Using Valve Performance in Gas Lift Design Software

Similar documents
32 nd Gas-Lift Workshop. Optimizing Subsea Well Kick-off Operations Case Study Using FlowLift2

Intermittent Gas Lift Utilizing a Pilot Valve

Troubleshooting Unloading Gas Lift Design using DynaLift TM

Advanced Intermittent Gas Lift Utilizing a Pilot Valve

Weatherford Inverse Gas Lift System (IGLS)

37 th Gas-Lift Workshop Houston, Texas, USA February 3 7, Alan Brodie, PTC

Global Gas Lift Optimization Using WellTracer Surveys

Anomaly Marker Method for Gas-Lift Wells

Two Short Topics 1) Using Compressors More Effectively 2) Improving Upon Poor-Boy Gas-Lift

Continuous Injection of Hydrate Inhibitor in Gas Lift Gas to Mitigate Downtime Due to Downhole Annular Plugging

Plunger Fall Velocity Model

Gas Well Deliquification Workshop Sheraton Hotel, Denver, Colorado February 20 22, 2017

Plunger Fall Velocity Model

Bellows Cycle Life & How Manufacturing Processes Can Impact it

Don-Nan Pump & Supply. Don-Nan Pump & Supply 1

FLOWING GRADIENTS IN LIQUID LOADED GAS WELLS

Honeywell s On-line Gas Lift Optimization Solution

Acoustic Techniques to Monitor and Troubleshoot Gas-lift Wells

Considerations for Qualifying Elastomers Used in Artificial Lift Equipment

Intermittent Gas Lift and Gas Assist Plunger Lift

Gas-Well De-Watering Method Field Study

Weatherford Inverse Gas Lift System (IGLS)

31 st Gas-Lift Workshop

Optimizing Chemical Injection

Gas Lift Valve Testing

A Longer Lasting Flowing Gas Well

36 th Gas-Lift Workshop. Reverse Flow Check Valve Reliability and Performance Testing of Gas Lift Barrier Check Valves

2010 Sucker Rod Pumping Workshop Optimizing Production and Reducing Costs by Solving Rod Pumping Problems With The Beam Gas Compressor

Troubleshooting Gas-lift Wells Using Dual Shot Acoustic Technique

Pacemaker Plunger Operations in Greater Natural Buttes

Dan Casey Pro-Seal Lift Systems, Inc.

Pressure Test Tubing for Leak

Downhole Pressure Boosting: A production enhancement tool for both dry and liquid loaded Gas wells

High Pressure Continuous Gas Circulation: A solution for the

Carbon Fiber Sucker Rods versus Steel and Fiberglass

Dynamic IPR and Gas Flow Rate Determined for Conventional Plunger Lift Well

Acoustic Troubleshooting of Coal Bed Methane Wells

Gas-liquid flow optimization with a Bubble Breaker device

Gas-Lift Test Facility for High- Pressure and High-Temperature Gas Flow Testing

Downhole Gas Separation Performance

Correlating Laboratory Approaches to Foamer Product Selectione

Is The Selection Of Artificial Lift

Setting Plunger Fall Velocity Using Venturi Plungers

Plunger Lift: SCSSSV Applications

Downhole Gas Separator Selection

Downhole Gas Separator Selection

Pump Fillage Problem Overview. Jim McCoy. 9 th Annual Sucker Rod Pumping Workshop. Renaissance Hotel Oklahoma City, Oklahoma September 17-20, 2013

How does an unstable GLV affect the producing zones?

Appalachian Basin Gas Well. Marietta College, Marietta, Ohio June 7-8, Development. Robert McKee, P.E. Design Engineer Multi Products Company

Using Gas Lift to Unload Horizontal Gas Wells

Downhole Diverter Gas Separator

Intrinsically Safe Acoustic Instrument Used in Troubleshooting Gas Lift Wells

Presented By Dr. Youness El Fadili. February 21 th 2017

TROUBLESHOOT ROD PUMPED WELLS USING TUBING FLUID LEVEL SHOTS

Plunger Lift Algorithms A Review

Modelling Gas Well Liquid (Un)Loading

Ball and Sleeve Plunger System Automation Algorithm Utilizing Ball Fall Rates

Beam Pumping to Dewater Horizontal Gas Wells

Down-Hole Gas Separator Performance Simulation

Sucker Rod Lift Downhole Gas Separators Proposed Industry Testing

Improving Performance of Gas Lift Compressors in Liquids-Rich Gas Service

Pressure Activated Chamber Technology (PACT)

A Combined Experimental & Numerical Research Program to Develop a Computer Simulator for Intermittent Gas-lift

Gas Locked Pumps are NOT Gas Locked!

Packer-Type Gas Separator with Seating Nipple

Barrier Philosophy for Wells on Gas lift and Ways of Reducing HSE Risks. Alan Brodie Feb 2011 For more info visit

Dual Gas Lift Well Analysis Using WellTracer

Wireless I/O, Connecting Remote Sensors in a Wide Range of Environments

New Single Well Gas Lift Process Facilitates Fracture Treatment Flowback

Selection, optimization and safe operation of bypass plungers

Gas Well Deliquification Workshop. Gas Assisted Rod Pump

Gas Well Deliquification Workshop. Sheraton Hotel, Denver, Colorado February 29 March 2, 2016

Jim McCoy. Tubing Anchor Effect on Pump Fillage. Lynn Rowlan Tony Podio Ken Skinner. Gas Well Deliquification Workshop.

Hydraulic Piston Pump Field Trial

De-Liquification and Revival of Oil & Gas Wells using Surface Jet Pump (SJP) Technology

Plunger Lift Optimize and Troubleshoot

Continuous Flow Gas Lift Design By Jack R. Blann 2/9/2008 1

New 1.5 Differential Gas Lift Valve

Horizontal Well Artificial Lift Simulation: Unconventional Oil & Gas Well Case Histories

Retrofit Gaslift System for TLP wells

Gas Lift Challenges. Gas-Lift Workshop. Qatar February 4-8, Mike Johnson ExxonMobil Production Company

SPE Copyright 2012, Society of Petroleum Engineers

Sizing, Selection, and Installation of Pressure-relieving Devices in Refineries

A COMPARATIVE ANALYSIS OF CONTINUOUS GAS LIFT VALVE POSITIONING METHODS AND ITS APPLICATION WITH MS EXCEL & VBA

10 Steps to Optimized Production

Instruction Manual 742 5/1/2009. Eclipse Ratio Regulators ES Series Version 1

92831 TEL: (714) FAX:

Instruction Manual No. 742, 8/98

An approach to account ESP head degradation in gassy well for ESP frequency optimization

INTEGRITY MANAGEMENT OF STRESS CORROSION CRACKING IN GAS PIPELINE HIGH CONSEQUENCE AREAS

THE TRANSIENT GAS LIFT SIMULATOR IN PROSPER (IPM10.0)

QPF Pneumatic Fenders. Operation Manual A EUROTECH BENELUX COMPANY

2007 Gas-Lift Workshop

MODEL 100 NITROGEN INFLATION CART

PRODUCT CATALOGUE WHATEVER YOU RIDE WHATEVER YOU DRIVE...

Cougar 21 MTR Performance Analysis Page 1 of 7

92831 TEL: (714) FAX:

I have to say that I had no idea about compressors. That means it s easy for everybody.

Venting Atmospheric and Low-pressure Storage Tanks API STANDARD 2000 SEVENTH EDITION, MARCH 2014

Acoustic Liquid-Level Determination of Liquid Loading in Gas Wells

Transcription:

32 nd Gas-Lift Workshop The Hague, The Netherlands February 2-6, 2009 Using Valve Performance in Gas Lift Design Software Tom Nations This presentation is the property of the author(s) and his/her/their company(ies). It may not be used for any purpose other than viewing by Workshop attendees without the expressed written permission of the author(s).

Contents Definition of Valve Performance. Differences between some of the available flow correlations. Valve Performance availability in gas lift design software programs. Using Valve Performance in Gas Lift Design. What can happen if Valve Performance is not considered. 2009 Gas-Lift Workshop 2

Valve Performance Valve Performance is the determination of the actual flow rate through a gas lift valve at different combinations of Pvo, temperature and Piod. Each make and model of gas lift valve is somewhat different. Bellows load rate and effective stem travel must be determined. Performance curves generated from dynamic tests. 2009 Gas-Lift Workshop 3

Valve Performance Methods VPC TM correlations. Proprietary and are available only to members of the Valve Performance Clearinghouse JIP. Dynamic flow testing of many gas lift valves. Predicted rates within 10% of actual performance. Winkler-Eads; T-C modified for the area open to flow. Good for small ports but errors increase with port size. API Simplified, from API RP 11V2. Requires knowledge of loadrate and flow coefficient. Thornhill-Craver. Probably the most popular, but never intended to be used for gas lift valves. Can be off by as much as 200%, and should never be used for live gas lift valves. 2009 Gas-Lift Workshop 4

Gas Lift Valve Flow Performance 2009 Gas-Lift Workshop 5

Valve Performance in software programs SNAP Ryder Scott, LLC. WellFlow Weatherford WinGLUE AppSmiths PROSPER Petroleum Experts 2009 Gas-Lift Workshop 6

Using Valve Performance Typical gas lift graph showing injection pressure, flowing tubing pressure gradient and unloading valve locations. Valve set pressure and unloading lift gas rates will be shown on the following output text report. 2009 Gas-Lift Workshop 7

Gas Lift Design Output Report 2009 Gas-Lift Workshop 8

Calculated lift gas flow rates Piod and tubing transfer pressures are used to calculate lift gas flow rates (Qgi). Thornhill-Craver predicts fully open square edge orifice rates. grossly over estimating flow thru a gas lift valve. More injection pressure or lower Pvo may be required to make the valves flow sufficient lift gas rates to get the well unloaded. 2009 Gas-Lift Workshop 9

Top unloading valve 147 mcfd of flow capacity is required to transfer to the next valve. At the transfer pressure of 450 psi, the valve is actually closed. A higher injection pressure or a lower Pvo is required. 2009 Gas-Lift Workshop 10

Top Valve with 25 psi additional Piod pressure Same valve set at the same Test Rack opening pressure. Only change is adding 25 psi additional casing pressure. Now the valve flows 180 mcfd at 450 psi transfer pressure. 2009 Gas-Lift Workshop 11

Top Valve with 25 psi reduction in Pvo A similar result can be obtained by changing the Pvo. Pvo @ 60 was decreased by 25 psi. The valve flows 200 mcfd at 450 psi tubing pressure with the original design casing pressure of 1050 psi (1100 psi at depth). 2009 Gas-Lift Workshop 12

Second Unloading Valve 399 mcfd of flow capacity is required to transfer to the next valve. At the transfer pressure of 655 psi, the valve is actually closed. Again, more injection pressure or a lower Pvo is necessary. 2009 Gas-Lift Workshop 13

Second Valve with 25 psi additional Piod pressure Same valve set at the same 1009 psi Pvo pressure. Only change is adding 25 psi additional casing pressure. Now the valve flows 191 mcfd at 555 psi tubing pressure. Still not enough to match the required 399 mcfd. 2009 Gas-Lift Workshop 14

Second Valve with 70 psi additional Piod pressure Same valve set at the same 1009 psi Pvo pressure. 70 psi additional injection pressure yields 420 mcfd flow rate. But, if only 50 psi of additional injection pressure is available. Also have to lower the Pvo as well as check flow at +50 psi. 2009 Gas-Lift Workshop 15

Using Full Injection Pressure for Unloading You could use your full design injection pressure all but the top valve would flow considerably more lift gas. I recommend you design with less injection pressure than you actually have available at the wellhead (50-100 psi less) to avoid unloading problems. 2009 Gas-Lift Workshop 16

Using Design Injection Pressure +50 psi Valve performance at full design injection pressure +50 psi. 2009 Gas-Lift Workshop 17

Well would not Unload Unloading valves designed for 1400 psi injection pressure. Well would only take lift gas sporadically. Valve Performance was not considered in this design. 2009 Gas-Lift Workshop 18

Valve Design Details Input dialog box Change the valve depths, types, port sizes, etc. Change the Pvo60 values. Adjust amount of additional injection pressure you wish to evaluate. 2009 Gas-Lift Workshop 19

Re-cap Definition of Valve Performance. Differences between some of the available flow correlations. Valve Performance availability in gas lift design software programs. Using Valve Performance in Gas Lift Design. 2009 Gas-Lift Workshop 20

Conclusions Do not rely on Thornhill-Craver flow rate calculations for gas lift design. Gas Lift Design Software can be greatly improved by incorporating Valve Performance. Without Valve Performance, the black box of a design program could easily result in a design that will have difficulty unloading. Always use a design pressure 50-100 psi less than maximum injection pressure available at the well head. Especially important if your are using 1 gas lift valves. 2009 Gas-Lift Workshop 21

Copyright Rights to this presentation are owned by the company(ies) and/or author(s) listed on the title page. By submitting this presentation to the Gas-Lift Workshop, they grant to the Workshop, the Artificial Lift Research and Development Council (ALRDC), and the American Society of Mechanical Engineers (ASME), rights to: Display the presentation at the Workshop. Place it on the www.alrdc.com web site, with access to the site to be as directed by the Workshop Steering Committee. Place it on a CD for distribution and/or sale as directed by the Workshop Steering Committee. Other uses of this presentation are prohibited without the expressed written permission of the company(ies) and/or author(s) who own it and the Workshop Steering Committee. 2009 Gas-Lift Workshop 22

Disclaimer The Artificial Lift Research and Development Council and its officers and trustees, and the Gas-Lift Workshop Steering Committee members, and their supporting organizations and companies (here-inafter referred to as the Sponsoring Organizations), and the author(s) of this Technical Presentation or Continuing Education Training Course and their company(ies), provide this presentation and/or training material at the Gas-Lift Workshop "as is" without any warranty of any kind, express or implied, as to the accuracy of the information or the products or services referred to by any presenter (in so far as such warranties may be excluded under any relevant law) and these members and their companies will not be liable for unlawful actions and any losses or damage that may result from use of any presentation as a consequence of any inaccuracies in, or any omission from, the information which therein may be contained. The views, opinions, and conclusions expressed in these presentations and/or training materials are those of the author and not necessarily those of the Sponsoring Organizations. The author is solely responsible for the content of the materials. The Sponsoring Organizations cannot and do not warrant the accuracy of these documents beyond the source documents, although we do make every attempt to work from authoritative sources. The Sponsoring Organizations provide these presentations and/or training materials as a service. The Sponsoring Organizations make no representations or warranties, express or implied, with respect to the presentations and/or training materials, or any part thereof, including any warrantees of title, noninfringement of copyright or patent rights of others, merchantability, or fitness or suitability for any purpose. 2009 Gas-Lift Workshop 23