SR 2108-A12 Forbes Avenue Betterment. March 1, 2018

Similar documents
SR 2108-A12/SR 2308-A02 Forbes Avenue Betterment and SR 2108-A13 Forbes Avenue Corridor Improvements. July 17, 2017

S.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project

U.S. HIGHWAY 50 IMPROVEMENT PROJECT

Watertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017

California Department of Transportation, District 4. Sloat Boulevard Project Skyline Blvd. to 19 th Ave. Community Update January 13, 2016

Henderson Ave. Complete Streets Project

Complete Streets Funding Program Project Prioritization Plan

Fulton Market Streetscape

F L E T C H E R A V E N U E

February 11, 2016 TPO Board Presentation

May 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013

Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014

2018 ROAD MAINTENANCE PROGRAM

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council

Improvements Infrastructure Gap Assessment and Improvements Street Striping

Cincinnati Dayton Rd Widening


Derby Street. Project Updates. Salem, Massachusetts

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Chapter 4: Funding and Implementation

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

FDOT Treasure Coast Traffic Report

CITY OF LANCASTER PROPOSED NEW PROJECTS

City Avenue Projects

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

Lincoln Way Multimodal Safety and Operations Study. City and University Summary Presentation

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

COMPLETE STREETS DURING CONSTRUCTION

Designing Pedestrian Facilities for Accessibility. Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in Work Zones

WELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015

Polk Streetscape Project

Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street)

APPENDIX L: COST ESTIMATING TOOLS

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements

North Avenue Corridor Study

PEDESTRIAN CROSSING TREATMENTS

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI

CITY OF PITTSBURGH. City of Pittsburgh Active Transportation Profile REGIONAL ACTIVE TRANSPORTATION PLAN FOR SOUTHWESTERN PENNSYLVANIA

Transportation and General Civil Engineering Projects

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

2017 Temporary traffic control guidelines for pedestrians. v.2

Taylor Road Resurfacing Project

Improving intersections for people that walk in Minneapolis

Road Diets FDOT Process

Clybourn Ave. Protected Bike Lane Study Halsted St. to Division St.

Route 47 (North Main Street) Reconstruction

Duwamish Way-finding and CTR Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

ADA PRESENTATION (CURB RAMPS)

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

Final Sidewalk Feasibility Study

Lawrence Avenue Streetscape Concepts August 30, 2011

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018

ADA Design Overview. Section 2. ADA Design Overview. Pedestrian Access Routes. Pedestrian Access Routes. Overview

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

City of Scotts Valley CITY COUNCIL STAFF REPORT

Welcome! Thank you for joining us today for a Geary Rapid project open house. Geary Rapid Project. SFMTA.com/GearyRapid

Montclair s Complete Streets Experience

Roosevelt Estates Neighborhood Improvements

MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017

Cycle Track Design Best Practices Cycle Track Sections

Hospital Link Project Project Update September 2017

City Avenue Projects

PROJECT FACT SHEET May 25, 2018

Scenarios. The following slides will show existing pictures that deny access, followed by a retrofitted picture that provides access.

5. RUNNINGWAY GUIDELINES

Agenda Item # Page # RECOMMENDATION

Complete Streets Needs. Complete Streets Project Origin (planning documentation or supporting analysis)

Steps to Conducting a Complete Streets Assessment

Long Island Rail Road Expansion Project Floral Park to Hicksville

Operations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No

ODOT construction cost is $51,000,000. State assumes and bears 100 percent of the cost of improvement.

ADA Training Accessible Pedestrian Signal (APS) 2018 MnDOT

Pavement Rehabilitation & Buffered Bike Lane

PROJECT FACT SHEET March 21, 2018

DESIGN PUBLIC HEARING SEPTEMBER 26, 2017 PULASKI ELEMENTARY SCHOOL NEW BEDFORD, MASSACHUSETTS 6:00 PM FOR THE PROPOSED

122 Avenue: 107 Street to Fort Road

20 minute presentation on proposed project. Comments and Questions following presentation. City of Madison

MILEGROUND - AIRPORT ROAD. Fall 2018/ Spring Fall 2020 TBD. US 119 Monongalia County HOW WILL TRAFFIC CONTROL BE HANDLED: KNOW BEFORE YOU GO

HYATTSVILLE TRANSPORTATION PLAN. City Council Update March 19, 2018

14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS

Rolling Out New Bike Facilities Within the North Bethesda & White Flint Area

Knox Street Complete Streets Project

Chicago Safe Routes to High School (SRHS) Kelly High School Recommended Improvements

Project Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information

FDOT Treasure Coast Traffic Report

Hospital Link Project Project Update November 2017

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

ExpressFall/Winter 2017

Hennepin County Transportation Department

Oakland Pedestrian Master Plan Oakland Pedestrian Plan Draft Recommendations Chapter Outline

ECONOMY PEOPLE ENVIRONMENT

R A M P U P! - City of Tacoma's Curb Ramp Installation Matrix

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Meade Street Bridge Design Alternative Study

Item No. 14 Town of Atherton

ODOT Major Construction, Bikeways and Enhancements Report for Clermont County. (State Fiscal Years 2007 to 2010)

Bluffdale/ UDOT South High-T Intersection Project Type Operations

Transcription:

SR 2108-A12 Forbes Avenue Betterment March 1, 2018

Introductions Project Team PENNDOT Cheryl Moon-Sirianni, PE; District Executive Jason Zang, P.E.; Acting Assistant District Executive-Construction John J. Zelesnak, PE; Project Manager-Design John Myler; Assistant Construction Manager 412.429.5063 jmyler@pa.gov Jonathan Grimm; Project Manager-Construction 609.214.0931 jogrimm@pa.gov WRA Eric C. Meyer, PE; Project Manager Daniel Fritz, PE; Senior Project Engineer Tyler Steele, PE; Project Engineer OTMA http://www.otma-pgh.org/ Mavis Rainey; Executive Director 412.687.4505 Gulisek Jonathan Gesinski, P.E.; Project Manager - 412.354.9207 - Jonathan.Gesinski@gulisek.com Brandon Farrell; Project Engineer 724.809.5804 - Brandon.Farrell@gulisek.com Terry Kostelnik; Daytime Superintendent 724.640.7104 - Terrance.Kostelnik@gulisek.com Richard Dickson; Nighttime Superintendent 724.640.7108 - Richard.Dickson@gulisek.com Lindy Paving Dave Kauer; Project Manager 724.333.6614 - DKauer@lindypaving.com Eric Yauger; Project Engineer 724.208.9474 - Eric.Yauger@lindypaving.com C.J. Grant; Superintendent 724.333.6758 - Charles.Grant@lindypaving.com Vantage Corporation Craig Thomas; Project Manager 412.429.4750 Craig.Thomas@vantagewbe.com 2

Agenda Overview of Project Project Improvements Maintenance and Protection of Traffic Schedule Q and A 3

Project Description SR 2108-A12 Forbes Avenue Betterment Birmingham Bridge to Margaret Morrison Street Resurfacing (mill/overlay) of the corridor Concrete pavement patching Grade Adjustments of existing Inlets, Manholes and Utility Valve Boxes. Eleven (11) New Traffic Signals with full pedestrian and Americans with Disabilities Act (ADA) compliant upgrades Six (6) Traffic Signal Upgrades at existing traffic signals Bicycle Improvements between Bigelow Blvd. and Margaret Morrison Street Converting existing four lanes to two lanes w/ center turn lane and bike lanes in each direction from Craig St. to Margaret Morrison St. 4

Pedestrian Improvements Physical Improvements Upgraded ADA curb ramps High visibility crosswalks (piano keys) New Stop Bars New Pedestrian countdown heads Audible signals/push buttons Operational Improvements Leading/advance pedestrian walk phase at all intersections except Forbes Ave/Morewood Ave and Forbes Ave/S. Craig St, which will remain an all-walk phase New signalized pedestrian crossing between Bouquet St and Bigelow Blvd/Schenley Dr 5

Bicycle Improvements New bike lanes between Bigelow Blvd/Schenley Dr and Margaret Morrison St Completes connectivity to existing bike facilities Two-stage left turns (Curb Cuts at T intersections) Minimum 5 width bike lanes with a 2-4 painted buffer where space permits New bicycle safe inlet grates New and updated signing and signals for bike infrastructure 6

Project Overview SR 2108- A12 Forbes Avenue Betterment Project Forbes at Margaret Morrison St Forbes at Birmingham Br Existing Signal minor upgrades Replaced Signal New Signal 7

Birmingham Bridge to Craft Avenue (Zone 1) Forbes at Birmingham Br Existing Signal Replaced Signal Forbes at Craft Ave 8

Craft Avenue to Bouquet Street (Zone 2) Forbes at Bouquet St Forbes at Craft Ave Existing Signal minor upgrades Replaced Signal 9

Bouquet Street to Bigelow Blvd (Zone 2) Forbes at Bigelow Blvd Forbes at Bouquet St Existing Signal minor upgrades New Pedestrian Signal 10

New Traffic Signal 11

Bigelow Blvd to Craig Street (Zone 2) Forbes at Bigelow Blvd Existing Signal minor upgrades Forbes at Craig St Replaced Signal 12

Craig Street to Beeler Street (Zone 3) Replaced Signal New Signal Forbes at Craig St Forbes at Beeler St 13

Existing Intersection Configurations Forbes Avenue at Bigelow Blvd/Schenley Drive & Schenley Drive Extension Existing Signal minor upgrades Replaced Signal 14

Proposed Intersection Configurations Forbes Avenue at Bigelow Blvd/Schenley Drive & Schenley Drive Extension Existing Signal minor upgrades Replaced Signal 15

Existing Intersection Configurations Forbes Avenue at Bellefield Avenue Pull Off Replaced Signal Schenley Dr. Ext to Bellefield Ave Bellefield Avenue to Craig Street 16

Proposed Intersection Configurations Forbes Avenue at Bellefield Avenue Pull Off Replaced Signal Schenley Dr. Ext to Bellefield Ave Bellefield Avenue to Craig Street 17

Existing Intersection Configurations Forbes Avenue at Craig Street Pull Off 18

Proposed Intersection Configurations Forbes Avenue at Craig Street Replaced Signal Pull Off 19

Corridor Improvements Tepper Quadrangle Replaced Signal New Signal Pull Offs 20

Proposed Intersection Configurations Forbes Avenue at CIC Drive and Tepper Garage Ramp New Signal Pull Off 21

Proposed Intersection Configurations Forbes Avenue at Cyert Drive Relocated and Replaced Signal 22

Existing Intersection Configurations Forbes Avenue at Morewood Avenue Pull Off Pull Off 23

Proposed Intersection Configurations Forbes Avenue at Morewood Avenue Replaced Signal Pull Off Pull Off 24

Proposed Roadway Configuration Morewood Avenue to Beeler Street 25

Existing Intersection Configurations Forbes Avenue at Beeler Street 26

Proposed Intersection Configurations Forbes Avenue at Beeler Street Replaced Signal 27

Proposed Roadway Configurations Beeler Street to Margaret Morrison Street 28

Existing Intersection Configurations Forbes Avenue at Margaret Morrison Street 29

Proposed Intersection Configurations Forbes Avenue at Margaret Morrison Street Replaced Signal 30

Maintenance and Protection of Traffic Construction Operations Combination of Daytime and Nighttime Work 9:00 AM to 3:00 PM daily 8:00 PM to 6:00 AM nightly Weekend Work 8:00 PM Friday to 6:00 AM Monday Seven weekend long single lane restrictions Five Block limit Otherwise maintain two lanes of traffic No work dates due to events (Attached Calendar) Weekend Closures - Two weekends Zone 1 Birmingham Bridge to Craft Avenue EMS notifications during closures and weekend restrictions Sidewalk and Signal Construction Maintain Pedestrian and Bike access at all times ADA Accessible Transit Accessibility 31

Maintenance and Protection of Traffic 32

Maintenance and Protection of Traffic 33

Construction Schedule (No Work) 34

Construction Schedule Zone 1: Birmingham Bridge to Craft Avenue March 12, 2018 April 30, 2018 (Week nights and weekends) Concrete Patching, inlet, manhole and utility valve adjustments along with asphalt milling and paving. 35

Construction Schedule Zone 3: S. Craig Street to Margaret Morrison Street March 8, 2018 June 25, 2018 (Week days and nights) Intersection section work for traffic signal infrastructure and ADA curb ramps. Inlet, manhole and utility valve adjustments. Mid June to late August (Weekends as permitted) Asphalt milling and paving August 8, 2018 August 31, 2018 (Week days and nights) Traffic signal installation 36

Construction Schedule Zone 2: Craft Avenue to S. Craig Street April 2, 2018 August 31, 2018 (Week days and nights) Intersection section work for traffic signal infrastructure and ADA curb ramps. Mid May to Mid June (Weekends as permitted) Asphalt milling and paving Mid June to September (Week days and nights) Inlet, manhole and utility valve adjustments. September 2018 (Weekends as permitted) Asphalt Wearing Course August 8, 2018 September 21, 2018 (Week days and nights) Traffic signal installation 37

Construction Schedule Project Wrap-up Mid September through October 2018(Week days and nights and weekends as permitted) Final Pavement Markings Sign Installation Miscellaneous delineation Traffic Signal testing 38

Questions? This presentation will be made available within 10 days on the OTMA website http://www.otma-pgh.org/.