Caltrans compendium of underwater sound data from pile driving 2014 update

Similar documents
Final. Technical Guidance for Assessment and Mitigation of the Hydroacoustic Effects of Pile Driving on Fish

SR 411, Lexington Bridge Underwater Noise Monitoring Results

Description of Underwater Noise Attenuation System Design Unit 2. New NY Bridge Project

Pile Driving and Barotrauma Effects

San Francisco Oakland Bay Bridge East Span Seismic Safety Project FISHERIES AND HYDROACOUSTIC MONITORING PROGRAM COMPLIANCE REPORT

Underwater Sound Level Report: I-90 Keechelus Lake Avalanche Bridge Blasting

UNDERWATER SOUND LEVELS ASSOCIATED WITH PILE DRIVING AT THE CAPE DISAPPOINTMENT BOAT LAUNCH FACILITY, WAVE BARRIER PROJECT

Janek LAANEARU and Aleksander KLAUSON Department of Mechanics, Tallinn University of Technology

Effect on Marine Life by Noise of Offshore Wind Farm S.JIANG 1 & J.P. HOU 1

SEISMIC SURVEY GREENLAND 2014 Underwater sound propagation for North East Greenland offshore seismic survey

Final Report: Measurements of Pile Driving Noise from Control Piles and Noise-Reduced Piles at the Vashon Island Ferry Dock

Use of a low power, airgun sound source to accurately determine sound. Transmission Loss characteristics at the proposed Robin Rigg. Windfarm site.

Benefit of ESTCP/SERDP Research Program on Underwater Explosive Safety

PRINCIPAL UNDERWATER NOISE SOURCES IN BALTIC SEA AND METRICS USED IN NOISE LEVEL ASSESSMENT

Assessment of cumulative Sound Exposure Levels (SEL) for marine piling events

Naval Base Kitsap-Bangor Explosives Handling Wharf 2. Year 1 Marine Mammal Monitoring Report ( )

Item 404 Driving Piling

ARA PROJECT Prepared by: Peter T. Dzwilewski Applied Research Associates, Inc Shaffer Parkway Littleton, Colorado 80127

Underwater noise and offshore windfarms

Characterizing The Surf Zone With Ambient Noise Measurements

7 th International Conference on Wind Turbine Noise Rotterdam 2 nd to 5 th May 2017

Appendix F: Ecology F-6 Methodology for Estimating Potential Hydroacoustic Impacts to Abundant Hudson River Fish Species and Shortnose Sturgeon from

USING A PROBABILITY APPROACH TO RANK IN-LINE INSPECTION ANOMALIES FOR EXCAVATION AND FOR SETTING REINSPECTION INTERVALS

APPENDIX D-2. Sea Level Rise Technical Memo

Distribution Statement A: Approved for public release; distribution is unlimited.

Centre for Marine Science and Technology

Chapter 20.0 Marine Noise and Vibration

The operational phase will result in noise from operational vessel movements.

APPENDIX P. Noise Model Results and Supporting Material

inter.noise 2000 The 29th International Congress and Exhibition on Noise Control Engineering August 2000, Nice, FRANCE

Habitat Use and Behavioral Monitoring of Hawaiian Monk Seals in Proximity to the Navy Hawaii Range Complex

Examples of Carter Corrected DBDB-V Applied to Acoustic Propagation Modeling

EXPERIMENTAL RESULTS OF GUIDED WAVE TRAVEL TIME TOMOGRAPHY

Guidance on piling, heavy loads, excavations, tunnelling and dewatering

APPENDIX S REVISED PAGES OF THE SUPPLEMENTAL TRAFFIC IMPACT ANALYSIS

Near-Field Sturgeon Monitoring for the New NY Bridge at Tappan Zee. Quarterly Report July 1 September 30, 2014

South King County High-Capacity Transit Corridor Study

Task 16: Impact on Lummi Cultural Properties

THE PRIMARY SOURCES OF SHIP NOISE OBSERVED ON THE BOTTOM OF SEA KAROL LISTEWNIK

Waves, Bubbles, Noise, and Underwater Communications

Offshore platforms survivability to underwater explosions: part I

7.0 Construction Noise Impact Assessment

Review of new information on pollution, underwater sound and disturbance: Military, including munitions

under: the Resource Management Act 1991

WESTHAVEN MARINA EXTENSION ACOUSTIC ASSESSMENT Rp December 2017

USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT

Sea State Analysis. Topics. Module 7 Sea State Analysis 2/22/2016. CE A676 Coastal Engineering Orson P. Smith, PE, Ph.D.

PUV Wave Directional Spectra How PUV Wave Analysis Works

INTEGRITY MANAGEMENT OF STRESS CORROSION CRACKING IN GAS PIPELINE HIGH CONSEQUENCE AREAS

Introduction to Underwater Acoustics Simulator. Poul Kronborg Product Area Owner, Marine MIKE Software Products DHI

Lesson 8 Piles Bearing & Acceptance Transcript. Welcome to the Pile Driving Inspector Course. This is Lesson 8 Piles Bearing & Acceptance.

Bob Battalio, PE Chief Engineer, ESA September 8, 2016

Final Cruise Report Marine Mammal Observer UNDET Monitoring Hawaii Range Complex, April, 2011

Outlet Structures T-12

Sizing Pulsation Dampeners Is Critical to Effectiveness

Status: Rev: Comments Date: Authors: Reviewer:

Perched Box Caisson Overview. January 2014

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY

LIFE TIME OF FREAK WAVES: EXPERIMENTAL INVESTIGATIONS

Appendix 10: Clarification Note Blasting Methodology and Mitigation

CMST Project 1504, Report , Date Prepared: 18-May-2017

Underwater noise generated by merchants ships in coastal waters of the Gulf of Gdansk

Ascent to Altitude After Diving

~ A Behavioral Response Study in 2007 &2008 (BRS 07/08) was conducted in the Bahamas to

Anthropogenic Noise and the Marine Environment

MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY

Managed Lanes in California:

Appendix 7. Wind and Comfort Impact Analysis

Waves, Bubbles, Noise, and Underwater Communications

Adulteration of underwater acoustic measurements

Final Report Alaska Department of Fish and Game State Wildlife Grant T July 1, 2003 June 30, 2006:

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Experimental Results of Motion Responses of High Speed Marine Crafts. Magnús Þór Jónsson

Federal Railroad Administration. HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018

Submarine Base, Groton, Conn.

Seismic Sources. Seismic sources. Recorders. Requirements; Principles; Onshore, offshore. Digitals recorders; Analog-to-Digital (A/D) converters.

Appendix E Cat Island Borrow Area Analysis

Annex E Bridge Pier Protection Plan

ANALYZING THE SHIP DISPOSAL OPTIONS

GROUND VIBRATION DURING GRAVEL PILE CONSTRUCTION

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

Influence of wind direction on noise emission and propagation from wind turbines

Calibration Summary of Test Report No.: Sample

DECEMBER 15-18, 1997 ADELAIDE, SOUTH AUSTRALIA. Douglas H. Cato. Defence Science and Technology Organisation PO Box 44, Pyrmont, NSW, 2009, Australia

Product outline. Titel. BBC-big bubble curtain. Revision: 12/10/2018

Regional Analysis of Extremal Wave Height Variability Oregon Coast, USA. Heidi P. Moritz and Hans R. Moritz

Tsunamis. Tsunamis COMMUNITY EMERGENCY RESPONSE TEAM TSUNAMIS

Measurements of underwater noise in the Arun River during piling at County Wharf, Littlehampton

Taking of Marine Mammals Incidental to Specified Activities; San Francisco- Oakland Bay Bridge Pier E3 Demolition via Controlled Implosion

Fortified For Safer Living

Northbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project

Approved. Property Test/Standard Description. gloss (70-85) Flash point ISO 3679 Method 1 55 C VOC-US/Hong Kong. US EPA method 24 (tested)

Utilization of Screw Piles in High Seismicity Areas of Cold and Warm Permafrost

Safety assessments for Aerodromes (Chapter 3 of the PANS-Aerodromes, 1 st ed)

The effect of close proximity, low height barriers on railway noise

APPENDIX 9.8-A. Construction and Terminal Activity Underwater Noise Modelling Study Technical Report

A REVIEW OF THE 2000 REVISIONS TO ANSI 2530/API MPMS 14.3/AGA REPORT NO. 3 - PART2 Paul J. LaNasa CPL & Associates

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 1 PINE COUNTY

5 HUMAN BEINGS ELECTRICAL AND MAGNETIC FIELDS

Sound and Light in the Ocean

Transcription:

Caltrans compendium of underwater sound data from pile driving 2014 update Richard RODKIN 1 ; Keith POMMERENCK 2 1 Illingworth & Rodkin, Inc., United States 2 Illingworth & Rodkin, Inc., United States ABSTRACT In 2009 the California Department of Transportation (Caltrans) published Technical Guidance for Assessment and Mitigation of Hydroacoustic Effects of Pile Driving on Fish (1). The purpose of the technical manual is to provide Caltrans engineers and biologists, and consultants with guidance related to the environmental permitting of pile driving projects in or near water. Appendix I Compendium of Pile Driving Sound Data provides a summary of measured underwater sound levels for a variety of pile driving situations. The Compendium originally summarized and reported data from 36 projects between years 2000 2006. The Compendium was updated in 2012 with addition of 21 projects and updated again in 2014 with the addition of new data from 12 projects. The projects added in 2012 and 2014 included various types of pile driving for coastal and river bridges, harbors and wharfs, additional construction of the San Francisco Oakland Bay Bridge, and a major structure over water being built for the US Navy. This paper highlights several interesting projects and updates analyses of the data base. Keywords: Underwater noise, Pile driving I-INCE Classification of Subjects Number(s): 54.3, 12.2.3 1. INTRODUCTION The 2014 Compendium update will provide information on sound levels measured underwater during pile driving in the states of California, Oregon, Washington, Alaska, Hawaii, Idaho, and Nebraska, USA. The document is an empirical database to assist in predicting underwater sound levels from marine pile driving projects and determining the effectiveness of measures used to reduce the sound level. Descriptions and data are provided for major and minor projects with a variety of different pile and hammer types that were completed within the last 14 years beginning with the Pile Installation Demonstration Project for the San Francisco-Oakland Bay Bridge in December 2000. The Compendium originally summarized and reported data from 36 projects between years 2000 2006. The Compendium was updated in 2012 with the addition of 21 projects and updated again in 2014 with the addition of new data from 12 projects. The projects added in 2012 and 2014 included various types of pile driving for coastal and river bridges, harbors and wharfs, additional construction of the San Francisco Oakland Bay Bridge, and a major structure over water being built for the US Navy. All monitoring projects included in the Compendium were completed by Illingworth & Rodkin, Inc. The nearly 70 projects described in the Compendium provide information on a wide variety of conditions that affect sound levels in the water in the vicinity of pile driving. These data can be very useful to engineers and scientists who are responsible for predicting the effects of pile driving on biological resources. The Compendium was written to address potential impacts on fish, but the data are also applicable to the assessment of potential effects upon other biological resources such as marine mammals, diving birds, and turtles. The data demonstrate that, in addition to the obvious factors expected to affect sound levels such as hammer size and pile type, other factors such as water depth, geotechnical conditions, and topography cause significant variations in sound levels generated by pile driving and the potential effectiveness of control measures. Guidance is provided on how to use 1 rrodkin@illingworthrodkin.com 2 kpommerenck@illingworthrodkin.com Inter-noise 2014 Page 1 of 9

Page 2 of 9 Inter-noise 2014 the data in the Compendium to best estimate sound levels and the noise reduction that may be achievable through the use of various control measures for the set of conditions specific to a particular project. 2. COMPENDIUM OVERVIEW 2.1 Organization The Compendium is generally organized by pile type and hammer type (either impact or vibratory). Large and complex projects that include a variety of pile types and hammer types are discussed in separate chapters. The 2014 Compendium update will include a summary chapter; chapters addressing various pile types including steel pipe, cast-in-steel shell (CISS), steel H-type, concrete, steel sheet, and timber; and, several chapters devoted to major multi-year projects that typically included a variety of pile types and driving hammers including the San Francisco Oakland Bay Bridge begun in 2000 and now in the demolition phase of the old bridge, the Benicia Martinez Bridge, and the Richmond San Rafael Bridge seismic strengthening project. The Summary provides an analysis of the data including representative data for various pile types during vibratory and impact pile driving. The data and relevant conditions from each monitoring project are then summarized. The discussion for each project includes a description of the conditions at the site, the pile type and size, the hammer type, the description of the attenuation system if one was used, measurement locations, and measurement results. During the early monitoring projects the criteria included Peak and RMS sound levels, so these data were measured and reported. Frequency spectra and pressure-time histories for the pile strikes were also measured and reported for most projects included in the Compendium. Beginning in 2002-2003 the Sound Exposure Level (SEL) for individual pile strikes and subsequently the cumulative SEL for the driving of each pile and the driving of piles during each day were calculated as the various criteria addressing the effects were refined. 2.2 Summary of Impact and Vibratory Pile Driving Data Data from many of the projects that are described in the Compendium are summarized in Table 2.2.1 for impact hammers and Table 2.2.2 for vibratory installation. Not included in these tables are sound levels associated with use of attenuation systems or use of a drop hammer. Results from these projects were highly variable and cannot be summarized into one level for a certain type of pile. These tables summarize results from un-attenuated pile driving at positions close to the pile. Information includes the pile type, pile size, water depth, and measured peak, root mean square (RMS), and sound exposure level (SEL) where available. The peak pressure is the level based on the absolute value of the largest positive or negative pressure associated with the pulse. The RMS level for impact driving is calculated using the portion of the pulse containing 90 percent of the energy, ignoring the 5 percent contained in the initial and final segments. For vibratory driving the RMS level is the average over the period of the driving time. The Compendium provides additional more extensive summary tables to assist the user. Table 2.2.3 is a portion of one project summary table from the Compendium for pile driving activities that did not use attenuation systems. These data can be used as a ready reference and for comparative purposes when screening a proposed project. In practice the Compendium is most helpful when one digs deeper and mines the projects with similar conditions for the most representative data. 2.3 Example Project Tongue Point Facility Pier Repairs, Astoria, Oregon Each pile driving project included in the Compendium is described in a summary report. The following summary report for the Tongue Point Facility Pier Repairs is a representative example: Ten piles were monitored over a two-day period at the Point Pier in Astoria, Oregon under the terms of the Underwater Noise Monitoring Plan. The hydroacoustic monitoring was conducted for pile driving with a D-46-42 Diesel impact hammer installing 24 steel shell piles through the existing pier. A multi-level bubble ring was used to reduce the sound pressure from the pile driving. The hydroacoustic data with and without bubble rings operating are primarily reported for individual pulses as peak sound pressure level (SPL), Root Mean Square (RMS) impulse sound pressure level, and the sound exposure level (SEL); and the accumulated SEL is reported for the driving events. Page 2 of 9 Inter-noise 2014

Inter-noise 2014 Page 3 of 9 Table 2.2.1 - Summary of near-source (10 m) un-attenuated sound levels for pile driving using an impact hammer Average Sound Level Relative Water Measured (db) 1 Pile Type and Approximate Size Depth Peak RMS SEL 0.30 m (12 in) steel H-type thin <5 m 190 175 160 0.30 m (12 in) steel H-type thick ~5 m 200 183 170 0.36 m (14 in) steel H type - thick ±6 m 208 -- 177 0.61 m (24 in) AZ steel sheet ~15 m 205 190 180 0.33 m (13 in) plastic pile 10 m 177 153 -- 0.30 m (12 in) concrete pile Land based 176 -- 146 0.46 m (18 in) concrete pile <3 m 185 166 155 0.61 m (24 in) concrete pile ~5 m 185 170 160 0.61 m (24 in concrete pile ~15 m 188 176 166 0.30 m (12 in) steel pipe pile <5 m 192 177 -- 0.36 m (14 in) steel pipe pile ~15 m 200 184 174 0.41 m (16 in) steel pipe pile 3 m 182 -- 158 0.51 m (20 in) steel pipe pile ± 3 m 204 161 -- 0.61 m (24 in) steel pipe pile ~15 m 207 194 178 0.61 m (24 in) steel pipe pile ~5 m 203 190 177 0.76 m (30 in) steel pipe pile ± 3 m 210 190 177 0.91 m (36 in) steel pipe pile <5 m 208 190 180 0.91 m (36 in) steel pipe pile ~10 m 210 193 183 1.52 m (60 in) steel CISS pile 2 <5 m 210 195 185 1.68 m (66 in) steel pipe pile 3 Land Based 197 3 -- 173 3 1.83 m (72 in) steel pipe pile Land Based 204 -- 175 2.21 m (87 in) steel pipe pile 4 Land Based 194 4 -- 160 4 2.44 m (96 in) steel CISS pile ~10 m 220 205 195 2 CISS - Cast-in-steel shell 3 Measured 17 meters from pile 4 Measured 35 meters from pile Inter-noise 2014 Page 3 of 9

Page 4 of 9 Inter-noise 2014 Table 2.2.2 - Summary of near-source (10 m) un-attenuated sound pressure levels for in-water pile installation using a vibratory driver/extractor Average Sound Level Relative Water Measured (db) 1 Pile Type and Approximate Size Depth Peak RMS SEL 0.30 m (12 in) steel H-type <5 m 165 150 150 0.30 m (12 in) steel pipe pile <5 m 171 155 155 0.91 m (36 in) steel pipe pile ~5 m 180 170 170 0.61 m (24 in) AZ steel sheet ~15 meters 175 160 160 0.61 m (24 in) AZ steel sheet ~15 meters 182 165 165 0.91 m (36 in) steel pipe pile ~5 meters 185 175 175 1.83 m (72 in) steel pipe pile ~5 meters 183 170 170 1.83 m (72 in) steel pipe pile ~5 meters 195 180 180 Project Tongue Point Pier, Astoria, OR 2 0.61 m (24 in) steel pipe pile - D46 SR 520 Test Piles, Seattle, WA 3 0.76 m (30 in) steel pipe pile Russian River Bridge, Ukiah, CA 4 1.68 m (66 in) steel pipe pile - D132 Parson Slough, Monterey, CA 5 Steel H-piles APE19-42 Table 2.2.3 Excerpt from expanded project summary table Water Depth Distance ± 4 m 10 m 20 m 3 7 m 10 m On-Land 200 m 500 m 17 m 110 m 4 m 10 m 20 m Average Sound Level (db) 1 Peak RMS SEL 205 198 196 177 160 197 183 200 190 188 180 185 161 145 185 168 178 174 173 162 172 146 135 173 157 166 162 Attenuation Rate with Distance 6 23Log 15Log 10m to 200m 20Log 10m to 500m 17Log 30Log - Peak 15Log - SEL 2 Permanent piles driven through holes in the existing pier. Measurements were part of a test of the effectiveness of a bubble ring system. 3 Test pile project, pile driven in soft substrate. 4 Permanent piles driven on land, the Russian River depth was less than 1 meter. 5 Small diesel hammer in deep water. 6 Calculated from the data values. Not valid within 10 m of pile. Page 4 of 9 Inter-noise 2014

Inter-noise 2014 Page 5 of 9 Figure 2.3.1 - One level of the multi-stage bubble ring Figure 2.3.2 Deployment of the bubble rings All piles were measured at 10 meters at the mid-water depth and three piles were additionally measured at 20 meters also at the mid-water depth. The underwater sound was measured continuously throughout the duration of the drive. The effectiveness of the bubble ring was tested by turning the bubble rings off for short intervals at the beginning of the drive, part way through the drive, and near the end of the drive. Table 2.3.1 shows a summary of the data collected in terms of the peak SPL, RMS and the single-strike SEL. With the bubble rings turned off the average Peak SPL was 197 db re: 1µPa and ranged from 189 db to 207 db. The average single strike SEL was 168 db re: 1uPa 2 -sec and the levels ranged from 160 db to 175 db. The average RMS imp was 182 db re: 1µPa and the levels ranged from 178 db to 189 db. With the bubble rings turned on the average Peak SPL was 183 db re: 1µPa and ranged from 172 db to 189 db. The average single strike SEL was 156 re: 1uPa 2 -sec and the levels ranged from 151 db to 160 db. The average RMS imp was 167 db re: 1µPa and the levels ranged from 159 db to 172 db. The average Accumulated SEL measured, including the bubble on/off tests was 189 re: 1uPa 2 -sec and the levels ranged from 180 db to 193 db. The average calculated Accumulated SEL, not including the bubble ring off portion of the tests, was 182 db re:1µpa 2 -sec and ranged from 177 db to 184 db. During driving time when the bubble rings were turned off the impulses were characterized by higher peak levels and a faster rise times that translated into higher frequency sound energy content. When the bubble ring was used the average reduction in peak SPL was 14 db and the reductions ranged from 5 db to 22 db. While the levels were reduced throughout the frequency range the 100 to 500 Hz range is where the greatest reduction occurred with the use of the bubble rings. Analyses of pulses recorded at 10 meters with the bubble rings on and off are shown in Figure 2.3.3. The bubble rings off pulse had considerable high frequency content that was effectively attenuated with the bubble ring on. The bubble ring provided about 19 db of attenuation of the peak pressure. The typical SEL per strike was 176 db without the bubble ring and 160 db with the bubble ring. A test of the effect of the power settings for the hammer was conducted on pile 5 with the bubble ring system on. The power setting was started out at 1 and was increased by one every couple of minutes until it reached the highest setting of 4. The average peak noise levels went up by 4 db from power setting one to power setting two. After the initial increase the average peak noise levels did not increase with the increase in power. Inter-noise 2014 Page 5 of 9

Page 6 of 9 Inter-noise 2014 Table 2.3.1 - Summary of sound levels measured at 10 meters during driving of 24-inch steel shell piles Pile # Peak (db) 1 RMS (db) 1 SEL (db) 1 Average Maximum Average Maximum Average Maximum Average Reduction Attenuated With Bubble Rings 1 197 196 183 181 171 169 14 2 206 202 186 183 175 171 19 3 193 193 178 178 168 168 10 4 196 195 186 184 167 167 10 5 ND 1 ND ND ND ND ND ND 6 ND ND ND ND ND ND ND 7 190 190 ND ND 161 161 12 8 205 204 189 188 174 173 17 9 199 196 ND ND 171 170 13 10 199 197 182 181 170 169 11 Un-attenuated Without Bubble Rings 1 188 182 172 166 161 155 14 2 183 180 175 164 159 155 19 3 190 186 170 168 160 157 10 4 189 189 174 168 160 158 10 5 187 184 169 167 157 156 ND 6 185 181 168 165 157 153 ND 7 178 175 165 161 153 151 12 8 190 187 174 169 161 159 17 9 187 185 171 169 159 156 13 10 188 186 171 172 159 157 11 2 ND No Data Page 6 of 9 Inter-noise 2014

Inter-noise 2014 Page 7 of 9 Table 2.3.2 - Summary of sound levels measured at 20 meters during driving of 24-inch steel shell piles Pile # Peak (db) 1 RMS (db) 1 SEL (db) 1 Average Maximum Average Maximum Average Maximum Average Reduction Attenuated With Bubble Rings 6 171 167 ND 2 ND 147 145 -- 7 173 167 ND ND 144 141 20 10 172 171 155 154 142 141 12 Un-attenuated Without Bubble Rings 6 ND ND ND ND ND ND -- 7 191 188 ND ND 163 161 20 10 192 182 170 166 157 153 12 2 ND No Data Table 2.3.3 - Average sound levels with various power settings on impact hammer (bubble rings on) Power Setting/ Energy Rating Peak (db) 1 RMS (db) 1 SEL (db) 1 1 st / 55,932 ft-lbs 180 164 152 2 nd / 75,646 ft-lbs 185 168 155 3 rd / 95,130 ft-lbs 186 169 156 4 th / 114,615 ft-lbs 185 168 156 Inter-noise 2014 Page 7 of 9

Page 8 of 9 Inter-noise 2014 Tongue Point Dock Repair - Comparison of Bubble Rings Off and ON - @ Pile 8 11/18/08 Figure a. Waveform 2.0E+10 1.5E+10 Figure b. Narrow Band Frequency Spectra 180 170 Bubbles Off Sound Pressure ( µpa ) 1.0E+10 5.0E+09 0.0E+00-5.0E+09-1.0E+10-1.5E+10 Bubbles Off Bubbles ON Spectral Sound Pressure (db re 1µPa) 160 150 140 130 120 110 Bubbles ON -2.0E+10 0.00 0.02 0.04 0.06 0.08 0.10 0.12 0.14 Time ( sec ) Figure c. Accumulation of Sound Energy Sound Energy Accumulation (db re 1µPa^2 sec) 180 170 160 150 Bubbles Off Bubbles ON 140 0.00 0.02 0.04 0.06 0.08 0.10 0.12 0.14 Time ( sec ) 100 0 625 1250 1875 2500 3125 3750 4375 5000 Frequency ( Hz ) Figure d. Sound Pressure and Sound Energy Levels Signal Analysis Sound Pressure / Energy Levels Peak RMS90%* SEL Bubbles Off 204 193 176 Bubbles On 185 172 160 Typical Sound Pressure / Energy Levels Throughout Drive Reported Average Reported Maximum Peak Off / On SEL Off / On 205 / 187 174 / 159 207 / 190 177 / 162 *Impulse averaged over 90% of accumulated energy ( 5% to 95% ) Figure 2.3.3 - Representative signal analyses for un-attenuated and attenuated piles 3. APPLICATION IN BIOLOGICAL ASSESSMENTS Data in the Compendium are useful when evaluating the potential adverse effects of underwater sound resulting from a proposed marine pile driving project upon biological resources. The sound field in the water results primarily from both direct sound transmission from the pile and sound radiated from the sea or river bottom. The relative contributions depend upon water depth, whether or not attenuation systems are used (and their effectiveness), and geotechnical conditions affecting the pile resistance and propagation characteristics beneath the bottom. The data in the Compendium have proven to provide a solid basis for empirical modeling for the purpose of biological assessments. There are several steps necessary to make a reasonable prediction of pile driving noise from the data in the Compendium. First, find examples of projects with similar pile types and sizes. Then select the appropriate hammer type, either impact or vibratory. Sometimes this information is not known, so assumptions that lead to credible worst case conditions must be made. Frequently a combination of pile driving methods is used, where the pile is vibrated in and then proofed with an impact hammer to confirm that the specified resistance has been achieved. The next step is to identify projects that have similar settings, for example a project where piles are driven in a bay or a river. Many projects include piles driven in the water and on land near the shore, and both can result in significant sound levels in the water. The other critical element is the prediction of the performance of the attenuation system. The attenuation provided by a bubble curtain or other system only affects the direct contribution radiated from the pile. Measurements of pile driving on land near shore and in fully de-watered coffer dams demonstrate that the ground-borne component of the pulse results in high sound levels in the water. So caution must be used when evaluating the benefits of proposed attenuation systems, particularly for piles driven in shallow water near shore. One can confidently use the data in the Compendium to predict underwater sound levels from a proposed project when these factors are properly considered. As more well documented data becomes available the accuracy of empirical and theoretical models will further improve. Page 8 of 9 Inter-noise 2014

Inter-noise 2014 Page 9 of 9 ACKNOWLEDGEMENTS The authors acknowledge the support of the California Department of Transportation and staff at Caltrans Headquarters for funding and directing the preparation of the Compendium, and David Buehler of ICF International for his leadership in the crafting of the manual Technical Guidance for Assessment and Mitigation of Hydroacoustic Effects of Pile Driving on Fish wherein the Compendium resides, REFERENCES 1. ICF International, Illingworth & Rodkin, Inc. Technical Guidance for Assessment and Mitigation of Hydroacoustic Effects of Pile Driving on Fish. California Department of Transportation, Sacramento, California. February 2009 (2014 update pending). http://www.dot.ca.gov/hq/env/bio/files/guidance_manual_2_09.pdf Inter-noise 2014 Page 9 of 9