Sliding Hill Road - Widening (UPC 104957) Scored HB 2 Application Project Application ID: 434 General Project Information Project Title Sliding Hill Road - Widening (UPC 104957) Principal Improvement Highway Organization Name Hanover County Does this project include any improvements to non-vdot maintained roadways? False Project Hanover County, through an agreement with VDOT, is presently developing a project through the public involvement stage to widen Sliding Hill Rd (Rt. 656) (UPC 104957) from 2 to 4 lanes between Atlee Station Rd and New Ashcake Rd (approximately 1.2 miles). The improvements will also include pedestrian and bicycle facilities, turn lanes and access management. Functionally classified as a Minor Arterial, Sliding Hill Rd is a 2-lane facility caring approximately 15,000 VPD in the project segment and is forecast to increase to 20-25,000 VPD by 2035. The Sliding Hill Rd corridor provides access to large residential, commercial and industrial developments including the Hanover County Airport and Industrial Air Park (5,000 employees, Freight Dependent, Knowledge, Local Serving per VTrans 2040 Economic Conditions Summary). The corridor is currently at capacity for a 2-lane facility. Interim improvements including turn lanes, signalization and limited widening has extended the useful life of the corridor; however, without a project to widen the facility to 4 lanes significant deterioration of this significant transportation facility is certain. The PE phase of the project is partially funded with RSTP funds allocated through the Richmond Regional Transportation Planning Organization (RRTPO). This application seeks HB2 funding to augment local and anticipated state revenue sharing funding to complete the design, right of way, utilities and construction portion of the project. The project is coordinated with land use and transportation through the Hanover County Comprehensive Plan and the RRTPO and is identified in the Secondary Six-Year Plan, Six-Year Improvement Program, and is consistent with the RRTPO Long Range Transportation Plan. HB2 Need Categories Regional Network Application Program District Grant
How does this project address VTrans 2040 need? This project will address Richmond Regional Network Need G (I-95 Corridor Reliability for the Commonwealth of Virginia as identified in VTrans 2040 Statewide Multimodal Transportation Plan for Regional Networks for the Richmond Region) by providing a 4-lane facility on Sliding Hill Rd to provide congestion relief in the I-95 and 295 corridors. This project improves corridor reliability by providing an outlet to Route 301, which functions as an alternate to I-95 during peak periods. Additionally, the project is consistent with the VTrans2040 Vision Plan goals of Economic Competitiveness & Prosperity, Accessible & Connected Places, Safety for All Users, Proactive System Management, and Healthy & Sustainable Communities. Specifically, as a reliever corridor to I-95 and 295 (Corridor of Significance, Washington to rth Carolina, Corridor K, Section 2), the project will provide congestion relief and assist with reliability overflow to Route 301. Because of its proximity to I-95 and 295, failure of the corridor over time has the potential to impact corridors of statewide importance due to peak hour back up onto the northbound exit ramp. These corridors are already heavily impacted by the merge of I-95 and 295 at this location. Sliding Hill Rd corridor also serves an important regional network function by providing an important reliever and connecting function between the I-95 / 295 corridors and Route 301 during congested periods. Economic Competitiveness & Prosperity goal is being achieved as a result of the project's connection to the Hanover Industrial Air Park, a large (5,000 person) employment center, and the Hanover County Airport, which are located in the Sliding Hill Rd corridor. The Sliding Hill Rd corridor supports a broad array of business and industry which are heavily freight dependent. These businesses are primarily located in the Industrial Air Park; however, potential for economic development expansion exists along the corridor through the development of a number of existing zoned or planned industrial and business developments. The corridor supports locally over 5,000 jobs according to VTrans 2040 Economic Conditions Summary and that is expected to grow. In addition the corridor supports the movement of residences from over 3,500 residential homes to a wide array of employment centers throughout the region and surrounding communities which relates to the goal of Accessible & Connected Places. Bicycle and pedestrian facilities are also important to the corridor and will be designed to facilitate mobility where appropriate, which will contribute to the lifestyle goal of Healthy & Sustainable Communities. Accident history suggests the need for operational improvements, which will be addressed by the project and help achieve the goal of Safety for All Users. The project utilizes existing infrastructure to the extent possible while also making necessary upgrades to pavements, drainage, signals and other project features, which contributes to the goal of Proactive System Management. Location PDCs Served Richmond Regional MPOs Served Richmond Area MPO Jurisdictions Served Hanover County Districts Served Richmond
Features Project Improvements Highway Improvement Comments Add New Through Lanes(s) Add an additional lane in each direction (2 lanes) from Kings Charter Dr. (sta. 114+00) to the existing 4-lane section at New Ashcake Rd (sta. 156+50) (2 x 4,250 ft). Shoulder Improvement(s) Construct new 8 ft shoulders (4 ft paved) beginning at the transition from the urban section at Atlee Commerce Blvd (sta. 132+00) to the existing 4-lane section at New Ashcake Rd (sta. 156+50) (2 x 2,450 ft). Access Management MS2 medians from Atlee Station Rd (sta. 102+30 to Kings Charter Dr (sta. 113+00), from Kings Charter Dr. to Totopotomoy Tr. (sta. 120+50), from Totopotomoy Tr. to Atlee Commerce Blvd (sta.129+00), from Atlee Commerce Blvd to Air Park Rd (sta. 136+50), from Air Park Rd to break at sta. 152+00, from break at station 152+00 to connection to existing 4-lane section at New Ashcake Rd. (sta. 156+50). Intersection Improvement(s) The following intersections are improved: Atlee Station Rd / Leadbetter Rd (east side), Kings Charter Dr., Totopotomy Tr., Atlee Commons Dr. / Atlee Commerce Blvd, Air Park Rd, King Braxton Ct. Turn Lane Improvement(s) Numerous right and left turn lane improvements which will reduce rear-end collisions and facilitate through movement of traffic in the corridor. Turn lane improvements include a continuous right turn lane from McDonald's through the intersection of Kings Charter Dr. Proposed right turn lane at Tototopomy Tr. Right turn lane maintained at Atlee Commerce Blvd. Proposed right turn lane at Atlee Commons Dr. Several left turn lanes along the corridor. New Traffic Signal/Signal Optimization Upgraded signal at intersection of Sliding Hill
Rd and Kings Charter Dr. to include pedestrian accommodations. Bike/Pedestrian Improvement Add/Construct Bike Lane Paved Shoulder (Minimum 4-Foot Ridable Surface) Construct Sidewalk Improve Bike/Pedestrian Crossing (At Grade) Comments Bike lane throughout commercial sections from sta. 102+30 to sta. 132+00 where bike facilities transition to paved shoulder (2 x 2,970 ft). (4 ft paved) beginning at the transition from the urban section at Atlee Commerce Blvd (sta. 132+00) to the existing 4-lane section at New Ashcake Rd (sta. 156+50) (2 x 2,450 ft). Sidewalk along commercial frontage approximately 2,650 ft providing access to residential areas. Pedestrian crossing added at intersection of Sliding Hill Rd and Kings Charter Dr. (sta. 113+00). Right of Way Improvement Right of Way/Easements acquisition required Comments Fee simple right of way and temporary construction, drainage and utility easements required throughout the corridor. Factors Accessibility Measure Response Additional tes Project includes transit system improvements or reduces delay on a roadway with scheduled peak service of one transit vehicle per hour. Project includes improvements to an existing or proposed park and ride lot (e.g., new lot, more spaces, entrance/exit, technology (payment, traveler information)). Project includes construction or replacement of bike facilities. For bicycle projects, off-road or on-road buffered or clearly delineated facilities are required. Yes The project includes approximately 5,940 ft of dedicated bike lane and 4,900 ft of 4 ft paved shoulder
Project includes construction or replacement of pedestrian facilities. For pedestrian projects, sidewalks, pedestrian signals, marked crosswalks, refuge islands, and other treatments are required (as appropriate). Project includes improvements to existing or new HOV/HOT lanes or ramps to HOV/HOT. Project provides real-time traveler information or wayfinding specifically for intermodal connections (access to transit station or park and ride lot). Provides traveler information or is directly linked to an existing TMC network/its architecture. Yes to accommodate bikes beyond the travel lanes. Sidewalk (2,650 ft) and signalized pedestrian crossing at Kings Charter Dr. and numerous ADA access points added. Land Use and Transportation Coordination Measure Response Additional tes Does the project promote walkable/bicycle friendly, mixed-use development? Yes The project includes bike and pedestrian facilities that will link existing commercial and retail shopping centers to approximately 3,200 adjacent Does the project promote in-fill development? Is there a locally/regionally adopted corridor/access management plan for the project area that addresses interparcel Yes residential homes There are a number of large pad ready sights available for infill in the development sites identified as Atlee Commerce Center and Atlee Commons. Several existing zoned parcels in excess of 200 acres are available for infill along and at the end of the corridor for Light Industrial and Industrial / Commercial. See the attached zoning map which identifies over 400 acres of undeveloped commercial and industrial zoned parcels in the corridor. On the map, Commercial designations are: O-S, B-O, B-1, B-2, B-3, MX. Industrial designations are: M-1, M-2, M-3.
connectivity and exceeds VDOT s minimum spacing standards? Environment Measure Response Additional tes Project includes construction or replacement of bike facilities. For bicycle projects, off-road or on-road buffered or clearly delineated facilities are required. Yes The project includes approximately 5,940 ft of dedicated bike lane and 4,900 ft of 4 ft paved shoulder to accommodate bikes Project includes construction or replacement of pedestrian facilities. For pedestrian projects, sidewalks, pedestrian signals, marked crosswalks, refuge islands, and other treatments are required (as appropriate). Project includes improvements to rail transit or passenger rail facilities. Project includes improvements to an existing or proposed park-and-ride lot (e.g., new lot, more spaces, entrance/exit, technology (payment, traveler information)). Project includes bus facility improvements or reduces delay on a roadway with scheduled peak service of one transit vehicle per hour.* Project includes improvements to freight rail network or intermodal (truck to rail) facilities/ports/terminals. Project include special accommodations for hybrid or electric vehicles, or space or infrastructure for electric vehicle parking/charging). Project includes energy efficient infrastructure or fleets, including: hybrid or electric buses, LED lights and signals, electronic/open road tolling, alternative energy infrastructure (e.g., roadside solar panels). Yes Yes beyond the travel lanes. Sidewalk (2,650 ft) and signalized pedestrian crossing at Kings Charter Dr. and numerous ADA access points added. Signal with LED lights Economic Development Factors Transportation project (consistency with Local Comprehensive Plan or Local Economic Development Strategy) Consistent With Transportation project (consistency with Regional Economic Development Strategy) Consistent With
Site Name Hanover County Industrial Air Park (consistent with locality Comprehensive Plan/Zoning) Consistent with comp. plan future land use/zoning (site plan status) Approved (site utilities status) (proposed (or projected) building square footage) Driving distance to development project from transportation project Does Transportation Project Provide Direct Access or Indirect Access to the Development Site? In place 3667132 0 Provides Primary Access to the Site or is Adjacent to the Site Site Name Air Park Associates (consistent with locality Comprehensive Plan/Zoning) Consistent with comp. plan future land use/zoning (site plan status) N/A (site utilities status) (proposed (or projected) building square footage) Driving distance to development project from transportation project Does Transportation Project Provide Direct Access or Indirect Access to the Development Site? In place 2121750 0.35 Provides Primary Access to the Site or is Adjacent to the Site Site Name Cedar Run (consistent with locality Comprehensive Plan/Zoning) Consistent with comp. plan future land use/zoning (site plan status) N/A (site utilities status) (proposed (or projected) building square footage) Driving distance to development project from transportation project Does Transportation Project Provide Direct Access or Indirect Access to the Development Site? In place 300000 0 Provides Primary Access to the Site or is Adjacent to the Site
Delivery/Funding Project Delivery Information Project Planning Transportation Element of Local Comprehensive Plan Planning/Safety Study Project Administered By Locality Existing Project UPCs or Project Numbers 104957 Project Delivery Method Design-bid-Build Please indicate who will be/was responsible for the design of this project VDOT: Locality: Consultant: N/A N/A 100% Phase Estimate and Schedule PE (Survey, Environmental, Design) Underway 60% Cost Estimate Start Date End Date $815,838 07/18/2014 07/04/2017 RW (Right of Way and Easement Acquisition, Utility Relocation) t Started 0% Cost Estimate Start Date End Date $3,197,114 07/04/2017 07/04/2019 CN (Construction, Oversight, Inspection, Contingencies) t Started 0%
Cost Estimate Start Date End Date $7,387,252 07/04/2019 08/04/2021 Cost Estimate Start Date End Date Cost Estimate Start Date End Date Cost Estimate Start Date End Date Cost Estimate Start Date End Date Cost Estimate Start Date End Date Total Cost Estimate $11,400,204.00
Project Funding Sources SYIP Allocations Committed Funding Amount Requested Funding Amount HB2 Amount Requested Total Proposed Project Funding $1,078,146 $1,500,000 $1,500,000 $7,332,058 $11,410,204.00 Committed Funding Amount Requested Funding Amount Locality Funds VDOT Revenue Sharing Scoring Project Located in Typology Category B Congestion Mitigation Safety Accessibility Environment Economic Development Land Use Increase in Daily Person Throughput Decrease in Person Hours Delay Reduction in Fatal and Severe Injury Reduction in Fatal and Severe Injury Rate Increase in Access to Jobs Increase in Access to Jobs for Disadvantaged Populations Improved Access to Multimodal Choices (Users Benefit Value) Air Quality (Total Benefit Value) Acres of Natural/Cultural Resources Potentially Impacted Economic Development Support (Sq. ft.) Intermodal Access Improvements (Tons Benefit Value) Travel Time Reliability Improvement Transportation Efficient Land Use Measure Score 0.1 0.8 2.6 0.7 0.2 0.0 0.1 0.1 0.7 14.2 1.5 3.4 4.9
Measure Weight Weighted Measure Score Raw Factor Score Factor Weighting Weighted Factor Score Project Score Total Project Cost Score Divided by Total Cost 50 % 50 % 50 % 50 % 60 % 20 % 20 % 50 % 50 % 60 % 20 % 20 % 100 % 0.0 0.4 1.3 0.4 0.1 0.0 0.0 0.0 0.3 8.5 0.3 0.7 0.5 0.4 1.6 0.1 0.4 9.5 4.9 15 % 20 % 25 % 10 % 20 % 10 % 0.1 0.3 0.0 0.0 1.9 0.5 2.9 $11,410,204 2.5 HB2 Cost $7,332,058 Project Benefit Score / HB2 Cost 3.9 Supporting Documents Current Attachments Project Traffic Study sliding hill road corridor - draft report 05-15-15.pdf Hanover Sliding Hill Corridor Business Properties Inventory
hanover sliding hill corridor buisness properties inventory august 2015.pdf Economic Development Strategic Plan final strategic plan- economic development 2009.pdf Comprehensive Plan - Econ Dev sec7 economic development 9-11-13.pdf Cedar Run Site Plan cedar run site plan.png AirPark Associates Site Plan airpark associates concept 3-buildout layout1.pdf Crash Data (Jan. '08 - Dec. 12) sliding hill crash data jan 08-dec 10.xlsx
TPO Resolution of Support tpo resolution of support - sliding hill rd widening.pdf 60 Percent Plans Vol 1 of 5 sliding hill ph plans - volume 1.pdf 60 Percent Plans Vol 2 of 5 sliding hill ph plans - volume 2.pdf 60 Percent Plans Vol 3 of 5 sliding hill ph plans - volume 3.pdf 60 Percent Plans Vol 4 of 5 sliding hill ph plans - volume 4.pdf 60 Percent Plans Vol 5 of 5
sliding hill ph plans - volume 5.pdf Sliding Hill Construction Estimate Quantities sliding hill construction estimate quantities.pdf Sliding Hill Detailed Project Estimate sliding hill - detailed project estimate.pdf Project Sketch Map project sketch map (9-24-15).pdf Zoning map zoning map - sliding hill rd corridor (3).pdf Richmon Regional Comprehensive Economic Development Strategy 2014 richmond reg. comp. econ. dev. strategy (pg. 61-65 & 83).pdf
Available Land Infill sliding hill rd corridor - available land-infill (1).pdf 434.Sliding_Hill_Road_Widening.01OCT2015.RN.B3 434.sliding_hill_road_widening.01oct2015.rn.b3.pdf