The shaded blocks below indicate the areas of activity published within this Bulletin.

Similar documents
The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

For live Kingfisher updates of offshore activities, visit and on Twitter. 1 of 10

The Array cable installation vessel Stemat 82 and Assist tugs Lydia D and Claudia B are expected to commence installing array cables during week 5.

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Other vessel's involved in the Swale cable pull in and burial operations will be the multicat Wiltango, and the barges Wilcarry 300, & Wilcarry 342.

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 20 th May 2012 Notice no: 75. London Array Offshore Wind Farm

The vessel Nova K, will be undertaking survey and PLGR work on the array cable routes.

Notice of operations at London Array Offshore Wind Farm

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 03 rd June 2012 Notice no: 77. London Array Offshore Wind Farm

Contents. 3) WTG Installation Vessel ) Array cable installation Vessel ) Hotel vessel ) Survey Vessel ) Guard Vessels...

All Array cables have been installed and the cables have now been buried.

The shaded blocks below indicate the areas of activity published within this Bulletin.

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 01 st July 2012 Notice no: 81. London Array Offshore Wind Farm

Contents. 3) Construction Vessels (All dates are weather dependant) ) Survey Vessel ) Guard Vessels... 5

The shaded blocks below indicate the areas of activity published within this Bulletin.

Contents. 3) WTG Installation Vessel ) Array cable installation Vessel ) Hotel vessel ) Rock bag removal Export cable ends...

Contents. 3) Construction Vessels (All dates are weather dependant) ) Survey Vessel ) Guard Vessels... 4

The shaded blocks below indicate the areas of activity published within this Bulletin.

Contents. 3) WTG Installation Vessel ) Hotel vessel ) Substation works ) Survey Vessel... 5

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

The shaded blocks below indicate the areas of activity published within this Bulletin.

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

WESTERMOST ROUGH. OffshOre Wind farm.

Contents. 3) WTG Installation Vessel ) Array cable burial Vessel ) Hotel vessel ) Substation works... 5

A2SEA corporate presentation. Søren Rønnow Poulsen Key Account Manager, Scandinacia & Baltic

Shaded blocks indicate activity.

Safety Zone Application Construction Phase Sheringham Shoal Wind Farm Project

Notice to Mariners No 24 / 2017 Blyth Offshore Demonstrator Project 9 th September 2017

ADANI PORTS & SEZ LTD. ++ MUNDRA PORT ++ GENERAL INFORMATION

TRACK RECORD. First Mover. Burbo Bank Ext. - Tristan Stedman

The shaded blocks below indicate the areas of activity published within this Bulletin.

TRACK RECORD FIRST MOVER. DEME: creating land for the future. Member of the DEME Group

Astrolabe Reef Access Plan Stakeholder Presentation

Admiralty Leisure Folio SC5601 East Devon and Dorset Coast, Exmouth to Christchurch

Scottish Hydro Electric Power Distribution Operation, Inspection, Maintenance and Decommissioning Strategy Bute Cumbrae Cable Replacement

Notice of operations at London Array Offshore Wind Farm

Burbo Bank Extension Offshore Wind Farm

Atlantic Array Wind Farm

Wind Mills of the Mind Delivering large scale offshore wind. Andy Kinsella CEO, Offshore November 24th, 2011, Dundalk

HYDROGRAPHIC AND SITE SURVEY REPORT

This project has been withdrawn by the developer. Atlantic Array Wind Farm

That is why. April 24, 2008

Anchoring Is Important

Potential applications of AUVs and Gliders in Offshore Windfarm Site Surveys

Marine Renewables Industry Association. Marine Renewables Industry: Requirements for Oceanographic Measurements, Data Processing and Modelling

G+ Global offshore wind health and safety organisation

Protection for Vessels Engaged in Servicing Submarine Cables

THE CHALLENGES OF A LARGE-AREA BATHYMETRIC SURVEY

Carbon Trust Offshore Wind Accelerator. OWA floating LiDAR campaign: Babcock trial at Gwynt Y Môr Copenhagen, 11 March 2015 Megan Smith

Nemo Link s puxo campaign

Isis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator.

Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca

LIST OF NOTICES TO MARINERS 2017 PAC 201 JUAN DE FUCA STRAIT AND STRAIT OF GEORGIA, FIRST EDITION, 2012

A FINAL REPORT BY PARTRAC LIMITED: MAY 2006

MARINERS BRIEFING NEW ENGLAND SURVEY ACTIVITY CONTACT. RODNEY AVILA FISHERIES LIAISON Phone:

MARINERS BRIEFING NEW ENGLAND SURVEY ACTIVITY CONTACT. RODNEY AVILA FISHERIES LIAISON Phone:

Storm Preparedness Plan for Manchester, Massachusetts Issued by the Manchester Harbormaster Department. A.

G9 Stakeholder Forum Marine Operations

UK Offshore wind HSE statistics

Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations

Marine Management Organisation Marine Licence

Admiralty Inlet Pilot Tidal Project FERC No Appendix C. Derelict Gear Monitoring Plan

Cargo and hull damage while at anchor in heavy weather

OFFSHORE CREDENTIALS. Accepted for wind resource assessment onshore and offshore by leading Banks Engineers, globally

SB20 UK OPEN CHAMPIONSHIP Thursday 4th Sunday 7 th July 2013 NOTICE OF RACE

EfFl(5)Y.20s 53 13' 0N., 4 43' 4W.

The Marking of Offshore Wind Farms. Provide guidance for a response to IALA. M-4 B445.8 &.9 (& B for on-shore wind farms).

CHAPTER I SUEZ CANAL NAVIGATION FEATURES SECTION 1 APPROACHES

Fort Hancock Sailing Center

NATIONAL MARINE RESEARCH VESSELS

Sea Views SEACAMS. month s edition. In this. Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog

Preliminary Survey Notification and Information for Fisheries Interests.

Orkney and Shetland Islands (2016)

Wave Hub Update All Energy 21/22 May Stuart Herbert Commercial Director

Certified Professionals in Hydrographic Solutions

Pioneer Array Micro-siting Public Input Process Frequently Asked Questions

Offshore Wind Energy Stringent quality assurance and quality control. Coastal and Freshwater Fast responding and flexible organisation

ASX Announcement. 27 February 2018 CETO Wave Energy Update

Code Of Practice For Towage Operations In The Port of St Helier (Towage Guidelines)

15B. Contents. Introduction...1. MGN 543 Checklist...1. Methodology Checklist INCH CAPE OFFSHORE LIMITED

OFFSHORE WIND Kosten heute und morgen welche Potentiale zur Kostensenkung gibt es

For live Kingfisher updates of offshore activities, visit and on Twitter. 1 of 10

Assessment and operation of Wind Turbine Installation Vessels.

Fukushima Floating Offshore Wind Farm Demonstration Project ( Fukushima FORWARD )

NORTHERN IRELAND RENEWABLE ENERGY PORTS PROSPECTUS

Scanning lidar measurements of offshore wind turbine wakes. Peter Clive Senior Scientist, SgurrEnergy All Energy, Glasgow

REVISED SILT CURTAIN DEPLOYMENT PLAN

UK Coastal Atlas of Recreational Boating 2.0: User Guide

Transcription:

The shaded blocks below indicate the areas of activity published within this Bulletin. Area 1 - Area 2 Page 2-4 Area 3 Pages 5-8 Area 4 Page 9 Area 5 Pages 10-12 Area 6 - This Bulletin, along with previous issues, can be viewed at: www.kingfishercharts.org, or you can register for an email alert by contacting: kingfisher@seafish.co.uk All co-ordinates listed in this Bulletin refer to WGS84 datum 1 of 12

Area 2 First Published: 08 May 2014 Latest Update: 08 May 2014 Dogger Bank Creyke Beck Notification of Hearings Following the acceptance for examination of the proposed Dogger Bank Creyke Beck offshore wind farm development by the Planning Inspectorate (September 2013), the Examining Authority will be holding the second of four anticipated sets of hearings. Notice is therefore given that issue specific hearings will be held by the Examining Authority on Tuesday 3, Wednesday 4, Thursday 5 and Friday 6 June as detailed below: Hearings: Date (2014) Tues 3 and Weds 4 June Thurs 5 and Fri 6 June Hearing Issue Specific Hearing Habitats Regulations Assessment Issue Specific Hearing Development consent order and deemed marine licence Full notice of the hearings can be downloaded from the Forewind website: http://www.forewind.co.uk/downloads/dogger-bank-creyke-beck-downloads/examination-2.html The hearings will be recorded and posted on the Planning Inspectorate website the following week: http://infrastructure.planningportal.gov.uk/projects/yorkshire-and-the-humber/dogger-bank-creyke-beck/?ipcsection=docs For further information, please contact: Elizabeth Eddy, Velvet First Published: 07 May 2014 Latest Update: 07 May 2014 Forewind Ltd Dogger Bank Teesside A&B Section 56 Planning Act 2008 Regulation 8 Forewind Limited Dogger Bank Teesside A & B Section 56, Planning Act 2008 Regulation 8, The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 Notice is hereby given that The Planning Inspectorate (on behalf of the Secretary of State for Energy and Climate Change) has accepted an application made by Forewind Limited of 55 Vastern Road, Reading, Berkshire, RG1 8BU for a development consent order (DCO) under the Planning Act 2008 (the Act) for the offshore development Dogger Bank Teesside A & B. The Application was made on 28 March 2014 and accepted for examination on 23 April 2014 (Application Reference: EN010051). Dogger Bank Teesside A & B is the second stage of development of the Dogger Bank Zone in the North Sea (the first stage being Dogger Bank Creyke Beck). It comprises two offshore wind farm arrays (Dogger Bank Teesside A and Dogger Bank Teesside B), each with a generating capacity of up to 1.2 gigawatts, and associated infrastructure. The full notice can be viewed at: http://www.forewind.co.uk/downloads/dogger-bank-teesside-a-b-2/application-documents-2.html For further information, please contact: Elizabeth Eddy, Velvet Communications Ltd, Tel: 01642 584790 email: www.velvetcommunications.co.uk 2 of 12

Area 2 First Published: 20 May 2014 Latest Update: 20 May 2014 Outer Moray Firth Survey Activities Mariners are advised that Calegeo will be carrying out geotechnical survey operations on behalf of Moray Offshore Renewables Limited (MORL) in the outer Moray Firth, as part of the Moray OWF project. Company, Vessel & Call Sign Area Covered Start Timeframe & Duration Area Calegeo MV Highland Spirit (Call Sign: MYJD2) 1. 58 06.543 N 002 41.888 W 2. 58 03.946 N 002 54.796 W 3. 58 05.943 N 002 51.407 W 4. 58 08.329 N 002 50.026 W 5. 58 10.782 N 002 50.612 W 6. 58 12.605 N 002 52.379 W 7. 58 16.609 N 002 46.348 W 8. 58 19.378 N 002 44.296 W 9. 58 13.141 N 002 34.265 W 10. 58 08.080 N 002 34.184 W 11. 58 06.543 N 002 41.888 W 2 June 2014 For 45 Days For further information, please contact: Carlos Alvarenga, Calegeo, Tel: +44(0) 1508 521 200 email: carlos.alvarenga@calegeo.com First Published: 23 April 2014 Latest Update: 07 May 2014 Outer Moray Firth Survey Activities Please be advised of the following marine survey operations that are taking place on behalf of Moray Offshore Renewables Limited (MORL) in the outer Moray Firth. Company, Vessel & Call Sign Area Covered Start Timeframe & Duration Area Gardline MV Titan Explorer (Call Sign: MZUZ2) MV Ivero (Call Sign: PCKA) MV Vigilant (Call Sign: PBNX) Approximate Survey Area: 1. 57 40.000'N 002 55.000'W 2. 58 20.000'N 002 55.000'W 3. 58 20.000'N 002 33.000'W 4. 57 40.000'N 002 33.000'W 1 May 2014 For 40/50 Days Fugro Ltd MV Ocean Dawn (Call Sign: HP3209) Approximate Survey Area: 1. 58 11.800'N 002 40.883'W 2. 58 11.800'N 002 41.033'W 3. 57 41.033'N 002 44.733'W 4. 57 40.267'N 002 33.250'W 8 May 2014 and 30 May 2014 For 5 Days For further information, please contact: Andrew Hamilton, EDPR, Tel: + 44 (0)131 556 7602, Email: Andrew.Hamilton@edpr.com 3 of 12

Area 2 First Published: 13 December 2013 Latest Update: 07 May 2014 Neart na Gaoithe Offshore Windfarm Metocean Buoy Deployment On the 20th April 2014, Neart na Gaoithe Offshore Wind Limited deployed two metocean buoys at their offshore Wind Farm site approximately 21km east of the Fife coast. Please find location details below. The buoys measure (1) wind speed and direction and (2) waves and currents; both buoys are deployed alongside each other. Both buoys are painted to IALA standard, have an amber navigation light set to flash 5 times at 1Hz every 20 seconds. Buoy (1) is moored using two delta flipper anchors with riser chains (max. 250m each). There are two pennant buoys floating on the surface above each of the two seabed anchors associated with the buoy. The pennant buoys are yellow, 1m long, diameter of 0.5m and are unlit. They are attached to the anchors by steel wire. Buoy (2) is moored via a single bungee line. The buoys will be deployed within the Neart na Gaoithe Wind farm boundary, at the following co-ordinates: (1) 56 15.762 N 02 15.011 W 92m drift radius (anchors marked with pennant buoys at 56 15.875 N 02 15.032 W and 56 15.654 N 02 15.029 W) (2) 56 15.766 N 02 15.203 W 82m drift radius Please note requirement for wide berth when passing buoys detailed below due to their large excursion as a result of their mooring configurations. The buoys were deployed on 20th April 2014 and are expected to stay in place for up to 12 months (until approx. 20th April 2015). For further information, please contact: Keith Harsham, Tel: +44(0)20 77765515 Mob +44(0)7876454649 email: Keith.Harsham@mainstreamrp.com 4 of 12

Area 3 First Published: 20 May 2014 Latest Update: 20 May 2014 Sheringham Shoal Offshore Wind Farm Survey Activities Mariners are advised that Marine Ecological Surveys Ltd. (MESL) will be undertaking environmental survey activities on behalf of Scira Offshore Energy Limited at the Sheringham Shoal Offshore Windfarm site. The survey will comprise the acquisition of seabed imagery only across a 1 2 day period between 22nd May and 6th June, weather permitting, aboard the Humber Guardian. Company, Vessel & Call Sign Marine Ecological Surveys Limited Humber Guardian Area Covered Boundary of SIZ Boundaries of Reference Areas Cable Route 53 11.389'N 01 00.908'E - (NW) 53 11.429'N 01 01.061'E 53 08.529'N 01 13.454'E (NE) 53 08.255'N 01 13.994'E 53 05.052'N 01 16.066'E (SE) 53 05.019'N 01 15.599'E 53 07.943'N 01 03.466'E (SW) 53 08.176'N 01 03.012'E 53 12.526' N 1 06.843' E (N) 53 11.800' N 1 10.062' E 53 10.947' N 1 10.099' E 53 11.704' N 1 06.879' E 53 10.915' N 0 58.181' E (W) 53 10.435' N 1 00.315' E 53 09.462' N 1 00.360' E 53 09.947' N 0 58.227' E 53 03.822' N 1 11.233' E (S) 53 03.245' N 1 13.751' E 53 01.359' N 1 13.829' E 53 01.909' N 1 11.313' E 53 07.090' N 1 07.580'E 53 06.432' N 1 10.330 E 53 04.076' N 1 08. 972 E 53 04.057' N 1 08.201 E 52 57.752' N 1 08.337 E 52 58.551' N 1 07.442 E Area For further information, please contact: Daniel Brutto, MESL, Tel: +44(0)1225 442211 email: dan@seasurvey.co.uk First Published: 14 August 2013 Latest New: 21 May 2014 Humber Gateway Offshore Wind Farm Foundation Installation Phase 1 Please be advised that E.ON will be installing 24 Wind Turbine Foundations approximately 10 miles offshore from Spurn Head, within the Humber Gateway Offshore Wind Farm. Boulder Removal Phase 3: Atlantic Explorer will be conducting boulder clearance operations until further notice. Array Cable Installation Atlantic Carrier: In Field ongoing trials. Project Wave Riders The Project wave rider buoys LAT LONG Eon Tri-axe Wave Rider 53 38.788 N 00 18.023 E Eon Data-well Wave Rider 53 38.199 N 00 15.846 E Foundation Installation Progress: MPI Resolution will be loading 2 foundations at a time and install when weather permits. Please note all foundations installed have temporary navigational aids fitted and are all operational. Important Locations: Characteristics Lat Long Met Mast 53 38.237 N 00 15.730 E West Cardinal Lighted Buoy (N) V Q (9) 10s 53 39.900 N 00 14.200 E West Cardinal Lighted Buoy (S) Q (9) 15s 53 37.000 N 00 15.600 E South Cardinal Lighted Buoy Q (6) + LFl 15s 53 36.500 N 00 17.400 E East Cardinal Lighted Buoy (S) Q (3) 10s 53 38.400 N 00 20.100 E East Cardinal Lighted Buoy (N) V Q (3) 5s 53 40.300 N 00 20.100 E Wave rider No 1 53 39.930 N 00 18.160 E Continued over the page 5 of 12

Area 3 Export Cable End Markers (South of the Offshore sub-station) Both cable ends have now been laid on the seabed. Please note a 800m exclusion zone has been implemented around the duct ends to protect the surface laid cable. LAT LONG North End Cable 53 39.248 N 00 15.181 E South End Cable 53 39.280 N 00 15.215 E For further information, please contact: Gordon Bain, Eon Tel:+44(0) 7787241442 or Nigel Proctor (Fisheries Liaison) Tel: +44(0)7702730891 First Published: 08 April 2014 Latest Update: 30 April 2014 London Array Wind Farm Construction Works Construction works at London Array Offshore Wind Farm are complete and the wind farm is operational. However, remedial construction works are required at a number of turbines and inter array cable locations. Diving Operations Please be advised that Red7Marine Offshore Ltd on behalf of London Array Offshore Ltd will be undertaking Diving and Construction work within the London Array Offshore Wind Farm. Operations will be conducted from the vessel Red7 Reel, a support RIB COM III and shallow water vessel Myss operated by Red7Marine Offshore Ltd. During operation the Red7 Reel will be acting as a mothership for the COM III and Myss. Throughout all diving operations a 500m exclusion zone will be enforced around each vessel. Estimated start date: 5 April 2014 Estimated finish date: August 2014 In order to avoid damage to the wind farm assets whilst remedial construction is conducted at London Array the following guidelines should be adhered to: Safety Exclusion Zones remain in operation for October 2013 and will be reinstated in March 2014 through to November 2014. This means an enforceable 50m safety zones from each turbine and 500m safety zones from a construction vessel will be in operation for this period. Between October 2013 and November 2014 an advisory 100m safety zone should be observed around each turbine and offshore substation due to the risk of exposures of array cable ends at foundations whilst remedial works are on-going. Cable reburial is required at the following locations and as such these areas should be avoided in totality. Location Coordinates Length of Exposure Location Coordinates Length of Exposure Location 1 51 35.149'N 001 27.963'E 20m Location 5 51 37.698 N 001 28.651 E 6m Location 2 51 35.447'N 001 31.478'E 8m Location 6 51 41.232'N 001 29.899'E 5m Location 3 51 36.653'N 001 26.513'E 7m Location 7 Start: 51 37.954'N 001 26.029'E 926m End: 51 38.412'N 001 25.904'E Location 4 51 38.153'N 001 26.331'E 5m Location 8 Start: 51 41.429'N 001 30.862'E End: 51 41.115 N 001 30.397'E 865m Care should be taken within the wind farm site to avoid snagging array cables. Although not expected, natural seabed variation may reduce the depth of burial over buried cables without London Array s immediate knowledge. Snagging cables not only poses a risk to health and safety but could also cause a serious risk of damage to wind farm assets. For further information, please contact: Email: londonarraytraffic@dongenergy.dk, Tel: +44(0)7909414690 or +45 31727585 6 of 12

Area 3 First Published: 28 April 2014 Latest Update: 28 April 2014 Sheringham Shoal Offshore Wind Farm Survey Activities Please be advised that Fugro Emu Limited will be conducting a Geophysical Survey Company, Vessel & Call Sign Fugro EMU Limited MV Fugro Seeker (Call Sign: MZUZ2) 1. 52 57.162'N 001 07.634'E 2. 52 58.350'N 001 07.226'E 3. 52 59.381'N 001 07.272'E 4. 53 00.940'N 001 08.055'E 5. 53 02.824'N 001 07.879'E 6. 53 05.087'N 001 08.035'E 7. 53 05.934'N 001 08.015'E 8. 53 06.687'N 001 07.846'E 9. 53 07.003'N 001 06.524'E 10. 53 11.001'N 001 03.897'E Area Covered 11. 53 09.265'N 001 11.196'E 12. 53 05.263'N 001 13.794'E 13. 53 06.177'N 001 10.008'E 14. 53 02.904'N 001 09.043'E 15. 53 01.251'N 001 09.357'E 16. 52 59.221'N 001 08.438'E 17. 52 58.415'N 001 08.423'E 18. 52 57.279'N 001 08.855'E 19. 52 57.007'N 001 08.781'E Start Timeframe & Duration 29 April 2014 1 st June 2014 For 10 Days Area For further information, please contact: Marcus Osmaston, Fugro Emu Ltd, Tel +44(0) 1489 861095 email: marcus.osmaston@fugroemu.com First Published: 17 April 2014 Latest New: 17 April 2014 Westermost Rough Wind Farm Operations & Activities The Westermost Rough Offshore Wind Farm is located 8 km from the Holderness coast, approximately 25 km North of Spurn Head at the river Humber estuary. The wind farm will be made up of 35 Siemens 6MW turbines, with construction beginning in the first half of 2014 and the wind farm is expected to be fully commissioned in the first half of 2015. Foundation installation is commencing with the vessels Innovation and MPI Lucinda. Survey work on installed foundations is being undertaken by the vessel Foryd Bay. The guard vessel Marja is on site. For further information, please contact: Marine Coordinator, Tel: +44 (0)7776 170914, Email:mcWMR@dongenergy.co.uk First Published: 27 June 2012 Latest Update: 09 April 2014 Lincs Offshore Wind Farm Aids to Navigation Outage Mariners are advised of imminent changes to the marine navigation markings associated with the Lincs Offshore Wind Farm. Mariners are advised that the Fishing Vessel Jubilee Spirit (GY25) (Length 21m, Breath 7m) will be operating in and around the Lincs Site from the 14th of April, performing standard survey operations. Mariners are requested to give the vessel clearance during operations as the vessel will have restricted manoeuvrability. The Fishing vessel The Two Brothers (LN1) (length 9.8m breath 5.1m) will be operating in and around the Lincs site conducting normal survey works, from the 15th of April until the 30th of April. Mariners are advised to give this vessel clearance during operations as the vessel will have restricted manoeuvrability. Mariners are advised that the following Aids to Navigation within the Lincs site remain out of operation and are undergoing maintenance works. Fog Horns on LS69 Continued over the page 7 of 12

Area 3 The locations and specification of the 8 permanent navigation aids, is shown below. Turbine N o Position Permanent Marine Navigation Specification LS01 53 14.475'N 000 27.569'E (Fl Y 5s) and Fog Horn LS05 53 13.069'N 000 28.162'E (Fl Y 5s) LS13 53 09.451'N 000 28.503'E (Fl Y 5s) LS33 53 07.712'N 000 29.403'E (Fl Y 5s) LS52 53 14.843'N 000 30.010'E (Fl Y 5s) and Fog Horn LS59 53 12.451'N 000 31.016'E (Fl Y 5s) and Fog Horn LS64 53 10.803'N 000 31.047'E (Fl Y 5s) LS69 53 09.088'N 000 31.048'E (Fl Y 5s) and Fog Horn For a copy of the Kingfisher Awareness Flyer for the Lincs Offshore Wind Farm, please contact the undersigned. Alternatively, click on the link below, or visit www.kingfishercharts.org Kingfisher Awareness Flyer: Lincs Offshore Wind Farm For further information, please contact: Angela Wilcock, RSS Marine, Tel: 0723 893930 email: awilcock@dsml.co.uk First Published: 08 April 2014 Latest Update: 08 April 2014 Rampion Offshore Wind Farm Survey Activity E.ON Climate and Renewables Rampion Offshore Limited has contracted Fugro to carry out a geotechnical site investigation for the proposed Rampion wind farm. Fugro will be undertaking the geotechnical site investigation at up to 183 locations within the wind farm site area. Company, Vessel & Call Sign Fugro SRV Bavenit MV Gargano Area Covered 1. 50 41.167'N 000 22.018'W 2. 50 37.375'N 000 20.760'W 3. 50 38.509'N 000 16.478'W 4. 50 37.182'N 000 15.731'W 5. 50 39.581'N 000 01.552'W 6. 50 40.709'N 000 04.462'W 7. 50 42.417'N 000 13.802'W Start Timeframe & Duration 16 th April 2014 Until May/June 2014 21 st April 2014 Until May/June 2014 Area For further information, please contact: Vicki Griffiths, Tel: +44(0)1491 820 696 email: v.griffiths@fugro.co.uk First Published: 12 March 2014 Latest Update: 12 March 2014 Sheringham Shoal Wind Farm Malfunction of Lights The following items relating to sign lighting are not functional within Sheringham Shoal Wind Farm. Sign lights are not navigational aids and are not to be used as such. Location Position ID Config Defect OS1 53 08.648'N 001 07.236'E 4 ID Boards around transition piece each with 3 lights (total 12 lights) East ID light board, left bulb of 3 unlit West ID light board, right bulb of 3 unlit North ID light board, centre bulb of 3 unlit OS2 53 07.602'N 001 10.549'E 4 ID Boards around transition piece each with 3 lights (total 12 lights) North West ID light board, right bulb of 3 unlit H6 53 07.194'N 001 10.482'E 3 ID Boards around transition piece. South East ID light board is unlit For further information, please contact: Gary Lorimer, Statkraft, Tel: +44 (0)1328 824356 email: Gary.Lorimer@statkraft.com 8 of 12

Area 4 First Published: 20 May 2014 Latest Update: 20 May 2014 North Cornwall Wave Hub Please be advised that Seatricity Ltd are planning to deploy their Oceanus 2 Wave Energy Converter at the Wave Hub Renewable Energy Development Area within Berth 1 which has the following co-ordinates SW Corner Berth 1 NW Corner Berth 1 NE Corner Berth 1 SE Corner Berth 1 Position 50 20.733'N 005 36.961'W 50 21.219'N 005 37.082'W 50 21.359'N 005 35.708'W 50 20.873'N 005 35.587'W The deployment is planned from 20th May 2014 to 25th May 2014 and the Oceanus 2 device will then remain on station for up to one year. For further information, please contact: Julius Besterman, Wave Hub, Tel: 01736 800291 email: Julius.besterman@wavehub.co.uk 9 of 12

Area 5 First Published: 07 May 2014 Latest Update: 21 May 2014 Sound of Islay Bottom Mounted ADCP frames Partrac proposes to deply five bottom mounted ADCP rames for 30 days within 50m of the following positions: Name ADCP 01 ADCP 02 ADCP 03 ADCP 04 ADCP 05 Position 55 50.249'N 006 05.839'W 55 50.254'N 006 05.706'W 55 50.165'N 006 05.830'W 55 50.080'N 006 05.820'W 55 49.995'N 006 05.810'W No surface markers will be used. One Turbulence Mooring will be deployed between the ADCP frame locations. All equipment (including ground weights) will be removed at the end of the study Deployments from 21 st April 2014 for 30 Days. For further information, please contact: Kevin Ransom, Partrac Ltd, Tel: +44 (0)141 2020644 email: Kransom@partrac.com First Published: 05 December 2012 Latest Update: 21 May 2014 West of Duddon Sands Offshore Wind Farm Construction Works The West of Duddon Sands offshore wind farm is a joint venture between DONG Energy West of Duddon Sands (UK) Limited and ScottishPower Renewables (WoDS) Limited. Sea Installer is on site installing Tower sections, Turbines and Blades. Rock Dump Positions Please note that rock dumping has been undertaken where the export cables are exposed due to either bad ground or other cable/pipeline crossings. Surveys will be carried out along the both of the export cables, to determine if there are any other positions. Please contact the undersigned to receive locations of these sections. Construction Dive activities from Dive Support Vessels will operate as and when required inside of the WoDS perimeter. Mariners should note that a minimum 500 meter Safety Exclusion Zone will be in force around vessels at all times whenever they are on site at any location. All turbine foundations and transition pieces have been installed. 'Sea Installer' is on site fitting Tower sections, Turbines and Blades. All of the Inter-Array or Infield Cables have been surface laid and are now being buried by 'Maersk Responder. The Guard Vessel for the Wind Farm site is 'Ocean Harvester' and this vessel can be contacted on VHF Channels 16 & 12 for information relating to vessel movements inside the Wind Farm only. Boundary of Location Activities: Latitude 54 00.15 N 54 01.78 N 53 58.35 N 53 56.64 N 53 56.72 N Longitude 003 33.52 W 003 26.67 W 003 22.80 W 003 25.37 W 003 29.33 W For a copy of the Kingfisher Awareness Flyer for the West of Duddon Sands Offshore Wind Farm, please contact the undersigned. Alternatively, click on the link below, or visit www.kingfishercharts.org Kingfisher Awareness Flyer: West of Duddon Sands Offshore Wind Farm In case of emergency, please contact: Dan Torben Christensen, Dong Energy, Tel: +44(0)7528921388 email: danch@dongenergy.dk 10 of 12

Area 5 First Published: 02 July 2012 Latest Update: 19 May 2014 Walney 1, 2 & Extension Offshore Wind Farm Construction Activity / Consultation The DP vessel Highland Eagle is on site continuing with the Geotechnical Ground Investigation at the proposed Walney 3 Offshore Wind Farm. Highland Eagle and is expected to remain on site throughout May 2014. Infield survey operations as well as Turbine and Foundation inspections will be carried out by the 14 meter survey vessel Argus-G in the Walney 1 & 2 Wind Farms. These survey operations are expected to start on Wednesday 24 April 2014 and will last for approx. 8 weeks and are not expected to interfere with any other vessel but, as sensitive survey and sounding equipment will be in use, a wide berth is requested around Argus-G at all times. Argus-G will keep a listening watch on VHF Channels 16 and 12 and can be contacted for information regarding vessel movement only. For a copy of the Kingfisher Awareness Flyers for the Walney Offshore Wind Farms, please contact the undersigned. Alternatively, click on the link below, or visit www.kingfishercharts.org Kingfisher Awareness Flyer: Walney 2 Offshore Wind Farm Kingfisher Awareness Flyer: Walney 1 Offshore Wind Farm For further information, please contact: Tom Watson, Tel: 01253 875565, Mobile: 07903 173624 First Published: 29 June 2012 Latest Update: 19 May 2014 Gwynt y Môr Offshore Wind Farm Construction Activities The Gwynt y Môr Offshore Wind Farm Project is located between 15km to 20km off the coast of North Wales in the Liverpool Bay area of the Irish Sea. It is adjacent to RWE Innogy s North Hoyle and Rhyl Flats offshore wind farms. The consented site covers an area of 124km2. The water depth ranges from 12m to 28m LAT. This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 19th May 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days Wind Farm Construction Status Monopiles: 160 installed. Monopile installation is complete. Transition pieces: 160 installed. Transition piece installation is complete Export cables: 4 export cables installed; installation is complete. Array cables: 86 array cables installed, 75 remaining. Wind Turbine Generators: 150 installed, 10 remaining. Work planned for next 7 days Wind Solution will remain at anchor position to the south of Gwynt y Môr, sailing into Liverpool for shelter as required (see our previous notice here). Sea Worker will continue with wind turbine installation (see our previous notice here). Scirocco, Gaillion, Abersoch Bay, Gardian 10, Santa Ana, Sea Storm, Sea Breeze, EMS Viking, Chinook, Bayard 2 and Bayard 5 will be utilised as Crew Transfer Vessels when required sailing from Canada Dock 3 and Liverpool Marina. Penrhyn Bay, Colwyn Bay, Caernarfon Bay, Gardian, Gardian 2, Iceni Defiant, Athenia, Adventure, Endeavour, Buzzard, Captain P, Commodore P, Kinmel Bay, Cymyran Bay, Aberdaron Bay and Iceni Victory sailed from the Port of Mostyn as required. Penrhos Bay & Tremadoc Bay are on 24 hour cover and being utilised by the Emergency Rescue Team sailing from RWE Pontoon Birkenhead. MCS Zephyr, Developer, Transporter, Commander P and Cwind Alliance sailed from Huskissons Dock as required to assist with cable operations. Normand Tonjer will continue diving operations including work with the Polar Prince to aid installation of array cables. HBC Supporter will continue diving operations. Isadale will continue performing guard duties and will be used as the Marine Mammal Observation vessel as and when required. Continued over the page 11 of 12

Area 5 Channel Chieftain VII, Cwind Challenger and Cwind Resolution will continue refuelling operations on site based from Mostyn. Cable vessel Sia will continue operations on site. Polar Prince will continue array cable installation with Polar King (see notice to mariners here) assisted by CTVs Rix Panther and Rix Tiger. Fugro Saltaire will continue trenching & survey operations at Gwynt y Môr Offshore Wind Farm. Survey vessel Line will continue surveying operations. Survey vessels Confidante and RV Discovery will continue UXO survey operations (see notice to mariners here). DSV Red7 Tonjer will continue with diving operations, assisting Polar Prince as required. DSV Toisa Vigilant will continue diving operations at the windfarm. For a copy of the Kingfisher Awareness Flyer for the Gwynt Y Mor Offshore Wind Farm, please contact the undersigned. Alternatively, click on the link below, or visit www.kingfishercharts.org Kingfisher Awareness Flyer: Gwynt Y Mor Offshore Wind Farm For further information, please contact: Lee Cornwell, RWE npower renewables, Mob: +44 (0) 7557 319473, Email: lee.cornwell@rwe.com First Published: 19 November 2013 Latest Update: 15 May 2014 Robin Rigg Offshore Wind Farm Hazard / Plotter Files / Operations The Bathymetric survey has now been completed. three personnel/crew transfer vessel vessels 'Rhoscolyn Head', 'Solway Challenger' and Porth Wen have joined the two vessels already in service, 'Solway Spirit' and 'Windcat 3', and a wide berth is requested around these vessels at all times while on site but all mariners, especially fishermen, are requested to keep a wide berth from any turbine where it can be observed that these vessels are working. For a copy of the Kingfisher Awareness Flyer for the Robin Rigg Offshore Wind Farm or Fishing Plotter CD, please contact the undersigned. Alternatively, click on the link below, or visit www.kingfishercharts.org Kingfisher Awareness Flyer: Robin Rigg Offshore Wind Farm Kingfisher Fishing Plotter CD: Robin Rigg Offshore Wind Farm For further information, please contact: Tom Watson, Tel: 01253 875565, Mob: 07903 173 624 First Published: 23 April 2014 Latest Update: 23 April 2014 Fair Head Tidal Energy Seabed Frame Deployment Deployment of three sea bed frames with velocity profiling and pressure sensor equipment will take place on the week beginning 21 April 2014, dependent on suitable weather conditions. The equipment will remain in-situ for a minimum of 35 days and recovery will take place with the first available weather window after this time period. A marker buoy will not be used for this survey. The deployment locations are as follows: 1. Loc 1 55 13.816'N 006 06.856'W 41m depth 2. Loc 2 55 13.704'N 006 06.787'W 42m depth 3. Loc 3 55 13.351'N 006 05.377'W 42m depth For further information, please contact: David Fitzgerald, Tel: +353 (0) 22 23955, Email: david.fitzgerald@dpenergy.com 12 of 12