Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report

Similar documents
Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report

UPC Design / CN Locally Administered PE Phase VDOT Administered CN Phase

VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations

Meade Street Bridge Design Alternative Study

DULLES AREA TRANSPORTATION ASSOCIATION (DATA) February 18, Susan Shaw, P.E., VDOT, Megaprojects Director

Planned Improvements from Sector & Area Plans that have been added to the MTP

Appendix P (Version 2) Bikeway Projects in Currently Approved Plans. Planned Improvements from Sector & Area Plans that have been added to the MTP

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN

Design Criteria. Design Criteria

Columbia Pike Implementation Team (CPIT) Meeting

Transform I-66. Chief Engineer Garrett W. Moore, P.E. July 12, 2018

Public Information Meeting

Appendix B: Forecasting and Traffic Operations Analysis Framework Document

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT

City of Scotts Valley CITY COUNCIL STAFF REPORT

GRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

Access Routes from US 101 to the Richmond San Rafael Bridge

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Station 1: Street & Sidewalk Upgrades

122 Avenue: 107 Street to Fort Road

Route 29 Solutions Projects

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL

MCA Member Meeting: Tysons Update. Fairfax County Department of Transportation November 13, 2017

Lincoln Highway Streetscape Plan Concept Plan

Fairfax Alliance for Better Bicycling. Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation

Update of the Master Transportation Plan s (MTP) Bicycle Element

Henderson Ave. Complete Streets Project

Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Project Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information

GEARY CORRIDOR BUS RAPID TRANSIT Environmental Analysis. Special Intersections: Preliminary Concepts

Arlington Public Schools New Elementary School at Thomas Jefferson Site Off-Site Transportation. Thomas Jefferson BLPC / PFRC Meeting July 27, 2016

David Agacinski FDOT District One Bicycle & Pedestrian Coordinator Daniels Parkway Ft. Myers, Florida 33913

BID Strategy Group and Stakeholders Meeting. April 17, 2018

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

5. RUNNINGWAY GUIDELINES

Make Lincoln Highway an economically vibrant corridor that is safe, efficient, and beautiful for local residents and visitors.

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

Attached for your reference please find project updates on ongoing VDOT construction projects in Southampton County.

Southcote Road Improvements Class Environmental Assessment Study

Legislative Update. Frederick County Fall Staunton District. Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017

EXHIBIT U THE SCOPE DOCUMENT

Comments EXECUTIVE SUMMARY

AGENDA ITEM SUMMARY SPECIAL AGENDA ITEM NO. _1A_

County of Fairfax, Virginia. Department of Transportation

Executive Summary Route 30 Corridor Master Plan

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of March 16, 2019

Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session

N. Frederick Street to N. Manchester Street

Knox Street Complete Streets Project

U.S. HIGHWAY 50 IMPROVEMENT PROJECT

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Financial Project ID No(s).: and ETDM No(s).: and 14181

Memo. Ocean Avenue Corridor Design Project Public Workshop #2 Summary

Project Description Form 8EE

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA

Governance and Priorities Committee Report For the July 2, 2015 Meeting

DEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:

Crystal City Citizen Review Council Meeting. July 10, 2013

Item No. 14 Town of Atherton

Fairfax County Parkway Widening Fairfax County

Road Alterations - Wellington Street East, Church Street, and Front Street Intersection

I-395 Express Lanes Northern Extension Project Crystal City Civic Association September 21, 2016

Old Dominion Drive (Route 309) Pedestrian Safety Project Phase II. North Glebe Road to 38 th Street N

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

Fulton Market Streetscape

Austin Avenue Bridges Project. Public Meeting Summary

Working Group Meeting

STREETSCAPE CONCEPT PLAN

I-395 Express Lanes Northern Extension Project Fairlington Citizens Association September 12, 2016

City of Fairfax, Virginia City Council Work Session

TLC GRANT K / WATER STREETSCAPE ENHANCEMENTS WILL HANDSFIELD, AICP TRANSPORTATION DIR, GEORGETOWN BID

5 CIRCULATION AND STREET DESIGN

BD RESOLUTION NO RESOLUTION ADOPTING THE VISION ZERO RAMP INTERSECTION STUDY PHASE 1

CSAH 101 Preliminary Design

Washington DC Section of ITE Project Briefing

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS

ACTION TRANSMITTAL No

PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia

Chapter 3: Multi-Modal Circulation and Streetscapes

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Transportation Policy Manual

S.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project

Tonight is for you. Learn everything you can. Share all your ideas.

ALBERTA AVENUE WHAT WE HEARD REPORT BUILDING GREAT NEIGHBOURHOODS

Core of Rosslyn Transportation Study Existing Conditions Report - Appendix. Appendix E: VISSIM Model Calibration Summary

Community Meeting February 27, 2007 Dorchester Avenue Transportation & Streetscape Improvements Action Plan February 27, 2007

R o s s l y n, A r l i n g t o n C o u n t y, V i r g i n i a. S i t e P l a n R e v i e w C o m m i t t e e M e e t i n g # 5

Terwillegar Drive Expressway Draft Concept Plan

Recommendations. Central Salem Mobility Study

Route 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66.

PROJECT FACT SHEET March 21, 2018

50 Avenue S.W. Corridor Study Glenmore Aquatic Centre Drop-In Event

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Transcription:

Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report UPC Design 70762 / CN 109813 Locally Administered PE Phase VDOT Administered CN Phase 4-9-2018 1

Project Overview The Lynn Street Esplanade and Custis Trail Improvements project is a pedestrian and bicycle safety, traffic management and street beautification initiative located in Rosslyn. The project incorporates findings from the 1999 Esplanade Study, the 2003 Rosslyn Circle Safety Study and the 2006 Lynn Street Esplanade Preliminary Design Study. (A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway (B) Custis Trail: Westbound Lee Highway from N. Lynn Street to N. Oak Street. 2

Project Location: (A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway (B) Custis Trail: westbound Lee Highway from N. Lynn Street to N. Oak Street. N B A 3

Project Location Street View: (A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway 4

Project Location Street View: (B) Custis Trail: westbound Lee Highway from N. Lynn Street to N. Oak Street. 5

The Lynn Street Esplanade (A) Project includes: Widened sidewalks and larger pedestrian and bike waiting areas 11 traffic lanes Upgraded traffic signals and new signage On-street bike lane on Lynn Street Upgraded street lights Corridor of Light public art elements at the four corners of the I-66 bridge Custom fencing Landscaping (A) Lynn Street Esplanade (B) Custis Trail 6

EB Lee Highway N N. Lynn Street Bridge Improvements (A) Gateway Park 7

N East side of Lynn Street Improvements (A) Plan and elevation showing new bridge barrier, custom fence, 20 wide sidewalk and integrated sculptures 8

N East side Lynn Street (B) NE Corner Luminous Body Foundation and Lighting 9

West Side Lynn Street / Gateway Park (A) Plan and Elevation Graphics N 10

Sculpture Locations: Foundations in scope of work, Sculptures by others N 11

East side Lynn Street Southeast corner of Lynn and Lee Highway Sculptures by others / NIC 12

Semi-Custom Fence Full size mock-up 15

Custis Trail Improvements (B) Project area includes: Bicycle and pedestrian facility upgrades Intersection improvement at Lee Highway and N. Lynn Street Trail widening to 16 Increased trail separation from traffic Westbound lane reduction from Ft. Myer to N. Oak Street Curb extensions and wider curb ramps New traffic and dedicated bike signals New streetlights on both sides of westbound Lee Highway (A) Lynn Street Esplanade (B) Custis Trail 16

Overview - Custis Trail and Westbound Lee Highway Improvements (B) N Planned 16 wide trail with 6-foot buffer (existing 10 & 3 buffer) VDOT approved lane reduction on westbound Lee Highway provides space for wider trail and improved sight distances Improved pedestrian queuing areas at street crosswalks Upgraded traffic and trail signals at major intersections N. Oak Street to N. Lynn Street 17

Custis Trail at N. Lynn Street (B) Reduced crossing distances N New traffic and trail signals Larger trail queuing areas Barrier removed for Improved visibility of trail users Tighter corners to slow traffic in pedestrian areas 18

Custis Trail at Fort Myer Drive (B) N Dashed lines show existing curb location 19

Custis Trail at Marriot Entrance (B) N. N. Nash Street and Marriot Entrance 20

Existing Custis Trail N. Fort Myer Drive to N. Oak Street (B) 36 3 10 21

Approved Lane Reduction N. Fort Myer Drive to N. Oak Street (B) 22

Project Status In 2017, The construction phase of the project was transferred from Arlington to VDOT. VDOT has greater construction management capacity for projects of this scale Structural modifications to the VDOT bridge over I-66 are part of their work All work is being performed in VDOT right of way Risk management related to proximity to I-66 tunnel would be conveyed to VDOT 23

Project Schedule Construction Begins Spring 2018 Spring, 2017 Design Plans Completed and sent to VDOT: Spring, 2017 Project Advertised for Construction: Fall, 2017 1 st Bid Opening Date / Project re-bid due to low bid activity Winter, 2018 2 nd Bid opening:. Spring 2018 VDOT has Approved Contract for Construction Spring, 2018 Planned Construction Start: Two years Duration of Construction: Spring, 2020 Substantial Completion Date: 24

For More Information Visit our project webpage: projects.arlingtonva.us/projects/lynn-street-esplanade-custis-trail-improvements/ Thank you! End of Presentation 25

Project History 2/1999 CB appropriates $50K of the Rosslyn Fund to prepare a study for Improvements to Rosslyn. 8/1999 The original Rosslyn Esplanade Study completed Simple concepts show ways to better link Rosslyn with the Potomac River. Study presented to the public and the Waterview SP committee. 7/2000 CB approves Waterview SP#25. $3.6M for the development of two offsite projects: - Improvements at 19 th and Kent Street - Improvements to N. Lynn Street 2/2002 Rosslyn Circle Safety Study Ph I, completed and presented to the Pedestrian Advisory Committee. 8/2003 Rosslyn Circle Safety Study Phase II completed. Explored additional bike and pedestrian options around Rosslyn Circle and along the Custis Trail. 12/2004 Planning work starts for19 th and Kent Street Improvements. 2/2005 Engineering design starts for 19 th and Kent Street. 6/2005 I-66 Entry Ramp Study completed 11/2005 CB approves Contract with Toole Design Group for Lynn Street Planning and Environmental Services. Project stakeholders include VDOT, NPS, Civic Associations and Rosslyn Renaissance. 3/2006 JBG Public Arts contribution linked to the Lynn Street project. 4/2006 Lynn Street design charrette completed 7/2006 NEPA / Environmental Assessment completed. 26

8/9/2016 100% Plans submitted to VDOT Project History (cont.) 4/2006 Lynn Street public engagement / design charrette completed. 2/2007 Lynn Street Esplanade Planning / Conceptual Design Completed. 2/2008 All Development Condition Funds received from JBG. 12/2008 Lynn and Custis Trail PE Phase Authorized by VDOT. 6/2009 MWCOG TLC Arlington Trail Study completed for Custis Trail improvements from N. Scott St. to N. Lynn St 3/2009 19 th and Kent Street Improvements complete. 11/2009 CB approves contract with Toole Engineering for Design Services for Lynn and WB Lee Highway and Custis Trail Improvements 2/2010 Lynn Street and Custis Trail 25% engineering design complete 6/2010 CB approves revision to VDOT Project Funding Agreement to combine the Rosslyn Circle Improvements project with the Lynn Street Esplanade Project. 12/2010 Scope changed to remove proposed improvements on NPS property. 5/2011 CB approves design contract amendment #1 for additional traffic analysis, geotechnical work and survey. 1/2013 60% Plans complete 9/2013 CB approves design contract amendment #2 for major geometry changes as requested by VDOT, coordination with artist and new signals on westbound Lee Highway. 4/2014 CB approves Amendment #3 for additional design services for modifications to the Lynn street Bridge barrier wall and water main relocation design. 7/2015 90% plans submitted to VDOT and Arlington County 27

Project History (cont.) 8/2016 100% Plans submitted to VDOT 9/2016 VDOT Risk Assessment and Pre Advertisement Conf. Complete 12/2016 Final VDOT comments Addressed and Plan Set resubmitted 2/2017 VDOT central Office approves Project for Advertisment 6/2017 Dominion Power Undergrounding work 90% complete 3/2017 Construction Advertised By VDOT 4/2017 Bid opening / One bid received 5/2017 Bid rejected / Contractor not qualified by VDOT for Project work over $1M 6/2017 Plans updated to address questions received during advertisement and in preparation for rebid. 7/2017 New Schedule set for re-advertisement in November 2017 1/2018 New Bid opening Date 3/2018 Construction Contract awarded by VDOT 4/2018 Planned Pre-construction Conference 5/2018 Planned Construction Start 28