Ground control for slurry TBM tunnelling GEO Report 249

Similar documents
SOIL IMPROVEMENT BY VACUUM PRELOADING FOR A POWER PLANT PROJECT IN VIETNAM

13 June Guy Bridges Aecom Asia

UNIT-I SOIL EXPLORATION

Critical face pressure and backfill pressure in shield TBM tunneling on soft ground

Sample Project with EPB TBM according to DIN 4085

Influence of Settlement on Bearing Capacity Analysis of Shallow Foundations on Sandy Clays in the Niger Delta, Nigeria

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1

CHAPTER 5: VACUUM TEST WITH VERTICAL DRAINS

Construction Dewatering

Bearing Capacity and Settlement Response of PMS Tanks on Cohesionless Soil Lithology in Lekki, Lagos of Nigeria

Earth Pressure Balance TBM Benny Lau

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE

m v = 1.04 x 10-4 m 2 /kn, C v = 1.29 x 10-2 cm 2 /min

DIRECTIONAL DRILLING

CIVE 554/650. Geotechnical Engineering. Rock. Soil. Water. Site Investigation Techniques. CIVE Knight 1. 1/8/2006 CIVE Knight 1

Submerged Slope with Excess Pore- Water Pressure

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

Difficult Ground Solutions: A Methodology for Enhanced TBM Performance in Challenging Conditions Introduction: Difficult Ground Solutions The

Theory of a vertically loaded Suction Pile in CLAY

3. Types of foundation

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING TUTORIAL QUESTION BANK

1) INTRODUCTION 2) THE UNFAIR ADVANTAGE

Desaturating sand deposit by air injection for reducing liquefaction potential

computed using Equation 3-18 by setting the 2nd term equal to 0 and K A equal to K o and using the pressure distribution as shown in Figure 3-23.

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT

Precision Liquid Settlement Array Manual

ISTANBUL STRAIT ROAD TUNNEL CROSSING

STABILITY ANALYSIS OF SHALLOW UNDRAINED TUNNEL HEADING USING FINITE ELEMENT LIMIT ANALYSIS

ATCE-II. Construction Dewatering. Advanced Topics in Civil Engineering Construction Dewatering. Professor Kamran M. Nemati Second Semester

Typical factors of safety for bearing capacity calculation in different situations

Vertical Uplift Capacity of a Group of Equally Spaced Helical Screw Anchors in Sand

TACKLING JACK-UP RIG NO-GO LOCATIONS. Prakasha Kuppalli ABSTRACT

using Strength Ratios

VW Liquid Settlement System VWLSS-200

Lecture 8&9: Construction Dewatering

The New Anchor Post Product


from ocean to cloud HEAVY DUTY PLOUGH PERFORMANCE IN VERY SOFT COHESIVE SEDIMENTS

Cubzac-les-Ponts Experimental Embankments on Soft Clay

Inflatable Packers for Grouting 11/10/00

HCMTCB MATERIALS SAMPLING & TESTING PERFORMANCE CHECKLIST

OP CHECKLIST FOR 1D CONSOLIDATION LABORATORY TEST

1 CHAPTER 1. Standard Penetration Test: Corrections and Correlations. 1.1 General. 1.2 Standard Penetration Test (SPT)

AUTOMATED MONITORING EQUIPMENT FOR ACIP AND DD PILES

SOFRASAR TUNNEL PRODUCTS CONNECTING ALL COMPONENTS

FP McCann Tunnels and Shafts 1

Mitigation of Abandoned Mine Entries at Swanbank Enterprise Development, Ipswich, Australia

Civil Application Solutions

Pressuremeters in Geotechnical Design

R.GRANDORI- SELI spa 1

Specialising in: Highly Accurate, Laser-Guided Microtunnels. Sydney Uni PHONE + 61 (2) WEBSITE

CONE PENETRATION TESTS

Inflatable Packer Single & Double. Single & Double Packer Dimension. Wireline Packer. Water Testing Packer (WTP) Packer

BIOREACTOR LANDFILLS: GEOTECHNICAL ASPECTS OF STABILITY EVALUATION

Displacement-based calculation method on soil-pile interaction of PHC pipe-piles

Formation level = m. Foundation level = m. Height of the wall above the Ground Level = 7.42 m

W I L D W E L L C O N T R O L FLUIDS

Reducing the cover-to-diameter ratio for shallow tunnels in soft soils

Self-drilling hollow anchor bolts and accessories

VSL MINING & TUNNELING SYSTEMS VSL. mining and tunneling

Design and Construction of Large Diameter Circular Shafts

DREDGING & MINING MEDIUM DUTY ABRASIVES HANDLING HOSE

Technical Service Bulletin July 2014 TSB

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS PSH HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective December 10, 2013

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective August 25, 2015

Shallow foundations settlement

SECTION PRESSURE TESTING OF PIPING

Air Eliminator Series

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

Hardware Triaxial and Consolidation Testing Systems Pressure Measurement and Control

_ pressure transducers. User Manual

White Paper. Overview of MAP Headspace Gas Measurement: Sample Volume Considerations:

Compensation Grouting. Laboratory Experiments in Sand

Identification on Unknown Bridge Foundations Using Geophysical Inspecting Methods

TBM tunnelling under the Suez Canal Port Said tunnels in challenging ground conditions

TEK-SUB 4800B. Submersible Level Transmitter. Flow Level Temperature Pressure Valves Analyzers Accessories TekValSys LEVEL

Analysis of dilatometer test in calibration chamber

An Introduction to Deep Foundations

An experimental study of inflatable offshore anchors in soft clay

Department of Civil & Geological Engineering GEOE Engineering Geology

Autodesk Moldflow Communicator Process settings

1800CPB2 Service Regulators

FINAL REPORT ON: GEOTECHNICAL INVESTIGATION FOR ENVIRONMENTAL REGULATORY TRAINING INSTITUTE AT NIMLI VILLAGE, TIJARA ALWAR, RAJASTHAN.

SOIL ANCHORS ETSAB/UPC J.Llorens - ETSAB/UPC PASSIVE ANCHORS - ANTECEDENTS

Appendix A Preliminary SEMs

This document downloaded from vulcanhammer.net vulcanhammer.info Chet Aero Marine

SUPER PRECISION AIR RELAYS

The purpose of this task is to prevent damage from occurring to the pipe or it s coating when backfilling an exposed pipeline.

GOM Diving Safety Work Group

Perforation Design for Well Stimulation. R. D. Barree Barree & Associates LLC

Development of Data Acquisition System for Consolidated Undrained Triaxial Test

FLEXIBLE AND RELIABLE ANCHORING

Our technical information is based on Tip: calls attention to special information.

382. Fellenius, B.H. and Terceros, M.H., Information on the single pile, static loading tests at B.E.S.T. Proceedings of the 3rd Bolivian

Mechanical Stabilisation for Permanent Roads

Unraveling the mysteries of liner compression

Soils for civil engineering purposes

better measurement Simply a question of SCHMIDT Flow Sensor SS The cost-effective alternative in pressurised systems up to 10 bars.

Transcription:

Cutter head Slurry feed line Excavation chamber Submerged wall Plenum air cushion Pressure bulkhead Opening at base of submerged wall Slurry suction line Nick Shirlaw Ground control for slurry TBM tunnelling GEO Report 249

Report 249 Report available on the web since January 2010 Can be downloaded from http://www.cedd.gov.hk/eng/publications/geo_ reports/geo_rpt249.htm

Genesis of Report 249 An internal report was prepared following the review of submissions for slurry shield tunnelling on KDB 200, part of the Kowloon Southern Link. The review was by Golder Associates (HK) Ltd, under a contract to provide expert advice on tunnel works to GEO The internal report was then reviewed by a number of very experienced engineers in Hong Kong, Germany and UK The final report has been turned into a GEO Report, made available in order to share technical knowledge with the industry April 22, 2010 3

Contents of Report 249 Slurry pressure assessment Tail void grouting, limiting pressures and volumes Excavation management control system (Volume Assessment) High risk activities, and discussion of possible control measures 60 pages in total, including figures, plates and tables

Contents of Report 249 Slurry pressure assessment the core of the report Factors of safety Effective stress calculations of minimum face pressure at ULS and SLS Total stress calculations of minimum face pressure at ULS and SLS Maximum face pressure Interfaces [between different strata] Variable ground conditions

Contents of Report 249 (Cont.) Slurry pressure assessment the core of the report (Cont.) Minimum and maximum acceptable face pressures Compressed air pressures for head access Adjustment of face pressures based on observation Presentation and communication of face pressures Key issues for designers and design checkers

Symbols - TBM Ground Level Water Level Z w Z S1 C Z 0 Sensor 1 D Sensor 2 D 1 D 0 Piezometer Sensor 3 TBM

More symbols P S P St Pressure in the excavation chamber Target pressure in the excavation chamber P St(Crown) Target pressure at the crown of the tunnel P St(S1) Target pressure at sensor 1 (or (S2) for sensor 2, St(S1) etc.) P S(S1) Slurry pressure measured at sensor 1 (or (S2) for sensor 2, etc.)

Face pressure variation with sensor location (q) Surcharge Ground Level Pressure to balance water pressure Water pressure p Slurry pressure 1 1 γ w γ SL TBM

Basis for calculating minimum target face pressures For slurry shields face pressure is generally based on effective stress. Need to check that total stress calculations do not govern where tunnel is in finegrained soils Need to check for both ULS and SLS conditions Minimum Partial Factors of Safety required: ULS SLS γ,γ 1.0 1.0 c, tanϕ 1.2 1.0 S U 1.5 1.0 q 1.5 1.0 For water pressure, use most onerous likely pressure, and partial factor of 1.0 April 22, 2010 10

Failure surface tunnel in sand, after Horn (1961) Used in subsequent work by Anagnostou and Kovari (1996)

Failure Mechanisms based on Centrifuge Model Tests (Mair, 1979) Clays Sands The Horn model is reasonable for sands, but not for clay

Effective support pressure needed Anagnostou and Kovari (1996): s = F O γ D F 1 c + F 2 γ h - F 3 c h /D where F O to F 3 are dimensionless coefficients, h is the difference between the original piezometric head at tunnel level (h o ) and that in the chamber (h f ). If the chamber pressure exceeds the water pressure, then: s = F O γ D F 1 c, and if c = 0 then: s = F O γ D [the pressure to support the soil skeleton, the water pressure needs to be added to obtain total pressure]

F O from Anagnostou and Kovari For H/D =2, Factored tanφ F O = 0.20 for dense sand 0.25 for medium sand 0.31 for loose sand

F 1 from Anagnostou and Kovari

Basis for calculating target face pressures at ULS Effective stress calculations at ULS based on Anagnostou and Kovari (1996). If the face pressure exceeds the water pressure, and a filter cake is formed: P target = (C-Z W )γ W +(Z S1 - C)γ SL + F O γ D F 1 c + variation Water pressure at crown, (C-Z W )γ W Control sensor (Z S1 -C) below crown, so correct by (Z S1 - C)γ SL Pressure to resist effective stress in soil Variation in face pressure, +/-v F O γ D F 1 c April 22, 2010 16

Example for calculating target face pressure at ULS in medium sand Example of calculation with axis level 31.85m below ground level, C = 28.5m, D = 6.7m, Z W = 1.5m: P target = (C-Z W )γ W +(Z S1 - C)γ SL + F O γ D F 1 c + v P target = 27 x 10 + 1x 11.5 + 0.25 x 10 x 6.7 + 20 kpa P target = 270 + 11.5 + 16.75 + 20 = 318.25 kpa = 3.2 bars Water pressure at crown, (C-Z W )γ W Control sensor 1m below crown, so correct by Pressure to resist effective stress in soil Variation in face pressure, +/-v 1 x γ SL F O γ D F 1 c April 22, 2010 17

Effective stress calculations - SLS Case Limited theoretical basis By comparing pressures with design pressures on rigid tunnel linings: P St(S1) = Fγ D + γ w (C-Z w ) + γ SL (Z S1 -C) + v where: F = 0.25 for Dense Saprolite (SPT >30) F = 0.40 for Medium Saprolite or Residual Soil (SPT 10-30) F = 0.55 for Loose Granular Superficial Deposit (SPT <10) To target 1% Volume Loss

Example for calculating target face pressure at SLS in medium saprolite Example of calculation with axis level 31.85m below ground level, C = 28.5m, D = 6.7m, Z W = 1.5m: P target = P target = (C-Z W )γ W +(Z S1 - C)γ SL + F O γ D F 1 c + v P target = 27 x 10 + 1x 11.5 + 0.4 x 10 x 6.7 + 20 kpa P target = 270 + 11.5 + 26.8 + 20 = 328.3 kpa = 3.3 bars Water pressure at crown, (C-Z W )γ W Control sensor 1m below crown, so correct by Pressure to resist effective stress in soil Variation in face pressure, +/-v 1 x γ SL F O γ D F 1 c April 22, 2010 19

Losses at tail void Face pressure not the only factor in settlement need to consider loss at tail void With good grouting typically about 15% to 20% of theoretical volume of the tail void will close in soft or loose soils Figure may reduce with improved technology

Other issues heave and/or loss of of slurry Need to consider maximum allowable face pressure excessive heave is a ULS case Need to check the presence of unfilled boreholes Loss of slurry onto road Leakage of air into the excavation chamber led to an airlift effect up an old borehole April 22, 2010 21

Basis for calculating target face pressures Total stress Total stress calculations can be based on data from model tunnels tested in a geotechnical centrifuge Minimum pressure to achieve ULS: P target =(γz O + q) - h 1 γ SL N C S U /F S + v Total overburden pressure and surcharge, γz O + q Control sensor 2.35m above axis, so correct by Effect of shear strength Variation in face pressure, +/-v h 1 γ SL N C S U /F S April 22, 2010 22

Influence of heading geometry on stability number at collapse Kimura and Mair (1981)

Heading geometry - P P=0 or P = Length of shield?

Heading geometry - P Type of shield ULS Calculation SLS calculation Slurry P=0 P=L EPB P=0 P=0, but add V l due to overcut closure EPB with slurry injection around skin, pressure = face pressure P=0 P=L

Basis for total stress calculation at SLS O S S U C VOLUME LOSS Kimura VS LOAD FACTOR and Mair (1981)

Volume loss vs load factor Figure from Dimmock and Mair (2007) V l = 0.23 e 4.4(LF) for LF > 0.2 At ULS (LF = 0.67) V l = 4.39% + closure of gaps around skin, at tail void

Excavation Management Control (EMC) Establish net dry weight of soil removed and compare with theoretical dry weight Accuracy typically +/- 5 to 10% [can be even worse] Not accurate enough to control SLS case, but gives warning of possible ULS (very large settlement or sinkhole) Face pressure is the primary control, EMC is a valuable back-up control Flow meter

Very large, localised settlements, generally because of over-excavation, inadequate face pressure Over 100 incidents worldwide in last 10 years over EPB and slurry shield drives

Risk areas for large settlements or sinkholes Launching Break-through Interfaces, between strata of contrasting strength Mixed face of rock and soil Head access (interventions) Mechanical problems (particularly for long drives in abrasive soil or rock) Extended periods of flushing Examples of risk mitigation measures are given in the report

Practical basis and use of Report 249 Calibrated against results of 20 EPB drives, North East Line, Singapore Developed from assessment of face pressures for 2 x slurry and 2 x EPB drives in Singapore, and 2 x slurry drives in Hong Kong Used for target face pressures for EPB driven sewer tunnel in Melbourne

Questions? April 22, 2010 32