COOPER POWER SERIES. 200 A 15, 25, and 35 KV class insulated standoff bushing installation instructions. Loadbreak Apparatus Connectors MN650039EN

Similar documents
COOPER POWER SERIES. 200 A 15, 25, and 35 kv class portable feedthru installation instructions. Loadbreak Apparatus Connectors MN650037EN

COOPER POWER SERIES. 600 Ampere Deadbreak Grounded Standoff Bushing 15 & 25 kv and 35 kv Class Installation Instructions. Bushings MN650045EN

COOPER POWER SERIES. 600 A 15, 25, and 35 kv class PUSH-OP bushing adapter cap installation instructions. Deadbreak Apparatus Connectors MN650050EN

COOPER POWER SERIES. 600 A 15, 25 and 35 kv class bushing adapter installation instructions. Deadbreak Apparatus Connectors MN650058EN

200 A, 15 and 25 kv class loadbreak bushing insert installation instructions

COOPER POWER SERIES. Series winding ratio test procedure instructions. Voltage Regulators MN225060EN. 120 Vac VOLTMETER

DT400/436 Tee Connector Installation Instructions

COOPER POWER SERIES. UltraSIL Polymer-Housed Distribution-Class MOV Surge Arrester Installation Instructions. Surge Arresters MN235006EN

COOPER POWER SERIES. D-73P3 bypass switches installation instructions. Switches MN008005EN. Effective April 2016 Supersedes S June 2013

COOPER POWER SERIES. EL Bay-O-Net Current-Limiting Fuse Installation Instructions. Fusing Equipment MN132023EN

Effective March 2015 Supersedes S August 2002

COOPER POWER SERIES. Manual or Hostick Operable, Padlockable 150 A Tap-Changer Switch Installation Instructions. Tap-Changer Switch MN800015EN

COOPER POWER SERIES. QD8 Quik-Drive tap-changer VR or VL reversing switch stationary contact assembly kit number A48 installation instructions

COOPER POWER SERIES. VariSTAR Storm Trapper high energy MOV arrester installation instructions. Surge Arresters MN235017EN

COOPER POWER SERIES. 600 A, 15, 25, and 35 kv Class Cleer Grounding Elbow Installation Instructions. Loadbreak Apparatus Connectors MN650056EN

COOPER POWER. SERIES VariSTAR type composite light-duty under-oil (CLU) MOV arrester installation instructions. Surge Arresters MN235023EN

COOPER POWER SERIES. 200 A 15/25 kv class deadbreak straight connector installation instructions. Deadbreak Apparatus Connectors MN650043EN

COOPER POWER SERIES. Under-oil arrester disconnector installation/operation instructions. OEM Equipment MN800010EN

COOPER POWER SERIES. 200 A 15/25 kv class elbow installation instructions. Deadbreak Apparatus Connectors MN650042EN

COOPER POWER SERIES. 50 A 2:1 series multiple (dual voltage) switch cap/wrench, lever or hotstick operable handles installation instructions

COOPER POWER SERIES. DS250 deadbreak straight connector installation instructions interface A. Connectors MN650027EN

COOPER POWER SERIES. UltraSIL polymer-housed VariSTAR surge arrester IEC for MV systems to 36 kv installation instructions

DAI630TB2669 Dead Front Arrester Installation Instruction

COOPER POWER SERIES. DE250 deadbreak elbow connector installation instructions interface A. Screened Separable Connectors MN650025EN

Effective May 2017 Supersedes July 2009 (S ) 600 A 35 kv Class T-OP II connector assembly installation instructions 200 A PROTECTIVE CAP LRTP

COOPER POWER SERIES. 600 A 35 kv class PUSH-OP deadbreak connector installation instructions. Deadbreak Apparatus Connectors MN650052EN

COOPER POWER SERIES. 200 A 35 kv class LE series elbow installation instructions. Loadbreak Apparatus Connectors MN650010EN

COOPER POWER SERIES. Operation Counter Replacement Instructions. Reclosers MN280047EN. Effective May 2016 Supersedes S December 2003

600 A 35 kv class PUSH-OP deadbreak connector installation instructions

COOPER POWER. SERIES VariSTAR type AZE station class surge arresters installation and maintenance instructions. Surge Arresters MN235022EN 0.

Effective January 2017 Supersedes July 2011 (I ) VariSTAR Type AZG4 Surge Arresters Installation and Maintenance Instructions

COOPER POWER SERIES. 200 A 15 and 25 kv class elbow with optional integral jacket seal installation instructions. Loadbreak Connectors MN650008EN

COOPER POWER SERIES. 200 A 15 and 25 kv class elbow with integral jacket seal* for use on tape and wire shielded cable installation instructions

COOPER POWER SERIES. VFI SF6-insulated vacuum fault interrupter installation, operation and maintenance instructions. Switchgear MN285004EN

COOPER POWER SERIES. Types E, 4E, V4E, H, 4H, V4H, L, and V4L single-phase recloser installation and operation instructions. Reclosers MN280051EN

S Surge Arresters

S Loadbreak Apparatus Connectors WARNING: WARNING:

Installation Instructions for the Walking Beam Interlock for Eaton EHD, FDB, FD, HFD, FDC, FW, HFW, FWC, Circuit Breakers and Molded Case Switches

Effective May 2017 Supersedes August 2005 (S )

Operation Manual Enabling Pole-Top Communication Via the TripSaver II Magnet Tool

Inspection Recommendations

Norrsken Family Booklet

DEH Instructions. Three-Phase, Platform-Mounted Distribution Transformers

Accu-Tab Systems 1000 Series by Axiall Corporation

Medium voltage standard-duty, heavyduty, and extreme-duty single-phase, unfused capacitor units and accessories

COOPER POWER SERIES. Type VFI, Fluid-insulated Switchgear; Installation, Operation and Maintenance Instructions

Accu-Tab Systems 2000 P Series by Axiall Corporation

NB/NBR NITROGEN BOOSTER FOR AVIATION SERVICE

Media-Isolated Mag Plus Probe Low Pressure-ISO Kit

S Surge Arresters. Handling and Storage. Standards. Acceptance and Initial Inspection

Acid- Rite ph Adjustment System 2500 by Axiall, a Westlake Company

USER MANUAL FLOW SELECTOR PM1000 SAVE THESE INSTRUCTIONS. Federal (USA) law restricts this device to sale by or on the order of a physician.

AWG Fittings LLC. Pressure Relief Valve Up to 250 PSI. Product Number Read this instruction manual before use.

SIX R (P ) AND SEVEN R (P ) POSITION CYLINDERS Service Information

Interface Devices, Inc. Hydraulic Mini Mule

Mini Pod Press. #78H-M2 Mini Pod Press Manual-R1

Operating Instructions for BAIR22-6 AIR-POWERED CRIMPING TOOL

This document to be used with Hurley traditional Davits

Permanent Roof Anchors

J Air and Water Kit Instructions Part# 02584

Installation, Operation and Maintenance Manual. TSV Temperature Shut-off Valve SPD Rev. 6 10/07

S Vacuum Switches. Contents. Type VCS-1 Single-Phase Vacuum Capacitor Switch Installation and Operation Instructions

D Series Air and Water Kit Part# 02550

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6

New AQF Filter Polymer Filtration System

INSTRUCTION MANUAL MP4AR Remote Convection Gauge Range: 1 x 10-3 Torr to 1 x 10+3 Torr

Pressure Relief Valve Instruction Manual

FLANGED TWO-PIECE BALL VALVES

Model ASSEMBLY and OPERATING INSTRUCTIONS

UE- 90- X X X X X X O P E R AT I N G M A N UA L 0 TO 90 HYDRAULIC UPENDER

Accu-Tab PowerBase 3012AT by Axiall Corporation

FLANGED TWO-PIECE BALL VALVES

U S E R M A N U A L CAUTION. SAVE THESE INSTRUCTIONS Federal (USA) law restricts this device to sale by or on the order of a physician.

92831 TEL: (714) FAX:

Wallmax Professional Aneroid Sphygmomanometer Model 222 User Manual

3M Liqui-Cel EXF-4x13 and 4x28 Series Membrane Contactors

INSTRUCTIONS FOR MODELS SG3897 AND SG3898 CROSS PURGE ASSEMBLIES

WATER HEATER THERMAL EXPANSION TANKS Owner s Manual. Safety Instructions Installation Maintenance Warranty. Models: 2-5 Gallon Capacity

CP-D/CP-M Circular Polarizer for Phoroptor. User s Guide

2000 lb manual winch

60 farm jack. Distributed exclusively by Harbor Freight Tools Mission Oaks Blvd., Camarillo, CA 93011

6 digital caliper with case

Instruction manual. Type Vector manual group-operated switch. Answers for infrastructure and cities.

TL-12 FLUSH TANK. Manual Ref. # MN-??? Polyurethane Machinery Corp. REVISION 1.0

Type Vector manual group-operated switch instruction manual. Installation operation maintenance E50001-F710-A420-X-4A00. Answers for energy.

6 & 8 Bubble Panel Installation Manual

U S E R M A N U A L AIR FLOWMETER. MODELS: 1MFA2001 (shown) 1MFA9001 CAUTION. ISO Certified

RGC-IR Remote Gas Calibrator for IR400

Accu-Tab PowerBase 3070AT by Axiall Corporation

INSTRUCTION MANUAL. Includes: OPERATION SETUP USE & CARE SERVICE. SPORTS ATTACK LLC

GETZ EQUIPMENT INNOVATORS PART NO.: 9G59554 MODEL: MS 36 SC-R HYDROSTATIC TEST PUMP

Instruction Manual. Model TC1-S TopSide Clamp. top side clamp. For your personal safety READ and UNDERSTAND instructions before using tools.

Cocoa Patio Pond with Lit Spillway

DEEPSEA. LED Micro SeaCam POWER & LIGHT. Operator s Manual. Original Instruction Ruffin Road San Diego, CA USA

CSA Sample Draw Aspirator Adapter Operator s Manual

4-in-1 Professional Inflator Kit

ULTRA HIGH PRESSURE PAINT GRATE CLEANER FCT-JS OPERATION AND MAINTENANCE MANUAL

Gemini Owner s Manual

Triple Tine Mechanical Grapple

ELECTRIC OPERATING PROCEDURES Date: 11/01/06

Transcription:

Loadbreak Apparatus Connectors MN650039EN Effective November 2016 Supersedes October 2013 (S500-22-1) COOPER POWER 200 A 15, 25, and 35 KV class insulated standoff bushing installation instructions SERIES

DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY The information, recommendations, descriptions and safety notations in this document are based on Eaton Corporation s ( Eaton ) experience and judgment and may not cover all contingencies. If further information is required, an Eaton sales office should be consulted. Sale of the product shown in this literature is subject to the terms and conditions outlined in appropriate Eaton selling policies or other contractual agreement between Eaton and the purchaser. THERE ARE NO UNDERSTANDINGS, AGREEMENTS, WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY, OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT BETWEEN THE PARTIES. ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON. THE CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES. In no event will Eaton be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or other-wise for any special, indirect, incidental or consequential damage or loss whatsoever, including but not limited to damage or loss of use of equipment, plant or power system, cost of capital, loss of power, additional expenses in the use of existing power facilities, or claims against the purchaser or user by its customers resulting from the use of the information, recommendations and descriptions contained herein. The information contained in this manual is subject to change without notice. INSTALLATION INSTRUCTIONS MN650039EN November 2016 i

Contents DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY... I SAFETY FOR LIFE... III SAFETY INFORMATION... III Safety instructions... iii PRODUCT INFORMATION.... 1 Introduction...1 Acceptance and initial inspection...1 Handling and storage...1 Quality standards................................................................................1 Equipment required...2 Tools required...2 INSTALLATION PROCEDURE.... 2 ii INSTALLATION INSTRUCTIONS MN650039EN November 2016

! SAFETY FOR LIFE Safety for life Eaton s Cooper Power series products meet or exceed all applicable industry standards relating to product safety. We actively promote safe practices in the use and maintenance of our products through our service literature, instructional training programs, and the continuous efforts of all Eaton employees involved in product design, manufacture, marketing, and service. We strongly urge that you always follow all locally approved safety procedures and safety instructions when working around high-voltage lines and equipment, and support our Safety For Life mission.! SAFETY FOR LIFE Safety information The instructions in this manual are not intended as a substitute for proper training or adequate experience in the safe operation of the equipment described. Only competent technicians who are familiar with this equipment should install, operate, and service it. A competent technician has these qualifications: Is thoroughly familiar with these instructions. Is trained in industry-accepted high and low-voltage safe operating practices and procedures. Is trained and authorized to energize, de-energize, clear, and ground power distribution equipment. Is trained in the care and use of protective equipment such as flash clothing, safety glasses, face shield, hard hat, rubber gloves, clampstick, hotstick, etc. Following is important safety information. For safe installation and operation of this equipment, be sure to read and understand all cautions and warnings. Hazard Statement Definitions This manual may contain four types of hazard statements: DANGER Indicates an imminently hazardous situation which, if not avoided, will result in death or serious injury. Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury. CAUTION Indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury. CAUTION Indicates a potentially hazardous situation which, if not avoided, may result in equipment damage only. Safety instructions Following are general caution and warning statements that apply to this equipment. Additional statements, related to specific tasks and procedures, are located throughout the manual. DANGER Hazardous voltage. Contact with hazardous voltage will cause death or severe personal injury. Follow all locally approved safety procedures when working around high- and low-voltage lines and equipment. G103.3 Before installing, operating, maintaining, or testing this equipment, carefully read and understand the contents of this manual. Improper operation, handling or maintenance can result in death, severe personal injury, and equipment damage. G101.0 This equipment is not intended to protect human life. Follow all locally approved procedures and safety practices when installing or operating this equipment. Failure to comply can result in death, severe personal injury and equipment damage. G102.1 Power distribution and transmission equipment must be properly selected for the intended application. It must be installed and serviced by competent personnel who have been trained and understand proper safety procedures. These instructions are written for such personnel and are not a substitute for adequate training and experience in safety procedures. Failure to properly select, install or maintain power distribution and transmission equipment can result in death, severe personal injury, and equipment damage. G122.3 INSTALLATION INSTRUCTIONS MN650039EN November 2016 iii

200 A 15, 25, and 35 kv class insulated standoff bushing installation instructions Product information Introduction Eaton s Cooper Power series 200 A Insulated Standoff Bushing A meets the full requirements of IEEE Std 386 standard - Separable Insulated Connector Systems and provides a single loadbreak interface made of high quality peroxide-cured EPDM rubber. It is used to isolate and sectionalize energized cable in pad-mounted cabinets, underground vaults, and other apparatus. Temporary or permanent parking of energized 200 A loadbreak elbow connectors that conform to IEEE Std 386 standard is simplified with use of the insulated standoff bushing. The insulated standoff bushing is designed to be installed in the parking stand mounted on a transformer or other apparatus. A grounding lug is provided on the standoff bushing bracket for attachment of a drain wire to ensure deadfront construction. When mated with a comparably rated product, the insulated standoff bushing provides a fully-shielded, submersible, separable connector for energized operation. Hazardous Voltage. All associated apparatus must be de-energized during any hands-on installation or maintenance. Failure to comply could result in death and severe personal injury. CAUTION The 200 A insulated standoff bushing is designed to be operated in accordance with normal safe operating procedures. These instructions are not intended to supersede or replace existing safety and operating procedures. Read this manual first Read and understand the contents of this manual and follow all locally approved procedures and safety practices before installing or operating this equipment. Additional information These instructions cannot cover all details or variations in the equipment, procedures, or process described nor provide directions for meeting every possible contingency during installation, operation, or maintenance. For additional information, contact your representative. Acceptance and initial inspection Each insulated standoff bushing is in good condition when accepted by the carrier for shipment. Upon receipt, inspect the shipping container for signs of damage. Unpack the insulated standoff bushing and inspect it thoroughly for damage incurred during shipment. If damage is discovered, file a claim with the carrier immediately. Handling and storage Be careful during handling and storage of the insulated standoff bushing to minimize the possibility of damage. If the insulated protective bushing is to be stored for any length of time prior to installation, provide a clean, dry storage area. Quality standards ISO 9001 Certified Quality Management System The insulated standoff bushing should be installed and serviced only by personnel familiar with good safety practices and the handling of high-voltage electrical equipment. 1 INSTALLATION INSTRUCTIONS MN650039EN November 2016

200 A 15, 25, and 35 kv class insulated standoff bushing installation instructions Equipment required Insulated Standoff Bushing Assembly Kit including: Insulated Standoff Bushing Instruction Sheet Tools required Hotstick Installation procedure Step 1. Clean and lubricate Remove protective shipping cap. Clean interface surface of standoff bushing and lubricate with lubricant (purchased separately). Step 2. Attach drain wire Attach copper drain wire (Minimum #14 AWG) from standoff bushing grounding lug to ground bus on apparatus. Step 3. Install standoff bushing Grasp the eyebolt on the standoff bushing with a hotstick. Using a hotstick, install the standoff bushing on the parking stand. Using a hotstick, turn the eyebolt clockwise to ensure rigid mounting. NNote: Step 4. Insulated standoff bushings are designed to fit standard standoff brackets furnished with most apparatus. Operating procedures Attach a hotstick into the pulling eye of the loadbreak elbow. Disconnect the elbow from the bushing, position the elbow probe into the standoff tap and push tightly onto the standoff bushing. Cover the energized bushing with a grounded insulated protective cap. NNote: Standoff bushings must be covered with an insulated protective cap when not in use to keep the interface clean. INSTALLATION INSTRUCTIONS MN650039EN November 2016 2

200 A 15, 25, and 35 kv class insulated standoff bushing installation instructions This page intentionally left blank. 3 INSTALLATION INSTRUCTIONS MN650039EN November 2016

! SAFETY FOR LIFE Eaton 1000 Eaton Boulevard Cleveland, OH 44122 United States Eaton.com Eaton s Power Systems Division 2300 Badger Drive Waukesha, WI 53188 United States Eaton.com/cooperpowerseries 2016 Eaton All Rights Reserved Printed in USA Publication No. MN650039EN Rev 0 (Supersedes S500221 Rev 0) November 2016 Eaton is a registered trademark. All trademarks are property of their respective owners. For Eaton's Cooper Power series product information call 1-877-277-4636 or visit: www.eaton.com/cooperpowerseries.