LECTURE 5 PRECEDENCE DIAGRAMING METHOD: LINK RELATIONSHIP

Similar documents
Basic CPM Calculations

Introduction ES = PEE 1. Progressive Feed Activities

LoneStar Fiberglass Pools. Do-It-Yourself. Installation Manual

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual Rhode Island

Step 1. PLANNING FOR THE INSTALLATION TOOLS REQUIRED

ADA Operations Contact Info

Inspector MUST Sign and Date Each Inspection

NCDOT S EXPERIENCE USING HYDRAULIC SETTLEMENT GAUGES. David L. Teague,P.E. NCDOT GEOTECHNICAL ENGINEERING UNIT

help make your spa installation a success Commissioned by Caldera Spas

Single slide rail system Linear shoring

Diaphragm pop-pop engine

EUROFLO CULVERT PIPE. Fittings / Pipes

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS

PROPOSAL. PROPOSAL OF, a corporation a

SWIMMING POOL & SPA DOCUMENT SUBMITTAL LIST

RELIABILITY ASSESSMENT, STATIC AND DYNAMIC RESPONSE OF TRANSMISSION LINE TOWER: A COMPARATIVE STUDY

Inspection Chambers and Covers

Bubble Tube Installations

Exercise 2-3. Flow Rate and Velocity EXERCISE OBJECTIVE C C C

CITY OF ROCK ISLAND. 46th Street Reconstruction North of 28th Avenue to 29th Avenue. 29th Avenue Reconstruction 46th Street to 47th Avenue Court

LABORATORY EXERCISE 1 CONTROL VALVE CHARACTERISTICS

Field Instruction. This instruction applies to Horizon Power employees and contractors involved in Horizon Power s underground projects.

Field Instruction. This instruction applies to Horizon Power employees and contractors involved in Horizon Power s underground projects.

Shade Sails - Installation Tips

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

Design Project 2 Sizing of a Bicycle Chain Ring Bolt Set ENGR 0135 Sangyeop Lee November 16, 2016 Jordan Gittleman Noah Sargent Seth Strayer Desmond

Siting and Installation Manual

Buoyancy Control Calculated Cost Allowance for 1 Year Study Cost Estimate

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

Project Goal and Description. Why Broadway? Broadway SFMTA.COM/BROADWAY. The goal of the Broadway Safety Improvement

Recommendations for Marking Gas Facilities Using 3M EMS Electronic Markers

Design Data 22M. Flotation of Circular Concrete Pipe. w w I = w - x 1000 (3) (SG x 1000)

San Antonio Water System Standard Specifications for Construction ITEM NO. 841 HYDROSTATIC TESTING OPERATIONS

Autodesk Moldflow Communicator Process settings

03/11/2017. Critical Determinants of Sprint Hurdle Performance. Dr Paul Brice Consultant Biomechanist. Applied Biomechanical Support Track + Field

VWP CONSTRUCTION INSPECTION REPORT. Project Name: Berkmar Drive Extension Locality: Albemarle County Inspector: ERM

2010 STANDARD SPECIFICATIONS STANDARD DRAWINGS

Installation of Nylon Putting NP50

Aluminum Sheeting Guide (ASG)

EVALUATION SUBJECT: SPUNSTRAND STANDARD AND INSULATED UNDERSLAB DUCTS

Unit 5: Prioritize and Manage Hazards and Risks STUDENT GUIDE

OCTOBER 2017 ISSUE Page 1 of 7

STATIONARY TRUCK INTERNAL HALYARD V-CLEAT FLAGPOLES FOR QUICK AND PROFESSIONAL INSTALLATION READ ALL INSTRUCTIONS BEFORE PROCEEDING

RVSS Appendix A Overview

CHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems

FAST 2K Fence Post Backfill

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if

Driveway Design Criteria

Memorandum. Dr. Wilbert Odem, Dr. Paul Trotta, and Mr. Justin Ramsey. From: Timothy Mahon, Patrick Belsheim, and Ali Alrayyes.

Universal DKU piling frame element

Reinstatement of sub-base and base (roadbase) in non-bituminous materials

Tree-Related Line Faults On the Power Distribution Grid During Windstorms That Affect Southwest British Columbia, Canada

SafetyBuletin. Se ingoutriggerstopreventaccidents

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax

Recommendations for Marking Power Facilities

D E L U X E S E R I E S. Your Hot Tub Pre-Delivery Guide D E L U X E

TECHNICAL MEMORANDUM 002 EMORANNO. 001

HOW TO DIG A TEST PIT

MARTIN COUNTY BOARD OF COUNTY COMMISSIONERS

Rio Intersection Traffic Restrictions Begin Monday

Hydronic Systems Balance

USER PROGRAMMABLE CONTROL SCRIPTS

Your Hot Tub Pre-Delivery Guide

Loughborough Dynamo Football Club Under 18's

Urban OR: Quiz 2 Solutions (2003) ( 1 ρ 1 )( 1 ρ 1 ρ 2 ) ( 1 12 )( ) σ S ] 24 [ 2 = 60, 2 2 ] ( 2 ) 3

Soma Wind Generators

Calculations for Line-of- Balance Diagrams

OPERATING MANUAL. SINGLE SLIDE RAIL RS Series 790

European Handball Federation TM EHF Beach Handball Commission

SWIMMING POOL PERMITS ARE ABOUT HEALTH AND SAFETY

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines.

Measuring Length. Goals. You will be able to

6.0 ENGINEERING. Build Anything Better. REPRINTED 2017

TESTING APPLICATION STANDARD (TAS)

3M Electrial Markets Division EMS. Electronic Marker System

Introduction Parks Open Space Standards Recreation & Open Space Land Use Design Principles

Deep Linear shoring. E+S Trench shoring systems / Sliding rail systems. Deep Linear shoring

1. SCOPE 2. REFERENCED DOCUMENTS. 2.1 SC Test Methods SC-T Forms SCDOT Electronic Forms SUMMARY OF TEST METHOD

Synchro Studio 8. Overview. By Ioannis Psarros

WIND AND SNOW FENCES

EUROFLO CULVERT PIPE. Fittings / Pipes

SGS MUSCOWPETUNG ABORIGINAL CONSTRUCTION MONITORING

ThyssenKrupp Bauservice

Actualtests ASF 45q. Number: ASF Passing Score: 800 Time Limit: 120 min File Version: 15.5 ASF. Agile Scrum Foundation

BATTLE FOR 2MM EARTH 1418: The Great War (Version 0.8)

CITY OF ROSEVILLE DESIGN AND CONSTRUCTION DETAILS

Recommendations for Marking Communication Facilities

Eilat 's artificial lagoons project on the Red Sea - Israel R. Raviv Ir. R. Raviv, Coastal Engineering Ltd., P.O. Box 7322, z/b 37072,

NCSS Statistical Software

ETL listed for installations within 5 ft. (1.5M) of outer edge of water

Anchor Component Material Standard Mechanical Properties

Exercise 1: Control Functions

Town of Sudbury Capital Improvement Budget Request FY2018 Form A

Exercise 8. Closed-Loop Pressure Control, Proportional-Plus-Integral Mode EXERCISE OBJECTIVE

Practice Test FOR GAS POSITIONS APTITUDE BATTERY

2.5 System-specific rules miniaturegolf

Life Smart Spas Frequently Asked Questions

Manufacturers Crimp Guidelines Sure Seal Crevice Free Hose Couplings

ACV-10 Automatic Control Valve

City of Turlock Traffic Calming Program

Transcription:

LECTURE 5 PRECEDENCE DIAGRAMING METHOD: LINK RELATIONSHIP

OUTLINE LECTURE 5 REVIEW LECTURE 4 INTRODUCTION THE FOUR TYPES OF RELATIONSHIPS PROBLEM FOR FINDING THE CRITICAL PATH AND CRITICAL TIME EXERCISE

REVIEW LECTURE 4 Critical - Activities, events, or paths which, IF DELAYED, WILL DELAY THE COMPLETION OF THE PROJECT. Critical Path path with the longest total duration CPM is a network diagramming technique used to PREDICT TOTAL PROJECT DURATION.

INTRODUCTION Precedence networks (Method) are node networks that allow for the use of four types of: relationships: finish to start (FS), start to start (SS), finish to finish (FF), and start to finish (SF).

Cont To understand the idea of precedence networks, consider the simple project of laying 1,000 LF (linear feet) of a utility pipe. The logic is simple: a. dig a trench, b. provide a 6-inch-thick gravel sub-base (bedding), c. lay the pipe, backfill, and d. compact five consecutive activities.

Cont However: Are they actually consecutive (berurutan)? Do you need to finish excavating the entire 1,000 LF before you can start the sub-base? Do you need to finish the sub-base completely before you start laying the pipe?

Cont If the answer is yes, your bar chart may look like the one shown in Figure below:

Cont Most likely, Practically: Once you have dug a reasonable amount, say 100 LF, Your second crew can start providing the sub-base, (while the first crew continues digging). Once digging reaches about 200 LF (say 20%), the sub-base is about 10% complete, and your third crew can start laying the pipe.

Cont Clearly, it is not the traditional FS relationship. As a result, the bar chart shown in figure below.

THE FOUR TYPES OF RELATIONSHIPS As mentioned previously, four types of relationships are possible in precedence networks: 1. Finish-to-Start (FS) Relationship: The most common type of relationship is the FS relationship. Examples of this type: The concrete cannot be placed (poured) until the formwork has been built. The doors can not be hung until door frames have been installed.

Cont 2. Start-to-Start (SS) Relationship: The SS relationship is common and extremely useful. Excavation for the foundation can not start until clearing and grubbing begins (usually with a certain lag; i.e., a certain percentage is finished).

Cont 3. Finish-to-Finish (FF) Relationship: The FF relationship is also common and useful. Landscaping can not finish until the driveway is finished. Backfilling a trench can not finish until the pipe in the trench has been laid. 4. Start-to-Finish (SF) Relationship: The SF relationship is uncommon and almost nonexistent in construction projects

INFORMATION CONTENTS IN AN AON NODE ES ID EF Slag Slag LS Dur LF

PROBLEM FOR FINDING THE CRITICAL PATH AND CRITICAL TIME Project X Activity Description A Prototype model design B Purchase of materials Manufacturing C Manufacture of prototype model activities D Revision of design E Initial production run F Staff training Training activities G Staff input on prototype models H Sales training Advertising activities I Pre-production advertising campaign J Post-redesign advertising campaign 14

Project X Precedence Relationships Chart Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45

Cont Question: Management would like to schedule the activities so that the project is completed in minimal time. Management wishes to know: The earliest and latest start times for each activity which will not alter the earliest completion time of the project. The earliest finish times for each activity which will not alter this date. Activities with rigid schedule and activities that have slack in their schedules.

Earliest Start Time / Earliest Finish Time Make a forward pass through the network as follows: Evaluate all the activities which have no immediate predecessors. The earliest start for such an activity is zero ES = 0. The earliest finish is the activity duration EF = Activity duration. Evaluate the ES of all the nodes for which EF of all the immediate predecessor has been determined. ES = Max EF of all its immediate predecessors. EF = ES + Activity duration. Repeat this process until all nodes have been evaluated EF of the finish node is the earliest finish time of the project. 17

AON NETWORK Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 B 15 C 5 E 21 A 90 F 25 G 14 D 20 H 28 I 30 J 45

Earliest Start / Earliest Finish Forward Pass Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 ES ID EF Slag LS Dur LF Always take larger number on Forward Pass 90,105 B 15 105,110 C 5 149,170170 E 21 0,90 A 90 90,115 F 25 110,124 115,129 129,149 G D 14 20 149,177177 H 28 194 EARLIEST FINISH 90,120 I 30 120,165 149,194194 J 45

Latest start time / Latest finish time Make a backward pass through the network as follows: Evaluate all the activities that immediately precede the finish node. The latest finish for such an activity is LF = minimal project completion time. The latest start for such an activity is LS = LF - activity duration. Evaluate the LF of all the nodes for which LS of all the immediate successors has been determined. LF = Min LS of all its immediate successors. LS = LF - Activity duration. Repeat this process backward until all nodes have been evaluated. 20

Latest Start / Latest Finish Backward Pass Always take Smaller number on Backward Pass Backward Pass= LF- Duration LS 90,105 105,110 B C 110,115 95,110 15 5 Activity Immediate Estimated Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 149,170 173,194 E 21 5,95 0,90 A 0,90 90 29,119 ES ID EF Slag LS Dur LF 90,115 90, 115 F 25 90,120 119,149 I 30 115,129 129,149 115,129 153,173 129,149 129,149 129,149 G 129,149 D 129,149 14 129,149 20 129,149 129,149 146,166 149,177 166,194 H 28 149,194 149,194 J 45 194 21

Slack Times Activity start time and completion time may be delayed by planned reasons as well as by unforeseen reasons. Some of these delays may affect the overall completion date. To learn about the effects of these delays, we calculate the slack time, and form the critical path. 22

Slack Times Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project. Slack Time = LS - ES 23

Slack time in the Project X Activity LS - ES Slack A 0-0 0 B 95-90 5 C 110-105 5 D 119-119 0 E 173-149 24 F 90-90 0 G 115-115 0 H 166-149 17 I 119-90 29 J 149-149 0 Critical activities must be rigidly scheduled 24

25 B F C A I E D G H H 28 166,194 J J 45 149,194 E 21 173,194 90,105 90,115 90,120 105,110 115,129 129,149 149,170 149,177 149,194 D 20 0,90 129,149 G 14 115,129 I 30 119,149 A 90 C 5 110,115 B 15 95,110 F 25 90, 115 0,90 The Critical Path

Exercise: Activity Predecessor Duration a -- 5 days b -- 4 c a 3 d a 4 e a 6 f b, c 4 g d 5 h d, e 6 i f 6 j g, h 4

A SAMPLE NETWORK

A COMPLETE NETWORK

THE CRITICAL PATH AND TIME FOR SAMPLE PROJECT

QUESTION..????