Investigation of Blowout and Fire Eugene Island Block 284 OCS-G 0991 Well A-13 March 1, 2001

Similar documents
Investigation of Loss of Well Control Eugene Island Block 277 OCS-G Well A-2 Off the Louisiana Coast July 6, 2001

Deepwater Horizon Incident Internal Investigation

SPE Forum: Source Control for Wells in Shallow Water. Lars Herbst, Gulf of Mexico Regional Director

Abstract Objective Scope of Study Introduction Procedures

1. The well has been shut in on a kick and the kill operation has not started.

SUBSEA KILL SHEET EXERCISE No. 5

Chapter 4 Key Findings. 4 Key Findings

Why Do Not Disturb Is a Safety Message for Well Integrity

DAY ONE. 2. Referring to the last question, what mud weight would be required to BALANCE normal formation pressure?

Casing Design. Casing Design. By Dr. Khaled El-shreef

PROPOSED NEW SUB- CODE 1 RIG UP AND TEAR. Possibly Fits into Existing Code. 7/26/2018 Review PROPOSED NEW CODE EXISTING OPERATION

Investigation of Blowout and Fire Ship Shoal Block 354 OCS-G Well A-2 September 9, 1999

APPENDIX A1 - Drilling and completion work programme

Offshore Managed Pressure Drilling Experiences in Asia Pacific. SPE paper

Study Guide IADC WellSharp Driller and Supervisor

Development of a Subsurface Mudline Packer to Reduce Risk of Flow after Cementing and Sustained Casing Pressure, While Providing a Platform for P&A.

Worked Questions and Answers

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD

IWCF Equipment Sample Questions (Surface Stack)

Texas Administrative Code

Float Equipment TYPE 925/926

BLACK HILLS PLATEAU PRODUCTION COMPANY

Well Control Drill Guide Example Only. Drill Guide is the list of drills, questions and attributes that are in DrillPad.

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS

August 21, Deepwater MPD / PMCD

Practice Exam IADC WellSharp Driller and Supervisor

University 31E 4. Ward County, TX. Rig: Union Drlg Rig 229. AFE: $1,393, DHC: $761, WI: Notes: Workover:

ECD Reduction Tool. R. K. Bansal, Brian Grayson, Jim Stanley Control Pressure Drilling & Testing

BANDAR PANJI-1 WELL CONTROL INCIDENT REPORT

Understanding pressure and pressure

Engineered solutions for complex pressure situations

National Maritime Center

IWCF Equipment Sample Questions (Combination of Surface and Subsea Stack)

Extended leak off testing

float equipment OPERATING MANUAL TYPE 505/506 Float Equipment 1. INFORMATION & RECOMMENDATIONS Float Equipment

Casing and Cementing Requirements

DUO-SQUEEZE H LCM Mixing Tables and Operating Procedures

Form MMS 123A1123S Electronic Version. Application. We have incorrect pressure tests for the annulars on subject ABP The ABP shows we

Commentary on the book by Andrew Hopkins. By Graham Dalzell

W I L D W E L L C O N T R O L SHUT-IN PROCEDURES

Squeeze Cementing. Brett W. Williams Cementing Technical Advisor January 2016 Tulsa API Meeting

W I L D W E L L C O N T R O L FLUIDS

INTERPRETATION NOTE ISSUED UNDER THE PETROLEUM DRILLING REGULATIONS (CNR 1150/96)

Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe

BP SIT Testing Franks Facility Lafayette

Well Control Modeling Software Comparisons with Single Bubble Techniques in a Vertical Well

Rig Math. Page 1.

Perforation Design for Well Stimulation. R. D. Barree Barree & Associates LLC

Hard or Soft Shut-in : Which is the Best Approach?

Railroad Commission of Texas. Chairman Barry T. Smitherman Commissioner David Porter Commissioner Christi Craddick

30 C.F.R. Subpart D Oil and Gas Drilling Operations

A New and Simplified Method for Determination of Conductor Surface Casing Setting Depths in Shallow Marine Sediments (SMS)

W I L D W E L L C O N T R O L CIRCULATION & WELL CONTROL

Terrace Petroleum Corporation Cunning Wolf UL No. 602H, 1980 FNL and 467 FWL Section 6, Block 23, ULS Pecos County, Texas

OIL AND GAS DOCKET NO

Restoring Fluid Flow in Tubing Strings

Chapter 5 HORIZONTAL DRILLING

D & V Oil Co. LP. Daily Completion Report - University CN A #6 API # /23/2016. Perfs ' ' Activity :

PHE KE30-A8 WORKOVER PROGRAM

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

Monte Besler Consultant FracN8R Consulting LLC UNITED STATES

7/27/2011. How Things Can Go Wrong In The Drilling Of Oil / Gas Wells

Appendix K Appendix K

Railroad Commission of Texas

EXAMINER S REPORT AND RECOMMENDATION STATEMENT OF THE CASE

NeoProducts, LLC 1201 Dealers Ave. Harahan, LA Ph:

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

International Well Control Forum. IWCF Drilling Well Control Syllabus Level 3 and 4 March 2017 Version 7.0

DEPARTMENT OF ENVIRONMENTAL PROTECTION Office of Oil and Gas Management

Performance and Value of the invision System : Offshore in Coiled Tubing Operations

Industry Code: Alberta Small Employer OHS Legislated Requirements

PTRT 1471: Exploration and Production I. Chapter 6: Drilling and Well Completion

OIL POLLUTION IN THE ARCTIC - RISKS AND MITIGATING MEASURES

Abandonment Program for Paramount Fort Liard F 36

The key to connectivity

AMERICAN ENERGY - PERMIAN BASIN, LLC UL Daily Drilling Partner Summary

Wednesday, March 6, 2013 Houston, TX. 2:30 4:00 p.m. CLOSING SESSION BLOWOUT! A NIGHTMARE IN THE OIL PATCH

TARPON A Minimal Facilities Platform

SURFACE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE

1. UPDATE 12/12/2014: What wells are regulated under the MIA Program? Must they be drilled, stimulated, and completed? Must they be in production?

Introduction to Emergency Response & Contingency Planning

DEPARTMENT OF ENVIRONMENTAL PROTECTION Office of Oil and Gas Management

Characterization of Completion Operational Safety for Deepwater Wells

INTERMEDIATE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE

But, who cares, it s done, end of story, [we] will probably be fine and we ll get a good cement job.

W I L D W E L L C O N T R O L COMPLICATIONS

RIH intermediate section casing in Bazian-1 exploration oil well

NEW PROGRAM! OIL AND GAS TECHNOLOGY PROGRAM

WELL SUSPENSION AND ABANDONMENT GUIDELINES AND INTERPRETATION NOTES OFFICE OF THE REGULATOR OF OIL AND GAS OPERATIONS

HPHT Annular Casing Packer. Obex Annular Casing Packer

ULTRADEEP WATER BLOWOUTS: COMASIM DYNAMIC KILL SIMULATOR VALIDATION AND BEST PRACTICES RECOMMENDATIONS

OCEAN DRILLING PROGRAM

Deepwater Horizon, by Metin Çakanyıldırım and references cited therein.

THE BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION AND ENFORCEMENT REPORT REGARDING THE CAUSES OF THE APRIL 20, 2010 MACONDO WELL BLOWOUT

Hydro-Mech Bridge Plug

Well Control Institute (WCI) Core Curriculum and Related Learning Outcomes: Supervisory Level

Case studies from classes led by Dr. Ron Fulbright, University of South Carolina Upstate. IMPROVED BLOWOUT PREVENTER

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

PETITION OF SHELL OIL COMPANY TO MAKE PERMANENT THE PRESENT SPECIAL FIELD RULES FOR THE SOUTHWEST PINEY

Transcription:

OCS Report MMS 2001-084 Investigation of Blowout and Fire Eugene Island Block 284 OCS-G 0991 Well A-13 March 1, 2001 Gulf of Mexico Off the Louisiana Coast U.S. Department of the Interior Minerals Management Service Gulf of Mexico OCS Regional Office

OCS Report MMS 2001-084 Investigation of Blowout and Fire Eugene Island Block 284 OCS-G 0991 Well A-13 March 1, 2001 Gulf of Mexico Off the Louisiana Coast Tom Basey John McCarroll Marty Rinaudo Buddy Stewart U.S. Department of the Interior Minerals Management Service New Orleans Gulf of Mexico OCS Regional Office August 2001

Contents Investigation and Report Authority, 1 Procedures, 1 Introduction Background, 4 Brief Description of Accident, 4 Findings Activities Prior to Loss of Well Control, 5 Loss of Well Control, 8 Attempts to Stop Well Flow, 8 Evacuation and Rescue, 9 Subsequent Activities, 10 Damages, 11 Cement Operations, 11 Management, 13 Conclusions The Accident, 15 Contributing Causes, 15 Recommendations Safety Alert, 17 Study, 18 Appendix Attachment 1, Location of Leases OCS-G 0987 Eugene Island Block 273 (surface location) and OCS-G 0991 Eugene Island 284 (bottom hole location) Eugene Island Block 273, Well A-13 wellbore schematic Slip-on wellhead schematic and +10 valve schematic Flow at +10 valve and fire monitors on location Flow at +10 valve Attachment 2, Attachment 3, Attachment 4, Attachment 5, Attachment 6, Platform/rig on fire Attachment 7, Damage to platform and rig resulting from fire Attachment 8, Installation of diverter system and BOP stack ii

Investigation and Report Authority An uncontrolled flow on Well A-13, resulting in a blowout and fire, occurred aboard the rig Ensco 51 during drilling operations on Forest Oil Corporation s Lease OCS-G 0987 Platform A, Eugene Island Block 273, in the Gulf of Mexico, offshore the State of Louisiana, on March 1, 2001, at approximately 0100 hours. The bottom hole location of Well A-13 is Lease OCS-G 0991, Eugene Island Block 284. Pursuant to Section 208, Subsection 22(d), (e), and (f), of the Outer Continental Shelf (OCS) Lands Act, as amended in 1978, and the Department of the Interior Regulations 30 CFR 250, the Minerals Management Service (MMS) is required to investigate and prepare a public report of this accident. By memorandum dated March 1, 2001, the following MMS personnel were named to the investigation panel: Buddy Stewart, Lafayette, Louisiana (Chairman) John McCarroll, Houma, Louisiana Tom Basey, Lafayette, Louisiana Marty Rinaudo, Lafayette, Louisiana Procedures On the morning of March 4, 2001, personnel (two engineers and two inspectors) from the MMS Lafayette District conducted an aerial reconnaissance of the platform and drilling rig. The MMS personnel then proceeded to Eugene Island Block 292, Platform B, where Forest personnel had set up their offshore command center. The MMS personnel were able to interview Forest s Representative and several Ensco personnel. Later that day, Forest relocated their offshore command center to the dynamically 1

positioned D/B 50, which had been brought on location to be used as a staging/support vessel. MMS personnel monitored the response effort from the D/B 50. On March 5, 2001, two MMS engineers returned to the incident location for an update on the response effort. The D/B 50 was on location and Forest, Ensco, and Wild Well Control were continuing operations to assess the site. MMS personnel were able to interview an additional Ensco person. On March 16, 2001, an MMS engineer and inspector returned to the incident location for an update on the response effort. On April 11, 2001, the Panel Members met at Forest Oil Corporation s office in Lafayette, Louisiana, and the following individuals were interviewed: Brian Roney, Ensco International David Harper, Ensco International Billy Whisenhunt, Ensco International Danny Hawkins, Ensco International Wayne Hession, Ensco International On April 25, 2001, the Panel Members met at Forest Oil Corporation s office in Lafayette, Louisiana, and the following individuals were interviewed: Harold Cody, Ensco International Reggie Howard, BJ Services Jim Steward, Forest Oil Corporation 2

On May 9, 2001, the Panel Members visited Seaboard International in Lafayette, Louisiana, and examined their wellhead design. On May 16, 2001, the Panel Members met at Forest Oil Corporation s office in Lafayette, Louisiana, and the following individuals were interviewed: Darin Hebert, Cameron Ned Shifflett, Forest Oil Corporation Cecil Colwell, Forest Oil Corporation The panel members met at various times throughout the investigative effort and, after having considered all of the information, produced this report. 3

Introduction Background Lease OCS-G 0991 covers approximately 5,000 acres and is located in Eugene Island Block 284, Gulf of Mexico, off the Louisiana coast. (For lease location, see Attachment 1.) The lease was issued effective June 1, 1962, and Forest became the designated operator of the lease on June 8, 1962. Platform A was installed in 1970. Brief Description On March 1, 2001, during an attempt to weld the casing head of a slip-on of Accident wellhead, gas flow was noticed coming from the +10 valve. Later, unsuccessful attempts were made to stop the flow, which was then coming from the drive pipe/surface casing annular region. The gas flow eventually ignited and caused extensive damage to the platform. The well bridged over and kill operations were completed. There were no injuries. 4

Findings Activities Prior to Planning Loss of Well Control February 9, 2001 The MMS Lafayette District approved Forest Oil Corporation s Eugene Island Block 284, Lease OCS-G-0991, Well A-13 Application for Permit to Drill (APD). In the APD, Forest Oil Corporation proposed drilling Well A-13 to a measured depth (MD) of 5,476 feet and a true vertical depth (TVD) of 5,153 feet, using the Ensco 51 jack-up rig. The well would be located in 191 feet of water. Forest Oil Corporation anticipated driving the 24-inch drive pipe to a measured depth of 441 feet MD (441 feet TVD), drilling a 22-inch conductor hole and setting 16-inch conductor casing at 650 feet MD (650 feet TVD), drilling a 14¾-inch surface hole and setting 10¾-inch surface casing at 1,900 feet MD (1,900 feet TVD), and drilling a 9-7/8 inch production hole and setting 7-5/8 inch casing at 5,476 feet MD (5,153 feet TVD). Summary of Drilling Operations February 16, 2001 The Ensco 51 rig arrived on location and began preload operations. It is important to point out that Forest normally conducts simultaneous operations when drilling on pre-existing platforms. During this drilling operation, extra precaution was used by installing back-pressure valves in all 12 wells located on the platform. February 22, 2001 The 24-inch drive pipe was driven to 460 feet MD. A starter flange was installed on the 24-inch drive pipe and a 6-inch, air- 5

operated, remotely controlled full opening valve was installed at the +10 level. February 23, 2001 The 21¼-inch diverter was installed, function tested, and Well A-13 was spudded. February 24, 2001 A 22-inch hole was drilled to 670 feet MD/TVD. The hole was circulated clean and a 16-inch scab liner was run to 633 feet MD/TVD and cemented with full returns taken at the +10 valve (see Attachment 2, for well schematic). February 25, 2001 The diverter system was rigged up on the 24-inch drive pipe and the 16-inch conductor casing was successfully tested to 200 psig. February 26, 2001 - The diverter system was function tested and drilling operations continued to a depth of 1,700 feet MD/TVD. The well was circulated for one hour, approximately two bottoms up. The well was checked for flow; none was detected. A pill was pumped and the drill pipe was pulled out of the hole. February 27, 2001 A Schlumberger wireline unit was rigged up and the 14¾-inch hole was initially logged from 1,694 feet MD/TVD to 633 feet MD/TVD. A second log was run over the same section of hole. The logs showed sands at 710 feet MD/TVD and 1,170 feet MD/TVD. Once the logging tools were pulled out of the hole, a 14¾-inch hole opener was picked up and run in the hole to 1,700 feet MD/TVD, and no fill was detected. 6

February 28, 2001 Running tools for the 10¾-inch surface casing were picked up, and the 10¾-inch surface casing was run in the hole to 1,700 feet MD/TVD. The BJ cement head was rigged up and the well was circulated with a 9.4-ppg mud (pumped two bottoms up). No gas-cut mud was detected and operations proceeded to cement the 10¾-inch surface casing (cement in place at 0930 hours). The drilling program then called for the washing of cement in the 24-inch drive pipe by 10¾-inch surface casing annulus (see attachment 2). This was accomplished by opening the +10 valve and running 1¼-inch wash pipe to a depth of 200 feet from the rotary-kelly-bushing (RKB). The drilling program also called for waiting on cement (WOC) a minimum of 8 hours before cutting off casing. During the period of WOC, the rig crew laid down the 1¼-inch wash pipe, removed the diverter lines, laid down the bell nipple, and rigged up to pick up the diverter. After WOC for 8 hours, the +10 valve was opened to drain the fluid in the 24-inch drive pipe by 10¾-inch surface casing annulus. The diverter was then picked up (1730 hours) to make a rough cut on the 10¾-inch surface casing. A hot work permit was filled out, the area was sniffed for gas, and a fire watch was established before welding/cutting operations began. The 10¾-inch surface casing was cut and the excess was laid down. After removing the diverter, a rough cut was made on the 24-inch drive pipe and the excess laid down. Final cuts began on the 24-inch drive pipe and 10¾-inch surface casing. 7

Loss of Well Control March 01, 2001 Final cuts on the 24-inch drive pipe and 10¾-inch surface casing were completed. While final cuts were being made by the welder, the night tool pusher and night driller went down to the boat landing to examine a means of removing the +10 valve. The well was static at this time. The 10¾-inch slip-on wellhead (SOW) by 11-inch, 5,000-psi casing head was lowered down to the wellbay for installation. The SOW was set on the 24-inch drive pipe and 10¾-inch surface casing. The SOW was leveled. The area was sniffed for gas and the welder tacked the 24-inch base plate in four places. The SOW was preheated, with some grease present. Once the SOW was preheated, the welder began to weld on the inside of the SOW. After the 3 rd welding rod was burned, a small blue flame was observed. The fire was extinguished and thought to be caused by grease from the wellhead. The area was sniffed for the presence of gas, resulting in no detection of any gas. Operations resumed welding inside the SOW; a second flame ignited and was larger than the previous flame. The flame was extinguished and the area sniffed for the presence of gas, resulting in the gas detector showing a maximum level of gas present. Approximately 0130 hours, the night driller observed a slight flow at the +10 valve. Attempts to Stop March 01, 2001 - The onsite Forest Company representative was alerted Well Flow and was informed that gas and fluid were escaping from the +10 valve. The Forest Company representative immediately instructed the crew to close the +10 valve to establish additional hydrostatic head by using 8.6-ppg seawater. An attempt was made to add seawater to the annulus through a ½ -inch gap located between the base plate and 10¾-inch surface casing (see Attachment #3). Because of the size of the opening on the base plate and the 8

rate of 8.6-ppg water being added, sufficient volume could not be added to slow down the current well flow. At this point, rig personnel attempted to install another hose to add 9.2-ppg mud to the 24-inch drive pipe by 10¾-inch surface casing annulus. The flow of the well continued at an increasing rate. An attempt to increase the mud weight to 17.0 ppg was planned. Because of the rapid increase in flow, it was decided to add what was being mixed in the slug pit, which at that time was 16.0 ppg mud. It became difficult for the mud to flow at a steady rate because of the density and the size of the opening between the 24-inch base plate and 10¾-inch casing. As a last attempt to control the well, the Forest Company representative decided to open the +10 valve to allow the 16.0-ppg mud to displace the lighter fluid present inside the 24-inch drive pipe by 10¾-inch surface casing annulus. With the flow of the well increasing and all attempts of adding mud to the 24-inch drive pipe by 10¾-inch surface casing annulus failing, the +10 valve was closed. At approximately 0300 hours, a decision was made to evacuate the rig, and the +10 valve was opened in an attempt to divert flow away from the platform and rig (see Attachment 4 & 5). The rig/platform was then abandoned. Evacuation and Rescue March 01, 2001 - Personnel abandonment of the Ensco 51 and the Eugene Island Block 273 Platform A was accomplished in a safe and orderly fashion. The rig abandonment alarm was activated at approximately 0300 hours. Personnel mustered at the escape capsules and all 43 personnel were accounted for prior to departing the rig. Personnel boarded two escape capsules. In transit to BP-Amoco Eugene Island 273 Platform B, personnel maintained two-way hand-held communication. Personnel were later 9

transferred to Forest s Eugene Island 292 Platform B. There were no injuries as a result of the incident. Subsequent Activities On March 1, 2001, the Forest Spill Management Team was mobilized to respond to the incident. Representatives from Wild Well Control were called in for expert support and to plan and carry out capping and kill operations. Several boats deployed to the location by the Spill Management Team to spray the platform. On March 2, 2001, 0330 hours, fire erupted on the Eugene Island 273-A Platform; source of ignition is unknown (see Attachment 6). Ensco 51 s derrick collapsed on the Eugene Island 273 A platform at 0345 hours (see Attachment 7). Because of the excessive heat, boats were unable to spray the platform continuously. Because the hydrocarbon flow was dry gas, dispersant application was not initiated and recovery action was not attempted. On the morning of March 2, 2001, representatives from Wild Well Control flew to the scene to begin investigations and plan kill operations. The dynamically positioned derrick barge DB-50 was contracted for well control support. The Ensco 55 jack-up drilling unit was mobilized to the location to stand by to drill a relief well if needed. On March 3, 2001, the well partially bridged and the fire went out. An initial visit was made to the platform by Wild Well Control representatives to 10

assess the situation. The well flowed sporadically until the well bridged on March 5, 2001. Numerous visits to the platform were made to remove debris around the wellhead to allow the installation of a Ventura Type sliplock connection over the 24-inch drive pipe. Once the Ventura Type sliplock connection was installed over the 24-inch drive pipe, a diverter and a BOP stack were installed to allow for safe kill operations (see Attachment 8). A portable crane was mobilized to the location and installed on the Ensco 51 to allow for further removal of debris. Wells A-1 and A-5 were prepared for back-up relief wells. Stimulation boats were mobilized to the location for kill operations. A snubbing unit was mobilized to the location and rigged up. Using a 2-3/8 work string, well A-13 was reentered and cemented to the mudline on June 15, 2001. Damages The Ensco 51 substructure and derrick were completely destroyed in the blowout and subsequent fire. There was severe damage to the production platform and associated production equipment. Cement Operations Cementing of 16-inch scab liner: The 16-inch liner was cemented with a total of 1,035 cubic feet of cement. A spacer of 20 bbls of seawater was used followed by 100 sacks, yield 3.07, of Class-H lead cement mixed at 11.4 ppg (55 barrels of slurry) and 668 sacks, 11

yield 1.09, of Class-H cement mixed at 16.4 ppg (129 barrels of slurry). After pumping 119 bbls of tail cement, the +10 valve was opened and the cement job was completed with full returns taken at the +10 valve. The cement was displaced with 11.5 bbls of 8.9-ppg mud and the plug was bumped with 1,000 psi. The pressure was released and the float equipment was holding. Cementing of 10-¾ inch casing: The 10¾-inch surface casing was cemented with a total of 1,796 cubic feet of cement. A spacer of 20 barrels of seawater was used followed by 487 sacks, yield 3.07, of Class-H lead cement mixed at 11.4 ppg (266 barrels of slurry) and 276 sacks, yield 1.09, of Class-H cement mixed at 16.4 ppg (54 barrels of slurry). Cement was displaced with 5 barrels of seawater. The seawater was followed by 160 barrels of 9.2-ppg mud and the plug was bumped with 1,000 psig. Full returns were observed during the entire cementing procedure, with a total of 30 barrels of cement returns observed at the +10 valve. The pressure was released and the float equipment was holding. Although both the 700-foot and the 1,200-foot were known to be present in the original well planning, the above 10¾-inch casing cement design did not include any additives for shallow-gas control. Further, the cement was not redesigned for the presence of shallow gas after the well was logged; the only change was the reduction in cement volume based on the caliper log. The cementing company representative was never made aware of any shallow-gas hazards. He stated that if he had been made aware of the shallow 12

hazards he would have requested a lab report from their engineering department so that they could redesign their slurry to combat gas. Gas flow was not apparent at the surface after the 10¾-inch surface casing was cemented, but flow did occur from either the 700-foot and/or the 1,200-foot sand. Uncontrolled flow occurred when the cement went through the gelation phase. The cement column lost its ability to transmit hydrostatic pressure onto the formation, allowing the gas to migrate into the cement, which formed channels. Management Forest Management did not review the drilling program developed by the drilling engineer prior to its implementation. When Forest Management was asked, if you had to drill the well over what would you change? the response was that the drilling program would have been revised. Forest did not conduct a prespud meeting prior to conducting drilling operations. When Forest was asked about having a prespud meeting for this well, the response was they feel prespud meetings are important, but in this case they didn t have enough time because of the level of activity. Communication was incomplete between Forest Management and the cementing company representative. Forest Management stated that a form is used to communicate pertinent information to the cement service company, such as shallow-gas hazards. The investigation could not determine whether the form was not used or the form was used but without a reference to shallow-gas hazards. When Forest Management was asked why the cement 13

service company didn t recommend revising the cement design appropriate for controlling shallow-gas hazards, the response was I think there was obviously a communication breakdown there. 14

Conclusions The Accident The most vulnerable period for the cement is immediately after placement and prior to its setting. It is during this time that cement, while developing gel strength, becomes self-supporting and loses its hydrostatic pressure. This hydrostatic pressure loss is responsible for the well reaching an underbalanced condition, which can lead to gas invasion. Slurries must be designed with the idea of minimizing this vulnerable time when an underbalanced condition exists. Formation gas migrated from the 700-ft sand and/or the 1,200-ft sand through the cement between the 24-inch drive pipe and the 10¾-inch surface casing, because of the above mentioned loss of hydrostatic pressure. Contributing 1. Failure of Forest Personnel to communicate the presence of shallow-gas Causes hazards to the contract cement service company. This resulted in cement not being properly designed to prevent gas migration into the cement. 2. A prespud meeting was not conducted to communicate known shallowgas hazards to all parties involved in drilling operations. 3. Once the hole section was logged and showed the presence of shallow gas, the well log information was not analyzed to verify that the cement program was properly designed for shallow gas. 15

4. Opening of the +10 valve allowed the fluid level in the 24-inch drive pipe by 10¾-inch surface casing annulus to fall, reducing the hydrostatic pressure on the cement, which could have contributed to gas migrating into the wellbore. 16

Recommendations Safety Alert The Gulf of Mexico OCS Region should issue a Safety Alert recommending the following: 1. Designated operators should develop specific strategies to prevent gas migration into the cement column. These strategies include the use of special slurries with physical and chemical properties that inhibit or block the invasion of gas. 2. Designated operators should implement methods to improve communication of any presence of shallow-gas hazards to the contract cement company. Through proper communication, cement companies can design proper cement for gas migration. 3. Designated operators should develop and put into practice a policy of having prespud meetings on all wells with shallow-gas hazards. 4. Designated operators should design a procedure to ensure that log information indicating shallow gas is used to verify proper cement designs. 5. Designated operators should analyze the safe use of the +10 valve where shallow-gas hazards are known to exist. 17

Study The Panel recommends that the Gulf of Mexico OCS Region should conduct a study on the complexity of effectively controlling annular flow when a scab liner is used where shallow-gas hazards exist. 18

MISSISSIPPI LOUISIANA ALABAMA CORPUS CHRISTI TEXAS NORTH PADRE IS. SOUTH PADRE IS. LAKE JACKSON MAT. IS. MUSTANG IS. CORPUS CHRISTI PORT ISABEL BRAZOS Western GALVESTON EAST BREAKS HIGH ISLAND ALAMINOS CANYON KEATHLEY CANYON LAKE CHARLES WEST CAMERON GARDEN BANKS EAST CAMERON VERMILION Eugene Island Blk. 273 G 0987 (surface location) NG 15-8 LAFAYETTE SOUTH MARSH IS. EUGENE IS. NEW ORLEANS HOUMA SHIP SHOAL SO. TIMBALIER G.I. GREEN CANYON Eugene Island Blk. 284 G 0991 (bottom hole location) WALKER RIDGE W.D. NG 15-9 BILOXI Central Eastern Location of Leases OCS-G 0987 Eugene Island Block 273 (surface location) and OCS-G 0991 Eugene Island Block 284(bottom hole location) S.P. ATWATER LUND MOBILE MAIN PASS B.S. KNOLL MISSISSIPPI CANYON NG 16-7 PENSACOLA MOBILE PENSACOLA VIOSCA DESTIN DOME DESOTO CANYON LLOYD HENDERSON NG 16-G APALACHICOLA GAINESVILLE FLORIDA MIDDLE GROUND TARPON SPRINGS THE ELBOW ST. PETERSBURG VERNON FLORIDA CHARLOTTE HARBOR FLORIDA TAMPA HOWELL HOOK PULLEY RIDGE RANKIN DRY TORTUGAS KEY WEST MIAMI Attachment 1

Attachment 2 RKB 83 feet Wellhead Sea Level MD = TVD Mudline Top of 16" Scab Liner set @ 335 feet 25 feet BML 24"x5/8", 156.1#, B Drive Pipe Set @ 460 feet 16", 75#, K-55, BT&C Conductor Casing Set @ 633 feet 200 feet 30 feet +10 Valve' Wash Cement w/8.6 seawater to 200 foot inside 24"x10-3/4" Annulus Forest Oil Corporation Eugene Eugene Island Island 273 - OCS-G 273 Well 0991 A-13- Well A-13 Well Configuration at the Time of Loss of Control 310 feet 184 feet 57 barrels of 11.4 ppg Lead Cement 33 barrels of 11.4 ppg Lead Cement 113 Feet 222 Feet Barrels of Lead Cement = 56.50068 23.375"x10.75" Annulus Barrels of Lead Cement = 32.77106 15.125"x10.75" Annulus 298 Feet 260 psi BHP 710'-720' Sand 14-3/4 Inch Hole Size 1170'-1180' Sand 55 barrels of 11.4 ppg 55 bbls Lead Cement 552.3 Feet Barrels of Lead Cement = 54.72567 14.75"x10.75" Annulus 499 psi BHP 10-3/4", 40.5#, k-55, BT&S Surface Casing Set at 1700 feet 9.4 ppg Mud Weight 3 bbls of Tail Cement in 10-3/4" Shoe 51 barrels of 16.4 ppg Tail Cement 514.7 Feet Barrels of Tail Cement = 51 14.75"x10.75" Annulus Eugene Island Block 273, Well A-13, wellbore schematic

Attachment 3 10-3/4 inch Slip On Wellhead (SOW) by 11 inch 5000 psi casing head Eugene Island 284 Slip on Wellhead and Plus 10 Valve Schematic 1/2 inch gap between 24 inch base plate & 10-3/4 inch surface casing 24 inch Drive Pipe 24 inch Drive Pipe by 10-3/4 inch Surface Casing Annulus 10-3/4 inch Surface Casing Control Line to Driller's Console Remote Controlled Full Opening 6" Air Operated Ball Valve 10' to water line Water Line Slip-on wellhead schematic and +10 valve schematic

Ensco 51 Eugene Island Block 273-A Gas Flow from +10 valve Flow at +10 valve and fire monitors on location Attachment 4

Ensco 51 jack-up legs Eugene Island Block 273-A P/F Flow at +10 valve Flow at +10 valve Attachment 5

Ensco 51 Eugene Island Block 273 P/FA Fire at +10 valve Platform/rig on fire Attachment 6

Ensco 51 collapsed sub-structure & derrick Ensco 51 Intermediate flow at A-13 wellhead Flow at +10 valve Damage to platform and rig resulting from fire Eugene Island Block 273 P/FA Attachment 7

BOP Stack Diverter Diverter line Cleared main deck Eugene Island 273-A P/F Installation of diverter system and BOP stack Attachment 8