WEEKLY CONSTRUCTION REPORT SEVEE & MAHER ENGINEERS, INC. PROJECT: PERIOD ENDING: FRI, 28 April 2017 JOB NO.: 16047.00 CLIENT: TOWN OF CUMBERLAND CONTRACTOR: STOREY BROTHERS, INC. PROJECT MANAGER: DAN DIFFIN AVERAGE FIELD FORCE Name of Contractor Non-manual Manual Remarks STOREY BROTHERS INC. 1 3 RICK STOREY, CREW CHIEF ACE SECURITY 2-4 FLAGGING CONSTRUCTION SERVICES AND IRRIGATION, INC. (CSI) 1 DAVID BERNARD INSPECTOR FOR PWD THIRSTY TURF 1 3 TEMPORARY WATER MAIN 4/17, 4/19, 4/20 JIM S TREE SERVICE 1 3 4/17, 4/18, 4/20 VISITORS Date Name Representing Remarks 4/19/17 Glen Miller, CSI Inspector PWD Inspector for Adjacent Tuttle Road project TYPICAL EQUIPMENT ON-SITE 1 to 3 EXCAVATORS, 1- MINI EXCAVATOR, 1- LOADER, 1 ROLLER, 2-4 DUMP TRUCKS & 2-BOX TRUCKS FOR MATERIALS AND EQUIPMENT CONSTRUCTION ACTIVITIES 4/19 Started reconfiguration of Middle/Tuttle water main connection and construction of temporary water main. Started tree cutting. 4/18 Installed drainage near 159 Middle. Cut/limb trees southward to Range Way. 4/19 Installed drainage towards Tuttle Road. Cut/limb trees to 42 Middle Road. 4/20 Completed drainage east of CB-7E to Tuttle. No tree work. Prepared for rain. 4/21 CANCELLED DUE TO RAIN. No work except for finish demolition of garage at 55 Middle Road. 4/24 Installed replacement services. 4/25 Installed replacement services. Resumed reconfigure of Middle/Tuttle watermain connection 4/26 CANCELLED DUE TO RAIN. 4-27 - Resumed reconfiguration of Middle/Tuttle watermain connection. 4/28 - Resumed reconfiguration of Middle/Tuttle watermain connection. QUALITY ASSURANCE: PWD Inspector, on-site overseeing installation of piping and valves and connection to existing pipe in Tuttle Road. SME on-site to review erosion control, quantity verification and work on Tuttle Road DISTRIBUTION: PAGE 1 OF 1 PAGE 1. Owner Town of Cumberland 2. Contractor - Storey Brothers 3. Engineer Sevee & Maher Engineers, Inc. 4. File BY: James, C. Manzer, P.E., PTOE TITLE: FIELD ENGINEER \\nserver\cfs\tcu\middle Road\Construction\Weekly Reports\Weekly Construction Report-04-28-17.doc 5/01/17
Photograph 1: Cutting in gate valves south of Tuttle Road for temporary water main connections. Photograph 2: Sleeve horizontally drilled under Tuttle Road to provide temporary water service to 3 houses north of Tuttle Road affected by reconfiguring watermain connection. Page 1 of 8
Photograph 3: New 18-inch HDPE pipe crossing northbound lane to CB-8B at 159 Middle Road. Photograph 4: Catch Basin CB-8B prior to connection of inlet underdrains. Page 2 of 8
Photograph 5: Trench preparation for new 12-inch underdrain from CB-8B (foreground) to CB-8A. Photograph 6: Existing Underdrain from Tuttle prior to connection to Catch Basin CB-8B. Page 3 of 8
Photograph 7: Catch Basin CB-8B cored to and connected to existing underdrain from Tuttle. Photograph 8: sweeping up Thursday afternoon preparing for a Friday rain out. Page 4 of 8
Photograph 9: Site cleaned up for Friday s rain out. Photograph 10: Erosion control berm protecting downstream properties during rain storm. Page 5 of 8
Photograph 11: Replacement water service at 159 Middle Road. Photograph 12: Temporary water main installed along east side out road south of Tuttle Road. Page 6 of 8
Photograph 13: Existing Middle/Tuttle Watermain connection to be removed and reconfigured. Photograph 14: New section of 12-inch ductile iron water main pipe installed in the vicinity of the proposed hydrant. Page 7 of 8
Photograph 15: Installing new 12 x8 tee on 12 line to Vault. Excavating existing 12 water main in Tuttle Road. Photograph 16: Water main connection trench in Tuttle Road to be installed under existing 18-inch sewer. Page 8 of 8