Stadium electricity supplies an assessment of the specification and readiness 2010 FIFA SOCCER WORLD CUP

Similar documents
2010 FIFA World Cup Organising Committee South Africa

Section Activity and instructions Skills Target year group(s) World Activity 1 Calculate stadium capacity and design your own stadium Cup venues

2010 NATIONAL COMMUNICATION PARTNERSHIP CONFERENCE 15 August FIFA World Cup Organising Committee South Africa

HOST The C. Preparation of a city for the 2014 FIFA World Cup. Host City: Natal

THE ROCKY ROAD TO LEGACY

Progress on the project is on schedule with work achieved to date being 90%. Various aspects of the construction are at different stages:

Football Lighting Policy & Requirements Season 2016

FINAL FACILITY STUDY. KV1C Transformer Addition at Badwater Substation 2009-T1. November 17, 2009

TO: FROM: SUBJECT: RECOMMENDATION

Onsite fan research FIFA Marketing Research Onsite fan Research

2012 Olympics National Grid s preparations

2013 Special Reliability Assessment: Accommodating an Increased Dependence on Natural Gas for Electric Power

PART 1: INFRASTRUCTURE OPPORTUNITIES

Authority to Enter Into Bid Agreements for the 2026 FIFA World Cup

11 June South Africa v Mexico Soccer City, Johannesburg. Germany v Australia. South Africa v Uruguay. Spain v Switzerland

PART III SECTION 5C OLYMPIC GAMES STATEMENT OF BADMINTON S REQUIREMENT

Status Date Prepared Reviewed Endorsed Approved

Planning for tennis in your Local Government Area. A resource from Tennis Australia

System Operating Limit Definition and Exceedance Clarification

SAN FRANCISCO UNIVERSITY 10 January 2019 Presented by Dr Jacques Grobbelaar

City of Ekurhuleni Cost of Electricity Supply Study

EUROPEAN YOUTH OLYMPIC GAMES QUALIFICATION EVENT BID DOCUMENT 2014

The LOC and all the partners will do their level best to organise a professional Championships and make you feel welcome in the South of Africa.

transport consultancy Stadia & Venues

London March Donna Taylor Head of Accommodation. 13th

Denver, Colorado USA. Olympic and Paralympic Winter Games Exploratory Process January-March 2018

Powering the Greenest Games

Edition 4 Summary Document Stage Rally Safety Requirements

MILTON ROAD LLF PROJECT UPDATE

Learning Week. #rethinklw

Report to COUNCIL for decision

School Games EXECUTIVE SUMMARY YEAR 1 August 2012

NATIONAL CERTIFICATE (VOCATIONAL) NQF LEVEL 2 NOVEMBER

BOARD OF AIRPORT COMMISSIONERS

BID APPLICATION QUESTIONNAIRE FOR THE CANDIDATES TO ORGANISE A UNITED WORLD WRESTLING EVENT

Tasmanian Netball League APPENDIX 13 - CONTINGENCY PLANS

CONFÉDÉRATION EUROPÉENNE DE VOLLEYBALL BEACH VOLLEYBALL. World Tour 1 Star & 2 Star Events in Europe CANDIDATURE APPLICATION GUIDELINES

Football in Mauritius The first Goal Project Financing of Goal project Use of FAP funds Project Project approved Status Financed by Goal FAP

AFCON2013 & CHAN 2014 Presentation to the Portfolio Committee on Sport LOC CEO: Mr. Mvuzo Mbebe 19 August 2014

METROPOLIS WORLD ASSOCIATION OF THE MAJOR METROPOLISES

Football in Zambia The first Goal Project Financing of Goal project Use of FAP funds Project Project approved Status Financed by Goal FAP Government

STCP 08-2 Issue 004: Circuit Live Trip & DAR Tests

The FA Cup, The FA Trophy, The FA Vase and The FA Youth Cup Competitions

The RCM Analyst - Beyond RCM

ETU EUROPEAN YOUTH TRIATHLON CHAMPIONSHIP & FESTIVAL BID DOCUMENT 2017

FIFA Development Activities in Africa

Economic Impact 2022 Commonwealth Games South Africa: Durban Host City

QLDC Council 29 October Report for Agenda Item: 3

Wangaratta & District Cricket Association

g) feeds: basic feed, multi feeds, additional feeds, audio feed, data feed and unilateral coverage

University of Leeds Travel Plan

Report to Cabinet. 18 May 2016

2010 FIFA World Cup South Africa Official Hospitality Programme 11 June - 11 July Suite Hospitality

A national cycling strategy for more and safer cycling

Rules for the FIG World Challenge Cup Series 2017, 2018, 2019, 2020

Bringing projects to life

UEFA EURO Technical Services & Overlay / Tender Process. Supplier for Temporary TV Broadcasting Power Phase 1 - Invitation to Express Interest

Managing Leakage and Preparing for the 2012 Olympics

IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY

STRATEGIC PLAN 2016 AUSTRALIAN OLYMPIC TEAM GAMES OF THE XXXI OLYMPIAD RIO DE JANEIRO, BRAZIL 5-21 AUGUST 2016 KITTY CHILLER CHEF DE MISSION

A national cycling strategy for more and safer cycling

Progress with the Road Investment Strategy

Big 12 Baseball Replay Protocol

2012 Olympics and Paralympics Challenges and Opportunities

RELIABILITY OF ENERGY SYSTEMS

WELLINGTON S FUTURE FOOTBALL HUB

Draft Western District Plan

FIL World Lacrosse Championship 2010

Support Infrastructure

CITY OF VANCOUVER ADMINISTRATIVE REPORT

[Grab your reader s attention with a great quote from the document or use this space to emphasize a key point. To place this text box anywhere on the

SOCOMEC UPS Participates 2008 Summer Olympic Games

SAFA NATIONAL TEAM ACTIVITIES

SAFA NATIONAL TEAM ACTIVITIES

Corporate. Report COUNCIL DATE: June 26, 2006 NO: C012 COUNCIL-IN-COMMITTEE. TO: Mayor & Council DATE: June 22, 2006

RESTORATION PROCEDURES

Design & Management Services

NON-RIGHTS HOLDING BROADCASTERS: ENR ACCREDITED PRESS CATEGORY. Non-rights holding broadcasters should remember five key points:

DEPARTMENT OF TRANSPORT

FIFA Football Development

Hazardous Waste Training Plan. Supersedes: 02/15/16 (Rev.02) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager

MONASH CROQUET CLUB STRATEGIC PLAN

OIL & GAS. MTS DP Committee. Workshop in Singapore Session 4 Day 2. Unwanted Thrust

PL AN. To be the premier swimming state in Australia by Photo courtesy of Delly Carr/Swimming Australia

THE TARRAGONA TRADE FAIR AND CONFERENCE CENTRE, THE VENUE FOR THE SEMINAR OF THE HEADS OF MISSION AND THE GENERAL ASSEMBLY OF THE ICMG

THE HORNS REV WIND FARM AND THE OPERATIONAL EXPERIENCE WITH THE WIND FARM MAIN CONTROLLER

THE APPROVAL FOR THE PROVISION AND USE OF A METER BY-PASS

District 18 Regionals: Planning Policies & Guidelines*

Elite Canada in Men s & Women s Artistic Gymnastics

Football on the Comoros Islands The first Goal project Financing of Goal project Use of FAP funds Project Project approved on Status

PlayStation 4 National Premier Leagues - Women's Club Licensing Criteria

2018 ICF CANOE SLALOM WORLD CHAMPIONSHIPS. Rio de Janeiro - Brazil

Phase 1 Invitation to Express Interest

XXth IAU 24H WORLD CHAMPIONSHIP 2017

Draft Greater Sydney Region Plan

FIS Rollerski World Cup Organisers Checklist 2015

Number 17 of Rugby World Cup 2023 Act 2017

Aliso Canyon Gas-Electric Coordination Phase 3 Draft Final Proposal

Operating Manual for the Evance Iskra R9000 Wind Turbine

HOSTING NCAA CHAMPIONSHIPS Collegiate Event & Facility Management Association (CEFMA)

Transcription:

Stadium electricity supplies an assessment of the specification and readiness 2010 FIFA SOCCER WORLD CUP Author & Presenter: T R Edmondson Eskom & member 2010 ESI forum Co-author: Dr. C G Carter-Brown Eskom & chairperson 2010 ESI forum 1. Introduction In a little over 250 Days the world s largest and most anticipated sporting event will take place in South Africa. South Africa and the African continent will be showcased. Millions of viewers will tune in to matches, the broadcast of which will be critically dependent on the provision of uninterrupted high quality electrical power. The South African Electrical Supply Industry is critical in the preparation and execution of this historical event. 2. Background The main electrical loads associated with the 2010 tournament include: Stadiums: The 10 stadiums in 9 Host Cities at which the matches will be played. Base camps: Each of the 32 teams will have a base camp, and are expected to arrive at base camp up to 2 months prior to the start of the tournament. Base camps could be located anywhere in South Africa. Training venues: Before each match (typically 5 days beforehand) teams will move from their base camps to the training venues within the Host Cities. Fan parks: FIFA fan parks will be located in Host Cities. Public viewing venues: Non-FIFA accredited viewing venues that will be set up by municipalities and private enterprise. FIFA hotels: Hotels at which FIFA will establish their local offices and command centre. Media centres: Journalists will be hosted at the International Broadcast Centre which will form the hub for broadcasting and reporting. Supporters: The accommodation, tourism and transport needs of visitors. In relation to the South African peak demand, the magnitude of the additional electrical load is expected to be relatively small. Complexity and risk arise due to the uncertain nature of this load, including its location. Certain loads, such as stadium lighting and broadcasting, have onerous power quality requirements. A momentary interruption or voltage dip could disrupt broadcast to millions of viewers. A problem in the supply chain (Eskom Generation, Eskom Transmission, Eskom Distribution, Municipal distribution or stadium distribution) will reflect poorly on the entire ESI, South Africa and Africa. It is critical that all role players in the ESI work together to minimise risks and optimise approaches. Role players include: Host Cities and municipalities. Eskom. Owners of the 2010 event stadiums. 2010 Local Organising Committee (LOC). Association of Municipal Electrical Undertakings (AMEU). Department of Energy (DoE). National Energy Regulator of South Africa (NERSA). South African Local Government Association (SALGA) The 2009 Confederations Cup was a successful tournament for the country and the electrical industry, but the real value was gained in the lessons learnt during and leading up to the event. Page 1 of 5

Figure 1 - Stadium electrical supply 1 3. Stadium electrical supply The Stadia and surrounding areas are fundamentally broken down into three (3) main focus areas, namely: Domestic / Stadium Power (Stadium itself) Technical Power (Media and Broadcasting) Overlay or Precinct (Area immediately surround the stadium including ticketing offices, hospitality, Accreditation etc) 3.1 Domestic/Stadium Power The agreements signed by the host cities and FIFA in the delivery of sufficient back-up power grids to deal with any power failure at the Stadium and elsewhere in the Host City which may arise during a Match, and that appropriate power management systems are in place - FIFA 2007 Specification Host City Agreement Below is what is expected with regards to this statement: Pitch Lighting: The primary goal of the event lighting system is to illuminate the event to digital video quality for the media without creating nuisance glare for the players/officials and adding spill light/glare to the spectators and surrounding environment. Permanent lighting, temporary lighting and a combination of both systems should be considered FIFA Football Stadiums Technical recommendations and requirements 4 th Edition Host City is responsible for pitch lighting. Lighting intensity of 2400Lux (Fixed camera lighting) with 1800Lux at pitch level (Field Camera) is required at all times. Available and functioning 100% during a match. Zero switch time tolerance. I.e. switching between electrical supplies must have no impact on the pitch lighting. Recommendation to have some sort of uninterruptable power supply (UPS) to ensure that any anomaly (Dips, surges etc) on the network (grid or generator) has no influence on the pitch lighting. Having a UPS would also ensure that the potential impact on pitch lighting during switching between electrical supplies will be mitigated. Generators or alternate power supply capable of sustaining the pitch lighting for a minimum of three (3) hours. Maintenance and refuelling are the responsibility of the Host City. Page 2 of 5

Configuration of the power supply is at the discretion of the Host City but must have a minimum n-1 redundancy. Zero supply switching tolerance. 3.3 Overlay/precinct Power Area immediately surrounding the stadium including ticketing offices, hospitality, accreditation etc Figure 2: Pitch Lighting 1 Stadium building power Stadium building power is the required supply within the stadium to power appliances, facilities and lighting within the stadium i.e. General stand lighting, administration offices and suites. Backup power requirement in the event of a power failure is limited to that of the Occupational health and safety act (OHSACT) This power excludes any broadcast or media provisioning. Configuration of the MV power supply is at the discretion of the Host City and is recommended to have minimum n-1 redundancy. 3.2 Technical Power This is power for the broadcasting and television requirements NO HOST CITY INVOLVEMENT. This is the responsibility of the LOC. NO GRID SUPPLY. Islanded from the grid power supply. Supply is provided via diesel generators supplied by the LOC. Covers all broadcasting mediums. Total of three 500Kva generators each capable of taking the full load. Two generators run in parallel with the third being a backup. A forth generator will be required for the venue hosting the final game. Host City responsible to supply a medium voltage (11kV) point/s of supply. For 2010 there may be as many as four required per stadium and the number and location of these bulk supply points will be stadium dependent. The requested capacity for the confederations cup was around 2MVA. 2010 is expected to require greater capacity. The LOC will install and operate the temporary distribution network linking the MV bulk supply point with the individual loads. The LOC will install and operate backup diesel generation for the overlay supply. Approximate 1 minute switch time tolerance between grid supply and and the backup generation. Figure 3: Nelson Mandela Stadium 1 4. Preparation The 2010 FWC is the event of events, a once in a life time experience, and the number of role players and stakeholders involved in the preparation and execution bears witness to this. Action plans and programs have been put in place to help in the preparation for 2010 FWC and minimise risk. The information found in the points below is relevant and applicable to the stadia preparation and other 2010 critical loads. 4.1 Generation & Transmission The mitigation of risks for these components is primarily an Eskom responsibility and includes: Ensuring adequate primary energy supply prior to the event. The management of plans for the taking of generation and transmission plant out of service Page 3 of 5

for planned maintenance or refuelling [Koeberg] in order that the risk to the tournament is minimised. The identification and assessment of Infrastructure providing supply to municipal distributor areas, which could directly or indirectly influence the supply to any of the stadiums, for condition and maintenance or refurbishment plans. Detailed emergency planning and simulation of these plans prior to the event. Plans for obtaining and storing of strategic spares, as well as logistic constraints such as communications and transport are in place. Inspection of networks will take place earlier than normal practice for those networks identified as critical for reliability and quality of supply. 4.2 Distribution The establishment of regional task teams (RTT) in all the host cities has enabled the preparation to be tracked and understood. The suggested actions that are being carried out (many have been completed) by the relevant Host Cities include: Identify and assess the condition of the electrical infrastructure that could directly or indirectly influence the supply to the stadium[s], training venues and key loads in their area of responsibility. Replacement, refurbishment or maintenance of these networks to be scheduled to be completed well before the commencement of the tournament. Evaluate the requirement and availability of strategic spares for their network. Assess loads connected to load shedding relays and revise existing plans to ensure that there is no impact on identified tournament critical loads should the need for load shedding arise. Arrange networks so that no abnormal conditions are maintained during the period of the tournament. Prepare contingency plans for supplies to the critical loads and ensure all control and operations personnel are thoroughly familiar with switching requirements. Plan leave and standby rosters well in advance to ensure the availability of an adequate level of competent staff. Optimise security measures for the protection of critical infrastructure. 4.3 Stadia Each of the host cities have achieved the requirements for stadium supplies differently considering legacy requirements and historical infrastructure and layout, namely; Ellis Park (Johannesburg) 2 x 700 KVA 2 x 800 KVA 1 x 500 KVA Prospect Delta Free State Stadium (Bloemfontein) 2 x 1250 KVA o Configured to run parallel. Royal Bafokeng Sports Palace (Rustenburg) 2 x 2200 KVA Loftus Versveld (Pretoria) 8 x 300 KVA o Uninterruptable power supply (UPS) per light mast. Green Point (Cape Town) o Primary Power Grid Supply (n-1) o Backup Power Two Sources of power. 2 X 2 MVA fixed generator supply supplemented by 4 x 500KVA generators. o Uninterruptable power supply (UPS) Moses Mabhida Stadium (Durban) o Primary Power - Generators 3 x 800 KVA o Backup Power Grid 2 x 11kv sources from separate locations. o There is currently no allowance made for any UPS supplies at the Moses Mabhida Stadium, albeit that the Consultants have made physical arrangements to incorporate as such. Page 4 of 5

Soccer City (Johannesburg) Mbombela Stadium (Nelspruit) Peter Mokaba Stadium (Polokwane) Nelson Mandela Stadium (Port Elizabeth) o Primary Supply - Grid supply (Mount Rd Substation @ 66/22kV) o Backup Power - Gas Turbine o There are rotary UPS's which are installed in each of the 4 stadium substations which will be dedicated for pitch lighting and emergency supplies. Note: The above configurations are not final and may change leading up to the final preparation for the 2010 FIFA World Cup event. 4.4 Human Resources The human factor in the preparation for 2010 FWC cannot and must not be underestimated. Below are a few points to note during these preparations: 2010 FWC coincides with a period synonymous with wage negotiations and labour action. Staff still taking care of business as usual whilst also supporting the event with priority response. Man power to support and be involved in event specific structures (Venue Operation Centres, Joint Operational Centres etc) Staff on site match day -1 at key supply points. 4.5 General Preparation These are other significant items that should be noted during the preparation for 2010 FWC; FIFA Exclusive use period is 15 business days before first game at stadium and 5 Business days after last game at stadium. - Electricity readiness needs to mirror this. 5. Conclusions A large amount of effort has gone and is going into the preparation of the 2010 FIFA World Cup with a large portion of these preparations dependant on the electrical supply and availability thereof. With only a few months to go, final preparations for this event are at the forefront of Host City and Eskom priorities. In every aspect of life, progress is constantly being made. -Joseph S. Blatter - FIFA President 6. References [1] FIFA World Cup 2010 State Of Readiness, Media Briefing by Deputy Minister of Finance, 15 May 2007. [2] ESI Preparedness for the 2010 FIFA Soccer World Cup, CG Carter-Brown and PE Fowles, AMEU Convention, October 2007. [3] Recommendations for the 2010 soccer world cup stadium supplies, Draft 6a, 2010 ESI forum, August 2007. [4] 2010 ESI Project Summary rev3, 2010 ESI forum, August 2007. [5] World Cup 2010 Base Camps - revision 2, 2010 ESI forum, March 2007. [6] Project: FCC and FWC Power Delivery presentation ArupMajorProjects Consulting 2009 [7] FIFA Football Stadiums Technical recommendations and requirements 4 th Edition 2007 7. Acknowledgements The authors would like to acknowledge the contributions made by all the Host City 2010 electrical task teams, Eskom task teams and the members of the 2010 ESI forum. Heightened electrical fault response and restoration is required to be in place +- 2 week prior to the first game. Fuel supplies and spares to be sent to site at least 48 hours before match and if used replaced within 24 hours. Page 5 of 5