Lecture 8&9: Construction Dewatering

Similar documents
Construction Dewatering

ATCE-II. Construction Dewatering. Advanced Topics in Civil Engineering Construction Dewatering. Professor Kamran M. Nemati Second Semester

An Introduction to Deep Foundations

DIRECTIONAL DRILLING

W I L D W E L L C O N T R O L FLUIDS

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

3. Types of foundation

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT

Item 404 Driving Piling

Special Provision No. 903S01 November OPSS 903, December 1983, Construction Specification for Piling is deleted and replaced with the following:

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS

TYPES OF FOUNDATION. Superstructure. Substructure. Foundation

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines.

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE

Design Data 22M. Flotation of Circular Concrete Pipe. w w I = w - x 1000 (3) (SG x 1000)

CHAPTER 5: VACUUM TEST WITH VERTICAL DRAINS

SPECIFICATION FOR CAISSON CONSTRUCTION

Septic Tank Buoyancy Control 101. David Lentz, P.E.

Division of Environmental Quality Wellhead Protection Section

Chapter 10 SWIMMING POOLS

APPENDIX A1 - Drilling and completion work programme

Department of Civil & Geological Engineering GEOE Engineering Geology

Water Storage for Agriculture

LAKOS Waterworks. PWC Series Sand Separators. Installation & Operation Manual LS-829 (10/12)

TAO Safety Policy No. HS-5.1 Page 1 of 15 Revision No. 2 Revision Date: July 19, 2005

AUTOMATED MONITORING EQUIPMENT FOR ACIP AND DD PILES

RESISTANCE OF COMPACTED ASPHALT MIXTURE TO MOISTURE INDUCED DAMAGE (Kansas Test Method KT-56)

TACKLING JACK-UP RIG NO-GO LOCATIONS. Prakasha Kuppalli ABSTRACT

CONE PENETRATION TESTS

Perched Box Caisson Overview. January 2014

Inflatable Packer Single & Double. Single & Double Packer Dimension. Wireline Packer. Water Testing Packer (WTP) Packer

GROUND IMPROVEMENT USING RAPID IMPACT COMPACTION

1 Exam Prep NSF/ANSI Tabs and Highlights

TECHNICAL MEMORANDUM 002 EMORANNO. 001

Annex E Bridge Pier Protection Plan

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

TECHNICAL BENEFITS OF CJS / RAISE HSP. Technical Advantages

UNIT-I SOIL EXPLORATION

Perforation Design for Well Stimulation. R. D. Barree Barree & Associates LLC

Guidance on piling, heavy loads, excavations, tunnelling and dewatering

TECHNICAL SPECIFICATIONS SECANT CAISSON WALL TECHNICAL SPECIFICATIONS. October 19, Nanaimo Colliery Dam Auxiliary Spillway, Nanaimo, BC

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)

Equipment Productivity

Casing Design. Casing Design. By Dr. Khaled El-shreef

22. Specialty Valves.

Well PGE-6 Decommissioning Evaluation PG&E Topock Compressor Station

Siting and Installation Manual

Swimming Pool Requirements

APPENDIX M Groundwater Monitoring Well Decommissioning Specifications

ROCKDALE COUNTY NEW SWIMMING POOL PLAN REVIEW

WATER TREATMENT SYSTEM OPERATION MANUAL

Chapter 8: Reservoir Mechanics

Sample Project with EPB TBM according to DIN 4085

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers.

SOIL ANCHORS ETSAB/UPC J.Llorens - ETSAB/UPC PASSIVE ANCHORS - ANTECEDENTS

SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE

GOM Diving Safety Work Group

Introduction. Geomembrane lining systems are used in a variety of different applications. Landfill Lining Landfill Capping Salt Piles Lagoons / Ponds

Protectingpipelinesfor

Float Equipment TYPE 925/926

Understanding pressure and pressure

Evaluation of the function of Vertical drains.

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1

Aeration of Dugouts or Ponds with Compressed Air

Ocean Motion Notes. Chapter 13 & 14

Desaturating sand deposit by air injection for reducing liquefaction potential

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Innovating Gas-Lift for Life of Well Artificial Lift Solution. The Unconventional Solution!

icon i150 / i350 Installation / Operation Manual

EMERGENCY CORE COOLING SYSTEM SIMPLIFICATION

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY

Introduction of world construction methods and trends. Franz-Werner Gerressen, Head of Method Development, Tokyo,

Blue Points 1 ¼ WELL POINT INSTALLATION INSTRUCTIONS

CAISSONS SECTION Section CAISSONS. Part 1-GENERAL

Office Use Only Fee Paid

STRUCTURAL STABILITY ASSESSMENT

Lecture Outline Chapter 15. Physics, 4 th Edition James S. Walker. Copyright 2010 Pearson Education, Inc.

Vacutrans Instructions

Attachment 6. HDD Feasibility Report

RIGID RISERS FOR TANKER FPSOs

Dri-Line Mk3 Monnier Compressed Air Drain Trap

Consult with manufacturers concerning permeation of the pipe walls, jointing materials, valve seats, etc.

CONSTRUCTION SPECIFICATION FOR PILING

CIVE 554/650. Geotechnical Engineering. Rock. Soil. Water. Site Investigation Techniques. CIVE Knight 1. 1/8/2006 CIVE Knight 1

SPEED SHORE MANUFACTURER S TABULATED DATA "MHS" MODELS. STEEL MANHOLE SHIELDS 4 Single Wall 4 Double Wall 4 Double Wall with Cut-Outs

ROTAMAT Rotary Drum Fine Screen Ro 2 / RPPS

HCMTCB MATERIALS SAMPLING & TESTING PERFORMANCE CHECKLIST

Step 1. PLANNING FOR THE INSTALLATION TOOLS REQUIRED

GWINNETT COUNTY SWIMMING POOL PLAN REVIEW CHECKLIST

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

Coal and Water Protection. PADEP: Well Plugging & Subsurface Activities Division Bureau of Oil and Gas Planning & Program Management

METHOD 2E - DETERMINATION OF LANDFILL GAS PRODUCTION FLOW RATE. NOTE: This method does not include all of the

Squeeze Cementing. Brett W. Williams Cementing Technical Advisor January 2016 Tulsa API Meeting

FP McCann Tunnels and Shafts 1

Dec 6 3:08 PM. Density. Over the last two periods we discussed/observed the concept of density. What have we learned?

Texas Administrative Code

Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer 1

Transcription:

Arab Academy for Science, Technology & Maritime Transport Colleague of Engineering & Technology Construction & Building Engineering CB 523 Methods and Equipment for Construction 1 Lecture 8&9: Construction Dewatering Instructor: Dr. Ahmed Elyamany Courtesy of Dr. Ahmed Alhakeem & Dr. Ahmed Alhady

Overview Soil dewatering means the removal of water from the soil. Construction dewatering means Control of the subsurface and surface water environment in order to allow construction to proceed. Techniques for dealing with the problems that result depend on the excavation dimensions, soiltype, groundwater control requirements 2

Overview The simplest dewatering operations are carried out with little planning. Major operations in difficult conditions require advanced engineering and construction methods. (An aquifer is a permeable geological stratum or formation that can both store and transmit water in significant quantities). 3

Introduction Construction dewatering can become a costly issue if overlooked during project planning. In most contracts, dewatering is the responsibility of the contractor. The contractor selects the dewatering method and is responsible for its design and operation. The purpose of construction dewatering is to control the surface and subsurface hydrologic environment in suchawayastopermitthestructuretobeconstructed in the dry. 4

Introduction If ground water issues are addressed appropriately at the investigation and design stage, construction dewatering is rarely a problem. Construction dewatering has existed as a specialty industry for a long time. Consequently, a number of well-established techniques have been developed to lower the ground water table during excavation. The geology, ground water conditions, and type of excavation all influence the selection of dewatering technology. 5

Introduction The most common methods for dewatering include sumps, wells and wellpoints. Sumps provide localized, very shallow dewatering (less than 3 feet) and consist of pumping from perforated drums or casings in a gravel-filled backhoe pit. Sumps work best in tight, fine grained soils, or very coarse, bouldery deposits. 6

Introduction Wells are large-diameter (greater than 6 inches) holes, drilled relatively deep(greater than 10 feet), and contain slotted casings and downhole pumps. Wells work best in soils consisting of sand, or sand and gravel mixtures, and can dewater large areas to great depths. 7

Introduction Wellpoints are small-diameter (less than 6 inches), shallow wells, and are closely spaced (2 to 10 feet apart). effectively dewater coarse sands and gravels, or silts and clays. Theyhaveawiderangeofapplications. Use a vacuum system and their depth is limited to about 25 feet. systems generally cost more than either sumps or wells, and require near-continual maintenance. 8

Introduction Other dewatering techniques include: oground freezing, oelectroosmosis, overtical Sand Drains, owick Drains, ogrouting, etc. However, such techniques are very costly and used only for particularly difficult dewatering applications. 9

Underwater Excavations In special cases where the soil is very pervious or when it is not possible or desirable to lower the groundwater table, underwater excavations can be considered. If underwater excavation is to be performed, the work area must be enclosed with an impervious structure. Once the impervious structure is in place, the excavation is performed within the structure. Once the desired excavation level is achieved within the structure, it is sealed with an impervious layer, such as concrete, in order to prevent water from sipping into the work area. After the impervious seal has been constructed, the water remaining within the structure is pumped out and construction is completed. 10

Caissons Caisson is a structure that is constructed at location if the project site is on land, but if the project site is offshore, it is constructed on land and then floated to the site offshore. In the caisson method of construction, the excavation is performed from within the permanent structure. 11

Caissons 12

Caissons After the caisson is in position, excavation from within the caisson structure begins. As the excavation is carried out, the caisson structure starts to sinkbyitsownweight,orifnecessary,byimposedloads. This procedure continues until the desired foundation level is achieved. Figure 1 shows this process schematically. 13

Caissons 14

Caissons By injecting bentonite clay slurry at the soil-structure interface, adding weight, or in case of cohesive soils using jetting, the frictional resistance between the caisson and the surrounding ground may be significantly reduced. When a pile, or in this case caisson, must be driven through dense and hard materials, several driving aids have been developed. The principal function of these driving aids is to speed the driving operation and to prevent damage to the structure that results from heavy driving. 15

Caissons Jetting is applicable to those situations where structure must be driven through cohesive soil materials to greater depths. Water jets can be used to displace granular soils from beneaththetoeofapileorcaisson. Jetting is accomplished by pumping water through pipes attached to the side or center of the structure as it is driven. The flow of water creates a quick condition and thereby reduces skin friction along the sides of the driven structure. The result is that the structure drives more easily. 16

Caissons 17

Caissons During unwatering (pumping the water to outside of caisson) a caisson in cohesive soils, the upward flow from the surrounding groundwater induces a quick condition, which results in loss of strength at the bottom of excavation. In other words, if the flow is upward then the water pressure tends to lift the soil element. If the upward water pressure is high enough the effective stresses in the soil disappear, no frictional strength can be mobilizedandthesoilbehavesasafluid. This is the quick condition and is associated with piping instabilities around excavations. 18

Caissons Quick condition is shown in Figure 3 19

Caissons To prevent quick condition, the head difference causing flow, i.e. the difference between the groundwater table level and the standing water level within the caisson, should be kept low. Caissons should not be used in the case of existing structures that can be damaged due to loss of ground from beneath their foundations. At the desired excavation level, an impervious seal is placed, usually by using tremie concrete. Once the Tremie concrete seal is in place, the dewatering of the caisson can begin. 20

Caissons The tremie concrete placement method uses a vertical or near vertical pipe, through which concrete is placed by gravity feed below water level. 21

DewateringAnalysis What information is needed to properly select and design a dewatering program? 22

DewateringAnalysis Understand the objective of the dewatering program: Dimensions of excavation Adjacent structures Construction sequence 23

DewateringAnalysis SoilData Layering Soil Properties(permeability and density) Rock locations and formation Water chemistry(corrosivity) 24

DewateringAnalysis Hydrology Water quantities have two components: Storage: Water needed tobe removed to lowerground water to intended level(can be up to 2/3 of total pumping volume) (Impact on schedule!!!) Steady-state recharge Sequence and duration of work: Is uplift a consideration? Requirements for pressure relief as the structure is being built Must dewatering be relocated as construction proceeds? Must portions of the system be installed inside the excavation? How / Can we remove the dewatering system after construction? 25

Design of Dewatering Analysis Typically water needs to be pumped out of the soil through the useofvarioustypesofpumps 26

Design of Dewatering Analysis Un-confined Aquifer(Water Table Aquifer) Q: Quantity of water pumped K: Soil permeability H: Height of ground water table above impervious layer h: Height of reduced ground water table Ro: Radius of influence r:radiusofwell 27

Confined Aquifer Construction Dewatering Design of Dewatering Analysis 28

Design of Dewatering Analysis Soil Permeability Theabilityofwatertoflowthroughasoil 29

Design of Dewatering Analysis Self-Practice Example In a construction dewatering job in an unconfined aquifer of depth 20m you have installed a 30 m3/h pump. The radius of influence extends for 10m around the well. What is the expected drawdown? 30

Design of Dewatering Analysis Multi-layered Aquifers In the case where we have different soil layers that make up the aquifer we can calculate the effective permeability of the aquifer as follows: where K is the effective permeability; Ki is the permeability of layer i; Bi is the thickness of layer i; and B is the overall thickness of aquifer. 31

Design of Dewatering Analysis Multi-well Analysis Howcanwecalculatetheeffectofmultiplewells? If the drawdown in the aquifer is a small percentage (about 10 20%) of the aquifer thickness, the effect of each well can be superimposed on the other to determine the cumulative effect. Unconfined Aquifer Confined Aquifer M is the number of pump wells; H is the original water table level; K is the effective permeability; B is the layer thickness; Qj is the pumping rate of well j; Rj is the influence radius of well j; and rj is the distance between pumping well j and the 32

Design of Dewatering Analysis Self-Practice Example In the shown 20x50m excavation three dewatering wells are installed at an offset of 4m from the edge of the excavation. The depth of the excavation is 5m and the ground water table is 2m below the natural ground level. The ground water is in an unconfined aquifer of 25m depth 33

Design of Dewatering Analysis Site Pumping Tests In order to determine actual well performance, a site pumping test is commonly performed prior to the final design of the dewatering system. This will help determine the actual performance and soil permeability. Observation wells / peizometers are installed to monitor the actual drawdown 34

-Techniques Sumps, Ditches and Trenches A trench is excavated around the area to be dewatered. Surface pumps with hoses are used to pump water from the ditches. Practical to be used with relatively small quantities of water and small water heads. 35

-Techniques Well point system Small pipes (up to 2.5 diameter) connected to screens at the bottom and a vacuum header pipe at the surface. Screens prevent soil particles from being pumped away with the water A centrifugal / vacum pump is connected to the manifold Wellpoint systems are constrained by the maximum possible suction head Common dewatering heights rangefrom4.5-7.5m 36

-Techniques Well point system Construction Steps 1. The wellpoints are jetted into the ground; 2. The annulars void is filled with filter media; 3. Thewellpointsareconnectedtoaheaderpipebymeansofariser; 4. Theheaderpipeisconnectedtosuctionpumpsforpumping 37

-Techniques Well point system 38

-Techniques Well point system Whatifweneedtolowerthegroundwatertablemore than the well point can handle? 2-stage well point system Deepwells 39

-Techniques Well point system 40

-Techniques Deep Well Consistsofaboreholefittedwithaslotted liner and an electric submersible pump. As the pump is submersible, there is no suction head limitation as for well points. Deep wells work best in soils with specific permeability profiles (k=1x10-5 cm/s to 1x10-7 cm/s)andtheamountofdrawdown that a well can achieve is limited only by thesizeofthepump. Pumps are engineered to withstand the aggressive corrosion factors associated withuseoversustainedperiodsoftimein a saline environment. 41

-Techniques DeepWell system 42

-Techniques DeepWell system Advantages: Ability to penetrate strata impervious to the jetting method of wellpoint systems. Installation of up to 100 feet deep or more in a single stage. Capable of pumping tens to thousands of gallons per minute per well. Deep Wells can be effective when placed outside of the jobsite work area. 43

-Techniques Ground Freezing Provides both a water cutoff and a structural cofferdam. Widely used in Europe. 44

-Techniques Ground Freezing Freeze pipe are installed along the line of the wall to be frozen every 1m. Pipe consists of an external casing and an internal pipe. A refrigerated brine solution is circulated through the system and the freeze pipes. At the freeze plant a heat exchanger transfers the heat to the ground. 45

-Techniques Ground Freezing Important Considerations: Natural ground water velocities. Prevent formation of wall. Presence of external heat source. (e.g. adjacent pipelines). Softclaywillcreepwhenfrozen. Ground movement. This technique requires continuous temperature monitoring. Not economic in hot climates. 46

Other considerations during dewatering Power supply: Provision of electricity source. Safe electrical wiring on site. Provision of backup power supply. Environmental considerations during dewatering: Disposal of water. Impact on ground water aquifers. Impact on surrounding structures. Conducting pumping tests to verify actual site performance 47

Thank You Questions? 48