Calculations for Line-of- Balance Diagrams

Similar documents
Algebra I: A Fresh Approach. By Christy Walters

Algebra I: A Fresh Approach. By Christy Walters

Describing a journey made by an object is very boring if you just use words. As with much of science, graphs are more revealing.

PSY201: Chapter 5: The Normal Curve and Standard Scores

Distillation Design The McCabe-Thiele Method

4-3 Rate of Change and Slope. Warm Up. 1. Find the x- and y-intercepts of 2x 5y = 20. Describe the correlation shown by the scatter plot. 2.

Equilibrium. Observations

Introduction ES = PEE 1. Progressive Feed Activities

Boyle s Law: Pressure-Volume Relationship in Gases

6.6 Gradually Varied Flow

Boyle s Law: Pressure-Volume. Relationship in Gases

REAL LIFE GRAPHS M.K. HOME TUITION. Mathematics Revision Guides Level: GCSE Higher Tier

SOFTWARE. Sesam user course. 12 May 2016 HydroD Hydrostatics & Stability. Ungraded SAFER, SMARTER, GREENER DNV GL 2016

Rural Highway Overtaking Lanes

1. What function relating the variables best describes this situation? 3. How high was the balloon 5 minutes before it was sighted?

O-Calc Pro Sag Tension Calculations Explained

Movement and Position

Flow in a shock tube

IMO DEVELOPMENT OF EXPLANATORY NOTES FOR HARMONIZED SOLAS CHAPTER II-1

Viva TPS. TS11/15 Total Stations Check and Adjust Procedure. October Summary

ATMOSPHERIC CIRCULATION

CHAPTER IV FINITE ELEMENT ANALYSIS OF THE KNEE JOINT WITHOUT A MEDICAL IMPLANT

Basic CPM Calculations

4-3 Rate of Change and Slope. Warm Up Lesson Presentation. Lesson Quiz

S0300-A6-MAN-010 CHAPTER 2 STABILITY

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

Agile Manager widget descriptions

Components of the 400m Hurdles

CHAPTER 6 DISCUSSION ON WAVE PREDICTION METHODS

Hydrostatic Force on a Submerged Surface

3. Answer the following questions with your group. How high do you think he was at the top of the stairs? How did you estimate that elevation?

y ) s x x )(y i (x i r = 1 n 1 s y Statistics Lecture 7 Exploring Data , y 2 ,y n (x 1 ),,(x n ),(x 2 ,y 1 How two variables vary together

OIL AND GAS INDUSTRY

1 Chapter 6: Stability. Chapter 6. Stability. 2000, John Wiley & Sons, Inc. Nise/Control Systems Engineering, 3/e

THERMALLING TECHNIQUES. Preface

DATA HANDLING EXAM QUESTIONS

Instruction Guide for using Dive Tables (draft)

Statistical Process Control Basics. LeanSix LLC

TRIP GENERATION RATES FOR SOUTH AFRICAN GOLF CLUBS AND ESTATES

Optimal Weather Routing Using Ensemble Weather Forecasts

Chapter 2: Modeling Distributions of Data

On street parking manoeuvres and their effects on design

Special edition paper

University of Cincinnati

Design of Turn Lane Guidelines

THE USE OF ENERGY BUILD UP TO IDENTIFY THE MOST CRITICAL HEELING AXIS DIRECTION FOR STABILITY CALCULATIONS FOR FLOATING OFFSHORE STRUCTURES

Walk - Run Activity --An S and P Wave Travel Time Simulation ( S minus P Earthquake Location Method)

1. The graph below shows how the velocity of a toy train moving in a straight line varies over a period of time.

Lesson 18: There Is Only One Line Passing Through a Given Point with a Given Slope

Optimization and Search. Jim Tørresen Optimization and Search

FUNCTIONAL SKILLS MATHEMATICS (level 1)

Aerodynamic Analyses of Horizontal Axis Wind Turbine By Different Blade Airfoil Using Computer Program

University of Cincinnati

Atmospheric & Ocean Circulation- I

CHAPTER 28 DEPENDENT FAILURE ANALYSIS CONTENTS

Developed by: The American Traffic Safety Services Association (ATSSA) 15 Riverside Parkway, Suite 100 Fredericksburg, VA

Research on Small Wind Power System Based on H-type Vertical Wind Turbine Rong-Qiang GUAN a, Jing YU b

Chapter 2: Pure Substances a) Phase Change, Property Tables and Diagrams

PUBLISHED PROJECT REPORT PPR850. Optimisation of water flow depth for SCRIM. S Brittain, P Sanders and H Viner

Where are you right now? How fast are you moving? To answer these questions precisely, you

Blocking time reduction for level crossings using the genetic algorithm

Chapter 2 Hydrostatics and Control

Two interconnected rubber balloons as a demonstration showing the effect of surface tension

Coriolis Mass Flow Meter

A Hare-Lynx Simulation Model

Evaluation of aerodynamic criteria in the design of a small wind turbine with the lifting line model

Influences on Weather and Climate Weather and Climate. Coriolis Effect

A Method Quantitatively Evaluating on Technical Progress of Students in Ship Handling Simulator Training ABSTRACT

SECTION 2 HYDROLOGY AND FLOW REGIMES

SAMPLE MAT Proceedings of the 10th International Conference on Stability of Ships

The Reliability of Intrinsic Batted Ball Statistics Appendix

INSTITUTE AND FACULTY OF ACTUARIES. Curriculum 2019 AUDIT TRAIL

Kennedy Bridge - Summary of Pier 6 Movement Records

UNIFIED INTERPRETATION OF PROVISIONS OF IMO SAFETY, SECURITY AND ENVIRONMENT-RELATED CONVENTIONS

Autodesk Moldflow Communicator Process settings

TECOTHERM NEO. Instructions for Use. MEDICAL EQUIPMENT for HYPOTHERMIA of NEONATES and INFANTS. Addendum 1 to

Goodyear Safety Research Project 2008 Presentation by Competitive Measure at the FEI Eventing Safety Forum. Presented by Tim Deans and Martin Herbert

PX400 P L A S T I C PX400 PERFORMANCE WIL T-02

Road safety on motorways

NAME: A graph contains five major parts: a. Title b. The independent variable c. The dependent variable d. The scales for each variable e.

AIRMOUNT VIBRATION ISOLATION

EFFICIENCY OF TRIPLE LEFT-TURN LANES AT SIGNALIZED INTERSECTIONS

Motion. 1 Describing Motion CHAPTER 2

BIOMECHANICAL MOVEMENT

Chapter 11 Applications in Trigonometry

Stability and Computational Flow Analysis on Boat Hull

Calculation of Trail Usage from Counter Data

Wind shear and its effect on wind turbine noise assessment Report by David McLaughlin MIOA, of SgurrEnergy

Advanced LOPA Topics

Risk-based method to Determine Inspections and Inspection Frequency

Motion Graphing Packet

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow

Energy Output. Outline. Characterizing Wind Variability. Characterizing Wind Variability 3/7/2015. for Wind Power Management

SHOT ON GOAL. Name: Football scoring a goal and trigonometry Ian Edwards Luther College Teachers Teaching with Technology

Hydrostatics and Stability Prof. Dr. Hari V Warrior Department of Ocean Engineering and Naval Architecture Indian Institute of Technology, Kharagpur

Tension Cracks. Topics Covered. Tension crack boundaries Tension crack depth Query slice data Thrust line Sensitivity analysis.

WIND DIRECTION ERROR IN THE LILLGRUND OFFSHORE WIND FARM

Physics: Principles and Applications, 6e Giancoli Chapter 3 Kinematics in Two Dimensions; Vectors. Conceptual Questions

1. SCOPE 2. REFERENCED DOCUMENTS. 2.1 SC Test Methods SC-T Forms SCDOT Electronic Forms SUMMARY OF TEST METHOD

yarn (1-2 meters) tape sticky notes slinky short piece of yarn or ribbon calculator stopwatch

Transcription:

Calculations for Line-of- Balance Diagrams Chapter 3 of the Handbook introduces the Line-of-Balance planning technique. (see Page 71). Here we show a structured approach to calculating and plotting a Line-of-Balance Schedule. Whilst software exists for producing Line-of-Balance schedules, the investment required (in time and money) to produce computerbased diagrams may not be justified. The approach shown below allows the planner to fully understand the basis of the resulting diagram and explore opportunities to optimise production. The way of working and the individual example selected for demonstration purposes are taken from Harris and McCaffer, 1996. Example Consider the calculation of the time taken to construct 30 houses. The target rate for completion of these houses is four houses per week. A working week comprises five 8-h days. The construction plan for each individual house is shown in Figure 1. These construction activities have been simplified for demonstration purposes. In practice the activities and their inter-relationship will be more complicated. A Handbook for Construction Planning and Scheduling, First Edition. Andrew Baldwin and David Bordoli. 2014 John Wiley & Sons, Ltd. Published 2014 by John Wiley & Sons, Ltd.

A B C D F 120 290 250 40 30 A = Substructure B = Superstructure C = Erect internal walls D = Install plumbing E = Electrical work F = Install finishes (All durations in hours) E 220 Figure 1 The construction plan for each house. The activities within the plan are as follows: Activity A Construction of the sub-structure Activity B Construction of the super-structure Activity C Internal partitions and walling Activity D Plumbing Activity E Electrical work Activity F Finishes It is assumed that there is a minimum buffer time of 5 days between each operation. Calculations The calculations required to draw the Line-of-Balance schedule for the construction of the houses are shown in Table 1. Each of the activities involved in the construction of a single house is listed. For each activity, it is necessary to determine the time taken in days to complete this activity for one house, (T). It is also required to calculate the time between the start of the first house and the finish of the last house, (S). (This represents the gradient of the line-of-balance for the activity and is useful in drawing the schedule.) With this information and details of the required rate of completion, it is then possible to draft the diagram. The Table shows seven calculations for each activity. Work from left to right across the table completing the calculations for each activity in turn. (No attempt should be made at this stage to balance the output of the different trades. This is made when the complete diagram has been drawn.) The calculations for the first activity, the Substructure, are as follows. The estimated time in man-hours per house (M) is 120 h. (This initial data comes from the planner s estimate of the time required after considerations of the drawings and specifications for the construction work.) The theoretical gang size (G) required to complete the target rate of build (R), 4 houses per week equals (R x M)/H where H is the hours worked per week. (In this contract, H equals 8 x 5 = 40 h per week. This may be different on other contracts. )

Table 1 Calculation of gang sizes and rates of build for Line of Balance Schedule. Activities Man-hours per house (M) Theoretical Gang Size (G) Men Per House (Q) Actual Gang size (multiples of Q) (g) Actual rate per week (U) Time in days for one house (T) Time between start of first house and the last house (S) Substructure 120 12 3 12 4.0 5.00 = 5 R 36.25 = 37 R Superstructure 290 29 6 30 4.14 6.04 = 6 R 35.02 = 35 R Erect internal walls 250 25 4 24 3.84 7.81 = 8 R 37.76 = 38 R Install Plumbing 40 4 3 3 3.0 1.67 = 2 R 48.33 = 49 R Electrical Work 30 3 2 2 2.67 1.87 = 2 R 54.31 = 55 R Install Finishes 220 22 5 20 3.64 5.50 = 6 R 39.84 = 40 R Additional Data d = the number of working days per week = 5 R = the Target Rate of Build = 4 houses per week B = the buffer time between activities = 5 H = the hours worked per week = 8 5 = 40 n = the number of units to be constructed = 104 h = the hours worked per day Notes: 1. R means rounded number. (Because the data will be used to plot the lines on the schedule, it is necessary to work with integers.) 2. The Man hours per House (M) is the required number of hours work required in the Activity in each house. 3. The Theoretical Gang Size (G) is the theoretical gang size required to produce the required output G = (R M)/H. 4. The Men per House (Q) is the total number of men to work on each Activity in each house. 5. g = The Actual Gang size selected (Q) must be a multiple of G selected as close as possible to the theoretical gang size. 6. The Actual rate per week (U) = (g/g) R. 7. The Time in Days for one house = T = (M/h) x (1/Q) is the time to complete the activity in one house based on the Actual Gang Size. 8. The Time between the start of first house and the finish of the last house = S = ((n 1) d)/u.

The Men per house (Q) is the usual gang size for the type of construction work. The planner compares this figure with the theoretical gang size to meet production requirements on this house and decides on the actual gang size (g) to be used on this contract. (g must be a multiple of Q) In this calculation, the actual gang size is determined as 12, that is four gangs of 3 will be used. This gives the actual rate of production per week as 4.0 the output required. (Compare this calculation with the calculation for the Superstructure. For the Superstructure, the theoretical gang size (G) is 29. The planner decides to use five gangs of six workers per house. The actual rate of production is therefore 4.14, greater than that required.) Given this actual rate of production per week, the time in days for one house (T) can be calculated. (For practical purposes, when drawing the schedule, this figure needs to be rounded to a whole number.) The time between the start of the first house and the finish of the last house (S) needs to be calculated. To do this, multiply the number of houses to be constructed minus 1, by the number of working days (d) and divide the total by the actual rate per week (U). Again for practical purposes, this figure needs to be rounded up or down into an integer. When the calculations for each activity have been completed the schedule may be drawn. Drawing the schedule Figure 2 is the completed schedule for the project. 30 87 93 37 42 47 53 61 69 85 91 98 104 30 20 20 Houses 10 10 1 0 5 12 18 23 31 36 38 58 64 1 Figure 2 The Line-of-Balance Schedule for the construction of the houses. The vertical axis shows the number of units to be constructed, in this example the house numbers from 1 to 30. The horizontal axis shows the number of working days. The schedule is drawn from left to right considering each activity in turn.

The first activity, A, the Substructure commences on house 1 at time zero, that is the start of the first working day. Construction work on the last of the houses, house 30, commences on day 37. (This is the calculated figure S taken from the table.) Work on the Substructure of the first house is completed at the end of day 5. Work on the Substructure of the last house commences on day 37 and is completed on day 42. Drawing the two lines, 0 37 and 5 42 presents an envelope of time representing the construction of the Substructure for all the houses. By reading horizontally across the schedule, it is possible to forecast when substructure work is scheduled to commence on each of the houses. Having drawn the schedule for the Substructure the schedule for the Superstructure can be drawn. It is known that there is to be a scheduled buffer time of 5 days between the two activities. (This was decided as part of the basic data for preparing the schedule.) Having completed the Substructure at the end of day 5, it is therefore possible to start the Superstructure after the buffer ends. If we assume this then the Superstructure on house 1 commences on day 11. Work on the Superstructure of the last house is then scheduled to start on day 11 + 35 equals day 46. This will not provide sufficient buffer time for the last house. It is therefore decided to delay the start of the Superstructure on House 1 until day 12. This then gives the working day number for the start of the superstructure on the last house to be day 47. The time taken for the Superstructure on each house is 6 days and therefore the work is completed on house 1 on day 18. It is completed on house 30 on day 53. In this way, the schedule of activities for all the construction work can be completed. As shown care must be taken when drawing the schedule to ensure that sufficient buffer time is allowed between the activities. This may require the commencement of work on the first house to be delayed form its earliest possible start date to avoid a possible clash with work on the preceding activity (or insufficient buffer time) as construction proceeds. When two or more activities take place in parallel, these are shown commencing on the same day. If the production rate for these activities varies, the envelopes of work in the schedule will be different. The day number for completion of the last activity is the completion date for construction. In this example, this is working day 104. Summary The production of a Line-of-Balance Schedule is always an iterative process. Having produced a schedule there will, inevitably, be the need to revisit the assumptions and the production decisions to improve productivity and reduce construction time. The aim with producing a Line-of-Balance schedule is to find a balanced schedule where all the activities are in parallel and the construction time is the minimum practical time. To achieve this, it is necessary to adjust gang sizes, (where possible), carry out activities in parallel (where possible) and reduce buffer times to the minimum. The level of buffer size (5 days) used in the example calculation is purely for demonstration purposes in this example. In practice, buffer sizes are much reduced, and apart from those determined by the specification (e.g. concrete curing times),

the time taken between activities only becomes significant where there are complex temporary works to dismantle. Buffer sizes may even be eliminated completely. The schedule as drawn assumes that the gang sizes at the start of the construction work will remain constant throughout the contract. In practice there will be opportunities to increase (or decrease) gang sizes as the work progresses. The calculations make no allowance for the learning curve in repetitive construction; this will influence actual production as the gangs move from one unit to the next. Despite the limitations of producing a schedule to reflect the influences of practical construction, there are considerable benefits in preparing a line-of-balance schedule for repetitive construction activities. The discipline of calculating and drawing out the schedule brings benefits in understanding both the basics of the construction and the alternatives as the work proceeds.