St. Mary Diversion Dam Case Study of a 100 year Old Diversion

Similar documents
Chadbourne Dam Repair and Fish Barrier

The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam

Guidance Note. Hydropower Guidance Note: HGN 8 Fish Passage. When do you need to install a fish pass?

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

Final Bull Trout Redd Monitoring Report for the Wallowa Falls Hydroelectric Project

Follow this and additional works at:

FSOC Upstream Fish Passage Guidance Document

Components of a Barrage

Big Spring Creek Habitat Enhancement and Fishery Management Plans

Washington State Fish Passage Barrier Removal Projects. Casey Kramer, PE WSDOT State Hydraulics Engineer

Designing Labyrinth Spillways for Less than Ideal Conditions Real World Application of Laboratory Design Methods

[FWS R1 ES 2015 N076; FXES FF01E00000] Endangered and Threatened Wildlife and Plants; Revised Draft Recovery Plan for

Fish Passage Behavior Behavior through Baffled and Nonbaffled Culvert

NUMERICAL AND PHYSICAL MODELING

Amendment to a Biological Assessment/Evaluation completed for the Coon Creek Land Disposal completed December Grand Valley Ranger District

AMERICAN FISHERIES SOCIETY HUMBOLDT CHAPTER CALIFORNIA-NEVADA CHAPTER 1990 NORTHEAST PACIFIC CHINOOK & COHO SALMON WORKSHOP PROCEEDINGS

Session C9: Priest Rapids Fish Bypass: A Case Study from Start to Finish

Restoring the Kootenai: A Tribal Approach to Restoration of a Large River in Idaho

SUBMERGED VENTURI FLUME. Tom Gill 1 Robert Einhellig 2 ABSTRACT

Applying Engineering Solutions to the Science of Protection and Enhancement of Aquatic Environments. Bill Holman, P.E. Stanley Consultants

Redd Dewatering and Juvenile Salmonid Stranding in the Lower Feather River,

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Project Award Presentation

Colusa Basin Drain Watershed Fish Stranding Tour Concept Paper Mike Hendrick and Brycen Swart NMFS

APPENDIX A STRUCTURE DESCRIPTIONS AND RATING CURVES

Union Pacific Railroad

Western native Trout Status report

Design of Spillway Upgrades

Lecture 10 : Sewer Appurtenances

Packwood Hydroelectric Project Barrier Analysis December 12, 2006

JAP Additional Information Sheet

Kootenai River Habitat Restoration Program. Kootenai Tribe of Idaho - January 27, 2014 Presentation for Kootenai Valley Resource Initiative

Rhode Island Department of Environmental Management Division of Fish and Wildlife American Shad Habitat Plan for the Pawcatuck River

PROFILE OF SACRAMENTO RIVER, FREEPORT TO VERONA, CALIFORNIA,

7.0 FISH PASSAGE PLANNING AND EVALUATION

Five Counties Salmonid Conservation Program - Fish Passage Design Workshop. February 2013

OKANAGAN RIVER RESTORATION INITIATIVE - FAQ

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

Chapter 11. Culverts and Bridges Design Checklist for Culvert Design

Rock Ramp Design Guidelines. David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E.

Trout Unlimited Comments on the Scope of Environmental Impact Statement for the Constitution Pipeline Project, Docket No. PF12-9

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN

CALIFORNIA SALMONID STREAM HABITAT RESTORATION MANUAL APPENDIX IX-A CULVERT CRITERIA FOR FISH PASSAGE INTRODUCTION

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

THE WESTERN NATIVE TROUT INITIATIVE PLAN FOR STRATEGIC ACTIONS November GOALS, OBJECTIVES, and KEY STRATEGIC ACTIONS

Applying Engineering Solutions to the Science of Invasive Aquatic Species Control Asian Carp and Sea Lamprey. Bill Holman, P.E. Stanley Consultants

Exercise (3): Open Channel Flow Rapidly Varied Flow

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models

Subject: Wells Hydroelectric Project FERC Project No Bull Trout Management Plan and Incidental Take Annual Report

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

Burns Paiute Tribe Fisheries Department. Evaluate The Life History Of Native Salmonids Within The Malheur Subbasin Project #

Proposed Terrestrial Critical Habitat for the Northwest Atlantic Loggerhead Sea Turtle Population. U.S. Fish and Wildlife Service

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 8 - LAC QUI PARLE COUNTY

Annex E Bridge Pier Protection Plan

GRAND RAPIDS RESTORATION GRAND RAPIDS REVITALIZATION

Hydraulic Modeling of Stream Enhancement Methods

HYDRAULIC JUMP AND WEIR FLOW

Session B7 - Santee-Cooper: A Lock on Fish Passage Success

Subject: Developed fish ladder alternatives for Pastori Avenue at San Anselmo Creek

COLUMBIA LAKE DAM REMOVAL PROJECT

1.Mill Creek Watershed Summary Description and Land Use

Evaluation of step s slope on energy dissipation in stepped spillway

TOP:001.3 U.S. Fish and Wildlife Service TECHNICAL OPERATING PROCEDURE

Endangered and Threatened Wildlife and Plants; Recovery Plan for the. SUMMARY: We, the U.S. Fish and Wildlife Service (Service), announce the

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 8 - LAC QUI PARLE COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - OTTER TAIL COUNTY

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017

DEADWOOD CREEK FISH PASSAGE IMPROVEMENT PROJECT

Management Plan for the Obey River Trout Fishery

Discussion on the Selection of the Recommended Fish Passage Design Discharge

Mountain Columbia Province

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

Scott Dam Spillway Comparing Physical Model Study Results

Spilling Water at Hydroelectric Projects in the Columbia and Snake Rivers How Does It Benefit Salmon?

Cabinet Gorge Dam Spillway Modifications for TDG Abatement - Design Evolution and Field Performance

Request Number IR1-12: Flow Passage. Information Request

Pre-Application Document Kaweah Project (FERC Project No. 298)

EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2018

SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING. Kara Hurtig, Water Resources Engineer, Northwest Hydraulic Consultants, BC, Canada

Fish Passage Planning and Design

Outlet Structures T-12

Presented by Fred Halterman, URS Jennie Agerton, URS

Fremont Weir Fish Passage Proof of Concept. Final Engineering Report

Final Fish Salvage & Temporary Tailrace Barrier Report for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) December 18, 2017

TECHNICAL MEMORANDUM 002 EMORANNO. 001

U.S. Fish and Wildlife Service Native American Crosscut Funding

FORMAT FOR SENDING COMMENTS. Title: CRITERIA FOR DESIGN OF CANAL HEAD REGULATORS (Second revision of IS 6531)

Figure 1 - Photo of Surveyed Area. Figure 2 - Void Survey Results

ADULT FISHWAY INSPECTIONS ON THE COLUMBIA AND SNAKE RIVERS 2012 ANNUAL REPORT

Dave Clugston U.S. Army, Corps of Engineers, Portland District. Tami Clabough, Eric Johnson, Dan Joosten, and Chris Peery

Plate 21: Vertical slot fishway retrofitted to a small power plant.

CENTRAL PROJECT: PLANNING EVERGLADES CENTRAL EVERGLADES RESTORING THE HEART OF THE EVERGLADES

Fish Passage Assessment Report Mare Brook Culverts

Upstream Passage Assessment of American Shad Using 3D Acoustic Telemetry

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A.

STEELHEAD SURVEYS IN OMAK CREEK

Stream Crossings I: Engineering and Design Approaches to Provide Fish Passage at Culvert Slipline Projects in Connecticut

SELBY CREEK SILVERADO TRAIL CULVERT FISH PASSAGE ASSESSMENT

Transcription:

Utah State University DigitalCommons@USU International Symposium on Hydraulic Structures Jun 29th, 4:00 PM - 6:00 PM St. Mary Diversion Dam Case Study of a 100 year Old Diversion B. J. Heiner U.S. Bureau of Reclamation, bheiner@usbr.gov J. Wagner U.S. Bureau of Reclamation Follow this and additional works at: http://digitalcommons.usu.edu/ishs Part of the Hydraulic Engineering Commons Recommended Citation Heiner, B., Wagner, J. (2016). St. Mary Diversion Dam Case Study of a 100 year Old Diversion. In B. Crookston & B. Tullis (Eds.), Hydraulic Structures and Water System Management. 6th IAHR International Symposium on Hydraulic Structures, Portland, OR, 27-30 June (pp. 220-229). doi:10.15142/t300628160857 (ISBN 978-1-884575-75-4). This Event is brought to you for free and open access by the Conferences and Events at DigitalCommons@USU. It has been accepted for inclusion in International Symposium on Hydraulic Structures by an authorized administrator of DigitalCommons@USU. For more information, please contact dylan.burns@usu.edu.

6 th International Symposium on Hydraulic Structures Portland, Oregon, USA, 27-30 June 2016 Hydraulic Structures and Water System Management ISBN 978-1-884575-75-4 DOI: 10.15142/T300628160857 ABSTRACT St. Mary Diversion Dam Case Study of a 100 year Old Diversion B.J. Heiner 1 and J. Wagner 2 1 Hydraulic Investigations and Laboratory Services U.S. Bureau of Reclamation Denver, CO 80225 USA 2 Civil Structures U.S. Bureau of Reclamation Denver, CO 80225 USA E-mail: bheiner@usbr.gov After 100 years of service, the St. Mary Diversion Dam is being replaced with a new design that will provide more effective fish passage and protection. The diversion is located in northern Montana, adjacent to the east side of Glacier National Park. It diverts water from the St. Mary River 1.21 km (0.75 mile) downstream of Lower St. Mary Lake. The existing 60.35-meter-long and 1.83-meter-high (198-foot-long and 6-foot-high) concrete weir diverts up to 24 cubic meters per second (850 cubic feet per second) design flow from the St. Mary River into the North Fork of the Milk River through a 46.67-km (29-mile) long canal, siphon, and drop system. The existing facility, which is maintained and operated by the U.S. Bureau of Reclamation (Reclamation), was completed in 1915 and is in need of replacement. The Endangered Species Act (ESA) listed species that have been adversely affected by limited passage and entrainment into the canal. The St. Mary Diversion and Milk River Irrigation project have been identified as the primary threat to Bull trout habitat in the St. Mary River drainage. Recovery efforts to restore Bull trout habitat in the St. Mary River drainage requires that Reclamation provide effective Bull trout passage and protection at the St. Mary Diversion. This paper presents a short history of the St. Mary Diversion and Milk River Irrigation project, which includes collaborations with all interested parties as well as modeling efforts that were used to enhance the design of the replacement structure to provide the best situation for Bull trout recovery without limiting diversion capability. Keywords: fish passage, protection, diversion, canal, screen, dam, physical modeling 1. INTRODUCTION The St. Mary Diversion Dam is part of the Bureau of Reclamation s (Reclamation) Milk River Project in northcentral Montana. Located near Babb, Montana, the diversion and canal were constructed in 1915 on the St. Mary River, 1.21 km (0.75 mile) downstream from Lower St. Mary Lake. The dam consists of a 60.35-meterlong and 1.83-meter-high (198-foot-long and 6-foot-high) concrete weir and sluiceway. A design discharge of 24 cubic meters per second (850 cubic feet per second) of water is diverted from the west side of the river upstream of the dam through a 46.67-km (29-mile) long canal. The canal transports the water through two large steel-plated siphons and five large concrete drop structures before it discharges into the North Fork Milk River (Figure 1). In 1999, the U.S. Fish and Wildlife Service (FWS) listed Bull trout (Savelinus confluentus) as a threatened species under the Endangered Species Act (ESA). When listed, FWS concluded that Bull trout native to the St. Mary River drainage are negatively affected by operation of the Reclamation Milk River Irrigation Project (Mogen 2011). More specifically, the St. Mary Diversion dam was cited as a known seasonal barrier to upstream migration of Bull trout (Mogen and Kaeding 2005a, 2005b and 2008) and a threat to the species due to the entrainment of fish during the irrigation season (Wagner and Fitzgerald 1995, Mogen and Kaeding 2000 and 2002). Fish entrained into the canal are either passed to the North Fork of the Milk River or remain in the canal until the gates are shut and the canal is dewatered during the non-irrigation season.

Figure 1. Overview map of the St. Mary Diversion and related features. To help aid growth of Bull trout and other species in the Milk River System, Reclamation began investigations on how to reduce the impact the St. Mary Diversion Dam and Canal has on Bull trout in the Milk River System. This paper discusses the history of the St. Mary Diversion Dam and Headworks including the condition of the existing facility and several of the recommended mitigation plans to provide fish screening and passage at the facility while still maintaining diversion flow rates. This paper is not a comprehensive list of all design options that have been evaluated over the past 15 years. 2. DESCRIPTION OF EXISTING FACILITY The St. Mary Diversion Dam is a concrete ogee weir with an overhead abandoned 3-span truss bridge (one span has been removed Figure 2). The spillway is a concrete overflow structure that consists of an uncontrolled weir and downstream horizontal slab. The spillway is ungated and has no mechanical features but is subdivided into two equal sections by a concrete bridge pier on which two abandoned 29.72-meter (97.5-foot) Pratt trusses span the crest of the spillway. Each section of the spillway weir is 28.9 meters wide (94 feet 10 inches). The concrete spillway weir crest is elevation 1362.76 m (4471.0 ft). The weir crest elevation was raised to elevation 1363.07 m (4472.0 ft) by mounting 0.31 m (1 ft) high weir-boards on top of the entire spillway crest. Figure 3 provides an overhead view of the spillway from the upstream channel. The sluiceway is located to the left of the spillway and consists of six openings with inverts at elevation 1361.24 m (4466.0 ft) controlled by 0.1- by 0.1- meter (4- by 4-inch) stop planks (Figure 4). The St. Mary Canal headworks is located on the left abutment and is controlled by eight 1.52- by 1.68-meter (5- by 5.5-foot) headgates with gate sills at elevation 1361.24 m (4466.0 ft) (Figure 6). The headworks are a concrete structure 17.98 meters (59 feet) wide and 6.71 meters (22 feet) long, with an upstream weir in front of the gates with a crest at elevation 1361.54 m (4467.0 ft). The 46.67-km-long (29-mile) St. Mary Canal was constructed between 1907 and 1915. The unlined canal was designed to convey 24 cubic meters per second (850 cubic feet per second) at a flow depth of 2.74 meters (9 feet). The canal was excavated to a bottom width of 7.92 meters (26 feet) with 2:1 side slopes at a channel invert slope of 0.000095 (Interior 1981). The dam is used to divert water into the canal from March through September. During the non-diversion period, the sluiceways are opened and canal headgates are closed. The canal was designed to convey 24 m 3 /s (850 ft 3 /s); however, the condition of the canal limits diversion to a

maximum of 18.41 m 3 /s (650 ft 3 /s). During March and early April, all river flow in excess of about 2.83 m 3 /s (100 ft 3 /s) is typically diverted. From June to August, diversions often reach 75 percent of total river flow. Diversion decreases sharply in late August and September (Mefford 2003). Figure 2. Original plan view drawing of the existing St. Mary Diversion Dam and Headworks (January 1914 note: elevations are based on project datum that is approximately 4.27 meter (14 feet) lower than NAVD88) Figure 3. Existing St. Mary Dam Diversion weir, sluiceway and abandoned bridge during low flow fall season (view is from upstream left bank) Figure 4. St. Mary Diversion sluiceway gates (view is from upstream left bank, standing on top of the headworks structure) Figure 5. St. Mary Diversion headworks structure (view of from downstream of the headworks, flow is towards reader) Recent examinations of the 100-year-old diversion dam, headworks, and canal revealed substantial freeze-thaw damage to exposed concrete surfaces. Concrete core samples taken from the piers on the dam and sluiceway indicated that the condition of the concrete is very poor where exposure to ice and frequent freeze-thaw cycles have degraded the strength (Mefford 2003). Based on available inspection data and visits to the structure, the weir (Figure 6), abutments (Figure 7), piers (Figure 8), sluiceways (Figure 9), and diversion headworks will

likely all require demolition and replacement in the near future. Recently, some modifications and repairs to the facility have been made that will prevent catastrophic failure of the structures. Figure 6. St. Mary Diversion weir concrete failure and exposed rebar. Figure 7. St. Mary Diversion right abutment damage and exposed rebar. Figure 8. Concrete degradation on the downstream end of piers surrounding sluice bays. Figure 9. Concrete degradation upstream end of piers surrounding sluice bays. 3. TIMELINE OF PROJECT DECISIONS Over the past 15 years, Reclamation has been working with all interested stake holders to help protect the threatened Bull trout at the St. Mary Diversion. This section describes some of the early concepts that were evaluated along with some of the design decisions that have shaped the project. This is not a comprehensive list of events and concepts. 3.1. Early Design Concepts Mefford (2003) conducted a conceptual design study and outlined two different concepts. Concept 1 recommended rehabilitating the diversion weir and replacing the headworks and sluiceway (Figure 10). Concept 2 recommended replacing all the existing structures (Figure 11). Both concepts included fish screens to prevent entrainment in the canal and a rock type fishway to allow passage over the dam. Both concepts proposed using a flat plate fish screen in the canal with a bypass at the end of the screen to return fish to the river. Main features were intended to maintain approach velocities of 0.12 m/s (0.4 ft/s), provide a 0.31-m (1-ft) sill on the bottom of the screen, and limit fish exposure to the screen to 60 seconds or less. The 0.31 m (1-ft) sill

was meant to provide better protection to the bottom-oriented behavior of Bull trout (Beyers and Bestgen 2002). The rock-type fishway for both options would provide passage on river right by extending a rock fishway at a 3.5 percent slope to approximately 45.72 meters (150 feet) downstream of the weir. The difference between the two options was the extent to which the existing weir structure was rehabilitated or replaced. Each design was sized to allow flows of 18.41 m 3 /s (650 ft 3 /s) (current canal maximum), 24.07 m 3 /s (850 ft 3 /s) (original design), and 28.32 m 3 /s (1000 ft 3 /s) (increased capacity) into the canal. 2003 costs for construction of each concept was estimated to between $6.9M and $10M, depending on which was chosen. Figure 10. St. Mary Diversion rehabilitation concept 1 as presented by Mefford (2003).

Figure 11. St. Mary Diversion rehabilitation concept 2 as presented by Mefford (2003). Since the 2003 concepts, many other configurations were investigated by a wide range of individuals and groups. TD&H Engineering Consultants (2006) provided a wide range of alternatives to repair/replace the existing diversion and canal; included in their report are costs and recommendations. More recently, Reclamation s Montana Area Office (MTAO) funded Reclamation s Technical Service Center (TSC) to develop a 100% design and specification package to allow replacement of the existing diversion facility. The TSC has worked in conjunction with MTAO, FWS, Blackfeet Nation Tribe, Montana Department of Natural Resources and Conservation (DNRC), Milk River Irrigators, St. Mary Rehabilitation Working Group, and many other stake holders to develop a design that met everyone s expectations and requirements. Team discussions and design reviews suggest as many as 6 different diversion and headwork options. Notable designs included a 0.91-meter (3-foot) dam raise, a rock ramp to provide passage, and many different configurations of concrete ladders and fish screen locations. 3.2. Original 60% Design Option Physical Model 1 In January of 2014, MTAO and other stakeholders met to complete a 60% design review on the to-date plans for the St. Mary Diversion Dam and Headworks. The designs were developed by the TSC with a multidisciplinary team led by Jason Wagner. The 60% design was to be robust, simple, and easy to operate. The fish ladder and fish screen were designed appropriately for juvenile Bull trout. The screens were designed such that a maximum screen approach velocity would not exceed 0.24 m/s (0.80 ft/s) at 30.58 m 3 /s (1080 ft 3 /s) flow in the canal. Typical design criteria for salmonids would usually only allow 0.12 m/s (0.4 ft/s) approach velocity, but the multi-agency biological review team obtained an exception due to the species and life stages present at the facility. Figure 12 provides a plan view drawing of the proposed 60% design. Included in the design are the following features: A) New diversion dam located downstream of the existing structure with a kinked ogee shape and an offset weir height to align flow and allow more flow on the right bank of the river. B) New sluice bays and overshot bays on both the right and left side of the dam adjacent to the abutments to allow sediment and floating debris removal and aid in ladder attraction. C) New headworks that consists of a trashrack with a maximum 0.61 m/s (2 ft/sec) approach velocity and nine 1.52- by 1.68-meter (5- by 5.5-ft) steel slide gates. D) New fish screen 54.86-m long by 2.3-m tall (180-ft long by 7.5-ft tall) and fish bypass to protect fish from entrainment.

E) All species fish ladder located on the right bank of the river. F) New lowered sluice channel on river left to allow non-irrigation flows to pass without inundating the headworks. Due to the complexity of the project, TSC constructed a 1:12 physical model of the complete structure and several numerical models of individual components of the proposed 60% design to ensure that all the hydraulic and structural components would function as intended and that the project would succeed at both protecting Bull trout and providing the necessary diversion to the St. Mary canal. Figure 13 provides an aerial view of the physical hydraulic model with annotations. Testing the physical model helped the design team identify several areas of concern with the proposed design. The following items were noted from the physical and numerical models: A) The kinked ogee crest dam caused severe scour downstream of the apron, which resulted in an unstable river bed. B) The entrance to the fish ladder was going to be difficult for species to locate due to extreme turbulence and eddies. C) The headworks was too large, resulting in small gate openings to operate the canal at the desired flowrates. D) The overshot bays intended for flushing floating debris over the dam were not in ideal locations and would require excessive operation and maintenance. E) Operation of the facility on two sides of the river would be difficult due to the access limitations on the right bank. F) Having the fish ladder on the opposite side of the river as the headworks required maintaining two thalwegs, which created additional complexity and may increase operation and maintenance costs. Figure 12. Originally proposed 60% design of the St. Mary Diversion Dam and Headworks.

Figure 13. Aerial photograph of the original 60% design of the St. Mary Diversion Dam with annotations. 3.3. Modified 60% Design Option Physical Model 2 Following the first modeling efforts, project members re-worked the 60% design and incorporated the changes shown in Figure 14. Modifications to the original 60% design include the following: A) A broad crested weir with reduced length (now 55.78-m (183-ft)) and a suitable energy dissipation basin downstream to prevent scour. B) The fish ladder located on river left to allow for easier operation, provide better attraction, and limit the access needed on the right bank. C) The headworks was reduced from nine to six 1.52- by 1.68-m (5- by 5.5- ft) gates. D) The overshot bays were removed on both sides of the diversion dam, and the right bank sluice gate was removed to reduce O&M requirements. Figure 15 provides an aerial view of the modifications to the physical hydraulic model with annotations. Additional information obtained during the model study enabled design team members to A) Set baffle configurations to allow uniform approach velocities for the fish screen at diversion flow rates of 18.41, 24.07, and 30.58 m 3 /s (650, 850 and 1080 ft 3 /s). Velocity uniformity was unachievable without baffling due to the screen s close proximity to upstream gates and channel curvature. B) Generate head discharge relationships for the dam with and without the fish ladder and headworks operational to verify that upstream water surface elevations were not too high and to provide a reasonable discharge curve for each structure. C) Verify the amount of headloss produced by the headworks and fish screens to ensure canal discharges could be met with adequate canal depths. D) Confirm that all flow during non-irrigation season can pass through the sluice gates without inundating the headworks with water.

Figure 14. Most recent proposed 60% design of the St. Mary Diversion Dam and Headworks. Figure 15. Aerial photograph of the modified 60% design of the St. Mary Diversion Dam with annotations. 4. SUMMARY In 1999 FWS listed Bull trout as a threatened species. Since then, Reclamation has been engaged in design efforts to provide fish passage and protection from entrainment at the St. Mary Diversion Dam and Headworks. Over the past 15 years, Reclamation has worked with interested parties to develop a rehabilitation plan to address the impact the diversion dam has had on Bull trout recovery. The Reclamation design team at the TSC developed 60% designs of a new facility and constructed physical and numerical models to ensure the facility would operate as intended. Once tested, design team members identified several areas for improvement. Modifications to the original 60% design provided both safe passage and protection to Bull trout while

maintaining the capability of the St. Mary canal to deliver water as desired. The design team and all stake holders are currently working on the completion of a 100% design package. 5. ACKNOWLEDGMENTS This work was conducted in collaboration with the U.S. Bureau of Reclamation, Department of Interior Montana Area Office, U.S. Fish and Wildlife, Blackfeet Nation Tribe, Montana DNRC, Milk River Irrigators, St. Mary Rehabilitation Working Group, and many other stake holders and interested parties. Thank you to everyone for their feedback and assistance during the design and modeling. 6. REFERENCES Beyers, D.W., and Bestgen, K.R. (2002). Bull trout Performance During Passage Over a Horizontal Flat Plate Screen, Larval Fish Laboratory, Department of Fishery and Wildlife Biology, Colorado State University, Fort Collins, Colorado. Interior, U.S. Department of the. (1981). Reclamation Data Book Engineering and Research Center, Denver Colorado 80225. Mefford, B. Sayer, K., and J. Baysinger. (2003). St. Mary Diversion Dam and Canal Headworks Concept Design Study, St. Mary Diversion and Fish Facilities. Mogen, J.T. and E. Best. (2011). Fish Entrainment at the Sain Mary Diversion, Montana. Technical Memorandum: 86-68290-10-05. US Bureau of Reclamation, Montana Area Office. Mogen, J.T. and L.R. Kaeding. (2002). Fish Entrainment Investigations at the St. Mary Diversion Dam, St. Mary River, Montana, a progress report based on field investigations conducted in 2002. Interagency Report. USFWS. Bozeman, MT. Mogen, J.T. and L.R. Kaeding. (2008). Investigations of Bull trout (Salvelinus confluentus) in the St. Mary River Drainage, Montana. Interagency Report. USFWS. Bozeman, MT. Mogen, J.T., and L.R. Kaeding. (2000). Ecology of Bull trout (Salvelinus confluentus) in the St. Mary River Drainage. Interagency Report. USFWS. Bozeman, MT. Mogen, J.T., and L.R. Kaeding. (2005a). Identification and characterization of migratory and nonmigratory Bull trout populations in the St. Mary River drainage, Montana. Transactions of the American Fisheries Society 134:841 852. Mogen, J.T., and L.R. Kaeding. (2005b). Large-scale, seasonal movements of radiotagged, adult Bull trout in the St. Mary River drainage, Montana and Alberta. Northwest Science 79:246-253. TD&H Engineering Consultants, (2006). St. Mary Diversion Facilities Feasibility and Preliminary Engineering Report for Facility Rehabilitation. Wagner, R. and G.W. FitzGerald. (1995). Fisheries status report: St. Mary storage unit. Final Report 1995. USFWS, Lewistown, Montana.