by R. Emsley) The Port appreciates public reports of marine mammal activity. This sighting will be included as a civilian sighting. 1. Was the sighting observed by the port environmental monitor? This particular sighting was not observed by the Port s environmental monitor. The activity on-site at the time of the sighting was limited in nature. Construction Page 3 of 6

practices were observed and recorded by the environmental monitor earlier that day until approximately 4:00pm. 2. At what time was the first sighting of this pod? Please see response to question #1. The contractor was not operating equipment within the vicinity of the pod. Most of the work underway was being conducted within the caisson alignment. 3. Is it possible to obtain a copy of the port environmental monitor s log? The daily logs are for the purpose of the environmental monitor to present daily records of activity to the contractor and the Port. The daily logs are used to create the weekly environmental monitor reports and are not provided outside of this scope. These reports would present a significant challenge for interpretation of the engineering aspects, scientific related aspects, and intent of the Authorization. 4. What work on DP3 was being done at that time? On August 5 th, the Shark Bite tug the Island Brave was only on day shift. From 06:45 to 17:00, all tugs were working on Caisson recovery. Assisting the No. 8, Bev Sue in the remaining parked caisson area. The tug was not active at 19:30. The Raider and the Pacific Hawk, both Gisbourne tugs, were only needed on night shift for two moves. The first at 19:30 to take a partial loaded dump scow from the 1402 clam shell, and dump the load, on the west side of caisson 22, building Rock Berm. After this dump, they put the empty barge on the small buoys adjacent to the work site. From 19:45 to 20:30 the tugs then picked up the loaded Ka Ala flat barge off one of the outside, large buoys and brought this barge to the west side of C19 adjacent to the 1402 clam shell. The only construction activity after this was the 1402 clam shell placing the berm filter along the west side of Caisson # 19. At midnight, the Raider conducted quick check of on all the floating barges. 5. Was the work stopped? No. Please see #1 and #4. 6. Why was the port tug allowed to drive at full speed right through the middle of the pod? We do not have enough information from this public report to identify and determine these details. Tug operators are aware of the marine mammal monitoring program. The Port is currently working on developing an education and awareness program for the general public and port tenants on marine mammal sightings. Page 4 of 6

Questions from DCLC regarding birds (submitted by R. Emsley) (Please note that the Port is reviewing these questions and will respond shortly) 1. Did the osprey nest this year noting that the birds are still in the area? I (Roger Emsley) have an additional to question in relation to this. The MOE response indicates that VFPA could be asked to develop an alternative nesting site. Has this/will this be considered since they are still in the area? 2. Is the list of birds in the fact sheet meant to be the list of all birds in the Deltaport 3 Berth area? If so it is certainly missing a lot of species where are all the duck species other than a couple mentioned, Pacific loon, Common loon, red-necked grebe? It is the most peculiar list I have ever seen for Roberts Bank birds, including some very rare accidental ones and missing many that are regulars. Was it meant to be just red and blue-listed species? This area is part of the Fraser River Estuary Important Bird Area and I would have thought consideration of the species on the IBA list would have been part of the monitoring. Follow-up regarding 28 th Avenue - concern that analysis be conducted DCLC s concern was forwarded to Gateway on July 2 nd. Please see response below. In conjunction with Port Metro Vancouver and the Corporation of Delta, the Gateway Program s South Fraser Perimeter Road (SFPR), jointly funded an analysis of intersections in the Deltaport Way Area including 28 th Avenue. The analysis supplements the broader Roberts Bank Rail Corridor Project that is being undertaken jointly by the federal government (Transport Canada) the Province, Port Metro Vancouver, TransLink, the Corporation of Delta and other municipalities, and railway companies including BC Rail. The analysis was conducted to support and facilitate discussions related to the proposed closing the south portion of the 57B Street/ Deltaport Way intersection, as a safety and efficiency measure, and provision of alternate access for farm traffic and local residents, via a new 28th Avenue overpass of Highway 17. Gateway Program arranged for traffic counts (including vehicle types) to be undertaken at 14 existing intersections in the Deltaport Way area. Gateway then undertook additional analysis to understand the potential traffic implications of the proposed new traffic routing. The traffic analysis included consideration of a redistribution of traffic patterns in the area as a result of the new road configuration, including potential changes in traffic volumes on 28 th Avenue and 34B Avenue in the vicinity of 57B Street. The results indicate that volume changes on the local roads would be minor and would not likely result in significant operational or safety issues. The results also indicate that traffic would increase along 28th Avenue if the overpass were built. Page 5 of 6

It should be noted that a new overpass at 28 th Avenue would only be constructed if the southern portion of the 57B Street/Deltaport Way intersection were closed. There currently has been no decision to reconfigure this intersection or construct a new overpass. In particular, it is specifically not part of the South Fraser Perimeter Road project scope. Any decision regarding this road network change would be made by all agencies involved and would consider the results of this traffic analysis as well required road upgrades, if any, and the potential effects, to Delta s overall road network. Page 6 of 6