EXPERIENCE WITH A PRE-SERIES SUPERFLUID HELIUM TEST BENCH FOR LHC MAGNETS

Similar documents
Cryogenic Benches for Superfluid Helium Testing of Full-Scale Prototype Superconducting Magnets for the CERN LHC Project

Figure 1 The LHC cryogenic islands and plants layout

PRELIMINARY RISK ANALYSIS OF THE LHC CRYOGENIC SYSTEM

QUALIFICATION OF SUB-ATMOSPHERIC PRESSURE SENSORS FOR THE CRYOMAGNET BAYONET HEAT EXCHANGERS OF THE LARGE HADRON COLLIDER

Magnet and RF Cavity Test Stand Design. Tom Peterson, SLAC USPAS January, 2017

DEVELOPMENT OF LARGE-CAPACITY REFRIGERATION AT 1.8 K FOR THE LARGE HADRON COLLIDER AT CERN. Philippe Lebrun*, Laurent Tavian*, Gérard Claudet**

First Experimental Data of the Cryogenic Safety Test Facility PICARD

LARGE CRYOGENIC SYSTEMS AT 1.8 K

JANIS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS

Current Leads for Cryogenic Systems

European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire

SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL

Fermilab MTF Cryogenic System & Vertical RF Cavity Test Facility. Yuenian Huang, on behalf of Fermilab, TD/TID May 11, 2006

Overview of Earlier Lecture

Proposal for the Cryogenic Supply of a Single TTF / FEL - Cryomodule Test Bench

Status on the DFBXF commissioning

RECENT PROGRESS IN POWER REFRIGERATION BELOW 2 K FOR SUPERCONDUCTING ACCELERATORS

Cryogenic System for a Large Superconducting Magnet in Space

The LHC Cryogenic System and Operational Experience from the First Three Years Run

National Accelerator Laboratory

Available online at ScienceDirect. Physics Procedia 67 (2015 )

Loss of Vacuum Experiments on a Superfluid Helium Vessel

Normal Cryogenic Fluid Behavior (emphasis on helium, but not superfluid, which will be covered later) Tom Peterson, SLAC January 2017

AN EXPERIMENTAL INVESTIGATION ON HELIUM LIQUEFACTION USING TWO-STAGE GIFFORD McMAHON CRYOCOOLER

FAILURE SCENARIOS AND MITIGATIONS FOR THE BABAR SUPERCONDUCTING SOLENOID

SPECIFICATION FOR AN MRBR 9.4 TESLA/310MM/AS CRYO-COOLED MAGNET SYSTEM

Short Introduction to Cryo-Pumps and Refrigerators. Dr Graham Rogers Leybold UK Ltd.

Cryogenics of SRF Spoke Cavity Development at SMTF

Spallation target cryogenic cooling design challenges at the European Spallation Source

A Brief Introduction to Helium Liquefaction At ITER

ESS SPOKE CRYOMODULE AND TEST VALVE BOX

RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00

Cryostream 800 Series

Design of Relief Valves/Devices/Systems for Cryogenic Apparatuses and Installations

Table of Contents Want full page pictures with most important parts labeled in the beginning.

Analysis of RPC Performance with Different Gas Mixture

Thomas Jefferson National Accelerator Facility Newport News, Virginia, 23606, USA

Series Environmental Chambers

Measurement And Control Appreciation

TECHNICAL SPECIFICATION. SPC-1 Stirling Process Cryogenerator

Liquid Helium Bath Cryostat

INTRODUCTION. The Quantum Technology system has the following advantages:, as it does not need plastic gas-bags which are volume-consuming,

TECHNICAL SPECIFICATION. SPC-4 Stirling Process Cryogenerator

Gas density monitor With integrated transmitter Model GDM-100-TI

TIGHTNESS. Glass sealing Thanks to our glass-sealing technology, ODU products can meet the most demanding tightness requirements.

Turnkey Industrial Gas Projects and Equipment

Yokosuka Cruise Report YK11-02

Helium recovery at the National High Magnetic Field Laboratory

Helium-Liquefaction by Cryocooler for High-Field Magnet Cooling

Microscopy Cryogenic WORKSTATION. Performance by Design

23.1 Functions, Basic Configuration, and Interfaces

Vacuum. Dry Turbo Pumping Stations. Roughing Pumps for 1 K Helium Pots and Lambda Refrigerators. Hermetically Sealed Pumps for He3 Recirculation

Research activities on cryogenic safety

An Investigative and Synoptic Review on Helium Liquefaction Using a Commercial 4 K Gifford- McMahon Cryocooler

LAr Filling and Commissioning of Cryogenics

Variable Temperature Storage Dewar Mount Inserts

To be published in the proceeding of ICEC-22, Seoul Korea, July 2008 MICE Note 231 1

SUMMARY AND RESULTS OF THE CRYOPLANT OPERATION FOR HERA

Influencing Factors Study of the Variable Speed Scroll Compressor with EVI Technology

Chapter 6 Leak detection

LEAK-TIGHT WELDING EXPERIENCE FROM THE INDUSTRIAL ASSEMBLY OF THE LHC CRYOSTATS AT CERN

Heliox Sorption Pumped 3 He Refrigerator Systems

Storage and transfer of cryofluids

NGN Series nitrogen generator

PREVENTION OF EXCESSIVE PRESSURE DURING FILLING OF CRYOGENIC VESSELS

LEAP CO 2 Laboratory CO 2 mixtures test facility

AC : MEASUREMENT OF HYDROGEN IN HELIUM FLOW

LESER Deutschland Standard Functional Tightness Test (Cryo) Content

Design and Performance of the Vacuum Chambers for the Undulator of the VUV FEL at the TESLA Test Facility at DESY

TESTING SAFETY OF HYDROGEN COMPONENTS

ATL. Take Control of your Helium Supply. Advanced Technology Liquefier The next generation of helium recycling

Dilution Refrigerator manual

DRAFT. Operating Procedures for the NPDGamma Liquid Hydrogen Target in TA-53, Building MPF-35

Specifications of Cryogenic vacuum jacketed valves

Cooling Strings of Superconducting Devices below 2 K: The Helium II Bayonet Heat Exchanger. Ph. Lebrun, L. Serio, L. Tavian and R.

Procedure of Xenon Transfer

ISO INTERNATIONAL STANDARD. Cryogenic vessels Pressure-relief accessories for cryogenic service Part 1: Reclosable pressure-relief valves

Verification and validation of computer codes Exercise

Gianluca Gemme LN2 DISTRIBUTION PLANT

Design Features. General Description

Profile LFR-45 LIFUS5 ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy

ESAIL D45.1 Final Report of Remote Unit Gas Thruster

from Thames Cryogenics Ltd Total Cryogenic Solutions Cryogenic Cluster Day 22/09/2010

Gas Absorption Column CAG

Agilent ICP-MS Interactive Troubleshooting tool for Plasma ignition problem

LS2 Activities for the ATLAS Gas Systems

MODIFICATION OF THE LHC VENTILATION SYSTEM

Procedure for Operating Columbia (Nevis) LHe Electron Bubble Chamber Cryostat. Version 5.1

Visual Observation of Nucleate Boiling and Sliding Phenomena of Boiling Bubbles on a Horizontal Tube Heater

A Depletion Compensated Wet Bath Simulator For Calibrating Evidential Breath Alcohol Analyzers

The Principles of Vacuum Technology

The Helium Leak Detector

E A C S. Engine Altitude Conditions Simulator. Technical description

Quantitative study of sniffer leak rate and pressure drop leak rate of liquid nitrogen panels of SST-1 tokamak

SENSITIVITY ANALYSIS OF THE FIRST CIRCUIT OF COLD CHANNEL PIPELINE RUPTURE SIZE FOR WWER 440/270 REACTOR

American made since 1954

Refrigeration Plants for the SSC

CRYO. SuperVariTemp Magnet Inserts

Ocean Observatories Initiative. Coastal & Global Scale Nodes. Hydrogen Safety. OOI Surface Mooring Hydrogen Safety Review

Transcription:

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 388 EXPERIENCE WITH A PRE-SERIES SUPERFLUID HELIUM TEST BENCH FOR LHC MAGNETS V. Benda, B. Vullierme, J. Schouten* Abstract The Large Hadron Collider (LHC) under construction at CERN is based on the use of high-field superconducting magnets operating in superfluid helium. For the validation of the machine dipoles and quadrupoles, a magnet test plant is under construction requiring 12 so-called Cryogenic Feeder Units (CFU). Based on experience done at CERN, two pre-series CFUs were designed and built by industry and are currently in use prior to final series delivery. This presentation describes the features of a CFU, its typical characteristics and the experience acquired with the first units. LHC Division *Oxford Instruments Ltd, Tubney Woods, Abingdon, Oxford OX13 5QX, UK Presented at the Eighteenth International Cryogenic Engineering Conference (ICEC 18) 21-25 February 2000, Bombay Mumbai, India Administrative Secretariat LHC Division CERN CH - 1211 Geneva 23 Switzerland Geneva, 26 July 2000

Experience with a Pre-Series Superfluid Helium Test Bench for LHC Magnets Vladislav Benda, Bruno Vullierme, Joseph Schouten* LHC Division, CERN, 1211 Geneva 23, Switzerland *Oxford Instruments Ltd, Tubney Woods, Abingdon, Oxford OX13 5QX, UK The Large Hadron Collider (LHC) under construction at CERN is based on the use of high-field superconducting magnets operating in superfluid helium. For the validation of the machine dipoles and quadrupoles, a magnet test plant is under construction requiring 12 so-called Cryogenic Feeder Units (CFU). Based on experience done at CERN, two pre-series CFUs were designed and built by industry and are currently in use prior to final series delivery. This presentation describes the features of a CFU, its typical characteristics and the experience acquired with the first units. 1 INTRODUCTION The main magnetic system of LHC will consist of about 1200 twin-aperture, high-field superconducting dipoles and 400 twin-aperture, high-gradient superconducting quadrupoles operating in pressurized superfluid helium below 1.9 K [1]. All these magnets will be tested at CERN before their final installation in the accelerator tunnel. In 1994 the first magnet test bench for LHC magnet prototypes was designed and built by CERN [2]. It was used to test 10 magnet prototypes before its dismantling in 1999. On the basis of the experience done with this first bench, two pre-series CFUs for testing of LHC pre-series magnets were designed and built by Oxford Instruments Ltd, installed and tested at CERN. The functions of the CFU are to control the cool down and warm up of a magnet, to maintain a magnet in saturated liquid helium at 4.5 K or in pressurized superfluid helium at 1.9 K for magnetic measurements and quench training, to recover as much liquid helium as possible after a quench and to automatically cool down the magnet again. The CFU also contains all the current leads for the main coil and for the auxiliary magnets. 2 PRINCIPLE OF OPERATION The magnet under test is fixed to three support posts, which are anchored to the concrete floor of the test hall. Cryogenic and electric feeding is done through the magnet feed box of the CFU, connected to one end of the magnet, the opposite end of the CFU being closed by a magnet return box. As the magnetic measurement equipment only operates at ambient temperature, both magnet apertures are equipped with warm bore inserts, which bring a heat load of 25 W into the superfluid helium bath. The process flow diagram is presented in Figure 1. The main operation modes are as follows: 2.1 Magnet pre-cooling (300 K to 90 K) When all electric and hydraulic CFU/magnet connections are completed and tested, the vacuum space of CFU/magnet is pumped down and globally leak tested. As the cold mass is about 35 tonnes, the cooldown from 300 to 90 K is done by helium gas pre-cooled with liquid nitrogen in a dedicated heat exchanger, which is not part of the CFU. The cold helium gas at 10 bar enters the system at interface L1, passes through the phase separator and control valve FV165 before flowing through the magnet from the far end. The cold helium gas passes

the magnet before flowing through FV149 into the decanter, then the flow is split into two. The main flow goes through FCV177 while the rest passes through the CFU and the magnet thermal shields. Both flows join again and leave the CFU through interface L2 at about 2 bar. This flow splitting is controlled such as to pass the maximum possible flow through the thermal shield without limiting the required flow for a simultaneous coldmass cool-down. The maximum mass flow during the pre-cooling phase is 80 g/s; the maximum temperature difference between cooling gas and cold mass is 60 K. 2.2 Magnet cooling (90 K to 1.9 K) When the cold mass reaches 90 K, the helium gas cooling is stopped and the cooling continues with liquid helium through the same circuit. Liquid helium enters the system at interface L3 and leaves CFU through interface L4. Whenever a cold mass is filled with saturated liquid helium at 1.3 bar, the level in the phase separator and in all the current lead vessels is kept at the required value. In this phase a magnet can be operated at 4.5 K or it can be cooled further down to its working temperature of 1.9 K. For this purpose the CFU is equipped with a low-pressure circuit connected to a liquid/liquid heat exchanger (LLHX) built inside the magnet. Saturated helium at 1.3 bar passes through TCV145 which is the main impedance in this circuit and which controls the helium level inside the LLHX. The liquid helium is pre-cooled in a liquid/gas heat exchanger with cold low pressure gas which is pumped via PCV144 controlling the pressure in the LLHX. The pre-cooling liquid continues through an internal pipe to the opposite end of the LLHX, thermally coupled to the cold mass. The cold low-pressure gas leaves the CFU, passes the Very Low Pressure Heater [3] before entering the Warm Pumping Unit [4]. The maximum flow capacity of this circuit is 6 g/s at 10 mbar. The gas/liquid heat exchanger is of the perforated plate type [5]. 2.3 Magnet warm-up After the magnetic measurement campaign, the magnet is quenched and the heaters inside the decanter and in the phase separator will boil off the liquid helium. Any remaining liquid helium is evaporated by a small flow of gaseous helium. Once the liquid helium is evaporated, the magnet is warmed up to room temperature with a large (80g/s) flow of warm helium gas using the same circuit (via L1 and L2) as during the pre-cooling phase. 2.4 Magnet powering In order to power all magnet coils, the CFU is equipped with one pair of main 13 ka current leads, two pairs of 1 ka and two pairs of 0.6 ka auxiliary current leads. In order to minimize the number of cryogenic valves, flowmeters, control loops etc., the 4 pairs of auxiliary current leads are built as twins. The cold terminals of the main current leads are connected to terminals of the main coil by a double superconducting cable, partially stabilized with copper. This double cable is soldered to the cold current lead terminal and mechanically clamped to a magnet coil terminal. Cold terminals of the auxiliary current leads are connected to auxiliary coils via a copper stabilized superconducting cable soldered at both ends. Each current lead and bus-bar is designed to withstand 2 kv with resistance to ground better than 10 9 Ω in pure gaseous helium at 1 bar and ambient temperature. In addition, the main current leads withstand 5 kv with resistance to ground better than 10 9 Ω under cold conditions, when a cold mass is filled with liquid helium. The magnet coils are operating in pressurized superfluid helium at 1.9 K and 1 bar and all current leads are operating at saturated liquid helium at 4.5 K. Hence the two helium circuits are separated by socalled lambda plates. The key component of the lambda plate is the ceramic feedthrough that was specially developed for this purpose [6]. 2.5 Magnetic measurements and magnet training In order to validate the required maximum magnetic field, each magnet must pass magnetic measurements and quench training [7]. Quench is a transient mode of a superconducting coil when it looses its superconducting state, because of poor cooling or high current/magnetic field. During the quench the liquid helium around the coil vaporises and the pressure increases rapidly. A mixture of gas

and liquid helium passes through a quench discharge valve (FV149) into a decanter of about 400 litres volume. The gas leaves partially through the recovery line and partially through the lowpressure line (interface L4). The liquid helium remaining in the decanter is used for recooling the cold mass, which may have warmed up to 35 K during the quench. 3 CONTROL AND INSTRUMENTATION The CFU is fitted with 12 pressure and vacuum transmitters, 23 temperature sensors and 3 cold flow meters. Also each current lead incorporate 3 temperature sensors and a dedicated flow sensor with control valve. The complete CFU is controlled by an industrial PLC with remote input/output units using a Profibus interface. The PLC monitors all parameters and devices. The software is written such that the CFU can be operated with minimum operator interaction. Once a magnet has been connected and leak tested the control system will perform all warm tasks, like pumping and purging of helium and vacuum circuits, cooling down of the magnet through its 3 phases (pre-cooling, 4.5 K and 1.9 K cooling), automatic quench recovery and warm-up. The interface with the operator is using a separate SCADA software package called PCVUE. 4 TEST RESULTS The first CFU has been in operation for testing of two 15 m dipole magnet prototypes for 7 months. The system has handled more than 150 quenches. The second CFU has been commissioned and successfully tested at the end of 1999. The duration of a typical magnet test cycle with the CFU is at present as follows: Magnet installation: 5 days ; Vacuum pump down: 8 hours ; Cool-down: 30 hours at m = 80 g/s and dt = 60 K ; Magnetic measurements: about one month ; Quench recovery: 3 hours ; Warm-up: 50 hours at m = 80 g/s and dt = 60 K ; Dismantling: 5 days. In future the CFU/magnet interfaces will be modified and the gas flow and temperature difference between gas and magnet will be increased in order to shorten the global time of a magnet test. The total heat loads of CFU in a dummy configuration (without magnet) are shown in Table 1. Temperature level (K) Heat load at I = 0A (W) 1.9 9.1 ~ 10 4.3 27 ~ 45 50 48 48 Table 1 CFU Heat Loads : PCVUE is a registered Trade Mark of ARC Informatique France. REFERENCES Heat load at I = 13kA (W) 1. Lebrun, Ph., Superfluid Helium Cryogenics for the Large Hadron Collider Project at CERN, Cryogenics (1994) 34 1-8 2. Benda, V. et al, Cryogenic Benches for Superfluid Helium Testing of Full-Scale Prototype Superconducting Magnets for the CERN LHC Project, Cryogenics (1994) 34 733-736 3. Benda, V. et al, Electrical heater for very-low pressure helium gas, Proceedings, 4th International Conference Cryogenocs 96 (1996), Praha, Czech Republic, pp. 40-43. 4. Benda, V. et al, Cryogenic infrastructure for superfluid helium testing of LHC prototype superconducting magnets CEC, ICMC (1993), Albuquerque, USA. 5. Viargues, F. et al, Construction and Preliminary Testing of Perforated Plate Heat Exchanger for Use in Helium II Refrigerators, Cryogenics (1994),.34, ICEC Supplement, 325-328. 6. Benda, V. et al, Current feedthroughs for superconducting magnets operating below 2K, ICEC 17 (1998), pp.739-742. 7. Billan, J. et al, Manufacturing features and performances of long models and first prototype for the LHC project, EPAC 98 (1998), Stockholm, Sweden

Figure 1 The process flow diagram