Planning Considerations for Nearshore Placement of Mixed Dredged Sediments

Similar documents
MOREHEAD CITY HARBOR, NC. Dredged Material Management Plan (DMMP)

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT

Dredging Keeping Our Underwater Highways Open

The 2017 Panama City Beaches Beach Interim Renourishment Project. Answers to Common Questions

Appendix E Cat Island Borrow Area Analysis

Chapter 4 EM THE COASTAL ENGINEERING MANUAL (Part I) 1 August 2008 (Change 2) Table of Contents. Page. I-4-1. Background...

Environmental. Effects of Dredging

First Year Morphological Evolution of an Artificial Berm at Fort Myers Beach, Florida

Beach Nourishment Impact on Beach Safety and Surfing in the North Reach of Brevard County, Florida

CROSS-SHORE SEDIMENT PROCESSES

Physical Modeling of Nearshore Placed Dredged Material Rusty Permenter, Ernie Smith, Michael C. Mohr, Shanon Chader

Chapter 11. Beach Fill and Soft Engineering Structures

Concepts & Phenomena

Nearshore Dredged Material Placement Pilot Study at Noyo Harbor, CA

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE 8-FOOT CHANNEL OF THE FEDERAL NAVIGATION PROJECT IN KENNEBUNK RIVER KENNEBUNK & KENNEBUNKPORT, ME

SHORE PROTECTION AND HABITAT CREATION AT SHAMROCK ISLAND, TEXAS ABSTRACT

Evaluation of Placement Alternatives for Matagorda Ship Channel Bottleneck Removal

OECS Regional Engineering Workshop September 29 October 3, 2014

Nearshore Placed Mound Physical Model Experiment

Dare County Nourishment Project Town of Duck

Kelly Legault, Ph.D., P.E. USACE SAJ

Follets Island Nearshore Beach Nourishment Project

Figure 1. Schematic illustration of the major environments on Mustang Island.

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION

Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION AND FUNCTIONAL DESIGN OF COASTAL STRUCTURES

Table 4. Volumetric Change Rates Pre-Project and Post-Project for the Town of Duck

USE OF SEGMENTED OFFSHORE BREAKWATERS FOR BEACH EROSION CONTROL

Southwest Washington Littoral Drift Restoration Project: Design, Construction, and Monitoring

TRANSPORT OF NEARSHORE DREDGE MATERIAL BERMS

A Single-Point Mooring System for Direct Pumpout of Hopper Dredges

OECS Regional Engineering Workshop September 29 October 3, 2014

Navarre Beach & Dune Restoration Project Status Report to be regularly updated June 17, 2016 Report

Nome Harbor Page 2 of 12

2018 Beach Preservation Project Information

VIMS CCRM Coastal Management Decision Tools. Decision Tree for Undefended Shorelines and Those with Failed Structures

Juneau Douglas Harbor

Dauphin Island East End Beach and Barrier Island Restoration Project. Beau Buhring South Coast Engineers

DEAD-ENDCHANNELFLUSHINGINHARBORS

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL

PLANNING AND CONSTRUCTION OF SHORE PROTECTION AT SHAMROCK ISLAND, TEXAS: PROJECT UPDATE ABSTRACT

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

BEACH FILL CONSTRUCTION USING SEABED REHANDLING AREAS. Kevin R. Bodge, Ph.D., P.E. 1

Technical Note AN EMPIRICAL. METHOD FOR DESIGN OF BREAKWATERS AS SHORE PROTECTION STRUCTURES

Long Term Success and Future Approach of the Captiva and Sanibel Islands Beach Renourishment Program

Beach Restoration in Okaloosa and Walton Counties. FSBPA Technology Conference Clearwater, FL

Strategic Placement an EWN/RSM Solution to Dredged Material Management

Regular Workshop October 20, 2014 Agenda Item: Dr. Albert E. Browder, PE; Olsen Associates, Inc.

BEACH NOURISHMENT COMBINED WITH SIC VERTICAL DRAIN IN MALAYSIA. Claus Brøgger 1 and Poul Jakobsen 2

Inlet Management Study for Pass-A-Grille and Bunces Pass, Pinellas County, Florida

Effectiveness of Beach Nourishment in Response to Sea Level Rise

Assateague Island National Seashore North End Restoration Project Timeline

Estimated on-the-ground start and end dates: 1 June October 2018

Delaware Chapter Surfrider Foundation - Indian River Inlet Monitoring

Good Mooring to You! Jensen Beach Mooring Field. Kathy Fitzpatrick, P.E. Coastal Engineer, Martin County

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

CLAM PASS ANNUAL RESTORATION & MANAGEMENT PLAN TIDAL ANALYSIS ELEMENT REPORT NO. 13

US Beach Nourishment Experience:

Ninilchik Harbor Page 2 of 11

Tanya M. Beck. Kelly Legault. Research Physical Scientist Coastal & Hydraulics Lab, ERDC Vicksburg, MS

Shoreline Studies Program, Department of Physical Sciences, VIMS

FINAL ENVIRONMENTAL IMPACT STATEMENT ON BROWARD COUNTY SHORE PROTECTION PROJECT SEGMENTS II AND III BROWARD COUNTY, FLORIDA

ST. LUCIE COUNTY, FLORIDA

Modeling Sediment Transport Along the Upper Texas Coast

page - Laboratory Exercise #5 Shoreline Processes

ST. JOSEPH PENINSULA, GULF COUNTY, FLORIDA Beach Re-Nourishment and Environmental Enhancement Project RECOMMENDATIONS

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING

SEDIMENT BUDGET OF LIDO OF PELLESTRINA (VENICE) Written by Marcello Di Risio Under the supervision of Giorgio Bellotti and Leopoldo Franco

Shoalwater Bay Shorline Erosion Dredging

Shoreline Response to an Offshore Wave Screen, Blairgowrie Safe Boat Harbour, Victoria, Australia

G. Meadows, H. Purcell and L. Meadows University of Michigan

RE: Hurricane Matthew Beach Damage Assessment and Recommendations [CSE 2416]

Public Notice U.S. Army Corps In Reply to Application Number CENAB-OP-RMS (NATIONAL HARBOR (FORMERLY PORT Baltimore District AMERICA])

CHAPTER 134 INTRODUCTION

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

Town of Duck, North Carolina

Habitat Fact Sheets. Rocky habitats are dominated by seaweeds and often mussels, which rely on the rocks for attachment.

North Shore of Long Island, Feasibility Study

MIAMI BEACH 32ND STREET HOT SPOT: NUMERICAL MODELING AND DESIGN OPTIMIZATION. Adam Shah - Coastal Engineer Harvey Sasso P.E.

Regional Sediment Management Opportunities within Intracoastal Waterway (IWW) Dredging Program in the State of Florida

Coastal Sediment Transport Modeling Ocean Beach & San Francisco Bight, CA

Nicholas Brown. 31 Bennett Rd Wolfeboro NH Application submitted

Unalaska Navigation Channel Improvements

Water Resources Report RKLD Annual Meeting July 30, 2016

CHAPTER 281 INFLUENCE OF NEARSHORE HARDBOTTOM ON REGIONAL SEDIMENT TRANSPORT

Absecon Island Shore Protection The planning behind the project

Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby

DREDGING. with particular emphasis on Oil and Gas activities in Canada

IMPACTS OF COASTAL PROTECTION STRATEGIES ON THE COASTS OF CRETE: NUMERICAL EXPERIMENTS

SELECTION OF THE PREFERRED MANAGEMENT OPTION FOR STOCKTON BEACH APPLICATION OF 2D COASTAL PROCESSES MODELLING

FEASIBILITY OF SAND BYPASSING SYSTEMS

For more information or permission to reprint slides, please contact Donna Milligan at 1

APPENDIX G DREDGING STUDIES. G.1: Fish Related Dredgi g I pacts a d Mitigatio

Sediment Management Plan Rehoboth Bay

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

Condition of Improvements 30 December 2014 Wrangell Harbors, Alaska (CWIS No , )

Cordova Harbor Page 2 of 9

Impact of Dredging the Lower Narrow River on Circulation and Flushing

National Oceanic and Atmospheric Administration (NOAA)/ Mulberry Phosphate Trustee Council September 12, 2013

Cook Inlet pipeline crossing is about making the best choices

Transcription:

Planning Considerations for Nearshore Placement of Mixed Dredged Sediments PURPOSE: Dredging planning and management decisions are based on a combination of engineering and economic factors tempered by environmental considerations. The purpose of this technical note is to address primary considerations (although not all-inclusive) for planning and managing nearshore placement of mixed sediment from dredging projects. BACKGROUND: As part of its ongoing navigation channel maintenance mission, the U.S. Army Corps of Engineers (USACE) dredges large amounts of noncontaminated sand/silt mixtures, which are then available for beneficial nearshore placement. Often this material is excluded from nearshore placement consideration because of unknowns related to regulatory concerns about the ultimate fate of fines: will the fines move onto the beach; is water quality negatively impacted; and what, if any, impact is there to environmental and economic resources like fisheries and oyster beds? Typically, USACE alternatives for disposing of mixed dredged sediments are limited by State and local regulatory requirements that restrict the percentage of fines (usually less than 20 per- cent) allowed to be placed directly on the beach. Beach placement of material containing large quantities of fines is undesirable because of the environmental impact that the smaller grain size (may cause the beach face to harden) and/or darker color (increases beach temperature, thus affecting sea turtle nesting and/or aesthetic appeal) may have on the beach and beach habitat. Little is known about the impact of placing sediments with larger relative percentages of fines in the nearshore. Because knowledge of the behavior of mixed sediments placed in the nearshore is limited, USACE has as its only alternatives offshore disposal or upland placement for mixed dredged sediments. This activity not only keeps much-needed sand resources from the local littoral zone, but it can also be more expensive and time-consuming than nearby placement (i.e., nearshore). Research on nearshore placement of mixed sediments is currently being conducted under the Dredging Operations and Environmental Research (DOER) Program at the U.S. Army Engineer Waterways Experiment Station (WES). One of the DOER focus areas, Dredged Material Nearshore and Offshore Placement, is investigating how fine- and coarse-grained sediments behave together and independently when placed in the nearshore as a mixed sediment. Results of this research will lead to tools that will assist planning, engineering, and operations personnel in (a) predicting the ability of a mixed-sediment placement to enhance the nearshore region, (b) assessing physical and environmental benefits/impacts, and (c) justifying USACE projects, promoting cost-sharing, and addressing regulatory agency concerns. NEARSHORE PLACEMENT PURPOSE: The primary purpose for nearshore placement of dredged material is to reduce overall navigation maintenance costs. Navigation channel

maintenance dredging can, for illustration purposes, be separated into dredging and disposal costs, the latter of which is the focus of this technical note. Much of the cost of disposal is a function of time (e.g., time for a hopper dredge to transit to/from an offshore disposal site). The farther a hopper dredge has to travel during the dredge cycle, the more fuel that is consumed, and the longer it takes to dredge a project. Nearshore placement of mixed dredged material, in many cases, would reduce transit times for hopper dredges and possibly reduce pumping distance for some pipeline dredges, both of which would result in reduced costs. In addition, nearshore placement has applications as a beneficial use approach, as material that traditionally is placed offshore and lost to the local littoral zone now would be kept nearby and possibly enhance nearshore profiles and/or beaches. Nearshore placement could also offer a link between the often independent channel dredging activities and beneficial use (e.g., beach nourishment) activities. By linking these activities, interactive project design is facilitated, and both navigation and beach use interests can collectively identify a least-cost dredging and nearshore placement solution benefitting all parties. Potential benefits from nearshore placement of mixed sediments are provided in the adjacent table. Potential Nearshore Placement Benefits Supplements beach profile by adding material to the littoral zone Renourishes beach Decreases nearshore wave heights, thereby reducing damage from erosive waves and storms Provides fisheries habitat Reduces use of limited-capacity upland and offshore disposal sites Decreases mobilization/demobilization costs Shortens haul distance for hopper dredges and shorter pumping distance for pipeline dredges NEARSHORE PLACEMENT OBJECTIVE: Initially, planners and designers must decide on the objective of the nearshore placement. Objectives of nearshore placement of dredged material vary from simply placing the material in the littoral zone to feed the littoral system to designing and constructing a nearshore berm feature that attenuates waves or serves as a habitat. Commonly, nearshore placement involves design and construction of a nearshore berm or mound. Typically, finer grained sediments (which are less desirable on beaches) placed with hopper dredges or barges (from clamshell/bucket dredges) are used to construct stable berms in deeper water. If the berm relief is sufficiently tall compared with the water depth and local wave climate, stable berms can reduce wave energy on their lee. For feeder berms, material more closely resembling native sands is used to match local beach sand and/or nearshore sand. Nearshore placement (in the form of berms) can also serve as fish habitat. Design guidance of nearshore berms was developed under the WES Dredging Research Program (DRP) and is provided in McLellan (1990a, b), Burke and Allison (1992), and Pollock and Allison (1993). For illustration, an analytical study (using the DRP guidance) was conducted to determine the economic feasibility of a nearshore berm alternative for the St. Johns County, Florida, Beach Erosion Control Project. This effort is described in Pollock, Curtis, and Moritz (in preparation). In some cases, a designed berm may not be desired or cannot be constructed with available material. However, nearshore placement may keep material in the local littoral zone to facilitate marsh creation (or slow marsh degradation) or act sacrificially in lieu of nearby beaches or marshes. 2

By way of example, the U.S. Army Engineer District, New Orleans, pumped fine-grained sands and silts from the Mississippi River-Gulf Outlet Navigation Channel to the nearshore of Breton Island to create a sacrificial feature approximately 7 ft high in 15 ft of water that persisted for 2 years (Williams and Mathies 1996). Figures 1 and 2 illustrate a nearshore feature as viewed from Figure 1. Illustration of nearshore placement (overhead view) Figure 2. Illustration of nearshore placement cross section 3

overhead and in cross section, respectively, demonstrating the likely movement of sand into the littoral system or onto the beach and fines moving offshore. DREDGING AND PLACEMENT ALTERNATIVES: The selected purpose for nearshore placement will to a large extent suggest the dredging and placement method used. In general, dredging can be conducted either mechanically (clamshell, bucket, or dipper dredge) or hydraulically (plain suction, cutterhead, hopper dredge). Usually, mechanically dredged material is placed in a bottom-release scow from which it is discharged into the water column to settle to the seafloor. Material (particularly fine-grained) dredged by this method tends to maintain bulk densities at or near those of in situ conditions, which contributes to a more cohesive mound or feature at the placement site. Mechanically dredged coarse-grained material (sands) also maintains high bulk densities, but is more likely to lose coherence during descent through the water column. Generally, however, mechanically dredged material, whether fine- or coarse-grained, is more conducive to forming a lasting berm. Hydraulic dredging involves fluidizing sediments for pumping. Hopper dredges fluidize bottom sediments for pumping into their hoppers, which significantly reduces bulk density from in situ. However, once in the hopper, sediment bulk density increases, though usually not to the predredging levels. Hopper dredges discharge material through doors or a split hull from which the dredged material settles to the bottom in much the same way as from a bottom-release barge or scow. When released, the fluidized material is more susceptible to dispersion during descent through the water column. Depending on the type of dredged material, however, densities that are nearly in situ can be realized to create more stable features. Hydraulic pipeline dredges (cutterhead and plain suction) fluidize material throughout the dredging and transport phases. Usually, pipeline-dredged material is discharged to a confined disposal facility for drying and consolidation. In some cases, pipeline dredges discharge directly into the water column, and evidence has shown that a feature can be created with relatively fine-grained material using a pipeline dredge (Williams and Mathies 1996). PLACEMENT SITE FACTORS: Many factors relating to mound or feature geometry should be considered for nearshore placement of dredged material. Placement site geometry depends on a wide range of factors including the placement objective, type and volume of material to be placed, dredging and placement methods, environmental restrictions (areal and material composition), existing profile, and restrictions on feature relief (from boating and navigation interests). In situ sediments at the dredging site must be characterized to determine type of material and if it is contaminated. Bathymetry of the proposed placement site defines the placement site location and boundaries, and knowledge of the hydrodynamic climate (wind, waves, and currents) is necessary to assess the potential physical behavior of dredged sediment and to properly site a mound or berm to optimize stability, wave breaking, or nearshore/beach feeding benefits. In addition, assessment of benefits and risks to submerged coastal habitats for shellfish, fisheries resources, and endangered species is necessary to determine short- and long-term environmental impacts. ECONOMIC CONSIDERATIONS: Economic considerations for nearshore placement of dredged material are primarily related to the type of dredging equipment used and placement/discharge method and location. Dredging costs are typically divided into two primary elements: mobilization/demobilization (mob/demob) and unit cost. Mechanical and pipeline dredges have 4

relatively higher mob/demob costs because those dredges require tugs to move, support vessels to transport pipe or barges, and in some cases, land-based equipment for reworking of the placed dredged material. Hopper dredges placing dredged material in open water typically have lower mob/demob costs because a hopper dredge is an oceangoing vessel requiring less support. However, if a hopper dredge is placing material via a direct pump-out buoy, mob/demob costs could be comparable with mechanical and pipeline dredges. Hopper dredges placing material nearshore by bottom discharge can help minimize overall dredging project costs in two ways: (a) the lower mob/demob cost becomes more attractive (relative to other dredge types); and (b) shorter haul distance to the nearshore placement site saves time and fuel costs. Pipeline dredges can also reduce overall dredging project costs by placing material nearshore. A pipeline dredge discharging into the nearshore reduces its own mob/demob costs by eliminating those factors associated with land-based equipment, and the shorter pumping distance reduces operating time and fuel consumption. Limitations that must be considered are that some hopper dredges may be unable to access desired shallow-water placement sites because of draft limitations. Alternatives include light-loading, which reduces the vessel draft, and speciality shallow-draft hopper dredges. Pipeline discharging into the nearshore may also be limited because of the more energetic hydrodynamic environment closer to shore, which can create large forces on the pipeline. Ultimately, projects considering nearshore placement of dredged material must optimize costs by closely examining the dredging requirement, cost of available equipment specific to the project of interest, type of nearshore feature desired, and volume of material to be dredged. In some cases, the benefitting parties may have to contribute larger portions of the dredging and placement costs to ensure that the desired feature is constructed with appropriate equipment if the selected equipment or method is more expensive than the least-cost method. SUMMARY: Planning and designing a dredging project with nearshore placement alternatives first require knowledge of the physical and ecological environment. Engineering decisions can then be made to determine potential placement alternatives that, in turn, provide a basis for decisions driven by economic factors. The results of such decisions may provide a beneficial, economically feasible nearshore placement alternative. Under the DOER Program, investigations will be conducted in the Evaluation and Design of Nearshore Placement of Mixed Sediments Work Unit to enhance opportunities for nearshore placement of mixed sediments. Additionally, other work units in the Nearshore and Offshore Placement Focus Area will include physical model investigations of mixed sediment movement, improvement of existing numerical models determining the fate of dredged material, and environmental effects of material placed in the nearshore. Benefits from this research will include improved use of maintenance dredged material for shoreline stabilization, increased acceptance by regulatory agencies of nearshore placement as a viable long-term disposal alternative, and lower costs for overall maintenance dredging operations. POINTS OF CONTACT: For additional information contact the authors, Mr. Gregory L. Williams (601-634-2089, williag3@ex1.wes.army.mil), and Ms. Terri L. Prickett (601-634-2337, 5

pricket@ex1.wes.army.mil), or the managers of the Dredging Operations and Environmental Research Program, Mr. E. Clark McNair (601-634-2070, mcnairc@ex1.wes.army.mil), and Dr. Robert M. Engler, (601-634-3624, englerr@ex1.wes.army.mil). This technical note should be cited as follows: U.S. Army Engineer Waterways Experiment Station. (1998). Considerations for planning nearshore placement of mixed dredged sediments, Technical Note DOER-N3, Vicksburg, MS. REFERENCES Burke, C. E., and Allison, M. C. (1992). Length and end slope considerations, interim design guidance update for nearshore berm construction, Technical Note DRP-5-06, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS. McLellan, N. (1990a). Engineering design considerations for nearshore berms, Technical Note DRP-5-01, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS.. (1990b). Interim design guidance for nearshore berm construction, Technical Note DRP-5-02, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS. Pollock, C. B., and Allison, M. C. (1993). Berm crest width consideration, interim design guidance update for nearshore berm construction, Technical Note DRP-5-08, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS. Pollock, C. B., Curtis, W. R., and Moritz, H. R. Numerical methods for nearshore berm evaluation, St. Johns County, Florida, in preparation, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS. USACE (1993). Coastal project monitoring, Engineer Manual 1110-2-1004, Headquarters, U.S. Army Corps of Engineers, Washington, DC.. (1994). Hydrographic surveying, Engineer Manual 1110-2-1003, Headquarters, U.S. Army Corps of Engineers, Washington, DC. Williams, G. L., and Mathies, L. (1996). Results of the pilot berm monitoring study at Breton Island, St. Bernard Parish, LA, Proceedings of the Western Dredging Association 17th Technical Conference (WEDA XVII) and 29th Annual Texas A&M Dredging Seminar, New Orleans, LA. 6