Cincinnati Dayton Rd Widening
Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge on Cincinnati Dayton Rd; Replacement of bridge on Station Rd New sidewalk and decorative lighting along corridor New closed storm system New mid-block crosswalks Includes rectangular rapid flashing beacons
Rectangular rapid flashing beacon: Corridor lighting:
Cincinnati Dayton Rd Bridge Mid-block crosswalks
Boys & Girls Club Cincinnati Dayton Rd Mid-block crosswalks
Cincinnati Dayton Rd Post Office Interstate 75 >>>
Existing Proposed Standing at the Intersection of Station Rd and Cincinnati Dayton Rd Looking north
Existing Proposed Standing south of the Cincinnati Dayton Rd bridge Looking south
Tentative Project Schedule Right-of-Way Acquisition Complete End of 2017 Utility Relocations Ongoing Contract Sell Date Spring, 2018 Construction Start Date Spring, 2018 Construction Completion Date Summer, 2019
General Construction Notes Operating hours: 7:00AM 9:00PM Monday through Saturday 1:00PM 9:00PM Sunday Lane restrictions allowed Monday-Friday during non-peak hours Peak hours: (7:00AM 8:30AM & 4:30PM 6:30PM) Lane restrictions will be allowed on weekends Pile driving for the Cincinnati Dayton Rd bridge will be restricted to the weekday hours of 8:00AM 4:00PM
Construction Sequence 2018: Phase 1 Phase 2 Phase 3 2019: Phase 4 Phase 5 Phase 6
Phase 1 Construction - 2018 Phase 1 construction begins in Spring, 2018 Construct temporary pavement on west side of Cincinnati Dayton Rd between Seminary St and I-75 Permanently widen east side of Cincinnati Dayton Rd bridge Permanently widen east side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement
Phase 1 Construction - 2018
Phase 1 Construction - 2018 West Chester Presbyterian Church
Phase 1 Construction - 2018 Lesourdsville West Chester Rd
Phase 1 Construction - 2018 Seminary St You are Here
Boys & Girls Club Phase 1 Construction - 2018 Cresthaven Ave
Phase 2 Construction 2018 (Realignment of Station Rd) Phase 2 construction will close Station Rd from May 14 th, 2018 through July 23 rd, 2018 (10 weeks). Realign Station Rd with the intersection of Cincinnati Dayton Rd and Lesourdsville West Chester Rd. Complete construction up to the intermediate pavement and open Station Rd on July 23 rd, 2018. This schedule was implemented to avoid detours during the St. John s festival (August 3-5, 2018).
Station Road Official Detour Official Detour (Trucks) Station Rd Closed
Phase 3 Construction - 2018 Phase 3 construction begins after the completion of Phase 1 (Phase 2 is independent of other phases) Shift traffic to completed east side of Cincinnati Dayton Rd Permanently widen west side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement All roadway widening north of the Cincinnati Dayton Rd bridge will be complete up to the intermediate pavement by Winter, 2018
Phase 3 Construction - 2018 West Chester Presbyterian Church
Phase 3 Construction - 2018 Lesourdsville West Chester Rd
Phase 3 Construction - 2018 Seminary St You are Here
Boys & Girls Club Phase 3 Construction - 2018 Cresthaven Ave
Phase 4 Construction 2019 (South of Cin Day Bridge) Phase 4 construction begins in Spring, 2019 Permanently widen the west side of the bridge on Cincinnati Dayton Rd Permanently widen the west side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cin Day bridge
Phase 4 Construction - 2019 Locust St
Phase 4 Construction - 2019 St. John Entrance
Phase 5 Construction 2019 (South of Cin Day Bridge) Phase 5 construction will begin after the completion of phase 4 Permanently widen the east side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cincinnati Dayton Rd bridge This is the final phase of widening construction. Will be completed by Summer, 2019.
Phase 5 Construction - 2019 Locust St
Phase 5 Construction - 2019 St. John Entrance
Phase 6 (Final) Construction - 2019 Phase 6 construction will begin once all widening phases are complete Pave the final asphalt surface course through the entire project Apply all final pavement markings Final completion date: Summer, 2019
West Chester Rd
Boys & Girls Club Cincinnati Dayton Rd
Post Office Cincinnati Dayton Rd