Dams as Systems. Pat Regan Federal Energy Regulatory Commission (FERC)

Similar documents
Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection

LESSONS LEARNED AT THE TAUM SAUK REBUILD. Paul C. Rizzo, Ph.D., P.E. 1 Carl Rizzo 2 John Bowen 3 ABSTRACT INTRODUCTION

FERC Division of Dam Safety & Inspections

Emergency Action Plan

STRUCTURAL STABILITY ASSESSMENT

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

HYDRAULIC JUMP AND WEIR FLOW

Huntington District. For More Information Contact (304)

Large-scale Field Test

Susitna-Watana Hydroelectric Project Document ARLIS Uniform Cover Page

CLAIBORNE LOCK AND DAM PERTINENT DATA

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b)

HAYWARD FLOW CONTROL TFS SERIES FLOW METER INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS

U.S. ARMY CORPS OF ENGINEERS INSTITUTE FOR WATER RESOURCES RISK MANAGEMENT CENTER PRELIMINARY LESSONS LEARNED FROM OROVILLE INCIDENT

HERBERT HOOVER DIKE REHABILITATION PROJECT

M EMORANDUM O CTOBER 6, 201 6

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

Operating Manual. Model BAC-30RT30/BAC-30DC

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Green CCR Surface Impoundment

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS.

GENERALIZED PROGRAMMATIC FRAMEWORK FOR SPILLWAY INSPECTION AND POTENTIAL FAILURE MODES ASSESSMENT

DAM SAFETY GUIDELINES 2007

Historic dam failures and recent incidents. Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman

Precision Liquid Settlement Array Manual

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

Guidelines for Developing Emergency Action Plans for Dams

What I ve Learned About Dam Safety Good, Bad and Ugly

What Happens Downstream Stays Downstream, or Does It? Potential Failure Modes from Spillway Exit Flows

IMPACT OF MAKING THE CREST OF WEIR MULTIFACETED ON DISCHARGE COEFFICIENT OF MORNING GLORY SPILLWAY

Water Storage for Agriculture

Design of Spillway Upgrades

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b)

White Paper. Electrical control valve actuators on oil and gas production separators

I T T Pressure Reducing Valve WARNING INSTALLATION, OPERATION, AND MAINTENANCE MANUAL

NUMERICAL AND PHYSICAL MODELING

Project 184 Preferred Canal Drainage Structure and Release Point Plan

GW DRY PIPE VALVE INSTALLATION & OPERATION 100mm (4 ) 150mm (6 )

Water Weir Flow Controller. Introduction. Safety Precautions. Mounting the Hardware

Final Fish Salvage & Temporary Tailrace Barrier Report for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) December 18, 2017

REGULATORY OBSERVATION

2007 Gas-Lift Workshop

Annex E Bridge Pier Protection Plan

FE Petro vs. New Red Jacket Competitive Comparison

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM

Final Fish Salvage & Temporary Tailrace Barrier Report for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) December 20, 2018

INFILTRATION PRACTICE MAINTENANCE INSPECTION FORM

Beavers are particularly adept at manipulating their

Wafer Check Valve. Contents. User s Manual. (1) Be sure to read the following description of our product warranty 1

Annex C Temporary Fish Passage Plan

Annual Meeting June 17, Research Stewardship Education

PRE-PURCHASE DECISIONS...1 BEFORE DELIVERY...1

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

BS Series Basket Strainer

Emergency Preparedness and Response plan

GREAT THINGS TO KNOW ABOUT YOUR. IRwin Methane Leak Detector

Lower Churchill Management Corporation. Nalcor Doc. No. MFA-PT-MD-0000-EN-PL

Scott Dam Spillway Comparing Physical Model Study Results

Model 7989T Steel Pipe Squeezer Sch. 40 & Sch. 80. Operations Manual

22. Specialty Valves.

Installation Instructions / Operating & Maintenance Manual Midi-Fill Digital Pressurisation Unit Models MFD15 & MFD22

Maintenance and Troubleshooting of Pneumatic Conveying Systems for Sand in a Foundry

ROUND ASSEMBLY. Positioning

Vibration and Pulsation Analysis and Solutions

Unique Challenges Influencing the Design and Construction Of Three Recent Australian RCC Dams

Pre-Application Document Kaweah Project (FERC Project No. 298)

SUBMITTAL NOTES PROJECT: Ross Model 50RWR-A Pilot Operated Surge Relief Valve with Hydraulic Anticipation. Size: inch / mm

JUST WHEN YOU HAD SEEN IT ALL: THE VALUE OF HIGH FREQUENCY PRESSURE DATA. James Dunning, CEO tel:

The Criticality of Cooling

Experiment Instructions

Managing Dam Safety Risks Related to Hydraulic Structures

Appalachian Adventure Unguided Tour #5

V48 Series 3-Way Pressure-Actuated Water-Regulating Valves With Union Fittings

COUNTER CURRENT UNIT. Instruction Manual

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

RICK FAUSEL, BUSINESS DEVELOPMENT ENGINEER TURBOMACHINERY CONTROL SYSTEM DESIGN OBJECTIVES

OPERATION OF SPILLWAY GATES HOW TO AVOID THE PROBLEMS AND PITFALLS. Peter Allen. DERM Qld

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA

SPECIFICATIONS APCEPH1

NB/NBR NITROGEN BOOSTER FOR AVIATION SERVICE

Plan B Dam Breach Assessment

Indiana LTAP Road Scholar Core Course #10 Culvert Drainage. Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd.

TEST SPECIFICATION NYT-909-C

User Instruction Manual For Davit Rescue System

KOBOLD KSM FLOWMETER. User Instructions

Irrigation System Winterization and Pressurization Procedures

WARNING! DO NOT THROW AWAY THESE INSTRUCTIONS! READ AND UNDERSTAND BEFORE USING EQUIPMENT!

Yokogawa Systems and PCI Training

FUNDAMENTALS OF PRESSURE RELIEF VALVES IN NATURAL GAS INSTALLATION - OPERATION - MAINTENANCE. Gary S. Beckett

TECHNICAL DATA MAINTENANCE AIR COMPRESSOR MODEL G-1

USER MANUAL. MACMAG magnetic separator MHK MHF

Hydraulic and Economic Analysis of Real Time Control

Coal Combustion Residuals Closure Plan

USER MANUAL. JET TST and JET TST S.

Teck Highland Valley Copper Partnership Highmont Tailings Storage Facility Operation, Maintenance & Surveillance Manual

FITTINGS AND VALVES Düker Plunger Valve RKV Type 7015 Professional control of flow rates, reservoir levels and pressures Safe, hygienic and durable!

Transcription:

Dams as Systems Pat Regan Federal Energy Regulatory Commission (FERC)

FERC >2,500 jurisdictional dams 770 feet to 0.5 feet high Five Regions Atlanta, Chicago, New York, Portland, San Francisco ~120 staff

Hoover Dam

Oroville Dam

Florence Lake Dam

Gibson Dam

Lower San Fernando

South Fork Failure with death

Potential Energy A major dam like Grand Coulee or Oroville can store more than 100 times the energy released by the atomic bomb dropped on Hiroshima. The Sayano-Shushenskaya dam in Russia stores nearly 800 times the energy of the Hiroshima bomb.

Teton Failure

Pre-Teton Dam (1976) Strictly standards based Three loading conditions Static (normal) Flood (unusual) Seismic (extreme) Defined minimum factor of safety Static (3.0*) Flood (2.0*) Seismic (1.3*) * from FERC Engineering Guidelines, Chapter 3, 2002

Federal Guidelines for Dam Safety Three categories of dams High Hazard Potential Dams where failure or mis-operation will probably cause loss of human life. (one or more) Significant Hazard Potential Dams where failure or mis-operation results in no probable loss of human life but can cause economic loss, environmental damage, disruption of lifeline facilities, or can impact other concerns. Low Hazard Potential Dams where failure or mis-operation results in no probable loss of human life and low economic and/or environmental losses.

Post Teton Reclamation implemented a risk-based dam safety program For the most part still only worried about the three loading conditions but included piping, the cause of the Teton failure Post Katrina, USACE is developing a risk-based program. Most states and the FERC are still in a deterministic world FERC is in the process of developing a risk-informed approach

Photo of Nimbus Dam

Wanapum Gear Picture

Taum Sauk - Failed Instrumentation

Taum Sauk Failure without death

Taum Sauk Report It is our conclusion that the root cause of the uncontrolled, rapid release of water from the Upper Reservoir was the breach of the Rockfill Dike a stability failure at the northwest corner of the Reservoir brought on by a rapid increase in the pore pressure at the Dike/foundation interface, stemming from the original design and construction which was flawed.

Phase Design Operation Organization Societal Decisions Design Taum Sauk Changes in Design Location limited surface area of reservoir. Needed storage volume required 10 high parapet wall with 8 of water stored against wall Assumed clean rockfill No spillway included Emergency shut-off system includes high water alarm (alarm in PH) and high-high alarm (shuts off pumps at 1 remaining freeboard) Water level monitoring equipment placed near morning glory inlet-outlet works (shortest distance to PH) 1-2 pump cycles per week One unit used to pump No person designated to assure dam safety Rate of Return cost structure Initial Construction Dirty Rockfill at best, rocky earthfill in some areas Instrumentation firmly fastened to concrete upstream face Operation State 1 (1963-1990) Operation State 2 (1990s) Basis Excessive settlement (~1 in 4.5 years) Water flow causes vortex development at inlet-outlet Experienced local operating staff Operations staff adjust water level controls to account for settlement Adjustment of water level controls not documents Arrogance - (letter to a FPC engineer) I told him there would be no structural damage if the pumps failed to shut down. (1968) Continuing settlement, up to ~2, results in cracking of concrete face slab and misalignment of parapet wall resulting in excessive seepage through dam Profit driven operation Remote operation Pump-turbines replaced, 25% greater capacity (1999) Multiple pump cycles/day Two unit pumping Retirement of experienced staff Loss of institutional knowledge No one considers impact of changed operation Deregulation of electric industry (~1997). No guaranteed rate of return Remediation (2004) Operation State 3 Failure Geomembrane liner installed on upstream face to reduce seepage Penetration of liner not allowed. Instruments supported from top of dam to bottom by suspension system. Turnbuckle nuts not locked PVC conduit houses instruments Emergency shut-off system installed at design elevations (ignoring the 2 of settlement that had taken place) Vibration from vortices loosens nuts on instrument support system PVC conduit bends due to vortices thereby giving erroneous water levels High water and high-high water level instruments re-wired in parallel to eliminate false readings Operators reprogram computer to account for deflection of conduits Overtopping events on Sept. 25 and 27, 2005 Repair to water level conduits delayed until future planned outage to minimize impact on generation On December 14, 2005, at about 0510 the dam overtopped during a pumping operation. The water level alarms did not sound because both alarms had to trigger to sound an alarm (after being rewired in parallel) and the highhigh water alarm was about two feet higher than the lowest point on the wall (due to ignoring the settlement). Due to the lack of a spillway the parapet wall overtops. The water falls 10 onto the earthen embankment rapidly eroding the material and undermining the parapet wall. The wall overturns unleashing a 10 wall of water that rapidly erodes the remaining embankment. It took only about 12 minutes to drain the reservoir. Peak outflow was estimated at 289,000 cfs (more than the Mississippi River above its confluence with the Ohio River). Luckily a downstream park and campground was empty due the time of year and 5 people in a house survived even though the house was swept from its foundation.

A Systems Perspective Interaction Diagram

The March to Failure 100 Design 90 Construction 80 70 100 90 Design Construction Operating & Performance History Aging 60 80 70 Operation Aging Remediation 50 40 30 20 10 0 60 50 40 30 20 10 0 As Envisioned 1958 As Envisioned 1958 1960 Begin Design 1960 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 Remediation ODSP Focus on financial performance OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 ODSP Focus on financial performance OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL

The March to Failure 100 Design 90 Construction 80 Operating & Performance History 70 Aging 60 Remediation 50 ODSP 40 Focus on financial performance 30 20 10 0 As Envisioned 1958 1960 Begin Design End Construction 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL

The March to Failure 100 Design 90 Construction 80 Operating & Performance History 70 Aging 60 Remediation 50 ODSP 40 Focus on financial performance 30 20 10 0 As Envisioned 1958 1960 Begin Design End Construction 1968 Letter 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL

The March to Failure 100 Design 90 Construction 80 Operating & Performance History 70 Aging 60 Remediation 50 40 End Primary Settlement ODSP Focus on financial performance 30 20 10 0 As Envisioned 1958 1960 Begin Design End Construction 1968 Letter 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL

The March to Failure 100 90 Deregulation Design Construction 80 70 Operating & Performance History Aging 60 Remediation 50 40 End Primary Settlement ODSP Focus on financial performance 30 20 10 0 As Envisioned 1958 1960 Begin Design End Construction 1968 Letter 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL

The March to Failure 100 90 Deregulation Design Construction 80 70 Operating & Performance History Aging 60 Remediation 50 40 End Primary Settlement ODSP Focus on financial performance 30 20 10 0 As Envisioned 1958 1960 Begin Design End Construction 1968 Letter 1962 1964 1966 1968 1970 1972 1974 1976 1978 Remediation 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 OSHA safety at the expense of system safety Fixing symptoms instead of fundamental problems Complacency, Arrogance and Ignorance Checking the regulatory box TOTAL

House Foundation

My Interests How can we use use systems engineering approaches to improve dam safety practices? How can we use systems engineering approaches to structure our approach to regulation?

My Interests Using Techniques and Practices built on STAMP to: Guide Hazard Analysis Guide Accident/Incident Causal Analysis and Understanding Guide development of guidelines Guide a study of the organizational structure of the FERC dam safety program