STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

TEST OF GMA SPINUP ASSEMBLY PRESSURE SENSOR CALIBRATION

POROUS PLUG CHARACTERIZATION TEST

GUARD TANK PRESSURIZATION FOR TRANSPORT

GMA FUNCTIONAL TEST SETTING & TESTING OF SPIN UP PARAMETERS. P0586 REV -- 20, June 2000 GPB SCIENCE MISSION PROCEDURE

GDS OPERATING PROCEDURE

GMA TO SPACE VEHICLE PLUMBING HOOKUP

Proton Monitor Thermal Vacuum Test Procedure GP-B P0635

LOW PRESSURE VOLTAGE BREAKDOWN TEST PROCEDURE FOR GSS FSU FLIGHT SPARE HVA BOARD October 28, P0938 Rev

PROCEDURE TO MEASURE READOUT LOOP RESISTANCE

GMA SLEEP PROCEDURE AT VAFB

DESIGN VERIFICATION AND QUALIFICATION OF NEW POPPET AND BUSHING ON GMA FLIGHT SOLENOID VALVES

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR DISCONNECT MAIN TANK VENT LINE FROM GAS MODULE MAIN TANK SUBATMOSPHERIC

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Prepare Payload for Mass/CG Measurements and Condition Payload During Spin Balance Test

SCRUB LAUNCH RECOVERY PROCEDURE FOR THE GMA

Pressurize Well to One Atmosphere with Probe Installed

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Burst Disk on SMD

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Relief Assembly on SMD

CHECK READOUT LOOP CONTINUITY IN PROBE C

CALIBRATING THE GMA PRESSURE SENSORS AND THE ECU ENGINEERING UNIT

PROBE-C CAGING VALVE INSTALLATION

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR STOP PUMPING ON SMD VACUUM SHELL / DISCONNECT VACUUM MODULE

GMA VENT EXTENSION SERVICE PROCEDURE

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR CONNECT VACUUM MODULE / PUMP ON SMD VACUUM SHELL

PREPARE FOR CRYO OPS FOLLOWING TRANSPORT TO B1610 To be performed at Vandenberg Air Force Base building 1610

GMA PREPARATION FOR E28 TESTING

BLEED DOWN OF THE GMA HIGH PRESSURE AT VAFB

PUMP DOWN MAIN TANK TO SUBATMOSPHERIC CONDITION

Proto-qual Vibration Test Procedure 2.5 and 6 Vacuum Valves (3179 and 3223) Retest of Flight Spare Valves. GP-B P0735 Rev.-

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR REGULATE GUARD TANK PRESSURE

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Spacecraft Battery Magnetic Field Survey

CLEANLINESS TEST OF PROBE SPINUP EXHAUST LINES

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR MAIN TANK SUBATMOSPHERIC FILL FROM NBP SUPPLY DEWAR GUARD TANK PRECOOL

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Upright SMD (Rotate from Horizontal to Vertical Orientation)

CLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD. 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems.

Reduce Liquid Level in Main Tank- Liquid at NBP To be performed at Vandenberg Air Force Base building 1610

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

HYDROSTATIC LEAK TEST PROCEDURE

EASTERN ENERGY SERVICES PTE LTD. 60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG Singapore Telephone: Fax:

(PTP) Un-vented Rate of Temperature Rise Using Guard Tank

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00

CLASS DH - PNEUMATIC TESTING - GREATER THAN 1 BAR (15 PSIG)

(PTP) Un-vented Rate of Rise of Main Tank w/ Gas in Well

Glove Box Installation Manual

DRAFT. Operating Procedures for the NPDGamma Liquid Hydrogen Target in TA-53, Building MPF-35

CERTIFICATION OF THE TEMPERATURE MONITOR AND ALARM

Gas Lines. Technical Manual. Sumitomo (SHI) Cryogenics of America, Inc Vultee Street Allentown, PA U.S.A.

Installation Operating Instructions for Simple Duplex Manual Manifolds PX-TSD Series

ASSEMBLY OF GAS FLOW HARDWARE INTO SM GMA

LRS(H)4 Pressure-Reducing Regulator User Manual

PROPORTIONING VALVE. Model 150 INSTRUCTION MANUAL. March 2017 IMS Company Stafford Road

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Configure SMD for Transport to SLC-2W To be performed at Vandenberg Air Force Base building 1610

Installation Operating Instructions for Duplex Manual Manifolds PX-TMD Series

Inert Air (N2) Systems Manual

Design DSA Steam-Atomized Desuperheater

ROTATING DISK VALVES INSTALLATION AND MAINTENANCE 1. SCOPE 3 2. INFORMATION ON USAGE 3 3. VALVE TYPES 3 4. OPERATORS 5 5. VALVE CONSTRUCTION 6

KENNEDY VALVE OPERATION & MAINTENANCE MANUAL

Type Testing of Rising Stem Valves Equipped with Graphite Packing for Fugitive Emissions

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR MAIN TANK SUBATMOSPHERIC FILL FROM NBP SUPPLY DEWAR GUARD TANK PRECOOL.

RD(H)20/25 Pressure-Reducing Regulator User Manual

BUTTERFLY VALVES Series 800

Assembly Drawing: W-311B-A01, or as applicable Parts List: W-311B-A01-1, or as applicable Special Tools: , , &

KTM OM-2 SPLIT BODY FLOATING BALL VALVES INSTALLATION AND MAINTENANCE INSTRUCTIONS

CS Controlled Dissolved Gas assembly with optional CS Air Aspirator assembly. Installation and Operation information

QUARTZ HOUSING COATING PROCEDURE

Tri-Tech Medical Inc.

DBML-60/80 Squeeze Tool

VIC offers a variety of Calibrated Gas Leaks

Oxford Instruments Austin, Inc.

TECHNICAL DATA Q = C. v P S. 2 Model G-2000 Dry valve. Page 1 of 13

Safety Aspects and Design of the Vent Isolation Chamber. Prepared: W.M. Snow Checked: H. Nann Approved: W. M. Snow

Manual Solvent Purification System. Innovative Technology, Inc.

Canadian Light Source Inc. Vacuum Component Leak Test Technical Procedure

Fisher DSA Steam-Atomized Desuperheater

FOR INSTALLING CO 2 BLENDER KIT (P/N IN BEER SYSTEM

Series 203 Granville-Phillips Variable Leak Valve

INSTALLATION, OPERATION and MAINTENANCE MANUAL

Rejuvenation Instructions

INSTRUCTION MANUAL. FLOW CONTROL DRAWERS MANUAL / PLC CONTROL SERIES Model Version Perma Pure LLC Tel:

MEDICAL EQUIPMENT CATALOG

ACCUMULATOR OPERATING & MAINTENANCE INSTRUCTIONS

JANIS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS

Dilution Refrigerator manual

Welker Sampler. Model GSS-1. Installation, Operation, and Maintenance Manual

TECHNICAL DATA. Q = C v P S

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Prep Payload for Thermal Vacuum Test

BEST KNOWN METHODS. Transpector XPR3 Gas Analysis System. 1 of 6 DESCRIPTION XPR3 APPLICATIONS PHYSICAL INSTALLATION

Assembly-, installation- and maintenance instruction manual for bladder accumulators IBV / EBV , top reparable

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test.

Hydraulic Piston Accumulators

RE: PROPANE SYSTEM & REGULATOR TESTING/INSPECTION PROCEDURE

Gas-Detection Instruments

Transcription:

Stanford University Gravity Probe B Program Procedure No. P0558 Rev. A Operation Order No. GRAVITY PROBE B PROCEDURE FOR PAYLOAD VERIFICATION (PTP) PROBE PRESSURE MEASUREMENT SYSTEM INSTALLATION AND LEAK CHECK PROCEDURE P0558 Rev. A 5/08/00 ECO 1125 Prepared by: M. Taber Approvals: Program Responsibility Signature Date C. Warren Gas/Vac. Engineer M. Taber Payload Test Director D. Ross GP-B Quality Assurance B. Muhlfelder Payload Technical Manager NOTES: Level of QA required during performance of this procedure: X Stanford QA Representative

Stanford University Government QA Representative Gravity Probe B Program Procedure No. P0558 Rev. A Operation Order No. All redlines must be approved by QA

Page 3 of 13 Revision Record: Rev Rev Date ECO # Summary Description A 4/20/00 1125 Incorporate redlines from previous use of procedure (op #1218); update Fig. 2a to show leak detector manifold. Acronyms and Abbreviations: Acronym / Abbreviation Meaning GSE Ground Support Equipment LD Leak Detector LGS Leakage Gas System PPMS Probe Pressure Measurement System RGA Residual Gas Analyzer SMD Science Mission Dewar NR Not required

Page 4 of 13 Table of Contents A Scope... 5 B Requirements Verification... 5 C Configuration Requirements... 5 D Hardware Required... 5 E Software Required... 6 F Procedures Required: N/A... 7 G Equipment Pretest Requirements: N/A... 7 H Personnel Requirements... 7 I Safety Requirements... 7 J General Instructions... 7 K References and Applicable Documents: N/A... 7 L Operations... 8

Page 5 of 13 A Scope This procedure effects the installation and leak check of the Probe Pressure Measurement System. It is mounted onto the upper cylinder portion of the SMD and is connected to the interior of the Probe-C via pressure sense port P1. B Requirements Verification C B.1 Requirements Cross Reference: N/A B.2 Expected Data for verification per requirement: N/A Configuration Requirements Probe-C is integrated into the SMD per drawing 65113-1C34292 and oriented with the +Z axis vertical. The exchange gas has been pumped out of the Probe. A Convectron pressure gauge (GSE version of P9) is attached to the P1 pressure sense port. (See Fig. 2a.) This gauge is mounted on a small manifold with a Nupro shutoff valve teed into it. The Nupro shutoff valve has a male VCR port. D Hardware Required D.1 Flight hardware required Description 65113-1C34292 Probe-C / Science Mission Dewar Assembly 1 No. Req d D.2 Commercial test equipment / instrumentation Manufacturer Model Serial Number Calibr. Exp. Date Varian He Leak Detector 960 DRAD6002 N/A Alternate leak detector: Varian He 636-60 W-161 N/A Leak Detector Varian Calibrated He leak for LD F3264302 Calibrated He leak for alternate F3264302 LD Granville-Phillips ion gauge 360101 97071702 readout for "Stable-ion" ion gauges (PPG-1, -2) designated as LGM-1 Granville-Phillips "Stable-ion" ion 360120 99012705 gauge (IG-1 = PPG-) Granville-Phillips "Stable-ion" ion 360120 97071808 gauge (IG-2 = PPG-2) Leybold-Inficon TSPTT100 F8TT11B00155 N/A

Page 6 of 13 D.3 Mechanical/Electrical Special test equipment: N/A D.4 GSE / hardware: Description PPMS Assembly 1 PPMS / Probe connection line (1/2" Gamah to 1/2" VCR) 1 PPMS mounting bracket (see Fig. 1) 1 10-32 x 3/4" stainless bolts 4 10-32 stainless nuts 4 #10 stainless washers 4 4 x 4 HEPA filter downflow unit with vinyl curtains mounted below gantry 1 1/2 aluminum Gamah gasket 1 Guard valve w/ 2.75" Conflat flange or KF / Conflat adapter (may already be 1 installed on PPMS pumpout valve; see Fig. 2b) 1" or 1.5" stainless flexible pumping line (length A/R) w/ KF tee, metering, and 1 isolation valves (see Fig. 2a) No. Req d D.5 Tools Description wrenches A/R 75 ft-lb. torque wrench 1 No. Req d D.6 Expendables Description Copper gaskets for 2.75" Conflat A/R 1/2 Ni or Cu VCR gasket 1 1/2 aluminum Gamah gasket 1 Aluminum foil A/R Felpro C5-A anti-seize compound or equivalent A/R He gas A/R Quantity E Software Required E.1 Flight Software: N/A E.2 CSTOL Scripts: N/A E.3 SPC Scripts: N/A E.4 Test Support Software Test Software Name Inficon TranspectorWare (for RGA) 3 Version No.

Page 7 of 13 F G Procedures Required: N/A Equipment Pretest Requirements: N/A H Personnel Requirements This procedure is to be conducted only by qualified personnel. Chuck Warren, Dave Murray, Tom Welsh, and Mike Taber are qualified to perform this procedure with either Mike Taber or Dave Murray being operations leader. The QA representative shall be either Russ Leese or Dorrene Ross. I Safety Requirements Movement of the gantry used to support the HEPA downflow booth requires two persons. Care should also be taken to prevent scratching or otherwise damaging vacuum sealing surfaces, particularly those which those which are on flight equipment and/or must be sealed with metal gaskets. General emergency instructions can be found in "FIST Emergency Procedures", P0141. J General Instructions J.1 QA Notification: The ONR representative and SU QA program office shall be notified 24 hours prior to the start of this procedure. Upon completion of this procedure, the QE Manager will certify her concurrence that the effort was performed and accomplished in accordance with the prescribed instructions by signing and dating in the designated place(s) in this document. J.2 Redlines can be initiated by Mike Taber or Dave Murray and must be approved by QA. J.3 A Quality Assurance Representative designated by D. Ross shall review any discrepancy noted during this procedure, and approve its disposition. Discrepancies will be recorded in a D-log or a DR per Quality Plan P0108. J.4 Only the following persons have the authority to exit/terminate this operation or approve D-Log dispositions: Mike Taber, Dave Murray. J.5 Work done inside the HEPA filter downflow unit should with proper clean room garb consistent with Class 1000 conditions. K References and Applicable Documents: N/A

Page 8 of 13 Op. Order No. Date Initiated Time Initiated L Operations L.1 Enter the calibration due dates for the equipment listed in section D.2 and verify that the calibrations are current. L.2 Verify Appropriate QA Notification ο ο Verify SU QA program office notified. Record: Individual notified, Date/time /. Verify ONR representative notified. Record: Individual notified, Date/time /. L.3 Mounting the PPMS: L.3.1 L.3.2 L.3.3 L.3.4 Verify that all the items identified in section D are available. Enter the calibrated leak serial number and calibration expiration date into the table in section D.2. Using the 10-32 hardware, secure the PPMS mounting bracket on the SMD per Fig. 1. Mount the PPMS on the clamp collars on the mounting bracket. Install / verify installed the HEPA downflow unit over the top of the SMD / probe; at least one hour of operation in this location should elapse before proceeding. Observe General Instruction J.4 in the following steps. L.4 Removing the Convectron gauge attached to P1: L.4.1 L.4.2 L.4.3 L.4.4 L.4.5 L.4.6 Connect flexible pumping line to access valve on "P-9" Convectron manifold. (See Fig. 2a.) Connect the other end of the pumping line to the leak checker via a KF tee and isolation valve. Install a metering valve to the other leg of the tee, and connect the metering valve to a source of He gas at 2-5 psig. Close the P1 isolation valve. Start up LD per manufacturer's instructions. Set the LD such that it will rough out the test port without entering into leak check mode. (This means setting the Transfer Pressure to "Hold" on the model 636 and the the Transfer switch / "to fine test" to "No" on the 960.) Start the LD rough pumping on the pumping line until the LD test port pressure is ~10 mtorr. Open the "P9" manifold access valve.

Page 9 of 13 L.4.7 L.4.8 L.4.9 Close the LD isolation valve. Slowly open the He let-up valve until the "P9" Convectron reads ~900 mtorr. Close the "P9" manifold access valve. L.4.10 Reopen the LD isolation valve until the test port pressure is ~10 mtorr and again close the LD isolation valve. L.4.11 Record the Convectron pressure for 15 minutes and verify that the pressure does not drop by more than 10 mtorr during the last 10 minutes. Time: Pressure: L.4.12 Vent the LD. L.4.13 Open the "P9" manifold access valve and disconnect the pumping line. L.4.14 Remove the "P9" manifold from the P1 isolation valve Gamah fitting. L.4.15 Inspect the P1 isolation valve Gamah fitting for damage and temporarily cover with clean aluminum foil. L.5 Connect the PPMS to the P1 port (see Figs. 1, 2b): L.5.1 Apply / verify applied a small amount of anti-seize compound to the interface between the nut and gland of the PPMS / Probe connection line (see sec. D.6.) NOTE: In the following steps involving the mating of VCR and Gamah fittings, care should be taken to avoid twisting the two gland halves with respect to one another. Twisting motion can cause stress on the bellows and may cause damage to the sealing gasket. L.5.2 L.5.3 L.5.4 Install the Gamah and VCR gaskets on the PPMS / Probe connection line and loosely install the line in place as shown in Fig. 1. It may be necessary to adjust the vertical position of the PPMS. Tightened the VCR nut finger tight and wrench the Gamah nut until it bottoms out. Tighten the VCR nut per manufacturer's instructions. L.6 Leak checking the PPMS: L.6.1 Verify leak detector operation: L.6.1.1 L.6.1.2 Install a blankoff plug on the LD test port. Perform LD autocal (model 960) or manually check LD tuning. L.6.1.3 Turn on LD calibrated leak and record: sccs

Page 10 of 13 He He Calibrated leak value: sccs QA witness: L.6.2 L.6.3 L.6.4 L.6.5 L.6.6 L.6.1.4 Turn off the calibrated leak and vent LD. Install / verify installed a guard valve connected to the PPMS pumpout valve per Fig. 2b. (This may require a KF/Conflat adapter.) Reconnect the pumping line (including the tee, He let-up, and LD isolation valves) to the LD and connect the other end to the guard valve. Install a plastic bag around the PPMS including the Conflat joint between the pumpout valve and the guard valve. Open the PPMS pumpout and guard valves and the LD isolation valve (Fig. 2a). Start LD and apply He to the bag for three minutes; increase above background should be <10-7 sccs He. Record results: L.6.7 L.6.8 L.6.9 Background leak rate: sccs Leak rate during test: sccs Connect ion gauge cables (to controller LGM-1) and RGA cables. Turn on IG-1 and verify proper operation. Record pressure: torr Turn on RGA and verify operation. QA witness: L.6.10 Set up the RGA to monitor He partial pressure with the minimum update delay. L.6.11 Close PPMS pumpout valve and torque to 25 ft.-lbs. L.6.12 Verify pumpout valve leak rate is <10-7 torr/sec (~10-7 sccs assuming a volume of 1 liter) He: L.6.12.1 Close the LD isolation valve and open let-up valve to vent to 1 atm. He gas. L.6.12.2 Record the rate of rise of the He partial pressure: torr in sec = torr/sec NOTE: In the following step the P1 isolation valve is opened to the PPMS. If the outgassing rate is too large relative to the pumping conductance of the P1 pressure sense line, the pressure may exceed that necessary to allow the RGA to operate. If that is the case, reopen the PPMS

Page 11 of 13 isolation valve and close the P1 isolation valve to continue pumping on the PPMS as long as necessary to allow the switchover. L.6.13 Open the P1 isolation valve and record the following partial pressures: Mass No. (species) 2 (hydrogen) 4 (helium) 18 (water) 28 (nitrogen) 32 (oxygen) 44 (carbon dioxide) Partial Pressure (torr) Record date/time: L.7 Secure PPMS and LD: L.7.1 L.7.2 L.7.3 L.7.4 L.7.5 Ensure that the He source valve is closed. Place the LD on Hold. Open LD isolation valve and and start the LD. When the LD background indication is <10-4 sccs, close the guard valve, and vent the LD. Disconnect the pumping line from the guard valve and cap the guard valve. Operation completed. Completed by: QA witness: Date: Time: QA Program Engineer Payload Test Director Date Date

Page 12 of 13

Page 13 of 13 Figure 2a Initial configuration plus added manifolding used for leak checking P1 Isolation Valve 1/2" Gamah connection "P9" Convectron Gauge To Probe "P9" manifold access valve Leak detection manifolding 1 flex line To LD Port 2-5 psi He Figure 2b Configuration with PPMS P1 Isolation Valve 1/2" Gamah connection 1/2" VCR connection PPG-1, 2 RGA P1 pressure sense line to Probe PPMS pumpout valve Guard valve To Leak Detector