INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES

Similar documents
Methods of installation of ADSS fiber optic cables

Chapter 2 Rigging. Cutting Wire Rope. Anchoring Wire Rope to Drum. Winding Wire Rope Onto Drum

Chapter 5 Site Considerations and Set-ups Table of Contents

Installation Guideline for Placing Fiber Optic Cable into an Underground Duct

WIRE ROPE PULLING MACHINE

TENSOREX C+ TENSOREX C+

Figure 1 - Parts Identification. Copyright 2002, DB Industries, Inc.

Storage, Handling, Assembly, and Maintenance of WIRE ROPES.

Premium PowerPoint Presentation. Rigging Review

Moor, Tend Mooring And Unmoor Ship - Supervisor Level -

Overspeed governors (113 OG Моment 250 MR, 114 OG Moment 250 A3, 115 OG Moment 250 MRL, 119 OG Moment 250 MRL/1)

September 27, DOE-RL-92-36, Hanford Site Hoisting and Rigging Manual. Wire Rope. Page 1 CONTENTS

Fiber Cable Puller with Tuf-Lugger lite

Donaghys Winch Ropes. Handling & Installation Guide

I. Purpose... 1 II. Introduction... 2 III. General and Safety Precautions... 2 IV. Reference Documents... 3 V. Installation Overview...

Manual winch MANISTOR 100 and 200

Winchline n a box WINCH LINE SELECTION GUIDE. Wire Rope Winchlines are superior to most other winchlines found in the market place due to the

Drawing Showing the Component Parts of a Standard Steel Wire Rope

Figure 1 - Cable Grip Horizontal Lifeline Termination ZORBIT ENERGY ABSORBER RELEASE TAB

MANITOWOC MODEL TON CAPACITY

Underground Cable Installation Practices

Security and confidence at height.

WI Rev C Page 1 of 17

INSTRUCTIONS AND MAINTENANCE MANUAL SERIES: RT

FLANGED TWO-PIECE BALL VALVES

Figure 1 - Parts Identification

OWNER'S MANUAL. Turnbuckle. Stanchions. Warning

OPERATIONS MANUAL IMPORTANT SAFETY INFORMATION

Proof load is the load applied in performance of a proof test. Proof test is a nondestructive tension test performed by the sling manufacturer or an

IMPORTANT: If you have questions on the use, care, or suitability of this equipment for your application, contact DBI/SALA.

SPIDER BASKET ST-17 Rev

Davorin Matanović DRILLING LINE (ROPE) AND BLOCKS

CORPORATE SAFETY MANUAL

Buckingham Mfg. Co., Inc. OX BLOCK TM Instructions and Warnings

Draft Indian Standard WIRE ROPE SLINGS AND SLING LEGS- SPECIFICATION (Second Revision) ICS ;

Life Cycle Testing of 3x19 Wire Rope

Wellhead Mast. Installation and Operation Guide. Nanometrics Inc. Kanata, Ontario Canada

Synthetic Rope Installation Guide Premium, Ultra Performance & Zeon Winch Lines

Buried Cable Installation Practices

PFC Lightweight Composite Push Up Mast. Operating Manual

Agilent 1220 Infinity II LC Mobile Upgrade Kit

Auto-Rewind Hose Reels INSTRUCTION MANUAL FOR OXY-LPG MODEL

A N C H O R T A B S N O R T H W E S T ANCHOR TAB VF. Patented. User Instructions


1.2 LIMITATIONS: Consider the following application limitations before using this equipment:

FLEXIBLE SHAFTING (Wet & Dry)

CP10K. 10,000 lb. Cable Puller Instruction Sheet. SAFETY ISSUES

Hoisting Equipment Cable puller & Accessories

Erection, maintenance and disposal Inverted installation. Zinc oxide silicone-housed surge arresters PEXLIM R-X, Q-X and P-X

TECH TIPS: ROPE DEFECTS

WINCH USER GUIDE WARN 3700 Utility Winch Part Number: 93700

1700ESL Kamvalok Coupler

ISO INTERNATIONAL STANDARD. Cranes and lifting appliances Selection of wire ropes Part 1: General

GUIDELINES FOR USE -GUARD

Zip-Line Kit Instructions

CONTENTS ORIGINAL MANUAL Page General warning 3 Technical data 3. Description of equipment. Rigging arrangements 3. Installing the wire rope 5. Releas

Safety System Installation Guide for ARE Wind Poles

PF30 Inspection & Maintenance Manual

FLANGED TWO-PIECE BALL VALVES

GENERAL GUIDELINES FOR PROPER RIGGING PRACTICES AND INSPECTION & REMOVAL CRITERIA FOR SLINGS PER OSHA

BC Shackle. Made in the China. Alloy Steel Anchor Shackle. Instructions for handling and use - Please read in full before using this device

Operating Procedures for GripTight 15.5 SDR & IPS Test Plugs

Product Guide. Crawler Crane

Heavy Equipment Technician Rigging

Instruction Manual. PE Pipe Squeeze-off Tool Model TR650

Wire Rope Ordering Information

Work Standard CABLE PULLING OPERATIONS

Safe Work Practices (SWP) SWP (6) FALL PROTECTION PROGRAM

CRANE WITH WINCH USE AND MAINTENANCE MANUAL. Code Rev. Release MD /03

Hand winch MANIBOX GR

Vertical Lifeline. Ladder Climb. User Instructions. 3M Occupational Health and Environmental Safety. Fall Protection Equipment

Installation. Use. Maintenance INSTRUCTIONS. Care

Operating Instructions for BAIR22-6 AIR-POWERED CRIMPING TOOL

USER MANUAL LTH-255A Hand Piece

Wafer Check Valve. Contents. User s Manual. (1) Be sure to read the following description of our product warranty 1

Teledyne Oil & Gas North Williamson Blvd. Daytona Beach, FL USA (phone) (fax)

WKM Model 320F Floating Ball Valve

Versie Date: USAGE AND SAFETY MANUAL SPREADERBEAMS

Allspeeds Ltd. Royal Works, Atlas St Clayton le Moors Accrington Lancashire England BB5 5LW. Tel +44 (0)

Chapter 8 Sagging, Terminations, and Suspensions Table of Contents

Health & Safety Policy and Procedures Manual SECTION 25 RIGGING AND HOISTING EQUIPMENT

GUIDELINES FOR USE GUARD

MECHANICAL ASPECTS OF SUBMARINE CABLE ARMOUR

Installation and Operation Instruction Manual

WARNING! DO NOT THROW AWAY THESE INSTRUCTIONS! READ AND UNDERSTAND BEFORE USING EQUIPMENT!

Suspension Ropes. Suspension Rope

Supplementary instructions. Rod and cable components. for VEGAFLEX series 80. Document ID: 44968

Ropes for Subsea Cable Laying

OPERATIONS/PARTS MANUAL FOR PATTERSON'S WWP50-H-14 HYDRAULIC WINCH.

HYDRAULIC WINCH FOR AUGERS UP TO WR10 X 71 / W130 X 41 ASSEMBLY & OPERATION MANUAL

User Instruction Manual Fixed Beam Anchor

User Instructions 1789 Parapet Wall Anchor

Fall Protection Checklist. Guardrail System

KTM OM-2 SPLIT BODY FLOATING BALL VALVES INSTALLATION AND MAINTENANCE INSTRUCTIONS

How to ensure optimal functionality of Campagnolo drivetrains

Vibration isolation system 1VIS10W. User manual

SECTION 15 RIGGING. b. Defective rigging shall be removed from service.

Insert Ring. Protection Ring from Tube Deformation. Protect tubes from deformation. Ultra soft tube is connectable to Fitting.

OPERATIONS/PARTS MANUAL FOR PATTERSON'S WWP75H-10 HYDRAULIC WINCH.

Dual Solenoid Gas Valve Installation

Transcription:

Page 1 of 15 INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES

Page 2 of 15 1. PURPOSE 2. SCOPE 3. REFERENCES 4. GENERAL INDEX 5. PROCEDURES 5.1 Line survey 5.2 Transport, loading, unloading and storage 5.3 Preparation for installation 5.4 Installation of OPGW cable 5.5 Sagging of the cable 5.6 Installation of fittings and accessories 5.7 Personnel training 5.8 Supervision 5.9 Splice points 5.10 Transmission testing during installation phases 5.11 Final acceptance test 5.12 Safety and hygiene 5.13 Environment 6. APPLICABLE PROCEDURES

Page 3 of 15 1. PURPOSE The procedure describes the recommendations for installation and delivery of OPGW fiber optic cables. 2. SCOPE This document covers the installation of OPGW fiber s, including transport, accessory assembly, verification of optical transmission characteristics and final certification. 3. REFERENCES Quality Assurance Manual 4. GENERAL In general, the system and the equipment used for installation of the OPGW Cable are similar to those used for installation of the standard ground wire cable. However, since there is an optical fiber core, special care should be taken to avoid any damage to the fibers by observing the minimum bending radius at all times. Therefore, specific components and machinery are used for the OPGW cable: pullers, tensioners, anti-twisting counterweights, swivels, pulling grips, pulley-blocks, self-gripping clamps, pulling ropes, pulling cables, etc. 5. PROCEDURES 5.1. Line survey Prior planning for installation of the OPGW cable is performed by monitoring the line, taking into account the following parameters: 5.1.1. Reel length The OPGW reel lengths are determined based on the following considerations: position of the tension towers, tower access, distance between supports and crossings of other lines, roads, railways, routes, services and other obstacles. 5.1.2. Splices The splice point locations depend on the maximum available length of OPGW and on the tower locations and accessibility.

Page 4 of 15 5.2. Transport, loading, unloading and storage The following procedures are recommended to prevent damage to the cable during handling, transport, and storage: a) The reels must be transported in the vertical position with the cable ends fixed to prevent the cable from slackening. All of the staves and/or safeguards should be maintained until the reels are situated for immediate installation. b) After transport, the reels should be inspected to verify that they have not been damaged and that the staves and/or safeguards are not broken. c) The reels should never, under any circumstances, be thrown from the truck during unloading, nor should they be moved by uncontrolled rolling. d) Loading and unloading are performed so that the reel remains in vertical position and the reel flanges are not damaged. e) The reels can be moved by rolling a short distance while ensuring that there are no objects that may damage the staves. The direction in which the reel turns should be the same as that in which the cable is wound during manufacture. f) The reel should not be stored on its side under any circumstances. g) The ends of the cable should be sealed to prevent water penetration. h) The reels should be stored on flooring that is strong enough to prevent sinking. i) The reels should be stored to facilitate handling and loading. They should be located far from any activity that may damage them. 5.3. Installation preparation 5.3.1. Equipment positioning 5.3.1.1 Reel The reel should be placed at the selected site (with the space required for its location) so that the cable end pulls from the top of the reel and is aligned with the planned direction of pull. The reel must be located 2 or 3 metres from the tensioner. The lifting components usually used are hydraulic jacks and a bar with the suitable dimensions is inserted through the reel arbour hole. The reel must be located at a height of 4 to 6 inches (10 to 15 cm) from the ground.

Page 5 of 15 Location of tensioner and drum 5.3.1.2 Puller and tensioner The puller and tensioner must be placed at a minimum distance from the tower equal or greater than 2 times the height of the tower. The tensioner as well as the puller should be placed so they are aligned with the conductors. The maximum acceptable deviation angle is 30º. (α < 30 º, see Figure 1) α Figure 1 If it is not possible to achieve this angle, the puller and/or the tensioner can be placed close to the following tower, using an additional pulling line of suitable length and tensile rating. If an installation in done in a way which allows the cable to move backward (back-tracking) on any of the pulleys, special care must be taken. Back-tracking is not allowed on any pulley where the cable is in contact for 90º or more (a right-angle turn or sharper). If a turn of 90 or sharper is required, two pulleys must be used, in order to reduce the angle at each pulley. The tensioner, as well as the puller, should be positioned at a distance of at least twice the height of the support to which the cable is fastened. In the first groove of the tensioner, the first groove or pulley the cable will pass through must be perpendicular to the axis of the drum. In the tensioner, double armour OPGW will enter from the right and leave from the left for left-hand lay sense (and from the left and leave from the right for right-hand lay sense).

Page 6 of 15 The tensioner must be equipped with a dynamometer (i). Reels must be protected with material that does not damage the outer layer of the OPGW cable. The puller must also be equipped with a dynamometer 1 (i) with automatic disconnection to prevent over tensioning of the cable (see 5.4.1.3). The pulling cable must be joined to the OPGW cable by a swivel and a pulling grip. The minimum diameter of the reels used for coiling the OPGW cable during installation should be at least 80 times the diameter of the OPGW cable; however, the diameter need not exceed 59 inches (1500 mm). For example: the tensioner reels for a 0.5 (12.7mm) cable should have a diameter of approximately 40 inches (1016mm). The breaking device and puller should be suitably connected to the ground by a system of moveable rollers such as that shown in the following picture. The grounding connection in the photo shown below should not apply any pressure or deform the OPGW cable. Ground connection of the OPGW cable at the tensioner outlet. 1 It is compulsory to perform the calibration of the dynamometer, at least once a year.

Page 7 of 15 5.3.1.3 Pulleys Pulleys must have a large enough diameter to meet the minimum bend radius rating of the cable. The pulley groove should be shaped as shown in the figure below. 17º ± 3º Ø > 1,2 Ø >1,20 Ø cable The tower pulleys should have a minimum diameter of at least 0.8 metres in the following cases: - In all towers with a change in laying direction equal to or greater than 15 degrees. - In the first and in the last tower of a single installation. - If the distance between the towers is greater than 1968 feet (600 m). In all the other cases, pulleys with a diameter of 24 inches (0.6 m) can be used. The pulleys must be in good conditions. The pulley groove should be protected with neoprene or other similar material. In case of sharp angles, the pulley must be placed so that the cable always passes through the center of the groove. If the angles are greater than 45 º, a dual pulley system must be used in order to increase the bending radius during the installation. The diameter of each pulley should be at least 0.6 m. 5.3.1.4 Anti-twisting devices When a single or double layer OPGW cable is installed, an anti-twisting system is required to compensate the inherent effect of torque of the OPWG cable. This device is always positioned at the pulling head of the OPGW cable and equipped with two counterweights placed at a distance that is at least 10 feet (3 meters) one from the other. In this way, when one counterweight goes through the pulley the other remains active

Page 8 of 15 Another anti-twisting device is installed at the end of the OPGW cable just prior to leaving the tensioner. The weight of the anti-twisting devices must be high enough to prevent OPGW cable rotation. The minimum values recommended for each counterweight are as follows: - Spans 1000 26.4 lbs (12 kg) - Spans 1000 2300 33 lbs (15 kg) - Spans > 2300 44 lbs (20 kg) For installation lengths longer than 13,000 (4km), these values should be increased by 11 lbs (5 kg). After the counterweights have been installed, they should not be removed until the cable is secure and cannot rotate. Special precaution must be taken in order to not rotate the cable inside the counterweights, due to unsuitable or incorrect tightening, during the tightening process, special attention must be taken on using the appropriate clamp size and correct installation procedure to prevent damaging the OPGW cable. 5.3.1.5 Auxiliary components Use swivels that are specifically designed for OPGW cables. They must be of suitable size relative to the cable to being installed and must be in optimal condition. The pulling grip for OPGW cable stringing must be at least 59 inches (1.5 m) long and be specifically designed for stringing OPGW cables. It must have the proper dimensions and be in optimal condition. The clamps used during the stringing and sagging operations must be specifically designed for OPGW cables and must be compatible with the OPGW cable diameter. If preformed fittings are used, these should be specifically designed for the OPGW cable to be installed. The diameter as well as the length and material of these components must be suitable for the OPGW cable. The torque wrenches used must be reliable and calibrated on a regular basis. If a fall or accidental damage occurs, the calibration must be verified. 5.3.1.6 Pulling rope The pulling rope must be specifically designed for cable stringing. When stringing is performed on a power line that is out of service, metallic rope/cable is recommended. The minimum breaking load must be 11,000 lbs. This value can be higher depending upon the OPGW cable

Page 9 of 15 mechanical characteristics and it must be at least equal to 2.5 times the maximum stringing load (see 5.4.3.1). If an old ground cable must be used as a pulling rope, ensure that it is not damaged and that its weight is lower than the OPGW cable one that is going to be installed. The pulling cable must be joined to the optical cable by a swivel and a pulling grip. The swivel is necessary to prevent any twisting of the cable when stringing is performed. Installation equipment Fig 1. Tensioner Fig 2. Puller Fig 3. Swivel Fig 4. Pulley

Page 10 of 15 Fig 5. Pulling grip Fig 6. Anti-twisting devices Fig 7. Clamp Fig 8. Pulling rope 5.4 Installation of OPGW cables 5.4.1 Important considerations during cable stringing. The general method of installation is shown in Figure 2. Figure 2 Pulley Counterweights Pulling grip Swivel OPGW cable drum Tensioner 2-3 m >2h Hydraulic puller Pulling rope h >2h

Page 11 of 15 As a rule, install one reel of OPGW cable is installed at a time. In case of any difficulties, contact PRYSMIAN to obtain the correct guidelines to proceed with the OPGW cable installation. 5.4.1.1 Basic controls Strict controls must be established during installation to ensure that it is performed correctly, without excess tension, twist of the OPGW, unsuitable compression, with correct sagging to assure the fibers or the aluminium tube are not damaged. The tensioner and the puller should be placed at a distance from the first tower pulley which is equivalent to at least twice the height of the pulley (see fig. 2). Intermediate control points should be established, with the necessary precautions that are required at critical points during installation (beginning/end of drum, angles, etc.). During installation, the OPGW cable should not contact (strike or graze) any objects other than the pulleys. The pulleys must be free to rotate in the correct direction; they must be free of obstacles that could prevent the proper pulley alignment. The minimum bending radius must be controlled during all installation operations. Ensure that the metal part of the pulleys do not make contact with the cable to prevent it from being damaged. 5.4.1.2 Stringing speed PRYSMIAN recommends an installation speed about 60 m/min, depending always on the environmental conditions and the topology of the overhead line. The supervisors for the installation must assure that all PRYSMIAN recommendations are fully applied during the installation process. 5.4.1.3 Pulling tension The recommended pulling tension shall be lower than 1.5 times the weight of 1 km (3280 ) of OPGW cable length. In cases where higher pulling tensions are required (i.e. live installations, ), contact PRYSMIAN to determine the maximum permissible pulling tension for the installation. 5.4.1.4 Minimum bending radius The minimum bending radius is as follows: - On tensioner reels 40 times the cable diameter - During installation 15.75 inches (400 mm) - After installation 20 times the cable diameter

Page 12 of 15

Page 13 of 15 5.4.1.5 Communications during stringing The personnel located at the puller, the tensioner, the pulley crossings, and the cable ends must be in communication at all times. 5.5 Sagging of the cable Generally, the methods used to obtain the correct sag values of the OPGW cables are the same used for conventional ground wire cables. The specific recommendations are as follows: Pulling is performed by using a preformed fitting or tension clamp (in intermediate spans) or by pulling the cable end. It is important that clamps are specified to the OPGW cable diameter. Sagging of the cable and installation of fittings are always performed after stringing. At this time, the attachment fittings are installed to prevent damage to the OPGW cable. The installer is responsible for any damage to the OPGW cable that may occur due to failure of following the proper procedures. If the tension and sags are different from the expected values, the stringing or sagging should be halted. PRYSMIAN should be consulted in order to safely continue the installation operations. 5.6 Installation of fittings and accessories The fittings (tension clamps, suspensions, earthing clamps, dampers, etc.) should be installed in accordance with the manufacturer s instructions and using the appropriate tools. Special attention must be taken on using appropriate clamps designed for the OPGW cable diameter. When bringing the OPGW cable down the tower for splicing, a coil should be placed near the top of the tower. The coil should contain at least 3 loops and have a diameter of 1 meter (3.3 feet). An additional coil should be placed every 20m (66 ) as the cable progresses down the tower. An additional coil should be placed next to the splice case. 5.7 Personnel training All personnel who participate in the installation of the OPGW cable must be properly trained and informed of handling problems and installation procedures for the OPGW cable. It is responsibility of the installer to assure the personnel are properly trained. 5.8 Supervision It is essential that the OPGW be supervised by technically competent personnel. This is critical for safety reasons, and to avoid any damage to the cable, which would void the warranty. It is recommended that the supervisor also log all of the hardware used for the installation (type and location). This is important for ensuring that the correct hardware has been installed. 5.9 Splice Points After installation and optical measurements are taken to verify the OPGW cable meets the

Page 14 of 15 customer s requirements, the OPGW cable will be spliced. The splice boxes should have a device for properly securing the center strength element (multitube configuration) or core tube (central tube designs) PRYSMIAN recommends the use of joint boxes specially designed for the correct jointing of OPGW, which can be obtained from approved hardware suppliers.. 5.10 Transmission testing during the installation phases Prior to, as well as during the installation phases, the transmission characteristics of the fiber s are verified in order to ensure proper installation and be sure that the final tests are within the specified range of tolerances. 5.10.1 Measurements before OPGW cable installation Prior to OPGW cable installation, the optical attenuation performance should be verified using an OTDR. The attenuation values at the specified wavelengths shall be recorded and saved on an electronic diskette. 5.10.2 - Measurements after installation After cable installation, prior to the splicing, the attenuation of each fiber shall be measured using an OTDR. These measurements are compared with those obtained prior to installation (see section 5.11.1.) to ensure the cable complies with the requirements and there are not any issues. The attenuation values shall be recorded and saved on an electronic diskette. 5.10.3 Splices measurement After splicing, each splice is measured using bi-directional OTDR measurements to ensure that the attenuation values are within the specified criteria. The attenuation values shall be recorded and saved on an electronic diskette. 5.11 Final acceptance test After installation, final measurements of the transmission characteristics shall be performed and recorded. 5.12 Environment 5.12.1 Withdrawal of special waste (toxic and dangerous) If any type of special waste such as oil, grease, solvents, saturation of gloves or rags, etc. are produced during cable installation, they must be disposed of in accordance to government and local regulations. 5.12.2 Withdrawal of non-special or inert waste If there are excess materials or waste such as aluminium, optic fiber, plastic, wood, iron, etc., whenever possible, this should be sent to an authorized recycler or a controlled dumping ground.

Page 15 of 15 Regardless of the amount, the waste should never be abandoned. Moreover, the area should be cleaned when the work is finished. 6.- APPLICABLE PROCEDURES Code SIG-07-PE-PA-008 Document INSTALLATION OF Prysmian EWJ and EWMJ SPLICE BOXES