SP3 Design and implementation of solutions at test sites WP3.5 Bremen tram track replacement techniques operator: BSAG

Similar documents
Application of Value Engineering The Crosstown Project

Flowtite GRP manholes Installation Manual

CHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems

Foundation Products. Poured In Ground Anchor Bolts E1 - E4. Structural Foundations E5 - E12. Copyright 2016 s Industry Inc. SIE-RA-CMP EN

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS

IL Route 71 Construction Update

Hospital Link Project Project Update September 2017

RoadNews 14 // September VÖGELE pavers rehabilitate race track in Brno, Czech Republic. Paving at Top Speed

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI

Made in U.S.A. Narrow-U Bike Rack Heavy Duty Submittal Sheet. Materials: Finishes: Mount Options: Setbacks:

MILEGROUND - AIRPORT ROAD. Fall 2018/ Spring Fall 2020 TBD. US 119 Monongalia County HOW WILL TRAFFIC CONTROL BE HANDLED: KNOW BEFORE YOU GO

better measurement Simply a question of SCHMIDT Flow Sensor SS The cost-effective alternative in pressurised systems up to 10 bars.

Bids MAY 24, 2018 AT 2:00 P.M. (EASTERN) (Estimated Cost: $7,500,000.00)

Tips on Permanent Powered Fencing and Temporary Powered Fencing

Weymouth - Abington Route 18 Widening and Reconstruction Project File No

20', 15', AND 12' BALL STOPS ASSEMBLY INSTRUCTIONS

Lockout / Tag out Program

Taylor Road Resurfacing Project

DOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE

1. SCOPE 2. REFERENCED DOCUMENTS. 2.1 SC Test Methods SC-T Forms SCDOT Electronic Forms SUMMARY OF TEST METHOD

Söll GlideLoc vertical rail system

4. Guided Bus Explained

Cincinnati Dayton Rd Widening

Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission

NZQA registered unit standard 1178 version 7 Page 1 of 6

Constructive Ideas. Assessing the risk of sprains and strains CI Introduction. Step 1: Identify hazards. What is musculoskeletal injury (MSI)?

MASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018

Summary of Findings Concerning Longitudinal Cracking on 16' Wide Ramps

ADA on Construction. Guidance for Section C Plan Preparers

Provided by. Personal Protective Equipment. Workers Health & Safety Division HS96-101C (07-04)

Accommodating Pedestrians in the Work Zone

STRAIGHT POLE TENSIONED BATTING TUNNEL POLE LAYOUT

Floor Mount Socket. T: +44 (0) F: +44 (0)

LEVEL CROSSING SIGHTING DISTANCES

A P TA J U N E TO M G E R E N D, E X E C U T I V E D I R E C TO R - O V ERVIEW KC S T R E E TC A R A U T H O R I T Y

BackCountry ebikes 2019 MULE Assembly

Overspeed governors (113 OG Моment 250 MR, 114 OG Moment 250 A3, 115 OG Moment 250 MRL, 119 OG Moment 250 MRL/1)

Metal Expansion Joints. System solutions for reliable connections in plant engineering and construction.

Constitution Instructions

WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES

BARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S

DiaSafe. Systems. Ballasted Fall Protection. DiaSafe Ballasted Single Solo DiaSafe Ballasted Single Duo DiaSafe Ballasted Line Multi. w w w.diadem.

DOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE

SUPPLEMENT TO AIRCRAFT FLIGHT MANUAL FOR MOTOR-DRIVEN ROPE WINCH TYPE RPM 11/01

Hospital Link Project Project Update November 2017

BiboBlock. Fall arrest system for flat roofs

Perched Box Caisson Overview. January 2014

HAZARD IDENTIFICATION & RISK ASSESSMENT

Advantage Lockers & Bike

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT

The Highways Agency is working to improve the M1 between junction 28 (near Alfreton) and junction 35a (the A616 Stocksbridge bypass).

Float operated valve TYPE (SWDS)

Moai Bike Rack Heavy Duty Submittal Sheet. Materials: 2.0 Schedule 40 Pipe (2.375 OD) Finishes: Capacity: Mount Options: Setbacks: 2 Bikes

ASSEMBLY INSTRUCTIONS S-Dome system

QUALITY ALUMINUM BOAT LIFTS, INC. INSTRUCTIONS. Dominator Lake Lift

Security and confidence at height.

Installation Instructions MODEL VSTI-A020 Tank Indicator Installation Model: VSTI-A020, Stainless Reverse Read System Versa Steel Inc. Guide Cables No

OSHA s new walking working surfaces standards

FINALIZATION OF THE HAND DUG WELL. Version : April 2009 Published by : Foundation Connect International Autors : Henk Holtslag & John de Wolf

Swim Spa Pre-delivery Guide

BMX Track Guide. Developing the Sport of BMX Racing

***PROJECT NO AWARDED TO E.S. WAGNER VIA RESOLUTION NO ON JANUARY 19, 2016***

PERFORMANCE ACTIVITY 306 DRAINAGE PIPE WORK DESCRIPTION 4

Safe Work Method Statement

The latest automotive systems require innovative leak test methods and fixturing.

Unit 24: Applications of Pneumatics and Hydraulics

Traffic Control Inspection Checklist Segment:

GUIDELINE: Roadside Worksites

Model PIV UL/FM Post Indicator Valve. Maintenance and Operation Manual UL/FM Post Indicator Valve Configuration AWWA C515

H ow To Buil d A Wa ter Rocket

KlassikDrain Section. Technical Handbook and Product Catalog. General purpose trench drainage

Measuring the Training Rig

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM

^ Lee County ^OU fewest T:foH^ Lee County

RIIWMG203D Drain and Dewater Civil Construction Site Learner Guide

FLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS. This work covers part of outcome 2 of the Edexcel standard module:

Depth sensor. Product reference : REV 1. USER GUIDE and INSTALLATION GUIDE. nke Sailing competition

OSHA's New Silica Rule Everything You Need to Know. Defined. Respirable Crystalline Silica Dust

Bids DECEMBER 21, 2018 AT 2:00 P.M. (EASTERN) (Estimated Cost: $4,700,000.00)

Basketball system mobile

COMPLETE STREETS DURING CONSTRUCTION

Illini Union Champaign, IL. February 24, Paul Lorton, P.E. Safety Programs Unit Chief IDOT, Division of Highways, Bureau of Safety Engineering

TRAFFIC FIELD OPERATIONS (1 of 7) - ADMINISTRATION

Safe distances when using explosives

Rio Intersection Traffic Restrictions Begin Monday

skate-park models 2011 EN 14974

AES Raptor, LLC Raptor R1000 Instruction Manual

RISK ASSESSMENT FOR Philips Smart Touch Installation 03/04/2012

FALL PROTECTION PLAN INSTRUCTIONS

UPDATES 11/14/2018: 10/25/2018: CLOSED 10/22/2018: 10/12/2018: 10/05/2018: 09/27/2018:

GAS PIPELINE SAFETY GUIDE.

Model Safety Program

CASE STUDY OXLEY HIGHWAY SLIP STABILISATION

Q&A for Safety Code. Prepared by the HAUC-UK Safety Code working group

Road Condition Statistics: Notes and definitions

DELUXE LOW PROFILE 18 & 30 STARTING PLATFORMS

BRUCE HAMMER SUCCESS STORY, BRIDGE PILING Model SGH-4719 Pile Hammer (Max. Energy 89.3 ton.m)

Warner Instruments, Inc Dixwell Avenue, Hamden, CT (800) / (203) (203) fax

I.H.S INSTALLATION INSTRUCTIONS

Special instruction of installation for SAINT FH-M800/RD-M800 and FH-M805/RD-M805

Transcription:

SP3 Design and implementation of solutions at test sites WP3.5 Bremen tram track replacement techniques operator: BSAG presented by Ingo Schnieders, BSAG and Nils Jänig, TTK at the Urban Track Final Conference June 24, 2010 in Prague

Objectives Challenges: Bremen track replacement works, state of the art: track replacement during action weekend (app. since 2000) total closure for individual traffic during construction phase full closure during action weekend performance of app. 200 m per action weekend Challenge for Urban Track replacement of a 375 m double track section plus 25 m adaption to link to the existing track section (with smaller track centre distance) 4 weeks closure for individual traffic, but open for tramway operation 57 h full closure action weekend Final Conference, June 25, 2010 - Prague 2

Description Overall situation Final Conference, June 25, 2010 - Prague 3

Description Overall situation Final Conference, June 25, 2010 - Prague 4

Description Local situation i Access to site Final Conference, June 25, 2010 - Prague 5

Description Initial situation: mixed operation with maximum speed of 50 km/h worn out rails and defective substructure high maintenance effort for paved surfaces noisy surface with car traffic narrow track centre distance (2,75m) Final Conference, June 25, 2010 - Prague 6

Description Beginning and end of replacement section including crossroads Bei den drei Pfählen / Stader Straße End and connection to existing track Beginning incl. crossroads Final Conference, June 25, 2010 - Prague 7

Planning Layout plans beginning end Final Conference, June 25, 2010 - Prague 8

Planning Cross sections Final Conference, June 25, 2010 - Prague 9

Planning Composition of Superstructure 3,5 cm mastic asphalt as top layer 0/11 S, PmB 45A separating layer (e.g. fibre glass) 3,5 cm mastic asphalt as sub-layer 0/11 S, PmB 45A 3 cm Underpour e.g. Icosit KC 340/65 Fillings (e.g. SEDRAPUR SPEZIAL) 14,5 cm base layer made out of concrete C30/37 with high resistance to frost and de-icing salt 20 cm concrete base plate C30/37, rapidly setting concrete with gritting material and high resistance to frost and de-icing salt, not reinforced 25 cm mineral layer B2 Final Conference, June 25, 2010 - Prague 10

Planning Reference to STUVA testing Final Conference, June 25, 2010 - Prague 11

Test facilities (circuit-machine) green track: V = 30 km/hr Axle Load 7t 18,000 crossings Embedded tracks V =50 km/hr Axle load = 10t 1 Mio crossings Axle Extra weight Revolving turret, drive Rubber wheels 16 Test bodies 35 cm Video Final Conference, June 25, 2010 - Prague 12

Planning Reference to STUVA testing rail underpour: Icosit 340/65 fill in material: Edilon Sedra, prefabricated, glued to the rail mastix asphalt as top layer on concrete base plate rail 59 Ri 2 STUVA recommends: The tested construction is suitable for streets with a low percentage of heavy load traffic Final Conference, June 25, 2010 - Prague 13

Planning Time schedule construction sequence working hours 6:00 22:00 working hours action weekend 0:00 24:00 working hours 6:00 22:00 week 1 week 2 week 3 week 4 time assembly of parts, Preparatory work 57h action weekend subsequent work, evacuation of building site facilities Tramway operation of the concerned 2 lines stopped only for the 57 h on the action weekend Final Conference, June 25, 2010 - Prague 14

Preparation before construction Coordination with local authorities and residents Public relations utilities detour of individual traffic detour of public transport road marking accessibility of residents emergency accessibility coordination of working times night shifts coordination with local events e.g. football matches Final Conference, June 25, 2010 - Prague 15

Planning Preparation Phase 15.09.2008 19.09.2008 2-shift operations between 6:00 a.m. and 10 p.m. Preparation of construction site Delivery of all material necessary for action weekend Cutting and removal of paving and asphalt Removal of old ballast Mounting of track sections Glueing of fillings Determination of ductwork and piping positions Final Conference, June 25, 2010 - Prague 16

Construction sequence I Preparation Phase 15.09.2008 19.09.2008 Final Conference, June 25, 2010 - Prague 17

Construction sequence I Preparation Phase 15.09.2008 19.09.2008 Final Conference, June 25, 2010 - Prague 18

Construction sequence I Preparation Phase 15.09.2008 19.09.2008 Final Conference, June 25, 2010 - Prague 19

Construction sequence I Preparation Phase 15.09.2008 19.09.2008 Corrosion at old tracks due to stray current Final Conference, June 25, 2010 - Prague 20

Construction sequence I sequence plan for 57 h action weekend Final Conference, June 25, 2010 - Prague 21

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Activities during action weekend 3-shift operations Dismantling of tracks Earthworks Ductworks Pouring of concrete base plate Installation of tracks Connection to existing tracks Underpouring of rails Connection to drainage Pouring of concrete surface in junction Stader Straße Final Conference, June 25, 2010 - Prague 22

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Friday, 19 September 2008 Last tram passing construction machinery Friday, 19 September 2008 Cutting off of rails Final Conference, June 25, 2010 - Prague 23

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. loading of worn rails Final Conference, June 25, 2010 - Prague 24

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. ductwork for wires Prefabrication of ductwork Final Conference, June 25, 2010 - Prague 25

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Sat 20 September 2008 Preparation for concrete slab Sat 20 September 2008 delivery of track sections Final Conference, June 25, 2010 - Prague 26

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Sat 20 September 2008 continuous earthworks along section Final Conference, June 25, 2010 - Prague 27

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. installation of shuttering and adjustment Final Conference, June 25, 2010 - Prague 28

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Sat 20 September 2008 Pouring of concrete slabs at starting point Sat 20 September 2008 Laying out the track sections Final Conference, June 25, 2010 - Prague 29

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Sat 20 September 2008 welding St 20 September 2008 drilling holes for fixations Final Conference, June 25, 2010 - Prague 30

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. drainage Final Conference, June 25, 2010 - Prague 31

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Sat 20 September 2008 fixation Final Conference, June 25, 2010 - Prague 32

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. underpour rails Sun 22 September 2008 Final Conference, June 25, 2010 - Prague 33

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Facts: mass: length of site: 375 m (+25m adaption) length of rails: 800 m Fillings: 4,300 tie bars: 500 weldings: 110 fixations: 1.300 concrete slab: 2,400 m² (or 750 m³) underpour: 9,000 l mastic asphalt: 100 to ground: 1,000 m³ pipings: 1,750 m drainage 50 incl. pipes staff workers on site: 80-100 Final Conference, June 25, 2010 - Prague 34

Action weekend 19.09.2008 7 p.m. to 22.09.2008 4 a.m. Re-start of public transport services: Monday 4 a.m. Final Conference, June 25, 2010 - Prague 35

Construction sequence II Activities from week 2 to 4 2-shift operations between 6 a.m. and 10 p.m. Connection welding to existing track Run cables Pouring concrete base layer Building in 2-layer mastix asphalt Pouring joints Cutting asphalt alongside Road marking Clearing construction site Final Conference, June 25, 2010 - Prague 36

Construction sequence II Finished Final Conference, June 25, 2010 - Prague 37

Summary and lessons learned Replacement of 400 m double track within a 57 h action weekend is possible! The length of the track to be converted was close to what is possible and sensible from a staff and technical feasibility point of view. In future Bremen will choose rather shorter conversion lengths (300-350 m) to be on the safe side. Final Conference, June 25, 2010 - Prague 38

Summary and lessons learned To achieve objectives all logistic activities have to be planned precisely and optimised accurately all the coordination work with local authorities and residents has to be done in advance weather conditions have to be favourable the contractor has to be reputable, skilled workers and technicians are essential the construction firm must be well equipped unforeseen circumstances have to be kept in mind a permanent physical presence of the employer at any time is essential Final Conference, June 25, 2010 - Prague 39

Thank you for your attention! Final Conference, June 25, 2010 - Prague 40