Tidal defences for Clevedon, North Somerset

Similar documents
Guidance Note. Hydropower Guidance Note: HGN 8 Fish Passage. When do you need to install a fish pass?

JAP Additional Information Sheet

Chiswell and Chesil Beach (to Wyke Narrows) 6a02 and 6a03 SUMMARY OF PREFERRED PLAN RECOMMENDATIONS AND JUSTIFICATION

Poole Bay, Poole Harbour and Wareham Flood and Coastal Erosion Risk Management. Final Strategy December Aerial photo credit: Kitchenham Ltd

Poole Harbour Aquatic Management Plan 2006

Pre-Application Document Kaweah Project (FERC Project No. 298)

What are National Parks?

THE RIVER LUNE. fact file NRA. National Rivers Authority North West Region

Waikanae River Environmental Strategy. 12. Arapawaiti/Otaihanga Reach

HISTORY OF CONSTRUCTION

7.Site Note Poders in Labutta Township Labutta North Polder Shansu Sluice Gate - Shansu sluice locates in Labutta (North) polder, it is about 1.5 km n

Fisheries newsletter. Wessex and Devon & Cornwall

Lincolnshire Walks. Grainthorpe. Three circular walks of 2 ¾, 9 and 9 ½ km (1 ¾, 5 ½ and 6 miles)

Harvey Dam. Dam Wall P CP. Lookout. Spillway. Intake Tower. Harvey River. Viewing Area. Key Buildings Stage Amphitheatre Gazebo

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

An Roinn Turasoireachta, lascaigh. agus Foraoiseachta THE IMPACT OF EEL FYKE NETTING ON OTHER FISHERIES

Venue Information - Access to the Greenway

MANERI DAM D/S VIEW. Er. SANDEEP SINGHAL Director (Projects) UJVN Limited, Dehradun, (UK)

Chapel Point to Anderby Creek

Fish population survey report

A guide to fisheries regulations ENVIRONMENT CORNWALL SEA FISHERIES COMMITTEE. WaW AGENCY

RESTORING THE CONNECTION BETWEEN CREEK AND LAKE: FRESH WATER ESTUARINE CREATION IN MISSISSAUGA

Components of a Barrage

Marine Ecosystems. Aquatic Ecosystems Section 2

Good Practice Guidelines

MESSOLOGI LAGOON AREA (GREECE)

Estuarine Shoreline Stabilization

Big Spring Creek Habitat Enhancement and Fishery Management Plans

Fifth otter survey of England

Marine Protected Areas (MPAs)

Lecture 10 : Sewer Appurtenances

Columbia Lake Dam Removal Project

LAKE TANEYCOMO 2011 ANNUAL LAKE REPORT

Our foundation introduce Nature and conservation in Lake Izunuma Uchinuma.

Bait collection and the law

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection

Tide Gate Modifications for Fish Passage and Water Quality Enhancement

The Railway from Pill Junction to Portishead in March 2015

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

Bathing Water Profile - Carne (2017)

THE DON DISTRICT SALMON FISHERY BOARD RIVER DON DRAFT GRAVEL MANAGEMENT PLAN NEWE DAM

Fish Ageing Survey Report The Gall Pond Our Ref: 14#194 Date:November 2014

Fish population survey report

VIDEO AUDIO Slide 1. Slide 2 Old timey 18 th century map of east coast

INFILTRATION PRACTICE MAINTENANCE INSPECTION FORM

United Kingdom names three Ramsar sites for World Wetlands Day

Tidal Energy from the Severn Estuary: Opportunities and Challenges

Draft report on one day visit to Brampton Bryan, R. Teme

Angling Trust East of England Fisheries Forum (Cambridge)

Coastal Processes Day Criccieth

You, your canoe and the environment

River Severn and Estuary

Part 9 Specific Land Uses - Foreshore & Waterway Development

Tunica Cutoff 2018 REEL FACTS Keith Meals Fisheries Biologist

Fish Ageing Survey Report The Gall Pond Our Ref:13#160 Date: 18/02/2014

GENERIC ENVIRONMENT RISK ASSESSMENT

Bathing Water Profile - Loughrea Lake (2013)

Walk 2: doniford to east quantoxhead

Crawford Reservoir. FISH SURVEY AND MANAGEMENT INFORMATION Eric Gardunio, Fish Biologist Montrose Service Center

Lincolnshire Walks. Ancaster. Three cir cular walks of2 3/4,4or 6km (11/3, 21/2 or 33/4 miles)

Nechako white sturgeon are an Endangered Species

Micro Hydropower and Fish.

Huntington District. For More Information Contact (304)

Shoreline Studies Program, Department of Physical Sciences, VIMS

WHAT ARE ECOSYSTEMS? Dr. V. N. Nayak Professor of Marine Biology (Retd)

Bay of Fundy Estuary Profile

Let s take a closer look at estuaries and learn why they are important.

Isar Plan in Munich,Bavaria Flood Protection, Restoration, Recreation

Maps The maps provided are a guide and are not to scale. Please use OS Explorer Map 120 (Chichester).

Fish population survey report

WATER LEVEL REGULATION

Stocking fish: A GUIDE FOR. fishery owners

FISH PASSAGE ALTERNATIVES ANALYSIS ON PENNYPACK CREEK AT VERREE ROAD DAM AND ROOSEVELT BOULEVARD DAM PHILADELPHIA, PENNSYLVANIA

Multi-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services

Downstream Migrant Trapping in Russian River Mainstem, Tributaries, and Estuary

NORTH SOMERSET LEVELS INTERNAL DRAINAGE BOARD LAND DRAINAGE ACT 1991 NOTICE TO FARMERS AND RIPARIAN OWNERS

Identifying Areas with Potential to Contain High Value Fish Habitat (HVFH) June 2007

M INEHEAD SEA DEFENCES SCHEME. the tempestuous tides

Design & Maintenance of Culverts

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

FISH PROTECTION STRUCTURES AND FISH PASSAGE FACILITIES. Toshio Hirose The honorary member of the Japan Society of Civil Engineers, Japan UNESCO EOLSS

New Brunswick Rainbow Trout Aquaculture Policy

Environmental Good Practice Guide: Guidance to help you maintain your watercourse

inc SIMON JACKSON Nature conservation Fact sheet 14

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering

INTRODUCTION TO COASTAL ENGINEERING

Chapter 1: Introduction

South East Wales Rivers Trust

IMPROVING THE SAFETY OF AN OLD AUSTRIAN DAM ABSTRACT

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

Feasibility and Planning Study

Upper/Lower Owl Creek Reservoir

Water Resources Report RKLD Annual Meeting July 30, 2016

Oceans Humans both depend on it and threaten it with their activities

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Storm Damage Floating Culverts & Other Inlet Issues

Blyth Estuary Green Travel Project

For more information or permission to reprint slides, please contact Donna Milligan at 1

Ocean Structures and Materials Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

The Study of Coastal Erosion on the Happisburgh Coast

Transcription:

Tidal defences for Clevedon, North Somerset

We are t\ your env and for fi Your envidrink anc- Governm environrr The Envir environm ENVIRONMENT AGENCY inform ation Services Unit Please return or renew this item by the due date Due Date look after B - for you, iter you ti business, iking your Published by: Environment Ag Manley House Kestrel Way Exeter EX2 7LQ Tel: 08708 506 506 Email: enquiries@environment-agency.gov.uk www.environment-agency.gov.uk Environment Agency All rights reserved. This document may be reproduced with prior permission of the Environment Agency. _

Blind Yeo sluice Clevedon Pill Marshall s Bank Land Yeo outfall Marshall's field River intake structure Three structures - the Land Yeo outfall, Blind Yeo sluice and Marshall s Bank - reduce the risk of flooding for more than 4,700 properties in Clevedon, North Somerset. All three - located on the edge of the Severn Estuary - have been significantly improved by the Environment Agency. This leaflet describes our work on the Land Yeo outfall and Marshall s Bank, carried out in 2005/2006, and the Blind Yeo sluice, carriedoulin 2004 ENVIRONMENT AGENCY II! 11 II J 102436 for Clevedon. North Somerset 3

background The Land Yeo drains mainly rural land upstream of Clevedon - including the low-lying Tickenham, Nailsea and Kenn Moors Site of Special Scientific Interest. When the M5 motorway was built in the 1970s the River Yeo was divided into two watercourses upstream of Clevedon - the Land Yeo and the manmade Blind Yeo. They are connected by the Yearling Ditch, which takes flow south from the Land Yeo to the Blind Yeo via a sluice at Cook s Clyse. The Land Yeo outfall - where the river discharges into the Severn Estuary - was an old masonry structure, thought to date back to the 1880s. Records show there has been an outfall structure at this location since medieval times. Marshall s Bank - a 500-metre long embankment that stretches between the Land Yeo outfall and the Blind Yeo sluice - also dates back to medieval times. Work took place in 1958 and 1984 to raise and strengthen the bank. The Blind Yeo sluice is not as historic as the other two tidal structures, but its purpose is no less significant. The sluice lies at the tidal outlet of the Blind Yeo, where it meets Clevedon Pill and the Severn Estuary. The sluice comprises two gates, known as the north and south eyes. The south eye dates from around 1952 and the north eye was added in the early 1970s to handle the extra water run-off from the M5. 4 Environment Agency Tidal defences for Clevedon. North Somerset

The problem The three tidal defence structures are located next to the Severn Estuary. The estuary has the second highest tidal range in the world. The most recent flooding happened in December 1981, when a large surge on a modest spring tide flooded 305 properties and land up to two kilometres from the sea. Since that time many hundreds of properties have been built in the tidal floodplain. Engineers found the previous Land Yeo outfall was in poor structural condition and nearing the end of its useful life. The outfall was also no longer watertight, did not control upstream water levels as required and did not meet health and safety requirements for operation and maintenance. Although Marshall s Bank was structurally stable, erosion and settlement had significantly reduced its height and width. In an extreme tidal event waves would overtop the low, narrow bank and cause further erosion and structural damage, and could eventually cause a breach of the defence. The Blind Yeo s north and south eyes - constructed of reinforced concrete - were in need of structural, mechanical and electrical refurbishment. The three tidal defence structures were only capable of preventing flooding from an extreme tidal event with a 1 in 25 (4 per cent) chance of happening in any one year. The Environment Agency s national target is to provide protection against a flood with a 1 in 100 to 1 in 300 (1 per cent - 0.33 per cent) chance of happening in any one year. In 2004 we carried out a 1 million project to refurbish the Blind Yeo sluice, and in 2005/2006 a 3.2 million scheme was completed on the Land Yeo outfall and Marshall s Bank. Environment Agency Tidal defences for Clevedon, North Somerset 5

construction work At the Land Yeo outfall we installed: tide flaps that prevent tidal flooding of the Land Yeo and Clevedon, but allow the river to discharge once the tide has receded powered automatic sluice gate (penstock) in case the tide flaps should block or fail a tilting weirto maintain water levels in the Land Yeo through Clevedon. This can be lowered to allow high river flows through the outfall water level monitoring equipment to allow automatic and remote control of the sluice gate (penstock) and tilting weir a trash screen to collect debris and prevent blockages to the new equipment vehicular and pedestrian access for maintenance purposes. Tidal headwall Winch beam and pullies Gabion mattresses and baskets Wing walls Clevedon Pill Tidal outfall structure 6 Environment Agency Tidal defences for Clevedon, North Somerset

Access ladders with safety lines Trash screen By pass High security double leaf gates Tilting weir Handrailing Elver pass Penstock and controls Downstream view of river intake structure Environment Agency Tidal defences for Cievedon, North Somerset 7

construction work continued Floodwalls were constructed around the outfall and linked with the higher ground at Wain s Hill to the west and Marshall s Bank to the east. The new walls were raised and faced with natural limestone and cock and hen coping to match the nearby boat store At Marshall s Bank we: raised 500 metres of the bank and surfaced its crest in crushed stone to minimise erosion and make a new footpath provided vehicular and pedestrian access for maintenance purposes A footpath runs along the crest of Marshall s Bank provided an access ramp - suitable for disabled access - onto the bank and into Marshall s Field. Local limestone was used to match existing boat store 8 Environment Agency Tidal defences for Clevedon. North Somerset

Telemetry kiosk Flood wall Penstock Tilting weir l mm i H ' Trash screen By pass chamber and penstock Weir plate Land Yeo river intake structure At the Blind Yeo sluice we: replaced major sections of the mechanical and electrical components of both eyes and refurbished the remaining elements installed remote water level monitoring equipment to provide better control of the sluice repaired the existing structure and access road newly equipped the control room and gave it an independent power supply addressed operational safety issues to bring it in line with modern health and safety regulations installed steel stoplogs to assist future maintenance replaced the outfall revetment to strengthen the bank against erosion from the sea improved public access across the structure. Environment Agency Tidal defences for Clevedon, North Somerset 9

the Severn Estuar The Severn Estuary is protected under both international and national law, reflecting the conservation importance of its habitats and species. It is designated as a Special Protection Area (SPA), a Ramsar site - a wetland of international importance - and a Site of Special Scientific Interest (SSSI). Its immense tidal range and its classic funnel shape make the estuary unique in Britain and rare worldwide. Its intertidal zone of mudflats, sandbanks, rocky platforms and saltmarsh is one of the largest and most important in Britain. The saltmarsh has a range of plant species such as glasswort, common cord grass, annual sea blite, corn parsley, common saltmarsh grass, sea club rush, sea clover, sea couch and sea milkwort. The mudflats support many important invertebrates, with high densities of lugworm and ragworm - an important food source for birds. These include internationally important populations of waterfowl including Bewick s swan, teal, ringed plover, dunlin, whimbrel and redshank. In late winter and early spring there are also nationally important populations of Shelduck and wigeon. Redshank Environmental considerations The boundary of the Severn Estuary SPA and SSSI lies at the base of Marshall s Bank. The new works were designed and built to avoid adverse impacts on the saltmarsh habitat. Construction activities were timed to reduce disturbance to waders and waterfowl and there was continued liaison with Natural England throughout the project. Where possible local materials were used in construction - hence local limestone was used around the Land Yeo outfall to match the local boat store. Numerous trees and shrubs were planted. 1 0 Environment Agency Tidal defences for Clevedon. North Somerset

Bewick s swan The area is very popular with dog walkers and birdwatchers. Throughout construction every effort was made to ensure access was maintained. Both the Land and Blind Yeo have healthy coarse fisheries - which include bream, roach, carp, gudgeon, perch and eel. Every summer the Blind Yeo sluice dams up water that maintains levels essential for livestock and farming. It also benefits coarse and eel fishermen and many types of flora and fauna. The works to the Land Yeo outfall will further enhance the habitat and amenity value of the Land Yeo upstream through Clevedon. The projects to improve Land Yeo outfall, Marshall s Bank and Blind Yeo sluice were funded by the Department for Environment, Food and Rural Affairs. Work on the Land Yeo and Marshall s Bank scheme was carried out by consultants Black and Veatch Ltd and contractors Carillion Regional Civil Engineering. Consultants for the Blind Yeo sluice project were Jacobs Babtie; the electrical and mechanical parts of the scheme were carried out by KPR Engineering Ltd and Avonmouth Ship Repairers and civil construction by Van Oord. Environment Agency Tidal defences for Clevedon, North Somerset 11

Would you like to find out more about us, or about your environment? Then call us on 08708 506 506 (Mon-Fri8-6) email enquiries@environment-agency.gov.uk or visit our website www.environment-agency.gov.uk incident hotline 0800 80 70 60 (24hrs) floodline 0845 9881188 Environment first: This publication is printed on paper made ^ W from 100 per cent previously used waste. By-products from making the pulp and paper are used for composting and fertiliser, for making cement and for generating energy. GESWl 206BLPG-E-P