Developed by Engineer Ben Wynkoop, Lieutenant Randy Stuart, and Firefighter Alex Klinger September 2011

Similar documents
Developed by Lt. Randy Stuart Eng. Ben Wynkoop, and FF. Alex Klinger in Sept 2011

Developed by Lieutenant Randy Stuart, Engineer Matt Hintzman and Firefighter Chris Sandoli November 2010

Chapter 14 Water Shuttle Operations

INSTRUCTOR GUIDE REFERENCES: PUMPING APPARATUS DRIVER/OPERATOR HANDBOOK, FIRST EDITION, IFSTA

Apparatus Operator Refresher Training Program

Water Supply for Suburban and Rural Firefighting

Essentials of Fire Fighting 6 th Edition Firefighter I

PROPERTY INSURANCE ASSOCIATION OF LOUISIANA

TurboDraft Fire Eductor

Driver Operator Pumps: Basic Pump Operations

The Evaluator shall ask the Apparatus Driver/Operator questions regarding the mechanical systems and size of the apparatus.

Atlantic County Tender Task Force B Bravo Division When Atlantic County Tender Task Force B is required the following procedure should be followed:

Driver Operator Pumps: Water Supplies. 2 Skills Total. NFPA 1002, Standard for Driver Operator Professional Qualifications, 2014 Edition

Essentials of Fire Fighting

MFD Monroe Fire Department. Standard Operating Guidelines. Drivers Clearance & Training Program Guidance ADMINISTRATION

Upon completion of this unit of study, the student should be able to: 1. Identify the parts of a water distribution system.

Apparatus Driver/Operator Evaluation Form Rosenbauer Tanker:

Varying pump capacity affects the required hoseline diameter

Topic: Equipment Scramble Reference #: DG14-03 Date: March 10, 2014 Level of Instruction: In service personnel Time Required: 3 Hours

TurboDraft. Fire Eductor Operating Instructions.

Idaho Fire Service Technology Pumping Apparatus Driver/Operator Skill Sheet: 1

Galva Fire Department SOP

Cozumel Turbodraft. Operational Considerations

Colorado Division of Fire Prevention & Control Driver Operator Pumper JPRs (NFPA 1002, 2014 Edition)

Wilson County Emergency Management Agency 110 Oak Street Lebanon, Tennessee 37087

ENGINE 260 REVISED

2017 Volunteer Week - Course Descriptions

Colorado Division of Fire Prevention & Control Driver Operator Pumper JPRs (NFPA 1002, 2009 Edition)

Ocean County Fire Academy. Fall 2018 Course Listings

Tanker Fill Tests. Evaluating Direct Fill Lines DeKalb County, Alabama. November 16, Tests DeKalb County, AL

Fire Apparatus Operator Aircraft Rescue and Fire Fighting

Fire Apparatus Operator: ARFF

San Ramon Valley Fire Protection District

Township of Cumru Fire Department 03/12/2008 Standard Operating Guidelines Page: 1 of 8 Section 15.05

Driver Releasal Manual

PERFORMANCE CRITERIA AND INSTRUCTIONS

Evaluating 2-1/2 Direct Fill Lines Colton, New York

FIRE FIGHTER I EMERGENCY PROCEDURES WHEN USING SCBA TOPIC: TIME FRAME: 0:30. Level II LEVEL OF INSTRUCTION:

FSRS Relative Point Value Guide

Iowa s s Minimum Training Standard. How to Be Prepared?

To establish a guideline for the safe and effective deployment of apparatus, personnel, and resources at the scene of structural fires.

UNIT OBJECTIVES Upon completion of this unit of study, the student should be able to:

INSTRUCT-O-GPAM THE HANDS-ON TRAINING GUIDE FOR THE FIRE INSTRUCTOR FIRE HOSE AND NOZZLES

Cedarville Township Volunteer Fire Department Fire Department Standard Operating Guidelines 2008

ESCONDIDO FIRE DEPT TRAINING MANUAL Section DRIVER OPERATOR Page 1 of 14 Hydraulics Revised

FIRE FIGHTER II SKILL PERFORMANCE CHECK SHEETS NFPA FIRE FIGHTER II SKILL STATION MENU

Apparatus Operator/Pumper

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines.

A PARTIAL GUIDE TO MCFRS SAFE STRUCTURAL FIREFIGHTING POLICY. Section II Rapid Intervention

PHILADELPHIA FIRE DEPARTMENT HIGH PRESSURE FIRE HYDRANT SYSTEM PFD TRAINING MANUAL SUPPLEMENT ENGINE PRACTICES SUPPLEMENT 101 PAGE 1

SUBJECT: RAPID INTERVENTION CREW (RIC) SOG DATE ADOPTED: OCTOBER 18, 2012 REVISED: PAGES: 7

Florissant Valley Fire Protection District Monthly Training Schedule

Fire Apparatus Operator: Pumper

ESCONDIDO FIRE DEPARTMENT TRAINING MANUAL ENGINE MODULE HOSE PAGE 1 OF 24 Attack Hose Lays Revised

Chapter 16 Test. Directions: Write the correct letter on the blank before each question.

COMMONWEALTH OF KENTUCKY COMMISSION ON FIRE PROTECTION PERSONNEL STANDARDS AND EDUCATION FIREFIGHTER 2 PERFORMANCE EVALUATION

Topic: Forward Lay/Offensive Fire Attack Reference #: DG 16-6 orig Level of Instruction: In service personnel Time Required: 3 hours

Industrial Fire Brigade: Interior Structural

FIRE FIGHTER II - SKILLS PERFORMANCE SHEET

AUTOMATED PNEUMATIC TANKER HATCH

TOPIC: EVALUATING FIREFIGHTER PROFICIENCY MATERIALS: PERSONAL PROTECTIVE CLOTHING AS REQUIRED FOR EACH EVOLUTION

Idaho Fire Service Technology Fire Fighter II

HANDBOOK. Squeeze Off Unit SOU 250. Please refer any queries to:

Chapter 5. Response Tactics and Strategies Delmar, Cengage Learning

INSTRUCTOR GUIDE MATERIALS: TWO FULLY EQUIPPED PUMPERS STATIC AND PRESSURIZED WATER SOURCES

Des Plaines Fire Dept. Engineer Program

FIRE FIGHTER II JPR: FFII-1A

BERMAD Fire Protection Hydraulic Control Valves

Discharge Relief Valve Operation & Maint.

SEPTEMBER 22-24, 2017

North Carolina Fire and Rescue Commission Live Fire Audit Form

Fire Apparatus Operator: Pumper

INCIDENT MANAGEMENT SYSTEM AND TACTICAL OPERATIONS MANUAL

Poudre Fire Authority Driver/Operator Manual Third Edition March 2006

Student Workbook SW2. Fireground Support operations

Volunteer Firefighter Applicant Information Package

Standard Operating Procedures S.O.P. Sample Template Drafted by: Oklahoma State Firefighters Association Educational Advisory Committee

STREAMLINE SHOP SERIES MODEL 30040V OPERATION & PARTS MANUAL

Operating Instructions Model and Hydrostatic Test Pump

STANDARD OPERATING GUIDELINE

S P E C I A L O P E R A T I O N S : S W I F T W A T E R B O A T O P E R A T I O N S ( 1. 1 ) T A S K S K I L L D E S C R I P T I O N A N D D E T A I L

20 10 SCOUT BLAST Fire Explorer Competition

Wilton Fire Protection District. TRAINING DIVISION New apparatus

Engine Compan. pany y Operations. Firefighting and Emergency Operations Volume I - General Firefighting Procedures Book 2 Issued November 2003

Waterous Relief Valve

Skilled and Technical Sciences Contests Contest Information

**ALL SHADED SKILLS MUST BE SIGNED OFF BEFORE LIVE FIRE TESTING MAY OCCUR**

ECONOMY FLOW TEST KIT u Choice of four nozzle tip sizes u One /2" NST Female swivel inlet u Plastic tool box with tool tray

HYDRANT/WATER POINT INSPECTION AND MAINTENANCE

Single and Triple Rain Barrel Setup

FIRE PREVENTION SKILLS

Button style shirt and firefighting gloves are not required. (This will be a requirement in 2019.)

City of Mesa Fire/Medical Department Ladder Company Certification Program

Aqua Pilot Suction Pool Cleaner

OPERATING INSTRUCTIONS FOR THE MODEL 85B

PUMP OPERATIONS SAN FRANCISCO FIRE DEPARTMENT

CLEARWATER FIRE AND RESCUE DEPARTMENT STANDARD OPERATING PROCEDURE APPROVED BY: EFFECTIVE DATE: 10/12/07 REVISION DATE:

CRITICAL TASK 9 PHASE PLAY ATTACK

second test was conducted using at 3/4inch nozzle to determine a practical maximum pressure for the pump.

FIRE LOGISTICS AND MATH EDUCATION A Rumpke Public Outreach Program

Transcription:

W ATER S UPPLY O PERATIONS R URAL (1.1) Developed by Engineer Ben Wynkoop, Lieutenant Randy Stuart, and Firefighter Alex Klinger September 2011 NFPA 1142 Standard on Water Supplies for Suburban and Rural Fire Fighting. T ASK S KILL DESCRIPTION AND DETAIL Having a consistent water supply in place is essential to support any fire ground operation. In a rural setting a municipal water supply system is rarely in place. This can make a sustainable water supply very challenging. With no hydrants being available, one tactic firefighters will use is the setup of a drafting operation at the attack engine utilizing one or more port a tanks. These will in turn be supplied by water tenders in a water shuttle operation (a.k.a. tender shuttle or tanker shuttle) that will be shuttling water to and from a designated fill site that is near a static water source (i.e. lake or river) or a hydrant that is a few miles away. In a water shuttle operation there will be two designated sites that need to be determined. 1) Dump Site The dump site will be in the area of where the fire operation will commence. This is where the attack engine will be positioned and the port a tank operation will be set up. 2) Fill Site The fill site will be located at the closest water source. In the rural area, the closest water source may be a static one. The word static can be defined as non pressurized. When a hydrant is not available we will turn to a static water source such as a lake or pond to supply water for the operation. If this is the case you will need a dedicated engine or water tender to set up a drafting operation at the fill site to support the tender shuttle. Water shuttle operations will be apparatus and personnel intensive. There will also be a large amount of radio traffic taking place; therefore, it is imperative for you to request the following: 1) A dedicated water supply officer This position should be held by an engineer or an officer. The person holding this position will be responsible for coordinating the entire water shuttle operation. They will be the one communicating with the attack engine operator as well as command to ensure the water supply needs are being met. 2) A separate radio channel Requesting a separate radio channel for the water shuttle operation will ensure that the main operating channel is not overwhelmed with radio traffic. Water Supply Operations Rural Page 1

Tasks 1 & 2 will describe the tools and appliances needed and demonstrate the task of setting up a single port a tank operation as well as a double port a tank (aka double diamond) operation that will provide the water supply to the attack engine in a rural setting. Task # 1 Set up for a single port a tank drafting operation at the dump site. Step # 1 Locate all of the tools and appliances needed to complete the set up. The tools and appliances you will need for the operation include: 1) One to two sections of 2 ½ or 5 hard suction hose. 2) 2 ½ or 5 low level strainer. 3) One port a tank. Note: Removal of the port a tank is a minimum two person operation. 4) One basketball The purpose of the basketball is not to have something to play with when we are bored. Its purpose is to float in the port a tank and keep air from being introduced into the low level strainer when a venturi event occurs. For the purpose of this manual we will be using the 5 appliances. Step # 2 Connect the low level strainer to the hard suction hose. Water Supply Operations Rural Page 2

Step # 3 Connect the hard suction hose to the intake on the driver s side of the pump panel. Make certain the connections are tight. If they are not secured tightly, air will be introduced into the system and in turn will disrupt the drafting process. Your end result will look like the picture below. Water Supply Operations Rural Page 3

Step # 4 Set up the port a tank Set the port a tank on the ground. With a firefighter gripping each of the unhinged sides, simply walk backwards and the port a tank will expand. Attempt to open the port a tank up as best as you can by pulling the liner out to the edges of the frame. Step # 5 Positioning the port a tank for operation When positioning the port a tank for operation, there are a few things you will want to keep in mind: 1) Position the port a tank on as level a surface as possible. 2) Set the port a tank up at 45 degree angle to the pump panel. 3) If you are on a slope, position one of the drain chutes on the downward slope. (Continued on next page) Water Supply Operations Rural Page 4

4) Position the port a tanks in a position so they will be easily accessible to the water tenders supporting the operation. When setting up this is the most important thing to keep in mind. As you can see in the photo below the port a tanks are set up to give multiple points of access for tenders. Water Supply Operations Rural Page 5

Step # 6 Off loading of water from a tender into the port a tank The water supply officer, or someone who has been designated by them, will be the one directing the water tenders into place at the dump site. The operator will have controls inside the cab for operating the chutes and will usually be the ones who will control this process. If not, there are controls on the outside of the apparatus as well. Task # 2 Setting up the double diamond for operation For this operation you will follow the same steps as in Task 1 but now you will be adding a second porta tank as well as setting up a jet siphon operation. Additional tools and appliances needed for the double diamond include: 1) A second port a tank. 2) A second low level strainer. 3) A second 10 5 section of hard suction. 4) At least one section of 1 ¾ hose. 5) A second basketball. 6) Two straps or pieces of webbing. Water Supply Operations Rural Page 6

Step #1 Set up the second port a tank For this operation set up the second port a tank at the corner of the first port a tank as seen above. Note: You are not limited to the double diamond set up for drafting operations. You can also set up the port a tanks side by side if it means better access for the tenders off loading water. Step #2 Set up jet siphon Connect the 1 ¾ hose to a discharge on the engine and then connect it to the low level strainer. Once the connection is made you will then attach the second piece of 5 hard suction to the low level strainer. Water Supply Operations Rural Page 7

Step #3 Set the second piece of hard suction into the second port a tank When setting the second piece of hard suction, the side with the low level strainer should be placed in the second port a tank and the other half of the hard suction should be placed in the first port a tank. Water Supply Operations Rural Page 8

Step # 4 Tie off the hard suction and the 1 ¾ hose lines Be sure to tie both of these hose lines down. These are tied down because this part of the system will be charged and this will prevent them from moving out of place and possibly injuring someone. Step # 5 Charge the jet siphon system Once everything is set up and there is water in the second port a tank you can now charge the jet siphon system. This will be done by the engineer charging the 1 ¾ line. This should be charged to 50 psi. Water Supply Operations Rural Page 9

Now that you have learned how to set up and run operations at the dump site we will now describe and demonstrate how to set up and run a fill site. The fill site you choose should be the closest suitable water source. The reason the word suitable is used is due to the fact that the closest water source may have some problems associated with it. Some problems you could run into are: 1) Traffic issues or unsuitable road conditions. 2) Water flow requirements 3) Access to the water source (can the fill site engine position close enough) 4) Can other apparatus position and maneuver around easily within the site. As discussed earlier, when choosing a fill site you will have two choices: Either a hydrant or a static water source. NFPA 1901 recommends that tenders be filled at the rate of 1,000 GPM so keep this in mind when choosing a fill site. If you choose a hydrant as your fill site: As far as hooking up to a hydrant you can follow the instructions that you have seen in the municipal water supply portion of the training manual. With using the hydrant as a fill site however there will be a few items you will need to know. 1) Make sure there will be plenty of room for apparatus to maneuver. 2) Make sure you use 5 hose when filling apparatus to cut down on the fill time. 3) Connect a 2 ½ gate valve to the hydrant in order to quickly relieve pressure when filling is complete. As pictured below. 4) If there is not a dedicated engine at the hydrant fill site, all tools and appliances needed for the fill operation may be left in place. This will save time as each tender will not have to set up the system each time. Water Supply Operations Rural Page 10

If you choose a static water source for your fill site: When a static water source has been chosen you will need to dedicate an engine to the fill site operation. Once that engine has set up a draft, it will stay there for the remainder of the incident. Task # 3 will describe and demonstrate how to set up a drafting operation at a fill site. Task # 3 Set up a drafting operation at a fill site 1) 10 20 of hard suction hose. 2) Barrel strainer. 3) Attic ladder or roof ladder. Step # 1 Locate tools and appliances needed for operation Step # 2 Connect the barrel strainer to the hard suction hose When making the connection, insure the connection is tight. The barrel strainer will prevent any debris from being introduced into the pump. Water Supply Operations Rural Page 11

Step # 3 Connect hard suction hose to the intake Once this step is complete there is one thing you can do to assist the engineer. You can check to make sure that all drains on the pump panel are in the closed position. As mentioned earlier, if air is introduced into the system, the draft will be disrupted and the engineer will have to spend valuable time regaining the draft. Water Supply Operations Rural Page 12

Step # 4 Place a ladder in the static water source Placing a ladder in the static water source will ensure two things: 1) The ladder will prevent the barrel strainer from falling to the bottom of your static source keeping any unnecessary debris that could slip by the strainer out of the pump. 2) Most importantly though, this will ensure that there will be 24 of water space around the strainer, which is optimum when using a barrel strainer for drafting. Water Supply Operations Rural Page 13

Step # 5 Drop in the hard suction hose in the water Once this is done, the engineer will be the one actually obtaining the draft. Your water supply is now limited to the size of your static water source and size of the apparatus pump. Step # 6 Connecting the 5 hose for the fill operation Choose a 5 piece of hose to insure maximum fill rate. Connect the 5 fill hose to a discharge on the fill engine. Connect the other end to an intake on the tender needing filled and open the valve. Signal the engineer that the fill operation can commence. Once the tank is full you can close the valve on the tender and disconnect the hose. Water Supply Operations Rural Page 14

R EFERENCE I NFORMATION The following material was used for reference: NFPA 1142 Standard on Water Supplies for Urban and Rural Fire Fighting. IFSTA Pumping Apparatus Driver/Operator Handbook, First edition 1999 Jones and Bartlett Publishers, IAFC and NFPA Fundamentals of Fire Fighting Skills First Edition 2004. Water Supply Operations Rural Page 15