APPENDIX G DREDGING STUDIES. G.1: Fish Related Dredgi g I pacts a d Mitigatio

Similar documents
Annacis Island Wastewater Treatment Plant OUTFALL PROJECT

Marine Environment Plans

Threatened and Endangered Species Issues on the Kennebec River, Maine

ATLANTIC STURGEON. Consultations on listing under the Species at Risk Act

Environmental Management Strategy for Dredging in the Fraser River Estuary

X.B WETLANDS ROGUE RIVER ESTUARY

Steelhead Society of BC. Thompson River Watershed Restoration and Enhancement Project #4 Nicola River Bank Stabilization and Enhancement Project

Proposed 2018 Fisheries Management Measures to Support Recovery of Interior Fraser River Steelhead

APPENDIX A AGENCY COORDINATION

Trout Unlimited Comments on the Scope of Environmental Impact Statement for the Constitution Pipeline Project, Docket No. PF12-9

Success through Stewardship: White Sturgeon Monitoring and Assessment in the Lower Fraser River, B.C.

Kootenai River Habitat Restoration Program. Kootenai Tribe of Idaho - January 27, 2014 Presentation for Kootenai Valley Resource Initiative

Navarre Beach & Dune Restoration Project Status Report to be regularly updated June 17, 2016 Report

Information To Assist In Compliance With Nationwide Permit General Condition 18, Endangered Species

Planning Considerations for Nearshore Placement of Mixed Dredged Sediments

N. Tay Evans Marine Fisheries Biologist & Technical Review Coordinator

Ocean and Plume Science Management Uncertainties, Questions and Potential Actions (Work Group draft 11/27/13)

A.23 RIVER LAMPREY (LAMPETRA

Dredging Engineering Short Course Texas A&M University January 2016

Meeting in Support of Species at Risk Act Listing Process for Lower Fraser River and Upper Fraser River White Sturgeon

Angela Lane, Lowe Environmental Impact / Karen Akuhata (WDC) The Wairoa wastewater treatment system requires a replacement consent by May 2019.

Eulachon: State of the Science and Science to Policy Forum

Endangered Species Act and FERC Hydroelectric Projects. Jeff Murphy & Julie Crocker NHA New England Meeting November 16, 2010

Appendix A Recommended EPA Temperature Thresholds for use in Establishing Thermal Potential and Species Life Stage Numeric Criteria

COA-F17-F-1343 YEAR END REPORT

Dredging Operations Technical Support Program

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

Green Sturgeon Feeding Observations in Humboldt Bay, California

Nome Harbor Page 2 of 12

Dredging Keeping Our Underwater Highways Open

Update from Port Metro Vancouver Deltaport Third Berth Project Community Liaison Group. Meeting Date: August 28, Construction Update

Project Completion Abstract Fish Passage Activity ( Engineering Activities)

Final Fish Salvage & Temporary Tailrace Barrier Report for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) December 18, 2017

Grays Harbor O&M and Deepening Dredging

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT

Critical Habitat for Atlantic Sturgeon

JAN Approved Measures. Dr. John Quinn Chairman New England Fishery Management Council 50 Water Street, Mill 2 Newburyport, MA 01950

Near-Field Sturgeon Monitoring for the New NY Bridge at Tappan Zee. Quarterly Report July 1 September 30, 2014

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

Hydraulic Modeling of Stream Enhancement Methods

Restoring the Kootenai: A Tribal Approach to Restoration of a Large River in Idaho

Refined Designated Uses for the Chesapeake Bay and Tidal Tributaries

EcoLogic Memorandum. TO: Ben Brezell; EDR FROM: Mark Arrigo RE: Possible Impacts of Dredging Snooks Pond DATE: 6/4/07

I. Monitoring and Adaptive Management Approach. Potential Effects, Monitoring Studies & Mitigation

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Final Fish Salvage & Temporary Tailrace Barrier Report for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) December 20, 2018

Listed species under the jurisdiction of NOAA Fisheries that occur in the geographic area of responsibility of the Wilmington District are:

Protectingpipelinesfor

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

Request Number IR1-12: Flow Passage. Information Request

Lesson 1-1: Introduction to the Nechako White Sturgeon

SURVEY METHODOLOGY. April 15, Rob Livick City of Morro Bay Public Services Director/City Engineer 955 Shasta Avenue San Luis Obispo, CA 93401

Information for File # SEW

Union Pacific Railroad

14 NOISE AND VIBRATION

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

The Life History and Management of Alewife (Alosa pseudoharengus)

New two-lane bridge to replace the existing structure spanning the Maple River just south of the Village s central business district

Species Conclusions Table

Report on BPC Special Project regarding the Future Study Recommendations and Peer Review of the Salmonid Fish Tagging Study (Hearn, et al.

Atlantic Sturgeon Workshop

Pat DeHaan and Brice Adams. Sam Brenkman and Pat Crain

Eelgrass Survey PARADISE CAY BELVEDERE, MARIN COUNTY CALIFORNIA. Prepared For:

Use of Conservation Moorings as a Component of Eelgrass Restoration in two Massachusetts Harbors

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

R. Randall Center for Dredging Studies Texas A&M University

Performance Report. B. Project Title: Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project

DREDGING. with particular emphasis on Oil and Gas activities in Canada

Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California

Savannah River, Georgia and South Carolina

Mid-Columbia Fisheries Enhancement Group Annual Report Fiscal Year 06: July 1, 2005 June 30, 2006

Annex E Bridge Pier Protection Plan

La Quinta Channel Extension Port of Corpus Christi Ingleside, Texas. Mark Coyle

Packwood Hydroelectric Project Barrier Analysis December 12, 2006

FRASER RIVER STURGEON CONSERVATION SOCIETY BACKGROUNDER RESULTS OF 5-YEAR LOWER FRASER RIVER WHITE STURGEON MONITORING AND ASSESSMENT PROGRAM

Warm-up # 7 A day 5/17 - B day 5/18 UPDATE YOUR TABLE OF CONTENTS

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FISHERIES BLUE MOUNTAINS ADAPTATION PARTNERSHIP

Salmon and Steelhead in the American River Tim Horner, PhD Geology Department California State University, Sacramento

[FWS R5 FR 2018 N053; FF05F FXFR ; OMB Control. Agency Information Collection Activities; Submission to the Office of Management

Ninilchik Harbor Page 2 of 11

Fish Conservation and Management

Appendix F: Ecology F-6 Methodology for Estimating Potential Hydroacoustic Impacts to Abundant Hudson River Fish Species and Shortnose Sturgeon from

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE 8-FOOT CHANNEL OF THE FEDERAL NAVIGATION PROJECT IN KENNEBUNK RIVER KENNEBUNK & KENNEBUNKPORT, ME

Fish Habitat Restoration and Monitoring in Southeast Washington. Andy Hill Eco Logical Research, Inc.

Rehabilitation of Grimes Creek, a Stream Impacted in the Past by Bucket-lined Dredge Gold Mining, Boise River Drainage, July 2008 to August 2011.

Okanagan Sockeye Reintroduction

Figure 1. Schematic illustration of the major environments on Mustang Island.

Cook Inlet pipeline crossing is about making the best choices

Condition of Improvements 30 December 2014 Wrangell Harbors, Alaska (CWIS No , )

Oregon Estuaries defined: (Goal 16)

Lesson 1 - Meet the White Sturgeon

Nechako White Sturgeon; SARA listing experience for Carrier Sekani First Nations. June 4, 2018 Christina Ciesielski Carrier Sekani Tribal Council

EFFECTS ON CUTTER SUCTION DREDGE PRODUCTION WHILE DREDGING SIMULATED DEBRIS IN THE LABORATORY

Appendix E Cat Island Borrow Area Analysis

OKANAGAN RIVER RESTORATION INITIATIVE - FAQ

Species at Risk Act (SARA) Consultation Workbook

REVIEW OF THE INFORMATION FOR THE IDENTIFICATION OF CRITICAL HABITAT FOR THE COWICHAN (VANCOUVER) LAMPREY

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

TRANSPORT OF NEARSHORE DREDGE MATERIAL BERMS

Transcription:

APPENDIX G DREDGING STUDIES G.1: Fish Related Dredgi g I pacts a d Mitigatio A acis Isla d WWTP Ne Outfall Syste Va cou er Fraser Port Authority Project a d E iro e tal Re ie Applicatio

This page intentionally left blank

FISH RELATED DREDGING IMPACTS AND MITIGATION VFPA PROJECT AND ENVIROMENTAL REVIEW ANNACIS ISLAND WASTEWATER TREATMENT PLANT NEW OUTFALL - ANNIEVILLE CHANNEL, FRASER RIVER METRO VANCOUVER 4330 KINGSWAY BURNABY, BC V5H 4G8 December 22, 2017 CDM SMITH CANADA ULC SUITE 1001 4710 KINGSWAY BURNABY, BC V5H 4M2 ENVIROWEST CONSULTANTS INC. SUITE 101 1515 BROADWAY STREET PORT COQUITLAM, BC V3C 6M2

This page intentionally left blank.

Fish Related Dredging Impacts and Mitigation Proposed Dredging Construction of the Diffuser Manifold for the Annacis Island Waste Water Treatment Plant New Outfall System will require: 1) dredging a temporary trench in the riverbed to about 5 meters below the navigation channel dredge depth; 2) installing a large diameter (2.5 metre) pipeline with vertical risers within the trench, and 3) backfilling the trench to the navigation channel dredge depth with native sand covered with armor rock. The estimated dredge area is 12,750 m2 assuming a dredge slope of 6 horizontal to 1 vertical on the navigation channel side of the excavation and the use of temporary shoring on the shoreline side as necessary control the dredging and limit the dredge slope from extending further toward the shore. Dredging volume is estimated to be less than 35,000 m3. Dredging will be conducted using a clamshell dredge (i.e. a crane equipped with a clamshell bucket). A clamshell dredge was selected, in part, due to its ability to precisely excavate to the limits delineated by the design and limit impacts on the river bed associated with construction. Clamshell dredging is mechanical dredging and is effective in minimizing induced turbidity, as opposed to the hydraulic dredging. Hydraulic dredges, such as cutterhead suction and hopper dredges, tend to over-excavate, especially where sand is the dominant sediment. The crane with bucket would be operated from a floating spud-derrick. The bucket is operated through a series of cables fitted to the crane. Dredged material is deposited onto a barge. It is anticipated that a portion of the dredged material would be utilized to restore the river bottom (sediment and elevation) upon completion of the installation of the manifold. Dredged material not used to restore the river bed at and about the riser and diffuser manifold would be disposed at sea (Disposal-at-Sea Permit) or unloaded from barges at an off-loading facility and disposed at a permitted upland site. Timing of Dredging in Relation to Fisheries Sensitive Periods Dredging will be conducted during the timing window for inwater works of least risk to fish (June 16 through to February 28) (Fisheries and Oceans Canada 2017). The inwater timing window is specific to the mitigation of impacts to downstream migrating juvenile salmonids. Incidentally, the work window also protects upstream migrating eulachon; this species is typically migrating through Annieville Channel from March through to May. Likewise, late juvenile and adult white sturgeon feeding upon eulachon during spring and summer (April 01- August 01; Fisheries and Oceans Canada 2014) are also protected. Adult salmon, Dolly Varden char and bull trout will be in the river during the inwater work window. Upstream migrating adult salmon move through the main channel. Since the location of the dredge area is along the northern margin of the main channel, there is limited potential for interaction with upstream migrating adult salmon.

Adult white sturgeon may occur at and about the location of the dredge area during the inwater work window. Juvenile sturgeon may occur intermittently at and about the location of dredge area; however, during low flows within the Fraser River that occur during the timing window, the salt wedge will commonly engage the location of works, pre-empting juvenile white sturgeon. Potential Impacts to Fish and Fish Habitat Turbidity Elevated turbidity and total suspended solids associated with sediment plumes are typically transitory and temporary (Water and Land Use Committee 2006). If juvenile salmon encounter a sediment plume, they will express avoidance behaviour (see ECORP Consulting, Inc. 2009). Prospective impacts to juvenile salmon are mitigated through restriction of dredging to the inwater work window (Water and Land Use Committee 2006). Mechanical Dredging It is anticipated that salmon and char will express avoidance behaviour in response to the operation of the clamshell. However, dredging with a clamshell has the potential to strike or entrain adult and juvenile white sturgeon as they predominantly reside on the river bottom. The prospective impacts of dredging on all species of sturgeon, let alone white sturgeon, have been poorly studied. When such studies have been conducted, the focus has been upon the potential impacts of hydraulic dredging. The impacts of mechanical dredging, as represented by clamshell dredging, have not been studied in the Fraser River. A perspective regarding the risk of harm or death of white sturgeon due to mechanical dredging may be derived from data pertaining to interactions between dredging and other species of sturgeon. Data pertaining to mortalities attributable to entrainment by mechanical dredging are provided by the US Army Corps of Engineers Sea Turtle Data Warehouse (2013) for the Atlantic and Gulf coasts. The data spans 18 years, from 1995 to 2013. Forty-two (42) sturgeon (3 Gulf sturgeon (A. oxyrinchus desotoi), 11 shortnose sturgeon (A. brevirostrum), and 34 Atlantic sturgeon (A. oxyrinchus oxyrinchus)) were taken during dredging. Five sturgeon survived their encounters with the dredges (2 shortnose sturgeon and 3 Atlantic sturgeon). The majority of mortalities were associated with hopper dredging (3 Gulf sturgeon, 5 shortnose sturgeon and 24 Atlantic sturgeon). Four (4) sturgeon (1 shortnose and 3 Atlantic sturgeon) were entrained by mechanical dredging; or 0.2 sturgeon per year. The Atlantic Sturgeon Status Review Team calculated a minimum entrainment of 0.6 Atlantic sturgeon per year, based strictly on hopper dredging operations and an assumption that dredging efforts were relatively similar among years (US Army Corps of Engineers Sea Turtle Data Warehouse 2006). As can be deduced from the US Army Corps of Engineers Sea Turtle Data Warehouse (2013) data, the rate of sturgeon entrainment by mechanical dredging appears to be substantively less than entrainment associated with hopper dredging. COSEWIC (2012) does not identify dredging as a threat to sturgeon in terms of mortalities induced by the act of dredging. In this regard, and in consideration of US Army Corps of Engineers Sea Turtle Data Warehouse (2013) data and the scale and scope of dredging, it is unlikely that dredging would result in the death of white sturgeon. As such, potential of serious harm to white sturgeon is low.

Residual Impacts The maximum design impact on the river bottom attributable to the diffuser manifold is 4100 m 2. This is largely attributable to the conversion of surficial substrates from sand to large riprap. It is anticipated that the maximum design impact will not be realized as sand will be deposited upon and bury some of the riprap associated with the manifold. Dredging beyond the design footprint of the diffuser manifold is mitigated by the restoration of the affected river bed, outside of the design impact of the outfall, to the pre-impact condition (sediment and elevation). Temporary disturbance of sediments would be further mitigated by the annual deposition of sediments associated with freshet. As such, the duration of temporary disturbance of sediments will be less than one year. References COSEWIC (Committee on the Status of Endangered Wildlife in Canada). 2012b. COSEWIC assessment and status report on the White Sturgeon Acipenser transmontanus in Canada. Ottawa, ON. xxvii + 75p. Available: http://www.sararegistry.gc.ca/default.asp?lang=en&n=b2e66909-1 (02/15/2017). ECORP Consulting, Inc. 2009. Literature Review (for studies conducted prior to 2008): Fish Behaviour in Response to Dredging and Dredged Material Placement Activities (Contract No.W912P7-07-0079). Prepared for: US Army Corps of Engineers, San Francisco, CA. 48p + tables. Fisheries and Oceans Canada. 2017. British Columbia Marine/Estuarine Timing Windows for the Protection of Fish and Fish Habitat South Coast and Lower Fraser Areas. http://www.dfompo.gc.ca/pnw-ppe/timing-periodes/bc-s-eng.html#area-28 (05/12/2017). Fisheries and Oceans Canada. 2014. Recovery Strategy for White Sturgeon (Acipenser transmontanus) in Canada [Final]. In Species at Risk Act Recovery Strategy Series. Fisheries and Oceans Canada, Ottawa. 252p. US Army Corps of Engineers Sea Turtle Data Warehouse. 2006. http://el.usace.army.army.mil/seaturtles/takes.cfm?type=cubic. Cited in: Atlantic Sturgeon Status Review Team: Status Review of Atlantic Sturgeon (Acipenser oxyrinchus oxyrinchus). Report to National Marine Fisheries Service, Northeast Regional Office. February 23, 2007. Gloucester, MA. 174p. US Army Corps of Engineers Sea Turtle Data Warehouse. 2013. http://el.erdc.usace.army.mil/seaturtles. Cited in: Reine, K., D. Clarke, M.Balzik, S. O Haire, C. Dickerson, C. Frederickson, G. Garman, C. Hager, A. Spells, and C. Turner. 2014. Assessing Impacts of Navigation Dredging on Atlantic Sturgeon (Acipenser oxyrinchus). ERDC/EL TR-14-12. US Army Corps of Engineers, Environmental Laboratory. Vicksburg, MS. 40p. Water and Land Use Committee. 2006. Environmental Management Strategy for Dredging in the Fraser River Estuary. Fraser River Estuary Management Program, Burnaby, BC. 47p.