FINAL FACILITY STUDY. KV1C Transformer Addition at Badwater Substation 2009-T1. November 17, 2009

Similar documents
Connection Engineering Study Report for AUC Application: Fortis Okotoks 678S and High River 65S Upgrades

STCP 01-1 Issue 005 Operational Switching

STCP 08-2 Issue 004: Circuit Live Trip & DAR Tests

Questions & Answers About the Operate within Operate within IROLs Standard

STCP 01-1 Issue 008 Operational Switching

Interconnection Feasibility Study Report Request # BHCT-G5

Power Supply Facilities Failure (Units 3-4 Temporary M/C (A), etc.) March 22, 2013 Tokyo Electric Power Company

PSSI 1 High Voltage Switching

i) Filtration machine, measuring equipment and other related machinery

Kodiak Electric Renewable Energy Implementation. Colin Young System Engineer 4/26/2016

System Impact Study 2008 T1 Kelim Load at Airport Substation

System Operating Limit Definition and Exceedance Clarification

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS

Power Unit 075. Maintain Substation Circuit Breakers

Infrared Thermography Inspection Guidelines. Date Issued:

2018 & 2022 Final LCR Study Results LA Basin and San Diego-Imperial Valley Areas

Why do I need to do an Arc-Flash Analysis?

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS

23.1 Functions, Basic Configuration, and Interfaces

------CHUG POWERING ALASKA'S futulle

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

Electrical Safety Program

Schedule of Quantity and Rate for Annual Maintenance Rate Contract for Electrical Jobs for the year (Section-F) Cleaning Jobs.

ICM Project Underground Infrastructure and Cable

System Operating Limit Definition and Exceedance Clarification

COOPER POWER SERIES. EL Bay-O-Net Current-Limiting Fuse Installation Instructions. Fusing Equipment MN132023EN

COOPER POWER SERIES. 200 A 15, 25, and 35 KV class insulated standoff bushing installation instructions. Loadbreak Apparatus Connectors MN650039EN

Con Edison, Inc. New York, NY March 11, Shields & Company Berenson & Company Transmission Seminar

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Stadium electricity supplies an assessment of the specification and readiness 2010 FIFA SOCCER WORLD CUP

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National

COOPER POWER SERIES. 600 A 15, 25, and 35 kv class PUSH-OP bushing adapter cap installation instructions. Deadbreak Apparatus Connectors MN650050EN

COOPER POWER SERIES. Under-oil arrester disconnector installation/operation instructions. OEM Equipment MN800010EN

Recent changes in workplace safety regulations have heightened the awareness of hazards associated with electrical arcs.

Safe Schools: A Health and Safety Check

: Electric Power Generation, Transmission, and Distribution. Region IV - OSHA

POW ER EN GIN EER S, LLC Electrical Engineering, Power, Lighting, Technical Studies and Utility Consulting

" High Voltage Switch Yards & How Safe are these really" <Peter Rhodes> <Principal and High Voltage Solution. Com Ltd>

Selection of Electrical PPE Tables

SERTP - 1 st Quarter Meeting

2017 NWHA TECHNICAL SEMINAR. Arc Flash Hazard Awareness MIKE BRENDLE LLC

2016 Electric Resource Plan Modeling Assumptions Update

Appendix A: Energized Work Permit

COOPER POWER SERIES. Manual or Hostick Operable, Padlockable 150 A Tap-Changer Switch Installation Instructions. Tap-Changer Switch MN800015EN

DEH Instructions. Three-Phase, Platform-Mounted Distribution Transformers

MINUTES OF MEETING BUSHING SUBCOMMITTEE OF THE IEEE/PES TRANSFORMER COMMITTEE MINNEAPLOS, MN OCT 17, 2007

COOPER POWER SERIES. 200 A 15, 25, and 35 kv class portable feedthru installation instructions. Loadbreak Apparatus Connectors MN650037EN

OPERATING CODE NO. 8 APPENDIX 2

Project Single Points of Failure

Innovative Techniques for Mitigating Arc Flash Exposure

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM

DOCUMENT CONTROL. Name: Mark Van Vuuren Position: Field Practices Coordinator Date: June 2014

Comments of the California Energy Storage Alliance (CESA) On Storage as a Transmission Asset (SATA) Straw Proposal

Hazardous Energy Control (Lockout-Tagout)

The Statkraft Way. Switching Supervisor

ATTACHMENT 2 REQUIREMENTS MILLE LACS ENERGY COOPERATIVE S SCHEDULE 3 DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS.

Nordel GRID DISTURBANCE AND FAULT STATISTICS

SAFETY QUALITY TECHNOLOGY. Guidance on Safe Isolation Procedures

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2014

COOPER POWER SERIES. 600 Ampere Deadbreak Grounded Standoff Bushing 15 & 25 kv and 35 kv Class Installation Instructions. Bushings MN650045EN

NORTHERN POWERGRID. Distribution Safety Rules 2015 Edition

2013 Special Reliability Assessment: Accommodating an Increased Dependence on Natural Gas for Electric Power

USER S MANUAL BASIC HORIZONTAL OIL-LUBRICATED MICROCOMPRESSOR Reference: RCMPBH

Field Instruction. 2.6 Worksite Clothing - Personal Protective Equipment (PPE) Requirements

Arc Flash 101. presented by Arc Flash Blaster LLC

IWU PHYSICAL PLANT SAFETY PROGRAM. Revision: 1 ELECTRICAL SAFETY Section: 4

TESTIMONY OF ROBERT C. KOTT ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

Lockout / Tagout Safety Program

Field Instruction. 2.6 Worksite Clothing - Personal Protective Equipment (PPE) Requirements

STCP Amendment Proposal Form

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Electrical Safety. Hazard Awareness

URC Voltage Sensor SEN-VOLT for use with MRX units containing sensor ports

HEALTH TECHNICAL MEMORANDUM Authorised persons logbook STATUS IN WALES APPLIES

COOPER POWER SERIES. VariSTAR Storm Trapper high energy MOV arrester installation instructions. Surge Arresters MN235017EN

INSTRUCTIONS FOR COMPLETING FORM H-9 STATEWIDE RULE 36 CERTIFICATE OF COMPLIANCE

Installation, Operation and Maintenance Instructions for Electronically Controlled Pressurisation Units

Project Budget and Schedule Status

Power System Safety Rules. Revision

APPENDIX Region 6 Inland Area Contingency Plan Compliance with Section 7 of the Endangered Species Act

Meeting Notes Project Definition of Bulk Electric System Standard Drafting Team

Operating Process Work on Low Voltage or Mechanical Apparatus

2014 RNA: Preliminary Results

200 A, 15 and 25 kv class loadbreak bushing insert installation instructions

Golden Rule #8: Equipment Safeguarding

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A.

Monitoring of Real-Time SOL and IROL Exceedances

Lockout/Energy Control

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Effective March 2015 Supersedes S August 2002

COOPER POWER SERIES. D-73P3 bypass switches installation instructions. Switches MN008005EN. Effective April 2016 Supersedes S June 2013

All TSOs of the Nordic Capacity Calculation Region Proposal for fallback procedures in accordance with Article 44 of Commission Regulation (EU)

C&G 2395 Exam Paper June Section A-All questions carry equal marks. Answer all three questions. Show all calculations.

Preparer: Owner: Approver: EHS Team Member TES Manager Site Manager

DT400/436 Tee Connector Installation Instructions

Status Date Prepared Reviewed Endorsed Approved

Scope of Work for Traffic Signal and Interconnect Design Services for Santa Rosa Road

Monitoring of Real-Time SOL and IROL Exceedances

Transcription:

FINAL FACILITY STUDY KV1C Transformer Addition at Badwater Substation 2009-T1 November 17, 2009

I. Introduction In October 2008, Western Area Power Administration (Western) received a Transmission Queue Request 2009-T1. On August 21, 2009, Western, the Customer, and the Customer s Member altered the scope of the Badwater Substation Transformer Addition Project. The proposed transformer rating increased from 50 MVA to 83 MVA. This modification is for additional loads, a future compression station and CO2 plant, to be served from the Badwater Substation. Badwater Substation resides in Fremont County, Wyoming and is presently owned, operated and maintained by Western. The new 69-kV loads will be served by modification and equipment additions in the Badwater Substation. Currently, the Badwater Substation has two 230/69/13.8-kV transformers: Transformer KV1A (18/24/30 MVA Western owned) and KV1B (30/40/50 MVA Customer owned). The Customer s Member requests replacement of KV1A with a third transformer which will be designated, KV1C. The in-service date for KV1C is expected to be within first calendar quarter of 2011. The rating of KV1C will be 50/67/83 MVA. The Customer s Member forecasts 23 MW of load, in addition to the existing 47 MW of load. The combination of the existing and new load gives a total of 70 MW load being served by Badwater Substation. Portions of the two existing 69-kV transmission lines serving Lost Cabin Gas Plant Phase III substation and Lost Cabin Gas Plant 1 & 2 may be rebuilt by the Customer s Member. The transmission line rebuild is not a part of this facility study or the Badwater Substation project. In October 2009, Western performed a second System Impact Study (SIS) to determine if there are any system criteria violations on the Wyoming power grid caused by the proposed 23 MW of additional load. The requested load increase presents no operating violations to voltages at Western s Badwater 230 kv bus 1. A switchyard expansion is not anticipated for this additional transformer and ancillary equipment. Modifications to the oil detention basin, part of the spill containment plan, may be modified as KV1C information becomes available. II. Project Description 230-kV Work: The addition of transformer KV1C at Badwater Substation will include, but is not limited to the construction of a new 230-kV transformer bus structure, additions and modifications of the 230-kV bus, a 230-kV interrupter with one fused disconnect switch, installation of associated instrument transformers, and associated protection and control equipment. 1 WAPA RMR Planning Engineering, " System Impact Study 2009-T1 Transformer Replacement at Badwater Substation," (October 2009): p.5. Page 1 of 5

69-kV Work: The addition of transformer KV1C at Badwater Substation will include, but not limited to additions and modifications to the 69-kV transformer bus structure, disconnect switch, associated protection, control equipment and boundary metering. (see Attachment A). The substation station service, currently served by the tertiary of KV1A, will be served by the KV1C tertiary. Transformer KV1C Work: Provision of a foundation, a metering structure for CT s, PT s, revenue metering, miscellaneous control cable and station service power through the cable trench. Operational Understanding: Construct the addition of transformer KV1C in such a manner that transformer KV1A remains in service until the cut over to transformer KV1C. Once transformer KV1C is energized, Western will decide whether to leave transformer KV1A in place as a backup or remove for use at another substation. (See Attachment B) III. Western s Requirements Western will provide project management, field data, design, construction contract administration, construction inspection, commissioning, lands, contracts, environmental and station equipment and installation of transformer KV1C and related equipment for the installation at Badwater Substation. The Customer will provide and install the 69-kV revenue metering for the new transformer. The Customer s Member will purchase the transformer KV1C at their cost. Western will install and commission KV1C. An agreement between Western and the Customer s Member will be required. Western will require funds equal to the estimated cost of the project scope as defined in Table 2 prior to the commencement of work. Western s project scope as described above will be confined to that work directly related to the Badwater Substation. All other work outside of the Badwater Substation including any construction or modification of additional 69kV transmission lines and distribution substations to serve the additional load will be the responsibility of the Customer s Member. Page 2 of 5

IV. Schedule The following preliminary project schedule is based on a one year manufacture and delivery time for transformer KV1C. The following schedule does not include delays due to not being able to take necessary outages to perform construction work when required. Please refer to Table 1. Table 1 Preliminary Project Schedule Activity Start Completion Facility Agreement August 2009 October 2009 Agreement Development October 2009 December 2009 Agreement Execution January 2010 Receipt of Funds January 2010 Planning/Field Data January 2010 March 2010 Design and Specifications February 2010 May 2010 Equipment Purchase/Manufacture/Delivery February 2010 April 2011 Construction Contract Development June 2010 July 2010 Award Construction Contract August 2010 Construction September 2010 March 2011 Commissioning March 2011 May 2011 In Service May 2011 Page 3 of 5

V. Cost Western s estimated cost for the addition of power transformer (KV1C) at Western s Badwater Substation is $2,630,000. Please refer to Table 2 for a cost estimate breakdown. This budgetary cost estimate includes project management, field data, design, construction inspection, construction, commissioning, lands, contracts, environmental, station equipment and 69-kV revenue metering for the addition of a new 230/69kV, 83 MVA power transformer (KV1C) at Western s Badwater Substation. Table 2 Badwater Substation Addition of 230/69kV, 83 MVA Transformer Cost Estimate TASK DESCRIPTION COST Project Management $25,000 Field Data $20,000 Design $225,000 Construction Inspection $155,000 Construction Contract $866,000 Commissioning $100,000 Miscellaneous 10% (Contingency) $139,100 Inflation(3%/year and late 2010 award = 4.5% $62,595 TOTAL: $1,592,695 Note: Cost in Table 2 does not include cost of the customer provided transformer KV1C or revenue metering equipment. Page 4 of 5

ATTACHMENT A Proposed Switching Diagram for Badwater Substation

ATTACHMENT B Proposed Arrangement Plan for Badwater Substation