Design and Installation of two Permanent Booms at La Romaine-2 to resist Ice, retain Debris and serve as Safety Booms.

Similar documents
CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL

Chief-Planning & Readiness USCG Sector Houston-Galveston

Exercise (3): Open Channel Flow Rapidly Varied Flow

ICE-INDUCED DAMAGE TO SHORELINE PROPERTIES ON ROUND AND GOLDEN LAKES

NUMERICAL AND PHYSICAL MODELING

Annex E Bridge Pier Protection Plan

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM

ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER

EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2018

This training is intended to be educational and should not be construed as legal guidance. It is provided as a courtesy to our customers and others

BC Ministry of Forests. March Fish Stream Crossing Guidebook. Forest Practices Code of British Columbia.

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

Greenup Lock Filling and Emptying System Study

TABLE OF CONTENTS EXECUTIVE SUMMARY 1

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Components of a Barrage

Wave Energy. ME922/927 Wave energy

Safe Work Practices (SWP) SWP (6) FALL PROTECTION PROGRAM

2012 Susitna River Water Temperature and Meteorological Field Study

Irrigation &Hydraulics Department lb / ft to kg/lit.

WIND AND SNOW FENCES

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

TECHNICAL MEMORANDUM 002 EMORANNO. 001

Broadly speaking, there are four different types of structures, each with its own particular function:

UNIT 15 WATER HAMMER AND SURGE TANKS

STRUCTURE 65-B PURPOSE SPILLWAY OPERATION

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

Hydraulic Evaluation of the Flow over Polyhedral Morning Glory Spillways

Yasuyuki Hirose 1. Abstract

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam.

river flow. Presented at International Technical Rescue Symposium. 6-8 November, Pueblo, CO. Gordon Smith can be contacted at

National Maritime Center

Hours / 100 Marks Seat No.

The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam

OPEN CHANNEL FLOW WORKSHEET 3 WATER SURFACE PROFILES

JAP Additional Information Sheet

Homework of chapter (3)

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Stability of Pipeline and details of Anchor blocks

DUAL-VORTEX SEPARATOR. Inspection and Maintenance Guide

MANERI DAM D/S VIEW. Er. SANDEEP SINGHAL Director (Projects) UJVN Limited, Dehradun, (UK)

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 8 - LAC QUI PARLE COUNTY

TOP:001.3 U.S. Fish and Wildlife Service TECHNICAL OPERATING PROCEDURE

UNIT-I SOIL EXPLORATION

Illinois State Water Survey

Ocean Motion Notes. Chapter 13 & 14

Chutes Part 2: Synthetic linings

STRUCTURAL STABILITY ASSESSMENT

HYDRAULIC JUMP AND WEIR FLOW

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

Exercise (4): Open Channel Flow - Gradually Varied Flow

Request Number IR1-12: Flow Passage. Information Request

Water Storage for Agriculture

Dams: costs/benefits. Positive. Negative. economic growth food production surface water enhancement recreation enhancement

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

CORPS FACTS. Harbor Dredging U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG

NOVEMBER 2006 FLOOD DOWNSTREAM OF THE KATSE DAM STRUCTURE

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Hydrographic Surveying Methods, Applications and Uses

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN

COA-F17-F-1343 YEAR END REPORT

Stevpris installation

Tutorial. BOSfluids. Relief valve

Lecture 10 : Sewer Appurtenances

LESOTHO HIGHLANDS DEVELOPMENT AUTHORITY

Innovative spillways. PK-weirs. Franska exempel 10/04/2018. Speaker : A. Chapuis,

AN INVESTIGATION OF LONGITUDINAL VENTILATION FOR SHORT ROAD TUNNELS WITH HIGH FIRE HRR

AIRFLOW GENERATION IN A TUNNEL USING A SACCARDO VENTILATION SYSTEM AGAINST THE BUOYANCY EFFECT PRODUCED BY A FIRE

1. In most economical rectangular section of a channel, depth is kept equal to

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow

Doug Hutton, Russell Anschell and Doug Seitz. Gordon Smith can be contacted at Gordon Smith, 2009.

FLOW MEASUREMENT (SEMI-SUBMERGIBLE OBJECT METHOD)

Adopted Regulation Strategy LWCB Regulation Meeting - March 22, 2010

19.1 Problem: Maximum Discharge

INCREASE METHODS OF DRAINAGE DISCHARGE OF INUNDATED WATER IN LOW FLAT LAND CONSIDERING BED DEFORMATION CHARACTERISTICS

Construction Dewatering

National Maritime Center

CSO/STORMWATER MANAGEMENT. HYDROVEX VHV / SVHV Vertical Vortex Flow Regulator

APPENDIX A STRUCTURE DESCRIPTIONS AND RATING CURVES

Akasison Flow phenomena of a siphonic roof outlet

A STUDY OF THE LOSSES AND INTERACTIONS BETWEEN ONE OR MORE BOW THRUSTERS AND A CATAMARAN HULL

Lecture Outlines PowerPoint. Chapter 15 Earth Science, 12e Tarbuck/Lutgens

FORMAT FOR SENDING COMMENTS. Title: CRITERIA FOR DESIGN OF CANAL HEAD REGULATORS (Second revision of IS 6531)

Northwest Hydro Association Dam Safety Impacts of 2017

Small. Regulation Reference: (see page 23 for link to the regulation)

TRIAXYS Acoustic Doppler Current Profiler Comparison Study

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

Rock Ramp Design Guidelines. David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E.

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS.

CONE PENETRATION TESTS

Old-Exam.Questions-Ch-14 T072 T071

Chapter 10 Lecture Outline. The Restless Oceans

FLUID MECHANICS Time: 1 hour (ECE-301) Max. Marks :30

Démocratisation des modèles hydrauliques CFD 3D : plusieurs exemples réalisés avec ANSYS CFX

Coquitlam/Buntzen Project Water Use Plan

Transcription:

CGU HS Committee on River Ice Processes and the Environment 18 th Workshop on the Hydraulics of Ice Covered Rivers Quebec City, QC, Canada, August 18-20, 2015 Design and Installation of two Permanent Booms at La Romaine-2 to resist Ice, retain Debris and serve as Safety Booms. Elie Abdelnour 1, Razek Abdelnour 2, George Comfort 3 and Phong Tran 4 1 Geniglace Inc., 120 Terence Matthews, Ottawa, ON, K2M 0J1 elie@geniglace.com 2 Geniglace Inc., 902-30 Berlioz Street, Montreal, QC, H3E 1L3 razek@geniglace.com 3 G. Comfort Ice Engineering Ltd., 2 Conacher Gate, Kanata, ON K2K 3H1 comfortga@gmail.com 4 Ingénieur, Hydro-Quebec, Montreal, Québec, Canada. Tran.Phong@hydro.qc.ca Two permanently installed debris booms were designed, constructed and deployed 70 km north of Havre St. Pierre, Quebec for Hydro Quebec s La Romaine-2 Project. The two booms were installed on the Romaine River, one upstream of the water intake, and the other upstream of the sluice gates, during the late fall and winter of 2013-2014. The purpose of both booms was primarily to protect the two structures from wooden debris, especially during the flooding period. The permanently deployed booms were also designed to resist the environmental conditions including 1.2m thick ice, and act as safety booms to warn boaters away from the hydraulic structures during the summer months. This paper describes the procedures followed for the selection of the boom layouts, the development of the scenarios of ice interactions and debris accumulations and the calculation of the ice, currents, waves and debris loads on the booms. The selection of the required anchor sizes, the anchor cables and pontoons sizes is also discussed.

1. Introduction The La Romaine 2 Hydroelectric Dam was built on the Romaine River, and was completed in late 2014. The Elevation of the river was well below 195m, the lowest anchor elevation of all anchors. The reservoir elevation during operation is between 224.8m and 244.1m. The two Booms were built on land at an elevation at least 40m below the operational level. When the reservoir water level started to rise, both booms slowly floated and took the designed shape. The first boom is located upstream of the spillway channel. The second boom is located upstream of the water intake. The booms were designed to retain the wooden debris following the water level rise, following the clear cutting that was done before the water level rise. They are also designed to be navigation booms, as demarcation lines to provide safety. Figure 1 is the general view of the reservoir with both boom locations. Figure 1, the general layout of the Water Intake and The Spillway of Romaine 2 Hydroelectric Dam. 2. Design Criteria The booms were designed to take into consideration the following: The environmental conditions at each site: o The flow rate and the associated current velocities and their distribution, o The expected wind speed and direction. Resistance to the ice and debris forces generated by current and wind on the booms.

Visibility of the booms: 1. The freeboard of the pontoons had to be at least 30cm. 2. The space between the pontoons should be as small as possible. 3. The booms are designed as a deterrent, not as a physical barrier to the public. The booms should not allow the debris to pass downstream towards the spillway or the water intake. They must also deflect the debris along the booms. The boom at the water intake must resist the ice forces generated by currents and winds for the maximum flow of the plant. The boom upstream of the spillway must withstand the forces generated by a maximum flow in presence of an ice cover. The booms must be designed to operate without incident and while fully retaining the debris for a water level fluctuation range in excess of 20 m. The booms must be designed to have minimal maintenance requirements. All components are to be designed to minimize wear. 3. Environmental Conditions 3.1. Thickness of the ice cover in the reservoir The ice cover reaches an ice thickness between 0.8m and 1.2m. During freeze up, ice may form in larger thicknesses, if driven by wind towards the boom. During the breakup, the ice may be driven by wind in different directions; as such the boom must be designed for all these scenarios. 3.2. Wind Speed and Direction The wind considered for the design was obtained from an internal Hydro Quebec Report that provides the 1:100 year winds. For ice and debris load calculations, a wind speed of 110km/hr was used. 3.3. Debris Volume and Types The kind of debris that will be drawn towards the booms at the intake and the spillway are composed of: Dead Wood (120,000m 3 ), left on the ground or still standing. Most of this wood will float immediately when filling the reservoir. Living Wood (160,000m 3 ) in the zone to be submerged in the reservoir. This wood will be broken and/or torn during the first few years of operation. It was estimated by Hydro Quebec that annually there will be approximately 20,000m 3 of debris that will reach the intake, and about 5,000 m 3 to 10,000m 3 that will reach the spillway. The booms upstream of the spillway and the water intake are to retain the majority of debris. A small percentage of debris may pass underneath the booms, when the wood becomes saturated with water, especially in the presence of currents and waves. 4. The boom upstream of the spillway The layout of the spillway boom was designed to be capable to float between the reservoir water elevations ranging from 224.8m and 244.1m. The goal was to have the boom upstream from the strong currents at these elevations so the current upstream of the boom would not cause the debris to pass through the boom and into the spillway canal and the spillway.

The boom layout was developed to ensure that the debris would be retained and/or diverted towards the reservoir banks as much as possible. The boom was placed a few hundred metres away from the gates of the spillway so that the average current along the boom would remain below 0.7m/s, which is the critical velocity at which the debris may begin to pass under the boom. The currents were calculated for three water levels, 224.8m, 238.8m and 244.1m and for the maximum expected discharge from 0 (at 224.8m elevation) to 2,976m 3 /s for 244.1m elevation. The boom was built with four spans. Figure 2 shows the arrangement of the boom. Each span ranges between 74m and 105m in length. The total length of the boom was 370m. Up to 12 pontoons are attached to the span cable to resist the ice and retain the debris. As illustrated, the layout changes are based on the water level. At low water level the span cables become slack while at high water they stretch to reach a straight line and the boom retracts upstream from the low water level by about 80m. Figure 3 shows the boom at about a 235m elevation. Figure 2, The layout of the Spillway Boom at the La Romaine 2 Hydroelectric Dam.

Figure 3, The Spillway Debris Boom at about a 235m reservoir elevation (July 10, 2014). The lengths of the anchor cables and side view of their projected lengths for three water levels 224.80m, 238.8m and 244.1m, are illustrated in Figure 4. The anchors at the shores of the reservoir were drilled at 244.1m elevation to ensure that the debris would not pass around the boom from the shores at all water levels. Figure 4 also shows the resulting movement of the boom on the water surface when the water level drops from 244.1m to 224.8m and a maximum of almost 40m. Figure 4, The actual lengths of the spillway boom anchor cables for three water levels. 5. Forces applied by the ice on the Spillway Boom The spillway boom is designed to withstand ice and debris for all possible water levels expected during the reservoir filling and later during the operation of the dam. The maximum operating level of 244.1m is the most critical. The minimum operating level is 238.8m. During the flooding of the reservoir, an elevation of 224.8m had to be reached for any flow to occur at the spillway.

The force applied on the boom by the current and wind generated forces are calculated based on a numerical model developed and calibrated by Abdelnour et al, 1993, 1995 and 1998. The maximum load applied on the boom depends on several factors including the layout and configuration of the boom, the effective area of the ice cover that transfers the environmental forces on the boom, the surface and bottom roughness of the ice accumulation upstream the boom, the average current, and wind speeds. The maximum ice force on the boom is given by: FHt = ( w + c) A [1] where: FHt = Total horizontal force acting on the ice cover w = Wind shear stress c = Current velocity shear stress A = Effective surface area of the ice cover affected by the current and wind The shear stress generated by the current and the wind is: t = w + c =. Cdw. Vw 2 +. Cdc. Vc 2 [2] where: t = Total shear stress ( w wind, c current) Cd = Drag coefficient (wind Cdw and current Cdc) = Water and air density (air w et water c) Vw, Vc = Wind and current velocities The values of Cdw and Cdc depend on the roughness of the surface and bottom of the ice. The value used for Cdw was 0.0033; and the value used for Cdc was 0.05, which is typical for a rough ice surface (Michel, 1978). The ice forces were calculated using the following inputs: The span width of the boom, including each span. The effective ice area; it was presumed to be a triangle with an apex angle of 20 for a boom in a wide open area. The design wind speed used was 110 km/hr. The 100-year wind speed for the area was less than 110km/hr. The average current velocity was calculated from the flow expected in the spillway canal for all three water level elevations, 224.8m, 238.8m and 244.1m. The average current velocity, V, upstream of the boom site was calculated: V = Q / A, where A is the cross section area below the 182m wide boom line and for the average water depth for the water elevation. Q is the flow for that level (from Hydro Quebec). The total load and the calculated line load are presented in Table 1. The maximum calculated total load is 563kN and the line load is 3.1 kn/m. Table 1, the ice forces calculated on the Spillway Boom for three water levels.

6. The boom upstream of the Water Intake The layout of the Water Intake boom was designed to efficiently retain debris and withstand ice forces for a maximum flow of 454m 3 /s and for all levels of operation from 224.8m and 244.1m. As for the spillway boom, the boom layout was developed to ensure that the debris would be retained and/or diverted towards the reservoir banks as much as possible. The boom was placed a few hundred metres away from the intake trashracks so that the average current along the boom would remain below 0.7 m/s, which is the critical velocity at which the debris may begin to pass under the boom. The currents were calculated for two water levels, 224.8m and 244.1m and for the maximum expected discharge of 454m 3 /s at all levels. The boom was built with four spans. Figure 5 shows the arrangement of the boom. Each span ranges between 54m and 105m in length. The total length of the boom was 323m. Up to 12 pontoons are attached to the span cable to resist the ice and retain the debris. As illustrated, the layout changes are based on the water level. At low water level the span cables become slack while at high water they stretch to reach a straight line and the boom retracts upstream from the low water level by about 80m. Figure 3 shows the boom at elevation close to a 235 m elevation. Figure 5, The layout of the Water Intake Boom at the La Romaine 2 Hydroelectric Dam.

The lengths of the anchor cables and side view of their projected lengths for two water levels 224.8m and 244.1m are illustrated in Figure 7. The anchors at the shores of the reservoir are drilled at 244.1m elevation to ensure that the debris would not pass around the boom from the shores at all water levels. Figure 7 also shows the resulting movement of the boom on the water surface when the water level drops from 244.1m to 224.8m. Figure 6, The Water Intake Boom at about a 235m reservoir elevation (July 9, 2014). Figure 7, the actual lengths of the water intake boom anchor cables for two water levels. The ice forces were calculated using the same inputs of the spillway boom. The total load and the calculated line load are presented in Table 2. The maximum calculated total load is 424kN and the line load is 4.2 kn/m. Table 2, the ice forces calculated on the Water Intake Boom for two water levels.

7. Debris loads on the booms The loads applied by the debris on the booms increase with the size of the debris jam that collects in front of the boom. Thus, in order to determine the debris forces, it is first necessary to evaluate limits imposed by the boom size in relation to the available volume of debris. The volume of debris expected every year at the water intake is 5,000m 3 and at the spill way is 10,000m 3, as defined in section 3.3. It was also presumed that debris would be removed annually, and thus debris would not accumulate from one year to the next. In fact, recent observations in late 2014 showed that the orientation of booms is helping to direct the debris away from the dam without the need to remove the debris from upstream of the booms. This happens when the wind blows from the northwest direction, it takes most of the accumulated debris away, particularly at high water level. If the water level later goes down, the debris would be deposited on the shores far away from the boom. In the absence of restraint from the shorelines or other boundaries, debris driven towards the boom by winds and currents can be expected to accumulate in front of the boom in a jam with a triangular shape. Previous investigations (Kennedy, 1962b) have shown that, for a jam consisting of pulpwood logs, the internal friction angle varies with the internal pressure of the jam as well as the solids ratio. This suggests that a triangular-shaped debris jam, similar to the ice, is to be expected in front of the boom. The apex angle of the debris jam will vary with the confinement. For loose accumulations, it is expected to have an apex angle of about 20. The calculated load on the spillway boom is: The load applied by the wind: 1.05kN/m The load applied by the currents: 0.64kN/m The calculated load on the Water Intake boom is: The load applied by the wind: 1.86kN/m The load applied by the currents: 1.48kN/m The total combined load is 3.34kN/m. These forces are smaller than the force applied by the ice and are an upper limit as it was assumed that the entire volume of debris will remain upstream of the boom. 8. Selection of the pontoon sizes of the boom Based on the resistance capacity required by the boom, two sizes were used, 24 diameter and 30 diameter. A model was developed to obtain the size of a pontoon that can withstand both the ice and the debris forces (Abdelnour et al, 1995). The result of the calculations determined the diameter and length of the pontoon necessary to resist the applied environmental forces. A pontoon 30 in diameter, with 7.5m length, has a resistance capacity of 6.2kN/m, which is 4kN/m, more than the maximum load applied by the ice on the centre section of both booms. For spans near the shores, the line load is much less, therefore 24 diameter pontoons were chosen. Figure 8 shows the 30 diameter pontoons. Figure 8, the size of the pontoons were similar, except the diameter was 24 for the side spans, and 30 for the central spans.

9. The boom construction The boom was constructed entirely on land, before the flooding of the reservoir occurred. The anchors were drilled in the rock and grouted. Mobilisation of the drill was relatively difficult at some locations due to the steep terrain and the presence of trees, rocks and branches. The pontoons were transported one by one and attached to the span cables, which were already laid down on the snow-covered ground. The pontoon chains were attached, forming a grill to retain the debris. Figure 9, Installation of the anchors at the spillway boom site. Figure 10, The pontoons and chains that retain the debris, and the boom at the intake installed. Figure 11, The spillway boom, days before the water level reaches the operation level.

10. The boom operation The boom was completed in April 2014, two months before the flooding reached the booms. A large amount of debris floated towards the booms, the spillway and the water intake. The debris was retained as expected. The need for debris removal was not as important as expected since the northeast wind transported most of the debris away from the booms. The booms resisted the ice in winter 2014/15, a relatively cold year. Figure 12, Debris at the spillway boom taken by the wind to a nearby bay. Acknowledgments The authors would like to acknowledge the assistance of Caroline Belley, Yves Tremblay and Pierre Grandmont, contracts administrators, Hydro-Quebec, during the execution of the project. Without their assistance it would not have been possible to access the desired roads and sites, particularly during the winter construction season. References Abdelnour, R., Abdelnour, E., Comfort, G., Simard, C., and Tran, P., (2010) Design, Fabrication and Deployment of Debris Booms for the Eastmain EM-1A Project in James Bay. Canadian Dam Association 2010 Annual Conference, Niagara Falls, Ontario, Canada, Oct 2-7. Abdelnour, E., Abdelnour, R., Malenchak, J., (2012) Design, Fabrication and Deployment of an Ice Boom at Jenpeg Generating Station Canadian Dam Association 2012 Annual Conference, Saskatoon, SK, Canada, Sept 22-27. Abdelnour, R., Nicholson, C., and Gong, Y., (1998), The Design, Fabrication and Deployment of an Ice Boom to Protect Two Hydroelectric Power Plant Water Intakes from Ice Blockages during Winter, IAHR Ice Symposium, 1998, Potsdam, New York, July. Abdelnour, R., Comfort, G., McGoey, L., and Gong, Y., (1993), «Lavaltrie Ice Boom: Preliminary Design for New Boom Pontoons», Report submitted to the canadian Coast Guard, Quebec City, October, 1993 Crissman, R., Abdelnour, R., and Shen, H.T. 1995 "Design Alternatives for the Lake Erie- Niagara River Ice Boom." 8th Workshop on River Ice, Kamloop, BC. Kennedy, R., 1962a, Manual of Forces Calculation for Pulpwood Holding Grounds, Technical Report # 293 to the Pulp and Paper Research Institute of Canada. Kennedy, R., 1962b, The Forces Involved in Pulpwood Holding Grounds, Technical Report # 292 to the Pulp and Paper Research Institute of Canada. Michel, B., 1978, Ice Mechanics, La Presse de l Université Laval, Québec, Canada.