COAL COMBUSTION RESIDUAL (CCR) FUGITIVE DUST CONTROL PLAN

Similar documents
COAL COMBUSTION RESIDUAL (CCR) FUGITIVE DUST CONTROL PLAN

COAL COMBUSTION RESIDUALS FUGITIVE DUST CONTROL PLAN

CCR Fugitive Dust Control Plan

Big Rivers Electric Corporation - D.B. Wilson Generating Station. Fugitive Dust Control Plan for Coal Combustion Residuals

Big Rivers Electric Corporation - Sebree Generating Station (R. A. Reid, R. D. Green and HMPL Station Two)

COAL COMBUSTION RESIDUALS (CCR) FUGITIVE DUST CONTROL PLAN SANDY CREEK ENERGY STATION RIESEL, TEXAS. Prepared for:

FUGITIVE DUST CONTROL PLAN

COAL COMBUSTION RESIDUALS (CCR) FUGITIVE DUST CONTROL PLAN SANDY CREEK ENERGY STATION RIESEL, TEXAS. Prepared for:

Coal Combustion Residuals Annual Fugitive Dust Control Report. Prepared for Montana-Dakota Utilities Company R.M. Heskett Station.

FUGITIVE DUST CONTROL PLAN

CCR Certification: Fugitive Dust Control Plan (b) for the. West Ash Pond. at the. F. B. Culley Generating Station.

Closure Plan for CCR Surface Impoundments

CCR Fugitive Dust Control Plan

CCR CLOSURE PLAN Sibley Slag Settling Impoundment Sibley Generating Station East Johnson Rd Sibley, Missouri

Written Closure Plan. Pawnee Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) UPPER RETENTION SUMP FC_ClosPlan_011_

Written Closure Plan. Comanche Station - Active CCR Surface Impoundment Public Service Company of Colorado Denver, Colorado

CCR Closure Plan Ash Impoundment

Annual CCR Landfill Inspection. Lansing Landfill. Interstate Power and Light Company. Prepared for:

Amended Written Closure Plan

Initial Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Written Closure Plan. Cherokee Station - Active CCR Impoundments Public Service Company of Colorado Denver, Colorado.

2018 Annual Inspection Report

D.B. Wilson Station CCR Landfill

TABLE OF CONTENTS LEGAL NOTICE

Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

TABLE OF CONTENTS LEGAL NOTICE

TABLE OF CONTENTS LEGAL NOTICE

Northern Indiana Public Service Company Michigan City Generating Station Primary Settling Pond Number Annual RCRA CCR Unit Inspection Report

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) COMBINED WASTE TREATMENT POND (CWTP) FC_ClosPlan_012_

TABLE OF CONTENTS 1.0 INTRODUCTION PLAN CERTIFICATION (B)(4) 1

Whitewater Valley Station Surface Impoundment Coal Combustion Residual Annual Report

LEGAL NOTICE. Report No. SL Revision: 0 Page No. i. Ottumwa Generating Station Notification of Intent to Initiate Closure

CCR Closure Plan. CCR Certification: Written Closure Plan (b) & (c) for the. Landfill Sedimentation Pond. A. B. Brown Generating Station

2016 Annual Landfill Inspection Report. SCE&G Wateree Station Class III Landfill

2017 Annual Inspection Report

CCR Landfill 2017 Annual Inspection Report NC1 Ash Disposal Area

Coal Combustion Residuals Closure Plan

Consulting Engineers and Scientists Annual Landfill Inspection Report. for the. Williams Station Highway 52 Class III Landfill

First Annual RCRA CCR Unit Inspection Report January 2016 RESTRICTED WASTE TYPE I LANDFILL OPERATING PERMIT NUMBER 37-01

Written Closure Plan. Pawnee Station - North CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

CHOLLA POWER PLANT CLOSURE PLAN (b) SEDIMENTATION POND CH_ClosPlan_004_

2016 Annual Inspection Report

CCR Landfill 2018 Annual Inspection Report North Omaha Ash Landfill

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

2016 Annual Inspection Report

Northern Indiana Public Service Company (NIPSCO) 2723 East 1500 North, Wheatfield, Indiana, USA Golder Associates Inc.

2018 INSPECTION REPORT

Mine Dust Management Plan

Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.

CCR Landfill 2015 Annual Inspection Report NC1 Ash Disposal Area

Notice of Intent to Close Inactive CCR Surface Impoundments

CCR Unit Closure and Post-Closure Plan. The business of sustainability. Texas Municipal Power Agency Gibbons Creek Steam Electric Station

CSU Channel Islands Lead Operations and Maintenance Program

What I ve Learned About Dam Safety Good, Bad and Ugly

PRESSURE SYSTEMS POLICY

Annual Inspection Report of CCR Impoundment and CCR Landfill Wenck Project # B

O&M MANUAL HIGHLIGHTS

ENGINEER S CERTIFICATION OF AQUIFER SEPARATION DEMONSTRATION (40 CFR )

CalARP Checklist Summary of Violations Program Level 3 Facilities

CONFINED SPACE WRITTEN PROGRAM

POSITION DESCRIPTION City of Monett

October 16, GRDA CCR Landfill Compliance Report Grand River Dam Energy Center 8142 Hwy 412B PO Box 609 Chouteau, OK Dear Mr.

Secondary Aluminum NESHAP 40 CFR Part 63 Subpart RRR. Example Malfunction Plan for Plant ABC

Title: Swimming Pool Chlorination Operations

Pressure Vessel Program

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE

SCHEDULE 08 Public Safety Plan

Holding Pond Annual Inspection Report

New Castle County Guidelines for the Certified Construction Reviewer, Owner/Developer, Site Contractor and Professional Engineer

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b)

IDEM Indiana Department of Environmental Management Office of Land Quality P.O. Box 6015 Indianapolis, IN OLQ PH: (317)

University of Vermont Department of Physical Plant Personal Protective Equipment Program

CLOSURE PLAN. CFR (b) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio. September, 2016

PRINTED COPY IS NOT CONTROLLED Page 1 of 22

MAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS

HISTORY OF CONSTRUCTION

McIlvaine Company Hot Topic Hour. April 9, Dry Sorbent Injection Options and Issues

Hazardous Materials Management Guidelines

CLOSURE PLAN. CFR (b) GERS Bottom Ash Pond. Northeastern 3&4 Power Station Oologah, Oklahoma. October, 2016

STRUCTURAL STABILITY ASSESSMENT

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

WHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015

Safety Regulations and Procedures GENERAL SAFETY Confined Spaces - S New 11/96. To provide guidance for the safe entry of confined spaces.

6A.004 SCBA MAINTENANCE. Policy Number. Page 1 of 5 SCOPE

SILICA EXPOSURE CONTROL PLAN

Holding Pond Annual Inspection Report

Procedure: Pressure equipment safety

Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant

RESPIRATORS & FIT TESTING

A. Evaluation of the written program

Personal Protective Equipment. Individual Unit Function: Safety Procedure No.: SOP-0147 Page: 1 of 9

This guidance applies to those individuals who perform acid cleaning or chemical treatment aboard Marine Depot Maintenance Command Yermo CA.

Emergency Eyewash & Shower Testing Program

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants

OSHA s Proposed Silica Rule Randy Nicholls Northwestern Energy

ROLE DESCRIPTIONS BY COMPETENCY LEVEL

Respiratory Protection Self Inspection Checklist

Transcription:

COAL COMBUSTION RESIDUAL (CCR) FUGITIVE DUST CONTROL PLAN Plant Barry October 2015 Professional Engineer Certification: Based upon my knowledge, information, and belief that the content in the attached is accurate, I hereby certify that this meets the requirements of 40 CFR 257.80(b)(1)-(7) (Coal Combustion Residuals Rule). Wyman Turner, PE No. 30102, 12-31-15 Date: 10-08-15 Name, P.E. License No., Expiration Date Signature Page 1 of 5

AMENDMENT SUMMARY Date Amendment # Comments I Notes Page 2 of 5

1.0 PURPOSE The purpose of this guideline is to demonstrate compliance with the fugitive dust requirements in 40 CFR 257.80 (b)(1) through (7). 2.0 SCOPE This fugitive dust plan identifies and describes the Coal Combustion Residuals (CCR) fugitive dust control measures that Plant Barry will use to minimize CCR from becoming airborne at the facility, including CCR fugitive dust originating from CCR units, roads, and other CCR management and material handling activities. Coal combustion residuals are generated from the burning of coal to produce electricity and are defined as fly ash, bottom ash, boiler slag, and flue gas desulfurization (FGD) materials. 3.0 REFERENCES 40 CFR 257.53, 257.80, 257.105(g)(2) 4.0 GENERAL INFORMATION EPA defines fugitive dust as solid airborne particulate matter that contains or is derived from CCR, emitted from any source other than through a stack, or chimney. 40 CFR 257.53. 5.0 PROCESSES 1) Identify the CCR units on plant site that are subject to the requirements in 257.80 to minimize CCR from becoming airborne. Ash Pond Gypsum Pond 2) Identify and describe the fugitive dust control measures that are applicable and appropriate to minimize CCR from becoming airborne at the units listed in Section 5.0 (1) of this plan. Page 3 of 5

Ash Pond Fugitive dust control measures in the ash pond area include the following: 1. Spraying dewatered ash with water using a water truck as needed to promote the formation of a surface crust and minimize the potential for fugitive dust generation. 2. Access to the CCR unit is minimized, allowing only necessary personnel to conduct operations, maintenance and inspections. 3. Plant personnel conduct routine inspections for fugitive dust; plant CCR personnel are notified if fugitive dust generation is observed and action is taken. 4. Areas with observed fugitive dust are sprayed with water using water truck or other means. 5. Vehicle speed is limited. A speed limit sign is posted at each access road entrance to the CCR unit. 6. Areas in the wet portion of the pond include vegetation to control erosion and minimize dust. Gypsum Pond Fugitive dust control measures in the gypsum pond area include the following steps: 1. Access to the CCR unit is minimized, allowing only necessary personnel and equipment to conduct operations, maintenance and inspection. 2. Operations include routine inspections for fugitive dust. 3. Areas with observed fugitive dust are watered using a water truck or other methods. 4. Vehicle speed is limited. A speed limit sign is posted at each access road entrance to the CCR unit. 5. Trucks carrying gypsum are covered prior to leaving the CCR unit. 3) Explain how the control measures described in Section 5.0 (2) of this plan are applicable and appropriate for each CCR unit. The fugitive dust control measures identified and described in this plan were adopted and implemented based upon an evaluation of site-specific conditions, engineering site visits, and subject matter expert input. Minimizing access to dust areas, regular watering of roads in CCR handling areas, using water to create a crust on top of dewatered ash, reducing vehicle speeds, including routine inspections, responding to fugitive dust concerns and using covered trucks for off-site hauling in the manner discussed in Section 5.0 (2) are determined to be applicable and appropriate dust control measures for the listed CCR units. The evaluation included assessing the effectiveness of the fugitive dust control measures for each CCR unit over time. Consideration was given to various factors such as site conditions, weather conditions, moisture content and physical condition of the CCR (ash and gypsum), as well as operating conditions within the CCR units. 4) Describe the process to emplace CCR as conditioned CCR for any CCR landfill listed in Section 5.0 (1) of this plan. The plant does not operate any dry CCR landfills. Measures to address dry areas within the pond are described in Section 5.0 (2). 5) Describe the fugitive dust control measures to minimize CCR from becoming airborne on roads and at other CCR management and material handling activities. Page 4 of 5

Any accumulation of CCR material or dust generation within the CCR units, production areas, and along CCR transport routes is promptly addressed to control fugitive dust by wetting using a water truck or other methods as needed. CCR materials may also be flushed to wet sumps or transported directly to the settling ponds to prevent releases of fugitive dust. See discussion of CCR units in Section 5.0 (2) of this plan. 6) Describe the process to periodically assess the effectiveness of the fugitive dust control measures described in this plan. Plant personnel perform routine CCR fugitive dust inspections and ensure the operation of the water spray trucks or other dust suppression activities as necessary. Plant personnel understand the importance of minimizing CCR fugitive dust generation and the requirement that any CCR fugitive dust observations should be promptly addressed. 7) Describe the process to log citizen complaints received involving CCR fugitive dust events at the facility. When a complaint is received regarding a CCR fugitive dust event at the facility, the complaint is documented and investigated. Appropriate steps are taken, including any appropriate action, if needed. Page 5 of 5