COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

Similar documents
USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION

Steven A. Hughes. Ph.D., P.E. David R. Basco. Ph.D., P.E.

Plan B Dam Breach Assessment

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models

Design of Spillway Upgrades

EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2018

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam

AMEC010570_0001. Via . Mt. Polley Mine Tailings Facility Optimization Potential- Follow Up from Dam Safety Review 1.

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

TABLE OF CONTENTS EXECUTIVE SUMMARY 1

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering

Exercise (3): Open Channel Flow Rapidly Varied Flow

STRUCTURAL STABILITY ASSESSMENT

Technical Report Culvert A Hydraulic Analysis

Large-scale Field Test

Designing Labyrinth Spillways for Less than Ideal Conditions Real World Application of Laboratory Design Methods

NUMERICAL AND PHYSICAL MODELING

General Information for Culvert Design

WAVE OVERTOPPING AND RUBBLE MOUND STABILITY UNDER COMBINED LOADING OF WAVES AND CURRENT

MEMORANDUM. TNC Fisher Slough Final Design and Permitting Subject: DRAFT Technical Memorandum: Levee Emergency Spillway Design

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection

HISTORY OF CONSTRUCTION

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS.

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER

Stability of Concrete Macro-Roughness Linings for Overflow Protection of Earth Embankment Dams ( 1 ) - Discussion

LESOTHO HIGHLANDS DEVELOPMENT AUTHORITY

CHAPTER 4 SPALDING COUNTY, GEORGIA 4.0 CULVERT DESIGN

Chutes Part 2: Synthetic linings

Greenup Lock Filling and Emptying System Study

Indiana LTAP Road Scholar Core Course #10 Culvert Drainage. Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd.

Evaluation of June 9, 2014 Federal Emergency Management Agency Flood Insurance Study for Town of Weymouth, Norfolk, Co, MA

HYDRAULIC JUMP AND WEIR FLOW

Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update

Chapter 4 EM THE COASTAL ENGINEERING MANUAL (Part I) 1 August 2008 (Change 2) Table of Contents. Page. I-4-1. Background...

APPENDIX A STRUCTURE DESCRIPTIONS AND RATING CURVES

Spillway Design for Small Dams

OPERATION OF SPILLWAY GATES HOW TO AVOID THE PROBLEMS AND PITFALLS. Peter Allen. DERM Qld

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING

PENNDRAIN.rep. HEC-RAS Version May 2005 U.S. Army Corp of Engineers Hydrologic Engineering Center 609 Second Street Davis, California

Discussion on the Selection of the Recommended Fish Passage Design Discharge

Experimental Investigation on Changes of Water Surface Profile with Gaussian Shaped Bottom and Side Roughness

WAVE OVERTOPPING OF RUBBLE MOUND BREAKWATERS

Components of a Barrage

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

Innovative spillways. PK-weirs. Franska exempel 10/04/2018. Speaker : A. Chapuis,

Hydraulics of stepped spillways : current status

Stormwater Level of Service Study - Phase 2 Flooding Adjacent to Rock Creek

Section 5: Pond Outlets

APPENDIX J HYDROLOGY AND WATER QUALITY

Period of Record from No data was available from 1955 to 1962, but the remaining 57 years of data was available. 2

WMS 8.4 Tutorial Hydraulics and Floodplain Modeling HY-8 Modeling Wizard Learn how to model a culvert using HY-8 and WMS

STUDY ON TSUNAMI PROPAGATION INTO RIVERS

LABORATORY EXPERIMENTS ON WAVE OVERTOPPING OVER SMOOTH AND STEPPED GENTLE SLOPE SEAWALLS


TROUT CREEK WATERSHED (Second Year of Snowline Data)

Design and Installation of two Permanent Booms at La Romaine-2 to resist Ice, retain Debris and serve as Safety Booms.

LABORATORY EXPERIMENTS FOR WAVE RUN-UP ON THE TETRAPOD ARMOURED RUBBLE MOUND STRUCTURE WITH A STEEP FRONT SLOPE

ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM

Performance of RCC Used for Overtopping Protection and Spillways

Modelling of Pressurised Pipes within InfoWorks ICM and CS

VIRGINIA SOIL AND WATER CONSERVATION BOARD GUIDANCE DOCUMENT ON DAM BREAK INUNDATION ZONE AND INCREMENTAL DAMAGE ANALYSIS AND MAPPING PROCEDURES

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

CALCASIEU SALINITY STRUCTURES. HYDRODYNAMIC MODELING (To Support Design of Salinity Barriers)

TDLP INC. The Dam & Levee Professionals. Kevin Chancey Sarah Edens. Monica Murie Jason Unruh

Low-crested offshore breakwaters: a functional tool for beach management

Wave Overtopping of Seawalls. Design and Assessment Manual. HR Wallingford Ltd. February R&D Technical Report W178. R&D Technical Report W178

Water Research Laboratory (WRL), School of Civil and Environmental Engineering, UNSW Australia, Manly Vale, NSW 2

Five Counties Salmonid Conservation Program - Fish Passage Design Workshop. February 2013

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

OECS Regional Engineering Workshop September 29 October 3, 2014

3D NUMERICAL MODELLING OF THE CAPACITY FOR A PARTIALLY PRESSURIZED SPILLWAY

2. Water levels and wave conditions. 2.1 Introduction

PKWeir and flap gate spillway for the Gage II Dam

Huntington District. For More Information Contact (304)

HY-8 Version 7.2 Build Date January 17, Federal Highway Administration.

MODELING OF CLIMATE CHANGE IMPACTS ON COASTAL STRUCTURES - CONTRIBUTION TO THEIR RE-DESIGN

Appendix D: SWAN Wave Modelling

Boston s Pilot Project to Measure CSO Flows Relies on New Technology and Scattergraphs to Detect Overflows

AN INVESTIGATION OF LONGITUDINAL VENTILATION FOR SHORT ROAD TUNNELS WITH HIGH FIRE HRR

Water Storage for Agriculture

Wave surcharge on long narrow reservoirs- a reality check

Pier 8 Wave Overtopping Analysis (65 Guise Street East) Our File:

SECTION 2 HYDROLOGY AND FLOW REGIMES

Structure and discharge test cases

Stormwater Management Pond Design Brief. Greely Village Centre - Commercial Phase - Ultimate Conditions - - City of Ottawa -

Fortified For Safer Living

Broadly speaking, there are four different types of structures, each with its own particular function:

RE: Hurricane Matthew Beach Damage Assessment and Recommendations [CSE 2416]

STRUCTURE 65-B PURPOSE SPILLWAY OPERATION

SUBMERGED VENTURI FLUME. Tom Gill 1 Robert Einhellig 2 ABSTRACT

TRANSPORT OF NEARSHORE DREDGE MATERIAL BERMS

Technical Brief - Wave Uprush Analysis 129 South Street, Gananoque

TECHNICAL NOTE THROUGH KERBSIDE LANE UTILISATION AT SIGNALISED INTERSECTIONS

Scour Analysis at Seawall in Salurang, Sangihe Islands Regency, North Sulawesi

Transcription:

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION Abstract Lonie I * Tailings and Dams, GHD Brisbane, QLD, Australia Queensland Alumina Limited operates an alumina refinery located at Parsons Point, Gladstone, Central Queensland. Tailings from the refinery, commonly referred to as red mud, are deposited in two dams, RMD# and RMD#2, which have an area of approximately 4Ha and 6Ha respectively. Continued placement of red mud in RMD#2 had progressively reduced the volume available within the dam. Action needed to be taken to increase storage capacity (based upon water storage and mud storage capacity). Traditionally the volume would be created by raising the embankments, an expensive and time consuming process. An innovative solution was proposed to upgrade the spillway only and avoid the need to raise the embankment. A workshop was carried out with the stakeholders to assess different spillway options with consideration of spillway performance, downstream impacts, freeboard impact and embankment impacts. A.m high cast in-situ concrete labyrinth spillway, founded on the existing spillway and within the existing spillway walls, was adopted as the final solution. A risk assessment was carried out to verify the acceptability of the spillway raise in accordance with the Australian National Committee on Large Dams risk acceptance criteria. The solution gave an equivalent storage capacity to an embankment raise of approximately.9m. The project, including design and construction, was completed within 3 months and provided a cost effective solution for the capacity increase which was implemented before the 2/2 wet season. This paper presents the process used for evaluating the labyrinth spillway option including wind and wave overtopping evaluation, risk assessment, labyrinth weir design and the advantages and disadvantages of the solution. Notation and units Mt mega tons = x 6 t Mtpa - mega tons per annum. Introduction The Queensland Alumina Limited (QAL) red mud dams, referred to as RMD # and RMD #2 cover an area of approximately 4Ha and 6Ha respectively. Both dams are located on Boyne Island in Gladstone, approximately 8 km south of the refinery site at Parsons Point, Gladstone. The RMD #2 embankments comprise a zoned earthfill with sloping upstream clay core and rocky and clayey general fill downstream shoulder with filter as shown on Figure. The dam has been in operation since the 97 s and has been subjected to six downstream raises with the latest Stage 6 raising the embankment crest level to RL 22.m. On the upstream side of the embankments a rip rap protection layer is provided to protect against wave action. The downstream slopes of the embankments are protected by weathered coarse rockfill and slightly weathered high strength rockfill on the northern and eastern sides respectively. The downstream slope angles are approximately V:.8H. Figure RMD #2 Typical Embankment Section Figure RMD #2 Typical Embankment Section Proceedings of the 9th International Alumina Quality Workshop 22 287

The spillway existing prior to the upgrade comprised a 3m wide broad crested weir with a concrete lined chute and stilling basin. Downstream of the spillway is a series of gabion energy dissipation structures leading into a maze style polishing pond and eventual discharge into South Trees Inlet leading to the ocean. 2. The Situation Prior to Spillway Raise Red Mud production from the refinery is in the order of 3.4 Mtpa, which, is deposited in either RMD # or RMD #2. Over time continued placement within the RMD #2 decant pond has reduced the available rainfall storage capacity and in early 2 the available volume became less than that required for the design in 5 year storm event. This required volume is based on a daily outflow volume of 9,m3 and equates to approximately 5.5 Mm3. Figure 2 presents graphically the reduction in volume with time. Volume (Mm 3 ) 9 8 7 6 5 4 3 2 Oct-7 Apr-8 Oct-8 Apr-9 Oct-9 Apr- Oct- Date Figure 2 RMD #2 Available Rainfall Water Storage Volume This reducing rainfall water storage volume prompted the need to increase the storage capacity within the dam. Traditionally at QAL, the capacity increase would be achieved through raising the perimeter embankments with a spillway raise, however, for this project a series of options were developed which would allow QAL to keep operating RMD #2 by providing the required storage. 3. Options Developed The options developed for assessment comprised: No need to construct an additional spillway which reduces the complexity and time of construction Low cost solution compared with the embankment raising or spillway duplication and raising options 4. Labyrinth Spillway Design The hydraulic performance of the labyrinth weir design was assessed using Tullis et al. (995) and Falvey (22) and a discharge rating curve was developed for use in the hydrological assessment of flood rise giving the required wet freeboard. The rating curve is presented in Figure 3. The labyrinth weir geometry was optimised to maximise efficiency by minimising depth of water flow over the weir within the existing spillway width of 3 m and with a base level of R.L. 9.65m. The final design is shown in Figure 4 and comprised the design parameters shown in Table. Table Labyrinth Weir Design Parameters Design aspect No. Cycles 8 Cycle Width (w) 3.75 m Height (P). m Effective Crest Length (L) 29. m Existing Spillway width 3. m Value The hydrological assessment was carried out using rainfall totals for the in, Annual Exceedance Probability (AEP) design flood event. These were determined by interpolating between the in, and in 2, AEP rainfalls and the Probable Maximum Precipitation (PMP) rainfall as specified in Book VI of Australian Rainfall and Runoff: A Guide to Flood Estimation (999). The in, AEP design storm event was routed through the spillway using XP-RAFTS for storm durations ranging between 3 hours and 72 hours. The storage elevation curve was taken from decant pond bathymetry and aerial survey..9.8 9 8 Raising the embankment with a raise to the spillway crest Widening and raising the existing spillway to reduce the wet freeboard Raising the existing spillway and increasing efficiency with a labyrinth or piano key to reduce the wet freeboard Fuse Gate Option Head Over Labyrinth.7.6.5.4.3 7 6 5 4 3 Equivalent linear Cd The options were developed to a point to allow a comparison of basic material quantities which required hydraulic and hydrological design to confirm that the water capacity increase was sufficient to allow continued operation of the dam. The options were compared on the basis of: Increase in water storage capacity Design and construction time with respect to onset of the wet season Construction cost The labyrinth spillway was selected as the preferred option because of the low cost benefit ratio compared with the other options, this was due to: the relatively simple construction when compared to a piano key system which was meant existing, on-site, contractors were able to be used No need to raise the dam embankments reducing the required construction period.2. 2 4 6 8 Discharge (m³/s) Head Linear Cd Figure 3 Labyrinth Discharge Rating Curve and Equivalent Linear Coefficient of Discharge As a comparison between the efficiency labyrinth spillway and the broad crested weir, Figure 3 shows a linear equivalent coefficient of discharge (Linear Cd) which ranges from 7 at low discharge flows to approximately 5.2 at the peak outflow. This compares to a typical coefficient of discharge of.45 for a wide broad crested spillway. 2 288 Proceedings of the 9th International Alumina Quality Workshop 22

The peak outflow was calculated to be 59 m 3 /s which is lower than the broad crested weir outflow of 66 m 3 /s for which much of the downstream works was designed. This is due to the increased spillway length of 29 m compared to the previous spillway length of 3m meaning the spillway is able to discharge a greater volume of water earlier in the storm event leading to a lower peak. This meant that no alterations were required to the downstream outlet works. Figure 4 Schematic of Labyrinth Design 5. Wind and Wave Considerations The freeboard assessment was carried out using two previously adopted scenarios:, year ARI rainfall with a year ARI wind 5 year ARI rainfall with a 2 year ARI wind The wet freeboard levels were taken from: in 5 AEP flood based on the design requirement for the available water storage capacity within the decant pond to exceed the 5 year ARI rainfall volume in, AEP flood level from the spillway hydraulic analysis The maximum fetch adopted for the freeboard assessment was calculated to be 2.6km as shown on Figure 5. The calculation to determine the maximum fetch length were carried out using radials drawn at 3 intervals, 2 either side of a central radial (ie resulting in nine radials total).the average water depth across the maximum fetch was determined from bathymetric survey of the RMD #2 decant pond. Wind speeds were adopted from the Australian Standard Structural Design Actions, Part 2 Wind Actions, AS7.2:22, using Wind Region C and are: 2 year ARI wind speed 6m/s year ARI wind speed 39m/s Since the fetch and water depth varies around the dam perimeter the dry freeboard assessment was carried out at six locations (named A through F) each with a varying fetch and water depth. The highest total freeboard requirement was found to be for the 5 year ARI rainfall and the 2 year ARI wind. The results are presented in Table 2 with the site locations, and critical overtopping areas shown in Figure 5. Table 2 Freeboard Assessment Results, year ARI rainfall year ARI wind Site Flood Level (R.L. m) Fetch (km) Water Depth Wave Height Run-up Set-up Required freeboard (R.L. m) A - Dam E 2.65 2.63 3..76 2..44 23. B - Dam E 2.65 2.9 2.3.38.56.38 22.59 C- Dam A 2.65.66 4.25.4.6.2 22.46 D - Dam A 2.65.8 2..2.44.45 22.54 E and F - limit of decant water 2.65 2.3.5.9.24.7 22.6 Proceedings of the 9th International Alumina Quality Workshop 22 289

The discharge resulting from overtopping of the embankment by waves was estimated using the methods given in USACE (22). Overtopping occurs when the run-up exceeds the freeboard above the still water level (SWL). For these analyses, the SWL was defined by the peak flood level. The discharge calculated is an average value (temporally and spatially) and is dependent on the wave characteristics and the freeboard. The method adopted was that proposed by Owen (included in USACE (22)) which is relevant to embankments which are: Impermeable Smooth or rough Straight-sloped or bermed Figure 5 RMD #2 Fetch Locations and Critical Overtopping Areas The maximum required freeboard was calculated to be R.L. 23. m at site A which is located beside the spillway on dam E. This exceeds the safety bund level of R.L. 22.5 m and, therefore, further assessment was carried out to assess the risk of embankment failure due to overtopping flows from wave action. Allowable average overtopping discharges are given in USACE (22) and reproduced on Figure 6. The figure shows that damage to an embankment is likely to commence at overtopping flows of between about 2 l/s/m and l/s/m (.2 m3/s/m and. m3/ s/m). The downstream slopes of the embankments are generally gravelly fill, which has a high resistance to erosion and erosion is likely to initiate for flows in excess of l/s/m. 2 to l/s/m Figure 6 USACE CEM, Critical Values of Overtopping Discharge 29 Proceedings of the 9th International Alumina Quality Workshop 22

Table 3 presents the results of the wave overtopping assessment, the critical scenario in all cases was the in 5 AEP flood with a 2 year wind ARI. Table 3 Wave Overtopping Assessment Results Site Flood ARI (Years) Wind ARI (Years) Fetch (km) Wave Height Run-up Set-up Overtopping Flow (l/s/m) Crest Bund A - Dam E 5 2 2.63.76 2..44 9..8 B - Dam E 5 2 2.9.38.56.38.7.2 C- Dam A 5 2.66.4.6.2 2..3 C- Dam A,.66..7..4. D - Dam A 5 2.8.2.44.45.. E and F - limit of decant water 5 2 2.3.9.24.7.3. The risk assessment found that, in all cases, the overtopping flows over the 5 mm safety bund are small in relation to the lowest damage level and the likelihood of breaching through the bunds was, therefore, considered to be low. Further analysis showed that the expected discharge velocities are well below the velocities likely to initiate erosion of the crest or downstream face of the embankment. On this basis it was considered that the risk of damage due to overtopping by wave action with the existing.5 m high bund is minimal and additional bund height was not necessary for the raised spillway design. 6. Storage Capacity Increase By providing a.m high raise to the spillway level, additional storage of 4. Mm 3 was realised, comprising: Table 4 Additional Storage Decant Water Storage below Spillway Level 4. 5 year rainfall storage.3 Additional Red Mud Storage below Spillway Level 2.7 Volume (Mm 3 ) The additional red mud storage beneath the spillway level allows further storage above the spillway level since only part of the discharged mud reaches the decant pond, the rest being deposited on the mud beaches. From the bathymetry and aerial survey, the overall increase in mud storage (on the mud beach and within the decant pond) is estimated to be 5.4 Mm 3 which is approximately equivalent to a.9 m embankment raise over the 6 Ha dam surface area. 7. Conclusions This project allowed QAL to increase their water and mud storage capacity through increasing the efficiency and height of the spillway. This was achieved through designing a labyrinth spillway to be installed on the existing spillway crest together with a rigorous assessment of the impact of wind and wave action within the decant water pond to confirm the acceptability of the approach. QAL have received a cost effective solution to a common problem within the alumina industry, implemented in fraction of the time and for a fraction of the cost of using a traditional embankment raise approach. 8. Acknowledgements I would like to acknowledge Queensland Alumina Limited for their permission to present this paper. References Falvey, H.T., 22, Hydraulic Design of Labyrinth Spillways, ASCE Press, Reston, Virginia. Tullis, J.P., Amanian, N. & Waldron, D., 995, Design of Labyrinth Spillways in J. Hyd. Eng., vol 2, no 3, pp 247-255, ASCE. United States Army Corps Of Engineers (USACE), 22, Coastal Engineering Manual, Engineer Manual EM--2-, USACE, Washington, D.C (in 6 volumes). Proceedings of the 9th International Alumina Quality Workshop 22 29