Easton Safer Streets - Final Project Report BRISTOL

Similar documents
ANNEX1 The investment required to achieve the Government s ambition to double cycling activity by 2025

LEA BRIDGE ROAD - A STREET FOR EVERYONE Public consultation document

National Cycle Network - Signing and Route Branding

Bristol City Council has produced a draft Bristol Transport Strategy document.

The One Path Initiative

DOE Climate Change Proposals

Cycle Superhighway 4 from Tower Bridge to Greenwich

REF. PE01595: MORATORIUM ON SHARED SPACE SCHEMES

ENFIELD TOWN THE REVISED DESIGN

March Maidstone Integrated Transport Strategy Boxley Parish Council Briefing Note. Context. Author: Parish Clerk 2 March 2016

Active Travel Strategy Dumfries and Galloway

Lea Bridge Road A street for everyone Tell us

FAQ s Walsh Road / Ferguson Road Pilot Scheme

Cambridgeshire floating bus stops interaction analysis

FUTUREDMS 2018 CONSULTATION REPORT

MARKHOUSE ROAD IMPROVEMENTS

BYRES ROAD: PUBLIC REALM Public Consultation

Our journey a 20 year Transport Manifesto for the North East

Charlbury Community Action Plan Group. Getting Around & Street Space / Keep Charlbury s Heart Beating. Draft Interim Report July 2017

E4 Cycle Route Exeter University to Redhayes Bridge. - Recommendations from Exeter Cycling Campaign

Route User Intercept Survey Report

NCN 78 Benderloch to Ledaig Summary

Part 3: Active travel and public transport planning in new housing developments

Tonight is for you. Learn everything you can. Share all your ideas.

The Cabinet Member for Highways & Streetscene. Aurang Zeb - Head of Highways & Transport

Cabinet Member for Highways & Streetscene. Highway Infrastructure Manager

Parapet Heights on Cycle Routes

Stepping up a gear. Our vision for cycling in Cardiff

Design Workshops Summary of all Feedback January 2017

20mph. We want to make Edinburgh a better and safer place to live, work and play.

London Cycle Network Annual Report 2000

IAN WHITE ASSOCIATES. Crawley Station Gateway Public Realm

Ormond & McKinnon Walks Response to Draft Glen Eira Community Plan

Nottingham Cycle City Frequently Asked Questions

Road Safety in Radyr and Morganstown: the Community Council's response to Cardiff Council's draft scheme layout for highway improvements

Low traffic neighbourhoods

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

PLACE CONCEPT! DESIGNS. Simplified crossroads junction to take traffic away from the heart of Picardy Place

Bulwell Cycling Consultation

Governance and Priorities Committee Report For the July 2, 2015 Meeting

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

CYCLING CHARTER ACTION PLAN EXECUTIVE SUMMARY

Broadway Market engagement report

Public Consultation on Braintree Integrated Transport Package (ITP) HAVE YOUR. Consultation open from 24 September to 5 November 2018 SAY

Update June 2018 OUR 2017 PUBLIC ENGAGEMENT

A future cycle route network for North Staffordshire mb/08/16 Need for a strategy. Existing cycle route network

Rhebogue Neighbourhood Greenway. Road Safety Audit Stage 2

Milton Road Project Update. Paul van de Bulk 30 January 2018

Walking and Cycling Action Plan Summary. A Catalyst for Change The Regional Transport Strategy for the west of Scotland

Glebe Neighbourhood Cycling Plan

The Infrastructure Impact Tool

NCN 78 Dalnatrat to Duror Summary

Guide to the Cycle Enfield Public Consultation on Enfield Town. Produced by the Save Our Enfield Town Campaign Group

Introduction. Prince Street Cycling Ambition Fund Public Realm Project

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

Travel Planning WC & NWCD Cycling Group. Thursday 2 nd July Amanda Holden

Frascati Road and Temple Hill Route Improvements. Outline Design Report to Accompany Public consultation

PROMOTING 20MPH. Photo

CHURCH ROAD. Public consultation document TELL US YOUR VIEWS.

MILTON ROAD LLF PROJECT UPDATE

Living Streets Aberdeenshire Summary Report Photo

Major Bike Routes 102 Avenue Workshop April 21, 2015

Have your say on the transformation of Oxford Street West

PERSONALISED TRAVEL PLANNING IN MIDLETON, COUNTY CORK

Derby Cycling Group, c/o 126, Station road, Mickleover, Derby, DE3 9FN. Date: 20 th November, 2018.

Space for Cycling. A guide for decision makers

Walthamstow Village: trial results and workshop summary

TRANSPORT AND MOVEMENT

1. TRANSFORM CITY ROAD WEST INTO A GREAT CENTRAL city street

Aiming for Zero Road Worker Safety. Mark Pooley Highways Agency Road Worker Safety Programme Manager Monday 11 June 2012

Background. Caversham a vision for the future. Joint public meeting arranged by:

Guildford Borough (Draft)

GD 0043/18 ACTIVE TRAVEL STRATEGY

Appendix N(b): Portishead Station Outline Travel Plan

Kings Road, Herne Bay: Proposed Crash Remedial Measure

WELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input

Living Streets response to the Draft London Plan

WEST YORKSHIRE LTP CYCLE PROSPECTUS

What do Passenger Transport Services do?

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

Our Cycle Promise. northernrailway.co.uk. Produced in partnership with Sustrans. July 2017

HISTON ROAD Have your say on better public transport, cycling and walking journeys

Road Safety Partnership

How do we design for pedestrians? Case study: transforming the Walworth Road

Dowling/Beaty Cycling Route

Horses on the National Cycle Network

Launceston's Transport Futures. Greater travel options for the people of Launceston

Becoming a travel champion

122 Avenue: 107 Street to Fort Road

Frome Street Bicycle Route

Cycle Lanes Dixon Street (Worksop Road to Crayne Street)

City of Perth Cycle Plan 2029

05 Pilot Projects 68

Scottish Parent Teacher Council School Travel Survey Introduction

Developing a Birmingham Transport Space Allocation policy. David Harris Transport Policy Manager Economy Directorate Birmingham City Council

Kelowna On the Move. Pedestrian and Bicycle Master Plan

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

RESTRICTED ROADS (20 MPH SPEED LIMIT) (SCOTLAND) BILL. 1. Is reducing the speed limit to 20mph the best way of achieving the aims of the Bill?

Transport Workshop Dearbhla Lawson Head of Transport & Infrastructure Policy & Funding University of the Third Age.

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

Transcription:

- Final Project Report BRISTOL A Sustrans Community Street Design Project in partnership with Bristol City Council February 07

About Sustrans Sustrans makes smarter travel choices possible, desirable and inevitable. We re a leading UK charity enabling people to travel by foot, bike or public transport for more of the journeys we make every day. We work with families, communities, policy-makers and partner organisations so that people are able to choose healthier, cleaner and cheaper journeys, with better places and spaces to move through and live in. It s time we all began making smarter travel choices. Make your move and support Sustrans today. www.sustrans.org.uk Head Office Sustrans Cathedral Square College Green Bristol BS 5DD Table of contents PROJECT SUMMARY... ISSUES & OPPORTUNITIES... PRIORITISING... CO-DESIGN... CONCLUSION... 5 8 Sustrans Registered Charity No. 6550 (England and Wales) SC096 (Scotland) VAT Registration No. 670656

Project Summary Sustrans and Bristol City Council are working with Easton s residents to increase levels of walking and cycling in the area. By improving street safety in Easton, people are more likely to switch away from private car use and towards sustainable transportation, like walking and cycling. Engagement approach and stages: INFORMATION GATHERING Aims The aims of the project are as follows: Engage the community of Easton, evidencing, and agreeing with the community, the impact of traffic on the quality of people s everyday lives. This community-led process has gathered the views of people living and working in the area, using an on-line portal and on-street events. This report summarises the information gathered, and sets out outline design solutions developed through a co-design process. The results show there is a clear demand for action in Easton, with patterns of issues emerging in different areas. For example, concerns over speeding, dangerous roads, driver behaviour and rat-running were commonly raised. By designing solutions with the community, we hope to deliver a scheme which reflects the needs of Easton s residents, and helps to make their streets safer for all road users. ISSUES & OPPORTUNITIES Raise awareness of the project Identify barriers to walking and cycling Identify opportunities for improvements PRIORITISING ISSUES AND LOCATIONS Summarise key issues Priorities key areas for improvement Assessing appetite for types of delivery Develop and agree with the community a strategic approach to developing solutions to issues identified as a result of community engagement. Assess appetite for the delivery of interventions addressing issues raised through engagement. Significantly reduce through traffic. Support the community in designing interventions acceptable to local people, and that meet local people s needs. Project area map: CO-DESIGN Participatory co-design workshops focussed around prioritised areas Phase I & II Outline design proposals DETAILED DESIGN Where appropriate, test proposals through street trials. Create improved street environments for walking and cycling, that better reflect the surrounding local community s needs, whilst addressing project objectives. CONSTRUCTION 855 Participants at workshops and on-line to date In addition to this, extensive separate engagement has been held with local stakeholders including: Local businesses May Park Primary School Bannerman Road Primary School 09 comments on-line and from workshops to date Whitehall Street Primary School Neighbourhood Partnership & Forum Disabilities forum

Issues & Opportunities Issues Raised The purpose of this stage was to provide opportunities for people to discuss what would encourage them to walk and cycle more in Easton. They were asked to identify the barriers to active travel, and opportunities for improvements in the project area. Pop-up events took place within the area, to capture feedback from the community using maps and a series of themed stickers, as well as collecting open comments. During this whole process an on-line mapping portal was used to give those who were unable to attend the events an opportunity to participate in the process. Key barriers to walking and cycling identified during this stage overwhelmingly related to issues of safety, with participants specifically citing issues of driver behaviour, speeding, parking and through traffic as key. + - Unsafe (fear of crime) Dangerous (road safety) Driver behaviour Speeding Parking Issues Rat running / through traffic Congestion Crossings Unknown Greenery / trees / planting Cycle path needed Signage / legibility Lighting Cycle parking needed Seating Barriers 8 6 05 85 6 9 9 9 5 9 6 0 50 00 50 00 08 Participants in the stage 7 Pop-up street events at locations across Easton 57 Comments for the stage Too many cars makes walking with children dangerous. Encouragement for cycling and walking is needed As cyclist I am often nearly forced into a parked car as I cycle along as a car tries to overtake me. People drive way too fast along both these streets putting pedestrians, cyclists and themselves at risk.

Prioritising 7 8 9 5 6 0 Area 8 9 7 0 6 5 Prioritising Results by Area Upper St Mark's Road 75 Kilburn/Owen Streets/ Chelsea/Roman/Albion Roads 7 Emlyn/ Greenbank/ Hinton/ Belle Vue Roads 69 Lower St Mark's Road 57 Devon Road/ Tudor Road Area 6 Rosemary Lane / East Park / May Park School 7 Johnson Road/ Railway Path Crossing/ Bruce Road Easton Road All Hallows Road/ Bannerman Road School 5 Devon Road - Southern Section Colston/ King's Road Area 5 Lansdown/ Villiers/Felix/Belton/Bannerman Roads 0 0 0 60 80 The purpose of this phase was to agree a series of focussed priority areas, as well as determining the level of appetite within the community for various design approaches. Findings from the previous stage were grouped into a series of geographical areas. Participants were invited to select the areas of most importance to them. They were also presented a list of potential design approaches, ranging from light touch art, through to filtered permeability, and asked to select which solutions represented their preferred approaches for their selected areas. It was decided that to ensure reasonable impact from a tight budget, the top 5 areas chosen would become the focus for on-going engagement. These were; Upper & Lower St Mark s Road, Chelsea Road, Greenbank/Bellevue Road and Devon Road. Evidencing the level of concern and appetite within the community to address issues around safety associated to vehicle volume and behaviour, all but one of these areas cited filtered permeability within the top choices for preferred intervention choices. 7 Pop-up street events mirroring the previous stage Participants in stage Preferred Solutions picked by participants for the Top 5 Areas : Upper St Marks Rd Solutions Cycle lane Plants & greenery Parking restrictions Creating street space for community Pavement widening Segregated cycle lane Artwork Speed humps Build-outs/road narrowing 0% 5% 0% 5% 0% : Chelsea Rd/Kilburn Solutions Speed humps Plants & greenery Cycle lane Creating street space for community Build-outs/road narrowing Parking restrictions Artwork Segregated cycle lane Pavement widening 0% % % 6% 8% 0%%%6% 8: Greenbank / Bellevue Rd Solutions Build-outs/road narrowing Speed humps Cycle lane Plants & greenery Parking restrictions Segregated cycle lane Pavement widening Creating street space for community Artwork 0% % % 6% 8% 0% % % : Lower St Mark's Rd Solutions Cycle lane Pavement widening Segregated cycle lane Parking restrictions Plants & greenery Speed humps Creating street space for community Artwork Build-outs/road narrowing 0% 5% 0% 5% 0% 9: Devon Rd North Solutions Speed humps Build-outs/road narrowing Cycle lane Plants & greenery Pavement widening Segregated cycle lane Parking restrictions Creating street space for community Artwork 0% 5% 0% 5% 0%

ts Aggregation of top 5 prioritised areas - Strategic Design Development - Strategic Plan - Development st draft Strategic Design KE KEY: Quiet route Focus Junction Workshop Area Focus Proposed filtered permeability Proposed one-way traffic Existing one-way traffic The map above shows an agragated picture of the top 5 prioritised areas. Focussing on these areas, information gathered was used to develop a strategic plan. The aim was to create a series of safe, traffic calmed routes connecting key locations; St Mark s Rd, May Park school, Bannerman Rd school, Whitehall Street school, Bellevue Park, Albion Green, Easton Community Centre as well as routes in and out of Easton. Along the route, a number of key junctions were identified, that would require improvements in order to reinforce this route. These junctions would then form the focus of further co-design workshops aimed at developing specific design improvements at each location.

What you told us Speeding and dangerous driving behaviour Pavements are too narrow Parking on pavements and at corners forcing people onto roads Poor/difficult crossings Cycle parking needed Often congestion & rat running Co-Design A small number of locations were proposed, these were; locations at High Street/St Mark s Road, and Rosemary Lane. The closures around St Mark s Road aimed at addressing community concerns around traffic volume and through traffic, particularly of large vehicles There had been significant concerns related to volume of traffic and driver behaviour around Rosemary Lane. Issues around Rosemary Lane were further reinforced as it is a key route for children traveling to and from May Park School. Pedestrians and cyclists would still be able to pass along these sections of closed road. Through the co-design process, further closure points were identified; Albion Road railway bridge, and York Road. Albion Road is key route to Bannerman Road School, and parents raised significant safety concerns around the volume of traffic and driver behaviour. Closing York Road at the selected point would remove the potential of vehicles to use it as a cut through from Chelsea Road to Bellevue Road. What you ve told us Great shopping street Behaviour of drivers making junction and area around feel unsafe Too car dominated - more priority for pedestrians & cycling would improve the feel Narrow pavements - not enough room for pedestrians Exacerbated by unrestricted & inconsiderate parking - delivery vehicles particularly are an issue Cycling contraflow works badly poorly marked Congestion and rat-running Safer s needed Physical traffic calming to reduce speed and improve driver behaviour - speed table (budget allowing) Increase pavement width where possible with bollards to protect pavement and stop pavement parking Crossing points with informal designs and artwork Parking restrictions at corners Loading bays for shop and pub Cycle parking serving the shop and pub Planting - built-in Cycle parking for pub/shop Physical traffic calming at junction including road closure wide support. Wider pavements where possible, and protection from pavement parking particularly under the bridge. Restricted parking on corners Introduce new re-aligned and extended one-way system. Improve crossings - informal, including informal artwork Clearer cycling route Cycle parking Planting - not planters Quiet route Focus Junction Workshop Area Focus Proposed one-way traffic Existing one-way traffic Workshop Location Rosemary Lane - key route to school & park key destination Busy rat running route - making roads and crossings difficult and dangerous - particularly for children Behaviour of drivers making junctions and area around feel unsafe Exacerbated by unrestricted & inconsiderate parking (Hinton Rd/Greenbank Rd Jct) - delivery vehicles particularly are an issue Speeding along Rosemary Lane St Mark s Road Schools - Art A local artist was commissioned to work with May Park Primary School, Whitehall Street Primary School, and Bannerman Road Primary School. The objective was to produce pieces of art representing the community, that will later be used at points along the route to further reinforce both the route and local identity. KEY: Proposed filtered permeability There were a number of concerns from businesses related to access of delivery vehicles, therefore these proposals are being re-considered In addition to filtered permeability at the locations mentioned, the initial strategic plan also included a proposal to change the direction of the existing one-way system, and extend it along the entire length of St Mark s Road. A number of concerns were raised about these proposals by shop keepers relating to access of delivery vehicles. As a result of this, it was agreed not to implement these proposals. Amendments to this proposal will now consider extending the existing oneway system to the junction with Lawrence Avenue. It is still proposed to put filtered permeability on High Street close to the junction with Church Street with another closure at the top of Chelsea Road close to Lena Street. Strategic Plan - Final Physical traffic calming including raised table at Robertson Rd/Emlyn Street junction and closure to traffic at Rosemary Lane. Restricted parking around corners Improved s - block colour Wider pavements where possible Planting - built in Artwork working with the school Safer s needed What you ve told us Speeding and dangerous driving behaviour Key route to school - lots of children Poor/difficult crossings Pavements are too narrow especially with prams Rat running Albion Green is great Physical traffic calming - close bridge to traffic. Raised crossing to provide clear safe - block colour or paved. Wider pavements where possible Increased cycle parking More planting - built in, not planters at railway bridge and Chelsea Road/Lena What you ve told us Fast and dangerous driving behaviour making the road feel unsafe - more priority for pedestrians & cycling is needed High levels of through traffic & rat running - congestion or speeding, depending on time of day Poor/dangerous crossings - key route across the area including school Narrow pavements - not enough room for pedestrians Parking at junctions blocking paths and s street. Road closure to prevent opportunity for traffic to cut through from Chelsea Road to Bellevue Road 5 Physical traffic calming - raised tables around Bruce Road and at point where road turns into lane at northern end of Devon Road. Introduce pavements where currently none exist and widen at other points where possible. Improved s - important Restrict parking at corners Planting - built in

Bike Parking Co-Design Phase I Participants in stage 5 Workshops at locations across Easton 5 Workshops were held, in or around each of the focus junctions. The purpose of the workshops was to discuss the general strategy, and develop and begin to agree a more refined approach to improvements at each of the focus junctions. Participants were asked to consider specific issues at each junction, indicating their preferred design approach. These included; traffic management, crossings, pavement width, planting and bike parking. Outputs from Co-design phase Bellevue Rd & Greenbank Rd Greenbank Road Artwork Raised table Widen pavement Bollards to prevent vehicles mounting pavement Parking restrictions Loading Bike parking Co-Design Phase II 9 Participants in stage 5 Workshops at locations across Easton Loading Bellevue Road Bus Stop Loading bays Planting opportunities, possibly SuDS Comments captured during the previous workshops were developed into a series of sketch proposals. The sketches aimed to address key, prioritised issues previously identified at each location, as well as preferred design approaches. Bike Parking Participants were asked for general feedback and asked to contribute to the development of the designs and the updated overall strategy. They were also again asked about acceptable design approaches aimed at addressing specific issues, such as raised tables, filtered permeability, use of bollards etc. Stanley Park As well as responses and contributions to the designs developed to date, a number of additional outputs were suggested. These included additional locations for filtered permeability; at Albion Road railway bridge close to the entrance to Bannerman Road School, and he junction of York Rd and Lena Avenue to reduce opportunities for alternative rat-running routes. Bellevue Rd & Washington Av Another key location that became a focus during the last engagement phases, was Devon Road, and the demand for a crossing between Alpine Road and railway bridge. This crossing is an existing Neighbourhood Partnership priority, and is being developed by Bristol City Council Highways Officers. Engagement delivered through Safer Streets has further reinforced the demand within the community for traffic calming measures and better crossings along Devon Road. It is still envisaged that this crossing will be delivered through the Neighbourhood Partnership. Bellevue Road Artwork Raised table Widen pavement Bollards to prevent vehicles mounting pavement Parking restrictions Planting opportunities, possibly SuDS The proceeding drawings summarise the design outputs for each focus junction, as developed through co-design stages I & II. These sketch designs have now been submitted to Bristol City Council highways engineers, who will develop these sketch solutions into a series of detailed designs. Once developed, the detailed designs will be displayed at a series of community events currently being planned. Greenbank Avenue West High Street

Outputs from Co-design phase Albion Green Rosemary Lane / Robertson Rd / Emlyn Rd Raised table Artwork Raised table Create footway Placemaking/Planting Emlyn Road Planting opportunities, possibly SuDS Albion Rd All Hallows Rd Devon Rd St Mark s Rd Artwork Artwork Raised table Create footway Restrict vehicle access to lane Parking restrictions Planting opportunities, possibly SuDS Widen pavement under bridge Maintain parking Parking/loading 5 Public space Parking/loading * * 5 Raised table Widen pavement Bollards to prevent vehicles mounting pavement Parking restrictions One-way traffic Additional parking/ loading Public space Clearly defined contra-flow Planting opportunities, possibly SuDS * Elements not to be implemented as a result of concerns raised by traders, relating access for delivery vehicles 7

Conclusion Over a month period, has engaged with in-excess of 855 residents and captured over 000 comments. accessible and interactive workshops held across Easton have identified key issues related to walking and cycling throughout the area, and residents have demonstrated a demand and a clear appetite to address these issues by means of a series of interventions throughout the area. In addition to the on-street workshops and on-line mapping, meetings and workshops were held with: May Park Primary School Whitehall Street Primary School Bannerman Road Primary School Presentations have been given to the Neighbourhood Partnership, the local sub traffic and transport group and disability forum. Local businesses have been extensively engaged, and Sustrans will continue to engage and deliver events until April 07 The geographical extent of project delivery has been prioritised and agreed, and a series of co-design workshops have developed and agreed outline proposals, providing a series of community led design solutions meeting the needs of the Easton Community.