Stability of Pipeline and details of Anchor blocks

Similar documents
Learn more at

Design Data 22M. Flotation of Circular Concrete Pipe. w w I = w - x 1000 (3) (SG x 1000)

ON-BOTTOM STABILITY CALCULATIONS FOR FIBRE OPTIC SUBMARINE CABLES

Homework of chapter (3)

Irrigation &Hydraulics Department lb / ft to kg/lit.

Assistant Lecturer Anees Kadhum AL Saadi

Theory of a vertically loaded Suction Pile in CLAY

U S F O S B u o y a n c y And Hydrodynamic M a s s

STRIDE PROJECT Steel Risers in Deepwater Environments Achievements

Presented by. Mr.Danish.D.R. M.Tech Coastal Management Institute for Ocean Management Anna University, Chennai Tamil Nadu, India.

Yasuyuki Hirose 1. Abstract

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE

UNIT-I SOIL EXPLORATION

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE

Field Development & Construction

Reinforced Soil Retaining Walls-Design and Construction

Learn more at

MASSACHUSETTS INSTITUTE OF TECHNOLOGY DEPARTMENT OF MECHANICAL ENGINEERING 2.06 Fluid Dynamics

TECHNICAL CIRCULAR. Circular No: S-P 32/13 Revision: 1 Page: 1 of 7 Date:

STABILITY OF MULTIHULLS Author: Jean Sans

The Challenge of Wave Scouring Design for the Confederation Bridge

EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE

Garrett McNamara, Portugal, 30 Jan What is a wave?

Slide 1 / What is the density of an aluminum block with a mass of 4050 kg and volume of 1.5 m 3?

Buoyancy Control Calculated Cost Allowance for 1 Year Study Cost Estimate

THE LIGHTS GO OUT The Ultimate Protection Technology for Protecting Submarine Cables

EXCITING WORLD OF STEEL STRUCTURES

Keywords: Submarine pipeline; Well graded soil; High hydraulic conductivity; Horizontal and vertical wave forces; Minimum safe burial depth.

Sustainable Installation & Maintenance Methods Keith McDermott Commercial Director for Tidal Energy Mike Wilson - Managing Director Mike Wilson

APPENDIX D Oil Loading Pipeline - Options

Cook Inlet pipeline crossing is about making the best choices

RIGID RISERS FOR TANKER FPSOs

Old-Exam.Questions-Ch-14 T072 T071

BEACH NOURISHMENT BY RAINBOWING FOR THE VISAKHAPATNAM PORT TRUST BY DCI. Capt. MVR MURTHY ABSTRACT

[Barve, 4(7): July, 2015] ISSN: (I2OR), Publication Impact Factor: 3.785

Undertow - Zonation of Flow in Broken Wave Bores

PIPELINE DESIGN, OPERATION AND MAINTENANCE COURSE CONTINUING PROFESSIONAL DEVELOPMENT RESULTS SHEET

Department of Civil & Geological Engineering GEOE Engineering Geology

Formation level = m. Foundation level = m. Height of the wall above the Ground Level = 7.42 m

CVEN 311 Fluid Dynamics Fall Semester 2011 Dr. Kelly Brumbelow, Texas A&M University. Final Exam

Septic Tank Buoyancy Control 101. David Lentz, P.E.

DESIGN OF AXIALLY LOADED STEPPED FOOTING DATA :- SBC of soil =200 KN /m 2 Concrete Mix =M20 Steel Grade = Fe 415 Clear cover of bottom slab =50 mm

TECHNICAL MEMORANDUM 002 EMORANNO. 001

BUOYANCY, FLOATATION AND STABILITY

Undertow - Zonation of Flow in Broken Wave Bores

Comparison and Sensitivity Investigations of a CALM and SALM Type Mooring System for Wave Energy Converters

Using sea bed roughness as a wave energy dissipater

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

Feasibility of Steel Lazy Wave Risers in the North Sea

. In an elevator accelerating upward (A) both the elevator accelerating upward (B) the first is equations are valid

Aidin Kazemi Daliri, Sepanta Naimi*

and its weight (in newtons) when located on a planet with an acceleration of gravity equal to 4.0 ft/s 2.

What is a wave? Even here the wave more or less keeps it s shape and travelled at a constant speed. YouTube. mexicanwave.mov

Ship Resistance and Propulsion Prof. Dr. P. Krishnankutty Ocean Department Indian Institute of Technology, Madras

FLUID MECHANICS Time: 1 hour (ECE-301) Max. Marks :30

Pumping Systems for Landscaping Pumps, Controls and Accessories. Mark Snyder, PE

Intro r duct u io i n o - 3 -

Hydrographic Surveying Methods, Applications and Uses

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

Design a grit chamber for population with water consumption of 135 LPCD.

Angela Lane, Lowe Environmental Impact / Karen Akuhata (WDC) The Wairoa wastewater treatment system requires a replacement consent by May 2019.

COURSE NUMBER: ME 321 Fluid Mechanics I Fluid statics. Course teacher Dr. M. Mahbubur Razzaque Professor Department of Mechanical Engineering BUET

CIVL473 Fundamentals of Steel Design

International Journal of Advanced Engineering Technology E-ISSN

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd

Edit this text for your title

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017

Learn more at

Module 15 : Grit Chamber. Lecture 20 : Grit Chamber

PHYS 101 Previous Exam Problems

Tutorial 5 Relative equilibrium

What are Waves? Earthquake. Waving flags. Vocal Cords Vibrate

Analysis and Research of Mooring System. Jiahui Fan*

19.1 Problem: Maximum Discharge

(Refer Slide Time: 1:01)

NPCA Buoyancy White Paper

New Innovative Anchor Solution for Deepwater Mooring Gravity Intalled Anchors Reduce Time and Costs of Marine Operations Jon Tore Lieng CTO

A NOVEL FLOATING OFFSHORE WIND TURBINE CONCEPT: NEW DEVELOPMENTS

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING TUTORIAL QUESTION BANK

Chapter 10 Waves. wave energy NOT the water particles moves across the surface of the sea. wave form moves and with it, energy is transmitted

IOPF Proceedings of the 6th International Offshore Pipeline Forum. IOPF 2011 October 19-20, 2011, Houston, Texas, USA

Artificial headlands for coastal restoration


Vertical Uplift Capacity of a Group of Equally Spaced Helical Screw Anchors in Sand

Preliminary study of moored power cables

ESCI 343 Atmospheric Dynamics II Lesson 10 - Topographic Waves

DIMENSIONING WATER SUPPLY SYSTEM IN BUILDING

Flexible Spools Solution at Hybrid Risers Base A. Karnikian, Total and S. Tarbadar, M. Bonnissel, S. Legeay, Technip France

NORDEX. Foundations. Nordex N117/3000

A Scale Model Test on Hydraulic Resistance of Tunnel Elements during Floating Transportation

ANALYSIS OF THE POSITIVE FORCES EXHIBITING ON THE MOORING LINE OF COMPOSITE-TYPE SEA CAGE

TEPZZ A_T EP A1 (19) (11) EP A1 (12) EUROPEAN PATENT APPLICATION

Maritime Renewable Energy

Effect of Wind Pressure on R.C Tall Buildings using Gust Factor Method

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

PHYSICS - CLUTCH CH 17: FLUID MECHANICS.

Wave Energy. ME922/927 Wave energy

STUDIES ON THE TRANQUILITY INSIDE THE GOPALPUR PORT

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

Transcription:

Stability of Pipeline and details of Anchor blocks For Offshore pipeline laying at Gulf of Kutch, Gujarat. Client WELSPUN (I) LTD, Gujarat EPC Contactor PATEL CONSTRUCTION CO. Consultants Prof. R. Sundaravadivelu Prof. K. Murali DEPARTMENT OF OCEAN ENGINEERING INDIAN INSTITUTE OF TECHNOLOGY MADRAS CHENNAI, INDIA - 600 036 November 2015

CONTENTS 1. Background of the client... 1 2. Introduction... 1 3. Stability of Outfall Pipeline... 1 4. Forces acting upon the Pipeline... 2 5. Stability Calculation... 2 List of Figures Fig 1: General Arrangements of Anchor block... 7 Fig 2: Reinforcement details of Lower anchor block... 8 Fig 3: Reinforcement details of Upper anchor block... 9 Fig 4: Details of Fastening and accessories...10 List of Tables Table 1: Design Specification for Anchor blocks... 2 Client: Patel Construction, Gujarat ii

1. Background of the client Welspun city is situated at Anjar town in Gujarat state is a diversified manufacturing base spread over 2500 acres land established in 2004 having more than 25000 employees. Welspun group companies harbors Home Textile-Terry Towel & Bed sheets, steel pipes & plates manufacturing units at Anjar facilities. Welspun Indian Ltd, a group co. of Welspun, intent to lay onshore & offshore pipeline into Gulf of Kutch & awarded an EPC contract to M/s Patel Construction Company for laying onshore & offshore pipeline for treated waste water disposal into sea. 2. Introduction Patel construction, Gandhidham, have taken up installation of an outfall pipeline near Tekra, Gandhidham. The pipeline carries treated industrial waste water. The total quantity of water is about 25 MLD discharged in 22 hrs. The pipeline diameter is envisaged to be 500mm OD. It is expected to be buried 5000mm below the prevailing sea bed. The density of effluent is 1005 kg/m3 and ambient water density if 1023 kg/m3. The following table summarizes details of pipeline parameters and wave cum current environment at site. For wave and conditions, earlier studies carried out at Gulf of Kutch by is used. Given Data Pipe Dia D = 500 mm Thckness of pipe t =20 mm Inner dia of pipe d = 460 mm Density of pipe ρ p = 950 kg/m 3 Density of water ρw = 1035 kg/m 3 Maximum possible wave height H 0 = 0.8 m Mean wave period T = 3.5 sec Surface current V = 1.2 m/sec Safety factor γ w = 2.5 3. Stability of Outfall Pipeline Stability calculation for HDPE pipelines have been performed for Effluent disposal at Gulf of Kutch, Gujarat. These pipelines span from pumping station on the landward end to the marine outfall location. The total length of outfall line is 9 km. The pipeline is to be laid below the seabed with a suitable over burden. The over burden suggested for the present pipeline is 5000mm. Normally, a over burden of 1 Diameter is the minimum required. In the present case, the project region has high currents. Hence, higher over burden may be needed. It is 1

recommended that a over burden of 1000 mm is sufficient as the stability of pipeline is ensured by anchor blocks. In buried pipelines, anchor blocks are needed for sinking the pipeline. However, in the present case, there is high possibility of pipeline being exposed by removal of over burden by current and wave. Hence, stability shall be provided by anchor blocks. The design shall be as per DNV RP- F109. From high water level to about 1m water depth location, the pipeline might be destabilized if not anchored properly. Hence, the stability of the same has to be critically evaluated to ensure serviceability of the pipelines all throughout its design period. 4. Forces acting upon the Pipeline A pipeline laid at or beneath the sea bed experiences an uplift force due to buoyancy and a downward force due to gravity. In deepwater conditions the weight of water column above the pipeline also accounts for the downward force in addition to the self-weight of the pipeline, and the bed particle velocity is also negligible. In near shore conditions the risk of uplift of pipelines is very high, since the net force acting in the downward direction is lesser than that in deepwater condition due to the absence of water column. To overcome this problem, anchorage block units made of RCC will be deployed. These blocks weigh 3.493 kn and are placed at 0.8m centre to centre spacing to ensure stability. 5. Stability Calculation Table 1: Design Specification for Anchor blocks Depth (m) Area of concrete Block (m 2 ) Thickness of Concrete (m) Volume of Concrete provided (m 3 ) Volume of Concrete required (m 3 ) Weight required Vertical stability (kn) Absolute lateral Stability (kn) Weight Provided (kn) Spacing 1 0.95 0.25 0.238 0.22 3.26 3.25 3.493 2 0.95 0.25 0.238 0.17 3.26 2.53 3.493 3 0.95 0.25 0.238 0.14 3.26 2.11 3.493 4 0.95 0.25 0.238 0.13 3.26 1.9 3.493 5 0.95 0.25 0.238 0.12 3.26 1.71 3.493 0.8 m C/C 6 0.95 0.25 0.238 0.11 3.26 1.54 3.493 7 0.95 0.25 0.238 0.10 3.26 1.46 3.493 2

Stability of pipeline and details of Anchor blocks Stability Calculation Given Pipe Dia Thickness Inner dia Density of pipe Density of sea water Maximum possible wave height Mean wave period Surface current Saftey factor Depth of Water Deep water wave angle D = 0.50 m t = 0.02 m d = 0.460m ρ p = 950 kg/m^3 9.5 kn/m^3 ρ w = 10.35 kn/m^3 Ho = 0.8 m T = 3.5 Se V = 1.2 m/sec γw = 2.5 d = 1 m θ0 = 40 Degree n0 = 0.5 Solution Vertical stability in water i)pipe buoyancy per unit length B =ρw x Vol. of submerged pipe b= 2.55 kn ii) Weight of submerged pipe Ws = Vol. of pipe x ρ p Ws= 0.50 kn I. Vertical stability in water Ws = Wpipe + W Anchor Block Take 1 Weight of anchor block Wc= 3.26 kn

Stability of pipeline and details of Anchor blocks II. Absolute lateral stability Horizontal Force Vertical Force Oscillatory velocity amplitude for single design oscillation, perpendicular to pipeline. U* Wave Length calculation Using linear wave theory, U* = 0.36 m/sec V* = 1.2 m/sec Peak horizontal co. efficient C*y = 1.35 From C*z = 0.94 table Penetration depth Trench depth Reduction factor Z.p = 0.25 M 50% of Dia of Pipe Z.t = 1.5 Z.p/D = 0.50 Z.t/D = 2.68 r.perm = 0.9 r.pent.y = 0.3 r.pent.z = r.tr.y = 0.7 r.tr.z = r.total.y = 0.19 r.total.z = 0.29 0.5 From chart 3.5 0.65 & 3.7 DNV Horizontal Force

1.79 kn Vertical Force 1.93 kn Absolute static stability Co-efficient of friction Saftey factor of soil 0.2 0.8 γ.sc = 1.4 From table 1.4 - DNV Passive soil resistence FR= VRL contact pressure Un-drained clay shear strength Dry unit soil weight FC= s.u = Ws-FZ 1.90 1 k.c = 0.30 γ.s = 18 kn/m 3 G.c = 0.10 for clay FR = 2.28 0 Absolute static stability Take 1 Weight of anchor block Wc = 3.25 kn I

Wc = 2.14 kn II Volume of Concrete Vc = 0.22 M 3 Towing Condition i) Buoyancy force for 1 pipe b= 2.55 kn ii) Weight of submerged pipe Ws = Vol. of pipe x ρp + Weight of Concrete block Ws= 4.06 kn Ws > b So provide one pipe on top of upper anchor block to enable floatation while towing. b= 5.10 kn Ws= 4.63 kn Ws < b The configuration of marine outfall pipelines and the reinforcement details for an Anchor block are shown in the Fig.1 to Fig.4 respectively.

Fig 1: General Arrangements of Anchor block 7

Fig 2: Reinforcement details of Lower anchor block 8

Fig 3: Reinforcement details of Upper anchor block 9

Fig 4: Details of Fastening and accessories 10