Hospital Link Project Project Update September 2017

Similar documents
Hospital Link Project Project Update November 2017

Replacement of N. Carlin Springs Road Bridge over George Mason Dr.

Design Criteria. Design Criteria

Cincinnati Dayton Rd Widening

PROJECT FACT SHEET May 25, 2018

COMPLETE STREETS DURING CONSTRUCTION

4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL

2017 Temporary traffic control guidelines for pedestrians. v.2

5. RUNNINGWAY GUIDELINES

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

PERFORMANCE ACTIVITY 405 LIMB MANAGEMENT

Traffic Control Inspection Checklist Segment:

PROJECT FACT SHEET March 21, 2018

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

I-215 / NEWPORT ROAD INTERCHANGE PROJECT PRESS KIT

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Attached for your reference please find project updates on ongoing VDOT construction projects in Southampton County.

IL Route 71 Construction Update

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY

December 15, City of Ottawa Planning and Growth Management Branch 110 Laurier Ave. W., 4 th Floor Ottawa, ON K1P 1J1

Chapter 3 DESIGN SPECIFICATIONS

CPC Parking Lot Riverside Drive. Transportation Rationale

Functional, Preliminary Design and Detailed Design

CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES

Agenda Item # Page # RECOMMENDATION

Southside Road. Prepared for: City of St. John s Police & Traffic Committee. Prepared by: City of St. John s Traffic Division

Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting

St. Francis Drive through the City of Santa Fe Corridor Study

83 AVENUE PRE-CONSTRUCTION MEETING

Welcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m.

Complete Streets. Designing Streets for Everyone. Sarnia

Zlatko Krstulich, P.Eng. City of O9awa

Tonight is for you. Learn everything you can. Share all your ideas.

Downtown Redevelopment Project Update

Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE

LESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #2

Washington St. Corridor Study

MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY

Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax

Accommodating Pedestrians in the Work Zone

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

INDEX. Geometric Design Guide for Canadian Roads INDEX

APPENDIX L. Design Criteria

Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE

Work Session. Agenda Item # 4. Meeting Date September 8, Daryl Braithwaite Public Works Director. Prepared By. Suzanne R. Ludlow City Manager

19 July 2016 OUR REF:

City of Margate, Florida. Neighborhood Traffic Management Manual

Cycle Track Design Best Practices Cycle Track Sections

DRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan

Pre-Construction Meeting

UPDATES 11/14/2018: 10/25/2018: CLOSED 10/22/2018: 10/12/2018: 10/05/2018: 09/27/2018:

C C C

Bases, Ballasts, and Paving

ADA on Construction. Guidance for Section C Plan Preparers

City of Beverly Hills North Santa Monica Blvd Reconstruction. Community Meeting Presentation September 30 and October 1, 2015

PERFORMANCE ACTIVITY 306 DRAINAGE PIPE WORK DESCRIPTION 4

MEMORANDUM. Earl Haugen and UND Transportation and Traffic Coordination Committee

ODOT construction cost is $51,000,000. State assumes and bears 100 percent of the cost of improvement.

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

3.9 Recreational Trails and Natural Areas

Broad Street Bicycle Boulevard Design Guidelines

RZC Appendix 8A Marymoor Subarea Street Requirements

Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017

Appendix A Guiding Principles for Cycling Safety in Work Zones

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007

Shore Drive Safety Task Force. Report to the SDAC

section 4 Existing Conditions, Issues, and Options

Rio Intersection Traffic Restrictions Begin Monday

Designing Pedestrian Facilities for Accessibility. Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in Work Zones

122 Avenue: 107 Street to Fort Road

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS

Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

Developed by: The American Traffic Safety Services Association (ATSSA) 15 Riverside Parkway, Suite 100 Fredericksburg, VA

A465 Heads of the Valleys Dualling Sections 5 and 6 Dowlais Top to Hirwaun SUMMARY PROOF OF EVIDENCE. Highways Engineering Document WG 1.3.

Pennsylvania Avenue (CR 484) Design Alternatives Study

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Spring/Summer Traffic and Construction Technical Briefing

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs

CITY OF ROHNERT PARK CITY COUNCIL AGENDA REPORT

6.4 RECOMMENDED IMPROVEMENTS

McKenzie Interchange Project Spring 2016 Comment Period. Appendix 1: Display Boards and Feedback Form

Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE

Information on display. Inside this handout. Triangle Area revisions. Project need displays. Preferred alternative on aerial maps

WORK ZONE TRAFFIC CONTROL PROCEDURES

Glebe Neighbourhood Cycling Plan

East Burke Transportation, Safety and Capacity Improvements

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI

CHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems

Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017

Blair/Williamson Intersection Expressed Needs

Traffic Circulation & Pedestrian Safety Study

Transcription:

Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important construction updates. Construction Forecast Over the next month, neighbours can expect the following impacts: Level of dust will be low to medium. North Level of noise will be low to medium. Level of vibration will be low. Key Plan of Hospital Link Level of construction traffic will be medium to high through Hincks lane, Frobisher Drive, Old Riverside Drive, and Alta Vista Drive. Work Completed To Date Dust monitoring equipment is installed near the VIA corridor and Old Riverside Drive. Riverside Drive is in its final configuration. All four lanes of traffic are now open. All the new mainline storm sewers have been installed on the project except for sections between Old Riverside Drive and Alta Vista Drive and at the east end of the Hospital Link. The 914 mm feedermain is commissioned. A new large diameter storm sewer is constructed from the Rideau River easterly toward Old Riverside Drive. Installation of the 2400 mm x 1800 mm box storm sewer between the Transitway and the VIA shoring wall is complete. The Riverside Structure is mostly complete except for expansion joints seal installation and testing. The Transitway Structure has been constructed as well as the adjacent retaining walls. Construction of the VIA structure and VIA culvert north of the structure is complete.

2 The majority of underground traffic plant and street lighting infrastructure has been installed west of Riverside drive and between Alta Vista Drive and the Hospital Ring Road. The VIA diversion track is in service. The VIA shoring wall installed is complete and monitored weekly. New Hydro Ottawa plant has been installed with sections along the east side of Realigned Riverside Drive, along the Hospital Link from the substation on Old Riverside Drive to Ring Road, along the Hospital Link east of Alta Vista and along Alta Vista Drive. Removal of all overhead Hydro Ottawa power cables and relocation to the new underground duct bank on Old Riverside Drive is complete. The north cul de sac on Old Riverside Drive is partially built, including placement of asphalt. Old Riverside remains permanently truncated where the Hospital Link crosses it with a pedestrian detour in place. Installation of the retaining walls adjacent to 1725 Old Riverside is complete. Storm sewer installation on Frobisher Lane between Realigned Riverside Drive and Old Riverside Drive is completed. Grading and maintenance of landscaping along Realigned Riverside Drive is complete. Grade raises along the VIA mainline and utility relocations at the VIA structure are complete. Riverside Structure deck paving is complete including installation of expansion joints and construction of the parapet walls. Concrete medians and islands at the Riverside Drive/Hincks Lane intersection are completed. Construction of the retaining walls at Old Riverside Drive is completed. Maintenance shoulders have been replaced along the Transitway. Key Activities this Month The key activities anticipated for the month of September 2017 include: Alta Vista Drive and Future Link Road intersection Roadway construction for the intersection of Alta Vista Drive and Link Road will continue in September 2017. Traffic control plan will be implemented to accommodate installation of underground utilities, streetlighting, traffic signals, concrete curbs and medians, and asphalt surfacing. The temporary pedestrian detour will be implemented in early September 2017 with pedestrians routed on the sidewalk along the east side of Alta Vista. Lane width reductions with reduced speeds will remain in place along Alta Vista Drive. The bike lane will remain closed on Alta Vista Drive. Realigned Riverside Drive Landscaping and sidewalks will be completed in early September at the Riverside Drive/Hincks Lane intersection. Old Riverside Drive Construction of the south cul de sac on Old Riverside Drive will commence in early September 2017.

3 Dust monitoring equipment is installed near the VIA corridor and Old Riverside Drive; monitoring will continue in September 2017. Frobisher Lane Frobisher Lane bridge modifications may start in end of September 2017 with traffic control plan in place. Construction of the multi use pathway on the Frobisher Lane Bridge over the Transitway will tie into the south cul de sac on Old Riverside Drive. The sidewalk between the Frobisher Bridge and Realigned Riverside Drive will be connected in September 2017. The multi use path along the west side of Riverside Drive (south of Frobisher) will be constructed in mid September 2017. Connection to Hospital property Tie ins to the Hospital Ring Road and Link Road T intersection is underway and will continue in September 2017 including grading and paving of the Link Road connection and implementation of the traffic control plan. Transitway Concrete curbs along the Transitway will be placed in September 2017. Transitway Structures Construction of the Transitway retained soil structures and backfilling of the Transitway structure will continue in September 2017. VIA Rail Structure and Track The new mainline track construction will be commissioned in September 2017. Night work may be required to completed adjustments on the new mainline track. Decommissioning and removal of the temporary diversion track and shoring wall will commence in September 2017. Riverside Structure Riverside Structure expansion joints will be injected and sealed in September 2017. Expansion joints will be tested in October 2017 following completion of asphalt and surfacing on the approaches to the bridge. Storm Sewer Installation Storm sewers between Alta Vista Drive and the Transitway will continue in September 2017 including the remaining installations of the Moses Pepper Drain. Traffic Impacts The project has been designed to mitigate lane closures along Riverside Drive and Alta Vista Drive as much as possible. The following activities summarize the anticipated traffic impacts expected over the next month:

4 Traffic Impacts There will be no weekday peak period lane reductions on Riverside Drive or Alta Vista Drive. Weekday peak lane reductions may be required in the traffic control plans for Frobisher Lane bridge modifications and the Hospital Ring Road construction. There is expected to be temporary lane width reductions with reduced speeds along Alta Vista Drive for construction of the Alta Vista/Link Road intersection. Traffic will be shifted to the west side as intended in the second phase of traffic control plan. There are no significant traffic impacts affecting vehicles, or cyclists expected on Riverside Drive. Old Riverside Drive is permanently closed to traffic, pedestrians and cyclists where the Hospital Link crosses it. Pedestrians are detoured on Realigned Riverside Drive. Access to all residents by motor vehicle is maintained through one access point at each end as follows: 1541 to 1635 Old Riverside, access Old Riverside by Hincks Lane. 1725 to 1841 Old Riverside, access Old Riverside by Frobisher Lane. The bike lane will remain closed on Alta Vista Drive. General Traffic Information Motorists are reminded to obey reduced speed limits within construction zones and exercise caution when driving through active construction sites. Motorists are notified of changes to traffic patterns using Portable Variable Message Signs. A pedestrian detour has been put in place for at the intersection of Hincks Lane and Old Riverside Drive to eliminate pedestrians traveling through Riverside Drive and Hincks Intersection. Signage has been put in place to caution vehicles to pedestrian crossing accordingly. Protected left turn signals are installed for south bound traffic at the intersection of Frobisher Lane and Realigned Riverside Drive, and at the intersection of Hincks Lane and Realigned Riverside Drive. Lane width reductions on Alta Vista Drive and staged traffic plans will continue in September 2017. The roadway lane will continue to be shared between motorist and cyclists. Construction vehicles will be entering and exiting the work areas listed below. The access will be similar to any private access location and flag personnel will be posted as required if potential traffic issues are identified. Alta Vista Drive; East of Riverside Drive accessed through Hincks Lane traffic signals; The Transitway work area accessed through Old Riverside Drive and Frobisher Lane; The VIA work zone accessed through Old Riverside Drive, west of Alta Vista intersection and Old Riverside Drive. Old Riverside Drive accessed from the north through Hincks Lane and from the south through Frobisher Lane. Pedestrian Impacts Temporary pedestrian detour to the sidewalk along the east side of Alta Vista will be implemented in early September 2017. The following sidewalks will remain temporarily closed to pedestrians:

5 Crosswalks through the intersection of Hincks Lane and Riverside Drive Sidewalks along Riverside Drive (from Hincks Lane north to the existing Transitway Structure) Pedestrians are detoured along the east sidewalk of Riverside Drive, the south sidewalk of Hincks Lane, and the east sidewalk of Old Riverside Drive. Signage will be posted directing pedestrians and vehicles through this detour for the duration of the closure. Old Riverside Drive truncated where the Hospital Link crosses it, and is permanently closed to pedestrian traffic through this area. Pedestrians are detoured through Frobisher Lane, the new multiuse pathways along the east side of Realigned Riverside Drive, and the Lycée Claudel OC Transpo Transit Station. Transitway Impacts There may be potential lane reductions during off peak hours on the Transitway for placement of concrete curbs in September 2017. Weekend and Night Work All night work is subject to the approved Noise By law exemption. Residents in close proximity to the work will be provided with advance notice when night work is required. The following activities summarize the anticipated weekend or night work over the next month: Weekday night work may be required in the VIA corridor for adjustments on the new mainline track. VIA Rail has a rail replacement project throughout their corridor including adjacent to the Hospital Link site. VIA may be doing night work outside of the contract limits.

6 Project Pictures The following pictures are provided for your information. Construction of the VIA bridge structure is complete. Preparation and construction of the VIA Rail new mainline track over the VIA structure

7 Construction of the retaining wall near Old Riverside Drive Retaining walls construction on new Transitway Structure

8 Asphalt surfacing on Link Road east of Alta Vista Construction of Alta Vista & Link Road intersection is underway