WELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015
Traffic Improvements Project Goals Widen roadway to construction two-way left turn lanes-greatly decreases congestion Ease access to & from residential side streets Reduce delays associated with turning movements improved side street turning radii Improve vehicular safety and decrease traffic accidents Decrease commuter delays Signal improvements at intersection of Shaw Road & 23rd Ave SE Relocate fixed objects within clear zone improving visibility and safety Reduce idle times, thus decreasing CO2 emissions Improve Pedestrian and Bicyclist Safety, Mobility & Connectivity Option A: 10 ft shared-use path for pedestrians & bicyclists +7 ft sidewalks Option B: 5 ft sidewalks and 5 ft bikes lane both sides of road Three new pedestrian crossings with pedestrian actuate rapid flasing beacons New LED lighting to improve roadway safety & pedestrian/bicyclist visibility Upgrade Sidewalks, Shared-Use Path, and Curb Ramps to current ADA standards Facilities encourage pedestrians and bicycle ridership increase corridor connectivity Stormwater Runoff Reduction & Water Quality Improvements Provide pervious concrete roadway and pervious sidewalks Porous asphalt shared-use path (Option A) Infiltrate and treat roadway, sidewalk, & path stormwater runoff on site Decrease roadway pollutants entering into local streams flowing to Puget Sound Increase groundwater recharge
Project Schedule (Shaw Road Open) End Date 30% Design August 31, 2015 Acquire Title Reports October 26, 2015 Right-of-Way Acquisition August 29, 2016 Complete Bid Documents August 31, 2016 Utility Window November 23, 2016 Bid November 22, 2016 Award Contract December 13, 2016 Notice to Proceed December 27, 2016 Suspension for Washington State Fair September 30, 2017 Construction/Substantial Completion May 8, 2018 Alternative Construction Schedule August 29, 2018 Possible Winter Suspension February 19, 2018 Suspension for Washington State Fair September 30, 2017 Alternate Substantial Completion August 30, 2018
Project Schedule (Closing Shaw Road) End Date 30% Design August 31, 2015 Acquire Title Reports October 26, 2015 Right-of-Way Acquisition August 29, 2016 Complete Bid Documents August 31, 2016 Utility Window November 23, 2016 Bid November 22, 2016 Award Contract December 13, 2016 Notice to Proceed December 27, 2016 Construction/Substantial Completion August 22, 2017
Project Cost Estimates, Funding & Alternate Comparison Cost Option A Option B Estimated Project Cost (Design, Right-of-Way, Construction Cost) $ 7,781,363.00 $ 7,764,363.00 Funding TIB Grant Funding $ 5,000,000.00 $ 5,000,000.00 City of Puyallup Matching Contribution $ 1,327,000.00 $ 1,327,000.00 Total Funding $ 6,327,000.00 $ 6,327,000.00 Additional Funding Required (Non-Closure Option) $ 1,454,363.00 $ 1,437,363.00 Savings with Closre of Shaw Road Construction Cost Savings for Closing Shaw Road $ 830,000.00 $ 625,000.00 Construction Time Reduction 3 Months 3 Months Additional Funding Required (Closure Option) $ 624,363.00 $ 812,363.00
Typical Road Section Option A (with Median)
Typical Road Section Option A (With Two Way Left Turn Lane)
Typical Road Section Option B (With Two Way Left Turn Lane)
Typical Road Section Option B (With Median)
Pervious Concrete Illustration Option A (with Median)-Looking North 10 6 PERVIOUS CONCRETE PERMEABLE BALLAST BASE COURSE EXISTING SUBGRADE, TYP. TYPICAL TRAVEL/BIKE LANE SECTION ROAD CENTER LINE POROUS HMA PERMEABLE BALLAST BASE COURSE 3 6 EXISTING SUBGRADE, TYP. 5 4 PERVIOUS CONCRETE PERMEABLE BALLAST BASE COURSE EXISTING SUBGRADE, TYP. TYPICAL SIDEWALK SECTION ROW TYPICAL SHARED-USE PATH SECTION ROW 7 7 11 8 11 4.5 10 SIDEWALK (PERVIOUS CONCRETE) TRAVEL LANE (PERVIOUS CONCRETE) MEDIAN TRAVEL LANE (PERVIOUS CONCRETE) PLANTER SHARED-USE PATH (POROUS ASPHALT)
Illustrative Crossing Option A PERVIOUS CONCRETE SIDEWALK WALL PERVIOUS CONCRETE 4.5 PLANTER 10 POROUS ASPHALT SHARED-USE PATH 2 SHOULDER 25 th Ave CT SE Wall CONCRETE RAMP WITH SCORING TO ALERT TRAIL USERS THAT A CROSSING IS COMING UP GREEN CONCRETE SIDEWALK WITH SCORING TO INDICATE TRAIL USER CROSSING
Current Condition Photo Simulations Near 25th Ave. Ct., looking North Option A Option B
Current Condition Photo Simulations Near 31st Ave. SE, looking South Option A Option B
Current Condition Photo Simulations Near Forest Green Blvd., looking North Option A Option B