Bollard Pull Certification Procedures Guidance Information, 1992

Similar documents
TECHNICAL INFORMATION BOLLARDPULL TRIALCODE. ForTugs with SteerpropPropulsion. Steerprop

Bollard Pull. Bollard Pull is, the tractive force of a tug, expressed in metric tonnes (t) or kn.

ITTC Recommended Procedures and Guidelines

IMO ANCHORING, MOORING AND TOWING EQUIPMENT. Submitted by the Republic of Korea

Note to Shipbuilders, shipowners, ship Managers and Masters. Summary

ClassNK Technical Information No. TEC Required minimum propulsion power In principle, the installed propulsion power (total main engine output

PART 1 GENERAL REQUIREMENTS

SECOND ENGINEER REG III/2 NAVAL ARCHITECTURE

TOWAGE GUIDELINES FOR THE GLOUCESTER HARBOUR. August 2018

RESOLUTION MSC.137(76) (adopted on 4 December 2002) STANDARDS FOR SHIP MANOEUVRABILITY

CERTIFICATES OF COMPETENCY IN THE MERCHANT NAVY MARINE ENGINEER OFFICER

CONTENTS AIRBERTH OWNER S MANUAL I 3

A1.1.5 It is assumed that under normal circumstances a ship uses only one bow anchor and chain cable at a time.

Technical Information

RULES FOR CLASSIFICATION Naval vessels. Part 1 Classification and surveys Chapter 5 Surveys for submarines. Edition January 2016 DNV GL AS

Conventional Ship Testing

ITTC Recommended Procedures and Guidelines

WAHSA PGN02 Practical Guidance Note 02 (formerly TGN03) GUIDANCE ON INSPECTING PERSONAL FALL PROTETION EQUIPMENT

Whitstable Harbour Pilotage Information

Code Of Practice For Towage Operations In The Port of St Helier (Towage Guidelines)

ANCHORING REQUIREMENTS FOR LARGE CONTAINER SHIPS

New Vessel Fuel Efficient Design and Construction Considerations Medium and Long-Term Options

ITTC Recommended Procedures and Guidelines

Part 7 Fleet in service Chapter 2 Inclining test and light weight check

Type Testing Procedure for Crankcase Explosion Relief Valves

MANOEUVRING BOOKLET V1.06

NIS/NOR Circular. Category: Circular no.: 07/2007

IACS History File + TB

REDUNDANT PROPULSION SHIPS RULES FOR CLASSIFICATION OF NEWBUILDINGS DET NORSKE VERITAS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2

MANOEUVRING BOOKLET V1.06

ABP South Wales and River Usk Towage Guidelines

SLOP RECEPTION AND PROCESSING FACILITIES

Opening and closing force guidelines

The Work At Height Safety Association

PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE

Presented to the International Technical Rescue Symposium, November Abstract

Rule Change Notice For: RULES FOR CLASSIFICATION OF MOBILE OFFSHORE UNITS

THE MOORING OF OIL CARRIERS AT SINGLE POINT MOORINGS

CALIBRATION SYSTEM REQUIREMENTS. ESCC Basic Specification No

05 Boat Handling. Captain

MEMORANDUM OF AGREEMENT

SCUBA DIVING SAFETY MANUAL

ANNEX 2 RESOLUTION MEPC.124(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER EXCHANGE (G6) THE MARINE ENVIRONMENT PROTECTION COMMITTEE,

2 FUSION FITTINGS FOR USE WITH POLYETHYLENE PRESSURE PIPES DESIGN FOR DYNAMIC STRESSES

Welcome to the Bollard Pull Calculator for Barges!

Autopilot setup. VRF (Virtual Rudder Feedback) calibration. Software setup NSS evo2 Installation Manual

Development of TEU Type Mega Container Carrier

PROJECT and MASTER THESES 2016/2017

RESOLUTION A.751(18) adopted on 4 November 1993 INTERIM STANDARDS FOR SHIP MANOEUVRABILITY

DQM Annual Hopper QA Checks

E2K-L. Liquid Level Sensor That Is Unaffected by the Color of the Pipe or Liquid. Liquid Level Sensor. Ordering Information

b) Submission of Crew list and arrival details (no later than 2 weeks prior to charter)

INFORMATION BULLETIN No. 159

An Investigation into the Capsizing Accident of a Pusher Tug Boat

Certified Accuracy. Ring Force Gauge. Models and Capacities Available. Design and Principle of Operation

ICE LOADS MONITORING SYSTEMS

MIL-STD-883G METHOD

6. EXPERIMENTAL METHOD. A primary result of the current research effort is the design of an experimental

APSP APPLIANCE EFFICIENCY POOL PUMP DATABASE INSTRUCTIONS, DECLARATION, AND TERMS OF USE (Instructions last updated 2/1/2018)

TOWMASTER. User Manual. Version : 1.0.0

GUIDELINES ON OPERATIONAL INFORMATION FOR MASTERS IN CASE OF FLOODING FOR PASSENGER SHIPS CONSTRUCTED BEFORE 1 JANUARY 2014 *

RESOLUTION MSC.235(82) (adopted on 1 December 2006) ADOPTION OF THE GUIDELINES FOR THE DESIGN AND CONSTRUCTION OF OFFSHORE SUPPLY VESSELS, 2006

ITTC Recommended Procedures Testing and Extrapolation Methods Manoeuvrability Free-Sailing Model Test Procedure

The balance of the charter fee will be paid to Cloud Nine Yacht Charters not less than 28 days before the start of the period of charter.

INSTALLATION. USE AND MAINTEINANCE INSTRUCTIONS FOR COLLAPSIBLE COLUMNS WITH HAND BALANCED SYSTEM

NEW BUILD - SB-ST 19 Steel Trawler Listing ID:

PRODUCT DISCLOSURE STATEMENTS FOR RACING SYNDICATES GUIDELINES FOR PROMOTERS IN NSW

Moor, Tend Mooring And Unmoor Ship - Supervisor Level -

RESOLUTION MSC.141(76) (adopted on 5 December 2002) REVISED MODEL TEST METHOD UNDER RESOLUTION 14 OF THE 1995 SOLAS CONFERENCE

RESULTS FROM PARACHUTE SEA ANCHOR DRAG TESTS FOR A SPACE CAPSULE, Jan. 10, 2013

ITTC Recommended Procedures and Guidelines

ANNEX 16 RESOLUTION MEPC.232(65) Adopted on 17 May 2013

Level MEASUREMENT 1/2016

3. The younger team member must be aged 18 years or over as at the date of the event (Saturday 7 October 2017).

Gulf Harbour Village Marina Licence of Berth Terms & Conditions

GUARDING OF FLOOR-TO-FLOOR WOOL PRESSES

REVO Single Boot System Binding Installation Manual

ATHLETICS AUSTRALIA SELECTION POLICY 2017 WORLD PARA ATHLETICS WORLD CHAMPIONSHIPS LONDON, UNITED KINGDOM JULY 2017

Doors in watertight bulkheads of cargo ships and passenger ships

Keeping People Safe CHURCH HEALTH & SAFETY TOOLKIT LADDERS

APPENDIX IV DEVELOPMENT AND MEASUREMENT RULES OF THE INTERNATIONAL TEN SQUARE METER SAILING CANOE

Marine Kit 4 Marine Kit 4 Sail Smooth, Sail Safe

A Planing Boat's Thrust and Resistanc

Marine Safety Center Technical Note

Assessment of Ships and Managers for the Acceptance of Extended Interval Between Bottom Surveys in Dry-Dock

PUBLISHED PROJECT REPORT PPR850. Optimisation of water flow depth for SCRIM. S Brittain, P Sanders and H Viner

BMA INFORMATION BULLETIN No. 96

SECTION 11 ADVENTUROUS ACTIVITIES BOATING: SAILING

Marine Safety Information Bulletin COAST GUARD GUIDANCE FOR DEAD SHIP MOVEMENT IN SECTOR HONOLULU CAPTAIN OF THE PORT ZONE.

Unit 18 LEAVING THE DOCK

SINGLE LONG TERM MOORING AGAINST PRIVATE RESIDENTIAL LAND

Chain Drives. 1. As no slip takes place during chain drive, hence perfect velocity ratio is obtained

GUIDELINES FOR NAVIGATION UNDER THE CONFEDERATION BRIDGE

Below are a number of questions and answers involved with someone who would like to volunteer as a boat captain for the THSBA

Part 1: General principles

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX

Dynamic Positioning Control Augmentation for Jack-up Vessels

Local Notice to Mariners 02/2018

Whittlebury Park Golf Club. Ride on Buggy Safe Working Practice Policy

Transcription:

Bollard Pull Certification Procedures Guidance Information, 1992 1. Introduction 1.1 Whilst full scale bollard pull certification is neither a statutory or classification requirement, a true figure of the bollard pull capability is often required. This may be particularly important should the vessel Owner s liability be raised in case of damage to a towed object or inability to achieve and/or maintain a minimum speed needed to ensure satisfactory steerage in adverse conditions. This procedure is primarily intended for tugs supply vessels and other vessels of similar type, generally referred to in the document on tug. However, consideration will be given to its application to other vessel types on an individual basis. The purpose of these notes concerning certification is to standardise the procedure as far as is possible in order to ensure that results of bollard pull testing performed at different locations yield comparable results. 1.2 At the request of the Owners and/or Shipbuilders, the Surveyors may witness and certify bollard pull performance testing. Such testing should normally be undertaken at an installation which affords sufficient sea room and which is equipped appropriately with suitable anchorage point and calibrated equipment. In all cases the presence of the Surveyor will be necessary throughout the testing programme. The Certificate to be issued after the tests will normally take the form of a factual statement on a Report form, a typical example of which is included for guidance purposes at Appendix A. 1.3 For geographic areas where properly equipped installations do not exist and therefore standard bollard pull testing is not possible, consideration will be given to the bollard pull certification using anchors of sufficient holding power as the anchorage point. 1.4 In exceptional cases when neither method of bollard pull testing described in para 1.2-1.3 is possible, the Society may at the specific request of the Shipyard or Owner, consider certification of bollard pull based on model testing and theoretical prediction analysis. However, in such a case the final Certificate will be headed "Certificate of Calculated Bollard Pull". 2. Data to be Submitted 2.1 Prior to actual testing the Shipyard/Owner should provide the following information:- Location of tests, Detailed plan of bollard pull test configuration, Specification of measuring equipment to be used, i.e, Instrumentation type, number and location of load cells, Recording procedure. 2.2 In addition the following plans and information will be required:- Main particulars and dimensions of the tug, Block coefficient at load draught, Load draught, Draught and trim for bollard pull test condition(s), Type of main engine(s), Max continuous rating and rpm, Continuous service rating and rpm, Gearing ratio, Propeller type and diameter, number of blades and pitch, Type of propeller duct where applicable, Open water service speed, Anticipated maximum bollard pull. 3. Bollard Pull Definitions 3.1 The following definitions have been made for the purposes of the procedure:- a) The Maximum Bollard Pull (MBP) -isequaltothemaximumaverageofrecordedtensioninthetowing wire over a period of one minute during testing at an approved installation. MBP is normally associated with the maximum engine output and optimum propeller pitch. b) The Steady Bollard Pull (SBP) - this bollard pull should be achievable over a period of not less than 5 minutes. It represents the continuously maintained tension in the towing wire. Where peculiarities of a particular testing site are such that sustained 5 minute pull is difficult to achieve, bollard pull readings could be made at the times when the tug s pull and direction are steady. c) The Effective Bollard Pull (EBP) - is the bollard pull which a tug can develop in an open seaway. EBP is not normally established during testing at approved establishments and in most cases represents a fraction of the SBP. This fraction is often taken to be about 0.75 x SBP after making due allowance for weather. 4. Test Procedure Bollard pull tests should be carried out under similar conditions to facilitate comparison with results obtained at different testing establishments. These conditions are:- Page 1

4.1 Testing environment:- Testing should be carried out in a location that provides a sufficient extent of deep open water and a shore anchorage point of adequate strength. For general guidance the following should be noted:- Clear open water, is defined as:- Open water between the stern and the shore line of not less than twice the tug s length. Open water to each side of the tug for a distance equal to the tug s length. Open water ahead of the tug for an adequately safe distance. Depth of water under the keel should be equal to twice the draught, with a minimum of 10 metres. Current speed at the test location should not exceed 0.5m/sec in any direction. Wind speed should be such that the performance of the tug is not materially affected. For guidance purposes it is suggested a maximum wind speed of 5 m/sec is adopted. Sea condition should be calm i.e, with no swell or other significant waves. 4.2 Condition of tug:- The tug s displacement at the time of bollard pull testing will be recorded and an appropriate note will be made tothat effect on the bollard pull certificate. Similarly all draughts will be stated. The trim of the tug before testing should, in principle, comply with the intended operating trim. All deck equipment and fittings such as the towing winch and drum, towing hooks and strongbacks, fairleads etc., must be in good condition and capable of exerting/withstanding a load of not less than two times the anticipated Maximum Bollard Pull. It is assumed that all equipment will be part of the tug s normal outfit. Similarly, the propellers fitted when performing the tests should be those used during normal service. At the initial phase of the bollard pull test the main engines of the tug will be set at dead slow or slow thus maintaining a minimal tension in the towing wire. During this phase the tug should be brought into position for the bollard pull trials proper. The engine revolutions should be increased until fairly steady bollard pull readings are reached with the main engines at maximum continuous power. 4.3 Shaft Horsepower and RPM Recordings:- Thefiveminuteintervalreferredtoinpara3(b)shouldbeselectedatthepeakportionofthebollardpullcurve.During bollard pull testing, difficulties may be experienced in maintaining the tug in a desired position particularly if the tug has an excessive tendency to yaw. In such a situation rudder action may be necessary. In general, the application of the rudder will tend to adversely effect the recording. Shaft revolutions, torsionmeter readings and all other relevant engine data coupled with recordings of the rudder angle indicator and the angle of yaw during the trial should be synchronised with the readings of bollard pull. If bollard pull is determined from a main engine overload condition, an appropriate statement will be made on the certificate. Similarly, if any auxiliary machinery normally driven from the main engine is disconnected during testing, asuitablenoteshouldalsobemadeonthecertificate. In all cases, for the purpose of certification, the testing programme should include a run with the main engine developing its maximum continuous power. 5. Instrumentation The dynamometer used during testing should produce continuous readout in numerical and graphical form. The instrument should be calibrated before each application by the Society or any other recognised authority. The combined accuracy and linearity of the calibrated mechanical load gauge or electrical load cell and the associated readout instrumentation is expected to be within ± 2% of the anticipated steady bollard pull. It is anticipated that propeller shaft power will be measured to an accuracy of ± 3% of the maximum continuously rated engine output. The dynamometer should be incorporated within the towing wire system and could, in principle, be located at the shore line or on the tug where there is sufficient space available on deck. The recordings of the dynamometer should be coupled with the recordings of the main engine output and shaft revolutions (see also paragraph 4.3) The dynamometer could be of the form of mechanical load gauge or an electric load cell. Background guidance concerning the method of measurement using this instrumentation is given in Appendix B. Page 2

Whilst the accuracy of the bollard pull measurements necessarily depends on the reliability and cumulative performance of all instruments utilised in the measurement process, it is anticipated that the accuracy of the certified bollard pull at the stated machinery output will be contained within ± 4% of thetruevalue. 6. Certification On completion of the bollard pull testing a full report should be prepared by the Society s Technical Investigations (TIPEE) Department or other authorised Agency responsible for carrying out the test. This report should contain all the relevant information concerning the tug, environmental data, propeller, machinery, instrumentation and all trial records. From the recorded curve of bollard pull, a steady bollard pull (SBP) will be established over any selected period lasting not less than 5 mintues. This value should in fact be the mean of the recordings achieved during that period. The maximum bollard pull (MBP) should correspond to the maximum recorded pull during the above period. If the above values are also obtained for the engine overload conditions, these should also be recorded. For the purpose of formal certification a Report will be issued to the builder or owner as per enclosed specimen. It is intended that all tug and supply vessels for which bollard pull certification is required will have the Steady Bollard Pull value entered into column 7 of the Register Book as reliable information on the towing capability. Where it is specially requested, bollard pull may be certified for more than one engine setting. This certification may cover a range of bollard pulls from idling to full speed and may be of interest for tugs engaged in regular harbour service. Appendix A A.1 Certificate of Bollard Pull A.1.1 For guidance purposes a sample "Bollard Pull Certificate" is appended. Tab A.1(a) - Certificate of Bollard Pull Ship s name Owner Certificate No. Office Date Shipbuilder Location bollad pull trials held Yard No. Trial date This certificate is issued to to certify that the undersigned Surveyors to Lloyd s Register attneded the bollard pull trials stated above for the purpose of ascertaining the bollard pull capacity of the subject ship, at the request of: The relevant particulars of the ship and its machinery and propellers together with the significant trials data are listed on the reverse of this certificate. The trials were completed and the following results were obtained: TRIAL RESULTS Run No. Start Time End Time Shaft RPM Shaft HP SBP MBP CERTIFIED BOLLARD PULL It is hereby certified that the vessel under the conditions described overleaf, exerted a Steady Bollard Pull (SBP) over a minimum of 5 minutesdurationof...tonnesforce. ItisalsocertifiedthattheMaximumBollardPull(MBP)duringthesamefiveminuteintervalwas...tonnesforce. These results were recorded, during run number......... without the main engine being overloaded. Shaft driven auxiliaries were fully engaged / not engaged / not fitted (delete as applicable) Page 3

Surveyor to Lloyd s Register NOTICE - This certificate is subject to the terms and conditions overleaf, whch form part of this certificate Tab A.1(b) - SHIP PARTICULARS Length B.P.(m) Moulded Breadth (m) Moulded Depth (m) Design Draught (m) MACHINERY PARTICULARS Engine Builders Engine Type Engine Number Shaft Driven Auxiliaries (HP) Gear Ratio Propeller Manufacturer Propeller Plan Number Number Fitted Fixed/CPP Propeller Diameter Number of Blades Propeller RPM Propeller Duct Type TRIAL PARTICULARS Draught Forward (m) Water Depth (m) Draught Aft (m) Temperature of Water ( C) Mean Draught (m) Density of Water (t/m 3 ) Trim (m) Displacement (t) Immersion of Propeller Tips (% diameter) Distance from Stern of Ship to Pier (m) Type of Load Cell Date of Calibration Wind Speed (m/s) Current Speed (m/s) Observed Wave Height (m) Height of Towing Hook above Water Level (m) Height of Bollard above Water Level (m) Angle of Hawser from Horizontal Plane (deg) TERMS AND CONDITIONS In providing services, information or advice, neither Lloyd s Register of Shipping (hereinafter referred to as LR ) noranyofitsofficers, employees or agents warrants the accuracy of any information or advice supplied. Except as set out herein, neither LR nor any of its officers, employees or agents (on behalf of each of whom LR has agreed this clause) shall be liable for any loss, damage or expense whatever sustained by any person due to any act, omission or error of whatsoever nature and howsoever caused of LR, its officers, employees or agents or due to any inaccuracy of whatsoever nature and howsoever caused in any information or advice given in any way whatsoever by or on behalf of LR, even if held to amount to a breach of warranty. Nevertheless, if any person, who is party to the agreement pursuant to which LR provides any service, uses LR s services or relies on any information or advice given by or on behalf of LR and suffers loss, damage or expense thereby which is proved to have been due to any negligent act, omission or error of LR, its officers, employees or agents or any negligent inaccuracy in information or advice given by or on behalf of LR, then LR will pay compensation to such person for his proved loss up to but not exceeding the amount of the fee (if any) charged by LR for that particular service, information or advice. LR, its officers, employees or agents (on behalf of each of whom this notice is given) shall be under no liability or responsibility in negligence or otherwise howsoever to any person who is not a party to the agreement with LR in respect of any information or advice expressly or impliedly given by LR or in respect of any act, omission or inaccuracy by LR. LR shall in no circumstances be liable for indirect or consequential loss or damage (including but without limitation loss of profit, loss of contracts or loss of user) suffered or incurred by any person resulting from any failure by LR in the performance of its obligations in an agreement. Appendix B B.1 Measurements Guidance Notes B.1.1 Either a mechanical load gauge or an electric load cell is usually suitable for bollard pull measurement purposes. If the load gauge is of one of the types designed for weighing crane loads, care should be taken to verify that the particular type of instrument is suitable for use in a horizontal position. The electric load cell has the advantage that it may Page 4

readily be connected to a suitable autographic recorder to give a continuous record of the pull. The gauge should be calibrated, preferably both before and after the trial, and it is advisable that the calibration should be carried out with the gauge in the horizontal position in which it is used. B.1.2 B.1.3 B.1.4 The arrangement should be such that the pull is taken on the tug s towing hook, or towing cable and the gauge may be inserted in the cable either adjacent to the towing hook or where it is anchored to the bollard ashore. The arrangement with the load gauge adjacent to the towing hook offers the advantage that the entire trials party can be stationed on the tug, but it has the disadvantage that the readings may be influenced by the friction of the cable on the towing horse and there may be practical difficulties in supporting the gauge so as to prevent it being damaged when the tension comes off the cable. With the gauge ashore, provision should be made to allow it to swing freely about the bollard so as to align itself with the cable as the tug sheers from side to side and to ensure that only the horizontal component of the pull is measured. A satisfactory arrangement is one in which the gauge is mounted on a special trolley running on a steel plate laid upon the quay. Alternatively, the gauge may be allowed to skid on greased plates or planks. The body of the gauge should be the anchored part and care should be taken to ensure that the cable runs clear from the gauge to the tug without fouling the coping of the quay wall or other obstruction. If the bollard pull is recorded continuously throughout a test, the record might be expected to show the principle features of the curve given at the end of this appendix. That is, the general level of the pull readings would show an initial rise while the engine revolutions are building up, followed by a period during which the readings are fairly steady, and finally the pull might start to fall as a result of induced circulation of the water. Superimposed on this characteristic trend, various oscillations will normally be noted, typically a cyclic variation with a period of about 10 or 20 seconds, which appears to be related to the rudder movements required to keep the tug in position, and a higher frequency oscillation with a period of one or two seconds, which probably represents the natural period of oscillation of the tug on the cable. The extent to which these oscillations are recorded depends upon the frequency with which the gauge is read and the mechanical characteristics of the particular gauge used. For this reason the average pull sustained for a minimum of five minutes should be taken. In the absence of an auto-graphic recorder, the load gauge should be monitored continuously and the maximum and minimum readings observed in each 30 second interval should be recorded. Curve of Bollard Pull Readings Against Time Page 5